Contract No: HK/2009/05 Wanchai Development Phase II and Sampling, Field Measurement and Testing Work (Stage
1) Environmental
Permit no. EP-364/2009/A, Further Evironmental permit nos. fep-01/364/2009,
fep-02/364/2009, FEP-03/364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A, FEp-06/364/2009/a and FEp-07/364/2009/a Quarterly
Environmental Monitoring
and Audit Report
- June 2011 to August 2011 -
|
CLIENTS: |
|
Civil Engineering and
Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED
by: |
|
                         Raymond Dai Environmental Team
Leader |
|
DATE: |
|
26 September 2011 |
1.1    Scope of the Report
1.2    Structure of the Report
2.   Project
Background
2.1    Background
2.2    Scope of the Project and Site Description
2.3    Division of the Project Responsibility
2.4    Project Organization and Contact Personnel
2.5    Principal Work and Activities
3.   Monitoring
Requirements
3.1.    Noise Monitoring
3.2.    Air Monitoring.
4.   Monitoring
Results
4.1.    Noise Monitoring Results
4.2.    Real Time Noise Monitoring Results
4.3.    Air Monitoring Results
4.4.    Waste Monitoring Results
5.1.    Noise Monitoring
5.2.    Air Monitoring.
5.3.    Site Audit
5.4.    Review of the Reasons for and the Implications of
Non-compliance
5.5.    Summary of action taken in the event of and follow-up
on non-compliance
6.   Complaints,
Notification of Summons and Prosecution
7.   Cumulative
Construction Impact due to the Concurrent Projects
lIST OF TABLES
Table I      Principal Work Activities for Contract no. HY/2009/17
Table II     Principal Work Activities for Contract no. HY/2009/18
Table III     Principal Work Activities for Contract no. HK/2009/01
Table IV     Principal Work Activities for Contract no. HK/2009/02
Table 2.1    Schedule 2 Designated Projects under this Project
Table 2.2   Details of Individual Contracts under the Project
Table 2.3   Contact Details of Key Personnel
Table 2.4    Principal Work Activities for Contract no. HY/2009/17
Table 2.5    Principal Work Activities for Contract no. HY/2009/18
Table 2.5    Principal Work Activities for Contract no. HK/2009/01
Table 2.6    Principal Work Activities for Contract no. HK/2009/02
Table 3.1   Noise Monitoring Station
Table 3.2   Real Time Noise Monitoring Station
Table 3.2   Air Monitoring Stations
Table 4.1    Noise Monitoring Stations for Contract no. HY/2009/17
Table 4.2
   Noise Monitoring Station for Contract no. HY/2009/18
Table 4.3
   Noise Monitoring Stations for Contract nos. HK/2009/01 and HK/2009/02
Table 4.4
   Noise Monitoring Station for Contract nos. HY/2009/15
Table 4.5    Noise Monitoring Stations for Contract no. HY/2009/19
Table 4.6   Real Time Noise Monitoring Station for Contract no. HY/2009/17
Table 4.7   Real Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 4.8    Air Monitoring Stations for Contract no. HY/2009/17
Table 4.97   Air Monitoring Stations for Contract no. 04/HY/2006 and HY/2009/18
Table 4.10   Air Monitoring Stations for Contract no. HK/2009/01
Table 4.11   Air Monitoring Station for Contract no. HK/2009/02
Table 4.12   Air Monitoring Station for Contract no. HY/2009/15
Table 4.13   Air Monitoring Stations for Contract no. HY/2009/19
Table 4.14  Details of Waste Disposal for Contract no. HY/2009/17
Table 4.15  Details of Waste Disposal for Contract no. 04/HY/2006
Table 4.16  Details of Waste Disposal for Contract no. HK/2009/01
Table 4.17  Details of Waste Disposal for Contract no. HK/2009/02
Table 4.18  Details of Waste Disposal for Contract no. HY/2009/18
Table 4.19  Details of Waste Disposal for Contract no. HY/2009/15
Table 5.20  Details of Waste Disposal for Contract no. HY/2009/19
Table 6.1   Cumulative Statistics on Complaints
Table 6.2   Cumulative Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure
2.1     Project
Layout
Figure
2.2     Project Organization Chart
Figure 3.1      Locations
of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 2.1   Environmental Mitigation Implementation
Schedule
Appendix 3.1   Action and Limit Level
Appendix 4.1   Noise Monitoring Results and Graphical
Presentations
Appendix
4.2   Real-time
Noise Monitoring Results and Graphical Presentations
Appendix 4.3   Air Quality Monitoring Results and
Graphical Presentations
Appendix 5.1   Event Action Plans
Appendix
6.1   Complaint
Log
Appendix 6.2   /span>Notification
of Exceedance
Appendix 8.1   Construction
Programme of Individual Contracts
EXECUTIVE
SUMMARY
Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot
- Advanced piling works under FEP-03/364/2009
Major construction activities for Contract
no. HK/2009/17 have been commenced on 5 October 2010. During this reporting
period, the principal work activities for Contract no. HY/2009/17 are
summarized as below:
Table I     Principal
Work Activities for Contract no. HY/2009/17
June
2011 |
July
2011 |
August
2011 |
Pile
cap construction |
Pile
cap construction |
ELS
works for basement construction for pile cap construction |
Contract no. 04/HY/2006  /span> Reconstruction of Bus Terminus near
Construction works were completed and a duly
signed report on Completion of Works was issued by the Engineer dated on 1
March 2011. In addition, acknowledge of
FEP surrender was under preparation by the Contractor
Contract no. HY/2009/18 - Central - Wan Chai
Bypass (CWB) - Central Interchange under
FEP-05/364/2009/A
Table II    Principal Work Activities for Contract no.
HY/2009/18
June
2011 |
July
2011 |
August
2011 |
Instrumentation
Manholes and Intake Culvert Survey
Excavation
of trial pit
Hoarding
erection
Tree
transplanting
Installation
of coupler in CR3
Drainage
diversion works
Site
investigation and pre-drilling works
Excavation
in Trough B
Man
Kwong Street Gate 1 & 2 setup
Sheet
piling
Retaining
wall |
Instrumentation
Manholes and Intake Culvert Survey
Excavation
of trial pit
Hoarding
erection
Tree
transplanting
Installation
of coupler in CR3
Drainage
diversion works
Site
investigation and pre-drilling works
Excavation
in Trough B
Man
Kwong Street Gate 1 & 2 setup
Sheet
piling
Guide
wall construction near PTI |
Instrumentation
Manholes and Intake Culvert Survey
Excavation
of trial pit
Hoarding
erection
Tree
transplanting
Installation
of coupler in CR3
Drainage
diversion works
Site
investigation and pre-drilling works
Excavation
in Trough B
Sheet
piling
Guide
wall construction near PTI
Diaphragm
wall
Emergency
exit construction at MTR by-law area |
Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at
Major construction activities for Contract
no. HK/2009/01 have been commenced on 25 August 2011. During this reporting
period, the principal work activities are summarized as below:
Table III    Principal
Work Activities for Contract no. HK/2009/01
Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
Major construction activities for Contract
no. HK/2009/02 have been commenced on 26 April 2011. During this reporting period, the principal
work activities are summarized as below:
Table IV    Principal
Work Activities for Contract no. HK/2009/02
June
2011 |
July
2011 |
August
2011 |
Guide
wall construction for diaphragm wall construction
Pre-drilling
for diaphragm wall construction at WCR1 area.
Tunnel
bored pile works at WCR1 area
Diaphragm
wall construction at WCR1 area |
Guide
wall construction for diaphragm wall construction.
Pre-drilling
for diaphragm wall construction at WCR1 area.
Tunnel
bored pile works at WCR1 area.
Diaphragm
wall construction at WCR1 area. |
Tunnel
bored pile works at WCR1 area
Diaphragm
wall construction at WCR1 area |
Contract
no. HY/2009/15 - Central-Wanchai Bypass  Tunnel (
Major construction activities for Contract
no. HY/2009/15 have been commenced on 13 July 2011. During this reporting
period, the principal work activities are summarized as below:
Table V          Principal Work
Activities for Contract no. HY/2009/15
June
2011 |
July
2011 |
August
2011 |
No major
construction activity was undertaken |
Diaphragm
wall construction at TS1 and TPCWAE |
Diaphragm
wall preparation work at TS1 and TPCWAE
Trial
trench work at |
Contract
no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under
FEP-07/364/2009/A
Major construction activities for Contract
no. HY/2009/19 have been commenced on March 2011. During this reporting period,
the principal work activities are summarized as below:
Table VI          Principal Work
Activities for Contract no. HY/2009/19
June
2011 |
July
2011 |
August
2011 |
Steel
fabrication of temporary platform
Erection
of platform to enable marine pre-drilling
Marine
Pre-drilling |
Steel
fabrication of temporary platform
Erection
of platform to enable marine pre-drilling
Marine
Pre-drilling
Trial
pitting at Portion XI |
Steel
fabrication of temporary platform
Erection
of platform to enable marine pre-drilling
Marine
Pre-drilling
Remove
existing dolphin pier |
Noise Monitoring
Air Quality Monitoring
Complaints, Notifications of Summons and Successful Prosecutions
1.1.1.
Lam Geotechnics
Limited (LGL) has been appointed to work as the Environmental Team (ET) under
Environmental Permit no. EP-364/2009A and Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-04/364/2009/A, FEP-05/364/2009/A, FEP-06/364/2009/A and FEP-07/364/2009/A to implement the Environmental Monitoring and Audit
(EM&A) programme as stipulated in the EM&A Manual of the approved
Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A
Manual of the approved EIA Report for Central-Wan Chai Bypass and Island
Eastern Corridor Link (Register No. AEIAR-014/2001).
1.1.2.
This report
presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.3 of EM&A
Manual and  /span>Environmental Monitoring and Audit Requirements 
under Particular Specification Section 27.
1.1.3.
This report
documents the finding of EM&A works during the period from 28th June 2011 to 27th August 2011.
Section
1     Introduction
 details the scope and structure of the report.
Section
2     Project Background
 summarizes background and scope of the project, site description, project
organization and contact details of key personnel during the reporting period.
Section
3     Monitoring Requirements
 summarizes all monitoring parameters, monitoring locations, monitoring
frequency, duration
and action plan.
Section
4     Monitoring Results
 summarizes the monitoring results obtained in the reporting period.
Section
5     Compliance Audit
 summarizes the auditing
of monitoring results, all exceedances environmental parameters.
Section
6     Complaints, Notification of
summons and Prosecution  summarizes the cumulative statistics on complaints,
notification of summons and prosecution
Section
7     Cumulative Construction
Impact due to the Concurrent Projects  
summarizes the relevant
cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section
8     Conclusion
2.1.1.
“Wan Chai
Development phase II and Central-Wan Chai Bypass and “Central-Wan Chai Bypass
and Island Eastern Corridor Link (hereafter called “the Project  are Designed
Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499)
(EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The key purpose
of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai North
and North Point for construction of the Central-Wan Chai Bypass and Island
Eastern Corridor Link (CWB). Land formed under the project will be developed as
a world-class waterfront promenade joining that at the new Central waterfront
for public enjoyment.
2.1.3.
There is a
compelling and present need for the CWB to provide relief to the very congested
2.2.1.
Design and Construction of Central  Wan Chai Bypass and Island Eastern
Corridor Link under the Project involves the construction and operation of a
trunk road and its road tunnel more than 800m in length between portals that is
shown at Figure 2.1.
2.2.2.
The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai
Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:
 -
A dual
three-lane trunk road, approximately 4.5 km in length, and tunnel approximately
3.7 km in length defined from the connection with the existing Rumsey Street
Flyover in Central, through to a connection with the existing Island Eastern
Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
 -
The
Central Interchange near the Rumsey Street Flyover to provide road connections
to the Central area;
 -
Tunnel
control buildings and ventilation buildings;
 -
Slip
roads to connect the CWB to the local road system in the Wan Chai North and
 -
Associated
road lighting, road signing, traffic control and surveillance system; and
 -
Other
associated works.
2.2.3.
The project also
contains various Schedule 2 DPs that, under the EIAO, require Environmental
Permits (EPs) to be granted by the DEP before they may be either constructed or
operated. Table 2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table 2.1   Schedule 2 Designated Projects under this
Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai
Bypass (CWB) including its road tunnel and slip roads |
Schedule
2, Part I, A.1 and A.7 |
Trunk
road and road tunnel more than 800 m in length |
DP2 |
Road P2
and other roads which are classified as primary/district distributor roads |
Schedule
2, Part I, A.1 |
Primary
/ district distributor roads |
DP3 |
Reclamation
works including associated dredging works |
Schedule
2, Part I, C.1 and C.12 |
Reclamation
more than 5 ha in size and a dredging operation less than 100 m from a
seawater intake point |
DP5 |
Wan Chai
East Sewage Outfall |
Schedule
2, Part I, F.5 and F.6 |
Submarine
sewage pipelines with a total diameter more than 1,200 mm and include a submarine
sewage outfall |
DP6 |
Dredging
for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui |
Schedule
2, Part I, C.12 |
A
dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the
multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be
commenced. Contractors of individual
contracts will be required by the EP holder to apply Further Environmental Permits such that the impact monitoring stations are sub-divided
accordingly to facilitate the implementation of EM&A programme and to
streamline the EM&A reporting for individual FEP holders correspondingly.
2.3.2.
In the reporting period, all the contracts were commenced
and contract no. 04/HY/2006 had been completed. The details of individual
contracts are summarized in Table2.2.
Table 2.2  Details of Individual Contracts under the
Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HY/2009/17 |
Central  
Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central  
Wan Chai Bypass (CWB)  Central Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction
of Bus Terminus near |
DP1 |
September 2010 |
HK/2009/01 |
Wan Chai
Development Phase II  Central  Wan Chai Bypass at |
DP1, DP2 |
25
August 2011 |
HK/2009/02 |
Wan Chai
Development Phase II  Central  Wan Chai Bypass at Wan Chai East(CWB Tunnel)
|
DP1 |
26 April
2011 |
HY/2009/15 |
Central-Wanchai
Bypass  Tunnel ( |
DP1 |
13 July
2011 |
HY/2009/19 |
Central  
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link |
DP1 |
24 March
2011 |
2.4.1.
Civil Engineering and Development Department and Highways Department are
the overall project controllers for the Wan Chai Development Phase II and
Central-Wan Chai Bypass respectively. For the construction phase of the
Project, Project Engineer, Contractor(s), Environmental Team and Independent
Environmental Checker are appointed to manage and control environmental issues.
2.4.2.
The proposed
project organization and lines of communication with respect to environmental
protection works are shown in Figure
2.2. Key personnel and contact particulars are
summarized in Table 2.3:
Table 2.3  Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer
for WDII |
Principal
Resident Engineer |
Mr.
Frankie Fan |
2587
1778 |
2587 1877 |
Engineer
for CWB |
Principal
Resident Engineer |
Mr.
Peter Poon |
3916
1818 |
3529 2829 |
|
Lam Woo &
CO., LTD. |
Contractor
under Contract no. HY/2009/17 |
Project
Manager |
Mr. K.
S. Law |
9090
1378 |
2566 7522 |
Site
Agent |
Mr. Tony
Au |
9725
5874 |
|||
Sub Agent |
Mr.
Johnny Wong |
9725
5870 |
|||
Chiu
Hing Construction & Transportation Co. Ltd. |
Contractor
under Contract no. 04/HY/2006 |
Contract
Manager |
Mr.
Frederick Tsui |
2967
6363 |
2967
6366 |
Senior
Site Agent |
Mr.
Alvin Ma |
2967
6363 |
2967
6366 |
||
Environmental
Consultant |
Mr.
Jimmy Cheng |
2965
0898 |
2556
9172 |
||
Chun Wo
 Leader Joint Venture |
Contractor
under Contract no. HK/2009/01 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
2634 1626 |
Operation Manager |
Mr Lau Yee Ching |
9466 3918 |
|||
Construction Manager |
Mr Jerry Siu |
9493 3664 |
|||
Construction Manager |
Mr Ricky Lai |
9487 6549 |
|||
Construction Manager |
Mr KK Yuen |
3498 1213 |
|||
Environmental Officer (Compliance
Manager) |
Mr Andy Mak |
9103 2370 |
|||
Environmental Supervisor |
Ms Kiwi Chan |
6227 8840 |
|||
Chun Wo
 CRGL Joint Venture |
Contractor
under Contract no. HK/2009/02 |
Project
Manager |
Mr. Chan
Sing Cho |
3658-3002 |
2827 9996 |
Site
Agent |
Mr. Mak
Kam Wing |
3658-3044 |
|||
Deputy
Site Agent |
Mr.
Anthony Wu |
3658-3004 |
|||
Quality
& Environmental Manager |
Mr. C.P.
Ho |
3658-3000 |
|||
Environmental
Officer |
Ms Flora
Ng |
3658-3064 |
|||
Chun Wo
 CRGL Joint Venture |
Contractor
under Contract no. HY/2009/19 |
Project
Manager |
Mr.
Rayland Lee |
3758 8879 |
2570 8013 |
Site
Agent |
Mr. Cheung
Kit Cheung |
6909
1555 |
|||
Environmental
Engineer |
Mr.
Simon Wong |
9281
4346 |
|||
Environmental
Manager / Environmental
Officer |
Mr. M.H.
Isa |
9884
0810 |
|||
Leighton
Contractors ( |
Contractor
under Contract no. HY/2009/18 |
Site
Agent |
Mr.
Brian Gillon |
2214 7700 |
|
Deputy
Site Agent |
Mr.
Desmond Sze |
2214 7703 |
|||
Environmental
Officer |
Mr.
Anfernee Chow |
2214 7721 |
|||
Environmental
Supervisor |
Mr.
Dennis Yu |
2214 7738 |
|||
Environmental
Supervisor |
Ryan
Tsui |
2214 7705 |
|||
|
Contractor
under Contract no. HY/2009/15 |
Project
Manager |
Mr. M Y
Wong |
2823
7879 |
2566 2192 |
Site
Agent |
Mr.
Simon Tang |
3557
6358 |
|||
Head of
construction |
Andrew
Kwan |
3557
6396 |
|||
Environmental
Officer |
Samuel
Tsui |
3557
6347 |
|||
Environmental
Officer |
Daniel
Sin |
3557
6215 |
|||
Environmental
Supervisor |
Kelven
Yip |
3557
6347 |
|||
Environmental
Supervisor |
Tim Fung |
3557
6349 |
|||
|
|
Environmental
Supervisor |
Hilda
Lau |
3557
6378 |
|
ENVIRON
Hong Kong Limited |
Independent Environmental Checker (IEC) |
Independent Environmental Checker (IEC) |
Mr.
David Yeung |
3743
0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.5.1.
Major construction activities for Contract no. HK/2009/17 have been
commenced on 5 October 2010. During this reporting period, the principal work
activities for Contract no. HY/2009/17 are summarized in Table2.4.
Table
2.4   Principal Work Activities for Contract no.
HY/2009/17
June 2011 |
July 2011 |
August 2011 |
Pile
cap construction |
Pile
cap construction |
ELS
works for basement construction for pile cap construction |
2.5.2.
Construction works were completed and a duly
signed report on Completion of Works was issued by the Engineer dated on
1 March 2011. In addition, acknowledge
of FEP surrender was under preparation by the Contractor
2.5.3.
Major construction activities for Contract no. HY/2009/18 have been
commenced on 21 April 2011. During this reporting period, the principal work
activities for Contract no. HY/2009/18 are summarized in Table2.5:
Table 2.5   Principal Work Activities for Contract no.
HY/2009/18
June 2011 |
July 2011 |
August 2011 |
Instrumentation
Manholes and Intake Culvert Survey
Excavation
of trial pit
Hoarding
erection
Tree
transplanting
Installation
of coupler in CR3
Drainage
diversion works
Site
investigation and pre-drilling works
Excavation
in Trough B
Man
Kwong Street Gate 1 & 2 setup
Sheet
piling
Retaining
wall |
Instrumentation
Manholes and Intake Culvert Survey
Excavation
of trial pit
Hoarding
erection
Tree
transplanting
Installation
of coupler in CR3
Drainage
diversion works
Site
investigation and pre-drilling works
Excavation
in Trough B
Man
Kwong Street Gate 1 & 2 setup
Sheet
piling
Guide
wall construction near PTI |
Instrumentation
Manholes and Intake Culvert Survey
Excavation
of trial pit
Hoarding
erection
Tree
transplanting
Installation
of coupler in CR3
Drainage
diversion works
Site
investigation and pre-drilling works
Excavation
in Trough B
Sheet
piling
Guide
wall construction near PTI
Diaphragm
wall
Emergency
exit construction at MTR by-law area |
2.5.4.
Major construction activities for Contract no. HK/2009/01 have been
commenced on 25 August 2011. During this reporting period, the principal work
activities are summarized in Table2.5:
Table 2.5
  Principal Work Activities for Contract
no. HK/2009/01
June 2011 |
July 2011 |
August 2011 |
Only
preparation works was commenced
Pre-drilling
works for SCL Protection Works and CWB.
Timber
scaffolding for subsequent site investigation works for the proposed jet
grouting at HKCEC foundation.
Pre-bored
H piling works for the proposed CWB. |
Only
preparation works was commenced
Pre-drilling
works for SCL Protection Works and CWB.
Site
investigation works for the proposed jet grouting at HKCEC foundation.
Pre-bored
H piling works for the proposed CWB.
Grout
treatment works for proposed diaphragm wall
Demolition
of existing promenade deck |
Pre-drilling
works for SCL Protection Works and CWB.
Pre-bored
H pilling works.
Ground
treatment works for proposed diaphragm wall in SCL Tunnels Protection Works. |
2.5.5.
Major construction activities for Contract no. HK/2009/02 have been
commenced on 26 April 2011. During
this reporting period, the principal work activities are summarized as below:
Table 2.6
  Principal Work Activities for Contract
no. HK/2009/02
June 2011 |
July 2011 |
August 2011 |
Guide
wall construction for diaphragm wall construction
Pre-drilling
for diaphragm wall construction at WCR1 area.
Tunnel
bored pile works at WCR1 area
Diaphragm
wall construction at WCR1 area |
Guide
wall construction for diaphragm wall construction.
Pre-drilling
for diaphragm wall construction at WCR1 area.
Tunnel
bored pile works at WCR1 area.
Diaphragm
wall construction at WCR1 area. |
Tunnel
bored pile works at WCR1 area
Diaphragm
wall construction at WCR1 area |
2.5.6.
Major construction activities for Contract no. HY/2009/15 have been
commenced on 13 July 2011. During this reporting period, the principal work
activities are summarized in Table 2.7:
Table 2.7         Principal
Work Activities for Contract no. HY/2009/15
June 2011 |
July 2011 |
August 2011 |
No major
construction activity was undertaken |
Diaphragm
wall construction at TS1 and TPCWAE |
Diaphragm
wall preparation work at TS1 and TPCWAE
Trial
trench work at |
2.5.7.
Major construction activities for Contract no. HY/2009/19 have been
commenced on March 2011. During this reporting period, the principal work
activities are summarized in Table 2.8:
Table 2.8         Principal
Work Activities for Contract no. HY/2009/19
June 2011 |
July 2011 |
August 2011 |
Steel
fabrication of temporary platform
Erection
of platform to enable marine pre-drilling
Marine
Pre-drilling |
Steel
fabrication of temporary platform
Erection
of platform to enable marine pre-drilling
Marine
Pre-drilling
Trial
pitting at Portion XI |
Steel
fabrication of temporary platform
Erection
of platform to enable marine pre-drilling
Marine
Pre-drilling
Remove
existing dolphin pier |
2.5.8.
Implementation
status of the recommended mitigation measures during this reporting period is
presented in Appendix 2.1.
3.1.1.
The noise
monitoring stations for the Project are listed and shown in Table
3.1 and Figure 3.1.  /span>Appendix
3.1 shows the established
Action/Limit Levels for the monitoring works.
Table 3.1  Noise
Monitoring Station
Station |
Description |
M1a |
Harbour
Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria
Centre |
M5b |
|
M6 |
HK |
M7e |
International
Finance Centre (Eastern End of Podium) |
M7w |
International
Finance Centre (Western End of Podium) |
Real time Noise
Monitoring Stations
3.1.2.
The noise
monitoring stations for the Project are listed and shown in Table 3.2 and
Figure 3.1..
Appendix 3.1 shows the established
Action/Limit Levels for the monitoring works.
Table
3.2  Real
Time Noise
Monitoring Station
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section
Whitefield Depot |
North Point |
RTN2 |
Oil Street Community Liaison
Centre |
Noise Monitoring Parameters, Frequency and Duration
3.1.3.
The construction noise level shall be measured in terms of the
A-weighted equivalent continuous sound pressure level (Leq). Leq
(30 minutes) shall be used as the monitoring parameter for the time period between
0700 and 1900 hours on normal weekdays. For all other time periods, Leq (5
minutes) shall be employed for comparison with the Noise Control
Ordinance (NCO) criteria. Supplementary information for data auditing,
statistical results such as L10 and L90 shall also be
obtained for reference.
3.1.4.
Noise monitoring
shall be carried out at all the designated monitoring stations. The monitoring
frequency shall depend on the scale of the construction activities. The
following is an initialguide on the regular monitoring frequency for each
station on a weekly basis when noise generating activities are underway:
 -
One set of measurements between
0700 and 1900 hours on normal weekdays.
3.1.5.
Real time noise
shall be carried out at the designated monitoring stations. The following is an
initial guide on the regular monitoring frequency for each station on a 24
hours daily basis when noise generating activities are underway:
 -
One set of measurements between
0700 and 1900 hours on normal weekdays.
 -
One set of measurements between 1900
and 2300 hours on normal weekdays and 0700 and 2300 hours on public holidays.
 -
One set of measurements between 2300
and 0700 hours on next day on everyday.
3.1.6.
If construction
works are extended to include works during the hours of 1900  0700 as well as
public holidays and Sundays, additional weekly impact monitoring shall be
carried out during respective restricted hours periods. Applicable permits
under NCO shall be obtained by the Contractor.
Monitoring Equipment
3.1.7.
As referred to
in the Technical Memorandum  issued under the NCO, sound level meters in
compliance with the International Electrotechnical Commission Publications 651:
1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying
out the noise monitoring. Immediately prior to and following each noise
measurement the accuracy of the sound level meter shall be checked using an
acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agree to within 1.0 dB.
3.1.8.
Noise
measurements shall not be made in fog, rain, wind with a steady speed exceeding
5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with
a portable wind speed meter capable of measuring the wind speed in m/s.
3.1.9.
The sound level
meter shall be checked using an acoustic calibrator generating a known sound
pressure level at a known frequency before deployment to the site and during
each site visit. Measurements may be accepted as valid only if the calibration
level from before and after the noise measurement agree to within 1.0 dB.
Air Quality Monitoring Stations
3.2.1.
The air
monitoring stations for the Project are listed and shown in Table
3.2 and Figure 3.1. Appendix 3.1 shows the established
Action/Limit Levels for the monitoring works.
Table 3.2  Air
Monitoring Stations
Station ID |
Monitoring Location |
Description |
CMA1b |
Oil Street Community Liaison Centre |
North Point |
CMA2a |
|
|
CMA3a |
Future CWB site office at Wanchai Waterfront Promenade |
|
CMA4a |
Society for the Prevention of Cruelty to Animals |
Wan Chai |
CMA5a |
Children Playgrounds opposite to |
Wan Chai |
CMA6a |
Future AECOM site office at Work Area |
Wan Chai |
MA1e |
International Finance Centre
(Eastern End of Podium) |
Central |
MA1w |
International Finance Centre
(Western End of Podium) |
Central |
Air Monitoring Parameters, Frequency and Duration
3.2.2.
One-hour and
24-hour TSP levels should be measured to indicate the impacts of construction
dust on air quality. The 24-hour TSP levels shall be measured by following the
standard high volume sampling method as set out in the Title 40 of the Code of
Federal Regulations, Chapter 1 (Part 50), Appendix B.
3.2.3.
All relevant
data including temperature, pressure, weather conditions, elapsed-time meter
reading for the start and stop of the sampler, identification and weight of the
filter paper, and any other local atmospheric factors affecting or affected by
site conditions, etc., shall be recorded down in detail.
3.2.4.
For regular
impact monitoring, the sampling frequency of at least once in every six-days,
shall be strictly observed at all the monitoring stations for 24-hour TSP
monitoring. For 1-hour TSP monitoring, the sampling frequency of at least three
times in every six-days should be undertaken when the highest dust impact occurs.
Sampling Procedure and Monitoring Equipment
3.2.5.
High volume
samplers (HVSs) in compliance with the following specifications shall be used
for carrying out the 1-hour and 24-hour TSP monitoring:
 -
0.6 - 1.7 m3 per minute
adjustable flow range;
 -
Equipped with a timing / control
device with +/- 5 minutes accuracy for 24 hours operation;
 -
Installed with elapsed-time meter
with +/- 2 minutes accuracy for 24 hours operation;
 -
Capable of providing a minimum
exposed area of 406 cm2;
 -
Flow control accuracy: +/- 2.5%
deviation over 24-hour sampling period;
 -
Equipped with a shelter to
protect the filter and sampler;
 -
Incorporated with an electronic
mass flow rate controller or other equivalent devices;
 -
Equipped with a flow recorder for
continuous monitoring;
 -
Provided with a peaked roof
inlet;
 -
Incorporated with a manometer;
 -
Able to hold and seal the filter
paper to the sampler housing at horizontal position;
 -
Easily changeable filter; and
 -
Capable of operating continuously
for a 24-hour period.
3.2.6.
Initial
calibration of dust monitoring equipment shall be conducted upon installation
and thereafter at bi-monthly intervals. The transfer standard shall be
traceable to the internationally recognized primary standard and be calibrated
annually. The concern parties such as IEC shall properly document the
calibration data for future reference. All the data should be converted into
standard temperature and pressure condition.
3.2.7.
Laboratory
Measurement / Analysis
3.2.8.
A clean
laboratory with constant temperature and humidity control, and equipped with necessary
measuring and conditioning instruments to handle the dust samples collected,
shall be available for sample analysis, and equipment calibration and
maintenance. The laboratory should be HOKLAS accredited.
3.2.9.
Filter paper of
size 8" x 10" shall be labeled before sampling. It shall be a clean
filter paper with no pinholes, and shall be conditioned in a
humidity-controlled chamber for over 24-hours and be pre-weighed before use for
the sampling.
3.2.10. After sampling, the filter paper loaded with dust
shall be kept in a clean and tightly sealed plastic bag. The filter paper shall
then be returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
readout down to 0.1 mg. The balance shall be regularly calibrated against a
traceable standard.
3.2.11. All the collected samples shall be kept in a good
condition for 6 months before disposal.
4.0.1.
The
environmental monitoring will be implemented based on the division of works areas
of each designed project managed under different contracts with separate FEP
applied by individual contractors. 
Overall layout showing work areas of various contracts, latest status of
work commencement and monitoring stations is shown in Figure
2.1 and Figure 3.1. The monitoring results
are presented in according to the Individual Contract(s).
4.0.2.
In the reporting
period, the concurrent contracts are as follows:
Contract no. HY/2009/15  
Central-Wanchai Bypass  Tunnel (
Contract no. HY/2009/17  Central
 Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works under
FEP-03/364/2009
Contract no. HY/2009/18  Central
 Wan Chai Bypass (CWB)  Central Interchange under FEP-05/364/2009/A
Contract no. HY/2009/19  Central
 Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009
Contract no. HK/2009/01  Wan
Chai Development Phase II  Central  Wan Chai Bypass at
Contract no. HK/2009/02 Wan Chai
Development Phase II  Central-Wan Chai Bypass at Wan Chai East
Contract no. HY/2009/17 –Central - Wan Chai Bypass (CWB) at FEHD
Whitfield Depot - Advanced piling works under FEP-03/364/2009
4.1.1.
The proposed
division of noise monitoring stations for Contract no. HY/2009/17 is summarized
in Table
4.1 below:
Table
4.1   Noise
Monitoring Stations for
Contract no.  /span>HY/2009/17
Station |
Description |
M4b |
Victoria
Centre |
4.1.2.
No action and
limit exceedance was recorded during day time and restricted hour period in the
reporting period. Noise monitoring results measured in this reporting period
are reviewed and summarized. Noise monitoring results measured in this
reporting period are reviewed and summarized. 
Details of graphical presentation can be referred in Appendix 4.1. 
Contract no. 04/HY/2006  /span> Reconstruction
of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A and
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB)  Central Interchange
under FEP-05/364/2009/A
4.1.3.
Construction
activity under contract no. 04/HY/2006 was completed, no noise monitoring for
the contract was conducted in this reporting period.
4.1.4.
Noise monitoring
for the Central Interchange works under contract no. HY/2009/18 was commenced
on 22 April 2011.The proposed division of noise monitoring stations for
Contract no. HY/2009/18 are summarized in Table 4.2 below.
Table 4.2   Noise
Monitoring Station for Contract
no. HY/2009/18
Station |
Description |
M7e |
International
Finance Centre (Eastern End of Podium) |
M7w |
International
Finance Centre (Western End of Podium) |
4.1.5.
A limit level
exceedance was recorded during day time on 19 July
2011. After checking contractor’s work schedules and investigation found
that sheet piling works were conducted during monitoring.
4.1.6.
One action level
exceedance was recorded due to a recorded noise
complaint on 30 July 2011 for the contract of HY/2009/18 and no limit
level exceedance was recorded during day time and restricted hour period
4.1.7.
Noise monitoring results measured in this reporting
period are reviewed and summarized. 
Details of noise monitoring results and graphical presentation can be
referred in Appendix 4.1 and the complaints can be referred in
Appendix 6.1. Details
of the Notification of Exceedance can be referred in
Appendix 6.2.
Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under
FEP-02/364/2009 and Contract no. HK/2009/02 - Wan Chai Development Phase II -
Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
4.1.8.
The commencement
of construction works for Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011 and HK/2009/02 under FEP-01/364/2009 is on 26
April 2011.The proposed division of air monitoring stations are summarized in Table
4.3 below.
Table 4.3   Noise Monitoring Stations for
Contract
nos. HK/2009/01 and HK/2009/02
Station |
Description |
M1a |
Harbour
Road Sports Centre |
4.1.9.
Only daytime and
evening period noise monitoring was conducted at the Harbour Road Sport Centre for
the contractor HK/2009/01 was conducted in the reporting period.
4.1.10.
Four limit level
exceedances were recorded at M1a - Harbour Road Sports Centre on 2, 8, 14 and 24 June 2011 during restricted hour. Major
noise source was contributed from
4.1.11.
Five limit level exceedances were recorded at M1a -
Harbour Road Sports Centre on 29 June, 5, 13,
19 and 25 July 2011 during restricted hour. Major noise source was contributed from
4.1.12.
One action level and one limit level exceedance was
recorded at M1a  Harbour Road Sports Centre due to a recorded
noise complaint on 26 August 2011 for the contractor of HK/2009/01 and on 22 August 2011 during restricted hour for the contractor of HK/2009/02. Major noise source was contributed from
4.1.13.
Noise monitoring results measured in this reporting
period are reviewed and summarized. 
Details of noise monitoring results and graphical presentation can be
referred in Appendix 4.1 and the complaints can be referred in
Appendix 6.1. Details
of the Notification of Exceedance can be referred in
Appendix 6.2.
Contract no. HY/2009/15 - Central-Wanchai
Bypass  Tunnel (
4.1.14.
The commencement
of construction works for Contract no. HY/2009/15 under FEP-06/364/2009/A was
on 13 July 2011. Noise monitoring
was commenced on 13 July 2011. The proposed division of noise
monitoring stations are summarized in in Table 4.4 below.
Table 4.4   Noise
Monitoring Station for Contract nos. HY/2009/15
Station |
Description |
M2b |
Noon Gun
Area |
M3a |
Tung Lo
Wan Fire Station |
4.1.15. Four Action level exceedances and no
limit level exceedance were recorded during day time
and restricted hour period due to four recorded noise
complaints on 23 and 27 July 2011
4.1.16. One action level exceedance and no limit
level exceedance was recorded during day time and restricted hour period due to a recorded noise complaint on 7 August 2011
4.1.17.
Details of noise monitoring results and graphical
presentation can be referred in
Appendix 4.1 and the complaints can be referred in
Appendix 6.1. 
4.1.18. Noise monitoring for the tunnel works under
contract no. HY/2009/19 was commenced on 24 April 2011. The proposed division
of noise monitoring stations are summarized in Table 4.5 below.
Table
4.5   Noise
Monitoring Stations for Contract
no. HY/2009/19
Station |
Description |
M3a |
Tung Lo
Wan Fire Station |
M4b |
Victoria
Centre |
M5b |
|
M6 |
HK |
4.1.19.
No action
level and three limit level exceedances were recorded at M6 - HK Baptist Church Henrietta Secondary School on 2, 8, 14 June 2011 during day time of examination period. After checking
contractor’s work schedules and investigation found that only minor works was
conducted during monitoring and traffic noises in IECL as major noise sources contributed
in the noise monitoring. It was considered the exceedances were not related to
the Project.
4.1.20.
No action level
and one limit level exceedance was recorded at M6 - HK Baptist Church Henrietta
Secondary School on 13 July 2011 during day time period.
After checking contractor’s work schedules and investigation found that no
major works were conducted during monitoring and traffic noises in IECL as
major noise sources contributed in the noise monitoring. It was considered the
exceedances were not related to the Project.
4.1.21.
No
action level and two limit level exceedances were recorded at M6  HK Baptist Church Henrietta Secondary School on 10 and 16 August 2011 during day time period.
After checking contractor’s work schedules and investigation found that traffic
noises in IECL as major noise sources contributed in the noise monitoring. It
was considered the exceedances were not related to the project.
4.1.22. Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring
results and graphical presentation can be referred in
Appendix 4.1 and the
Notification of Exceedance can be referred in Appendix 6.2.
4.2.1.
No construction
activity with valid Construction Noise Permit was conducted during night time period
(2300 to 0700) in this reporting month.
4.2.2.
Calibration and
maintenance of real time noise meters were conducted at RTN1 on 5 July 2011
from 0900 to 0930 hours and at RTN2 on 7 July 2011 from 1600 to 1630 hours,
respectively. No monitoring was conducted during the mentioned periods.
Contract no. HY/2009/17 –Central - Wan Chai Bypass (CWB) at FEHD Whitfield
Depot - Advanced piling works under FEP-03/364/2009 and
Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section)
and Island Eastern Corridor Link under
FEP-07/364/2009/A
4.2.3.
The proposed
division of real time noise monitoring stations are summarized in Table 4.6
below. Real time noise monitoring for the piling works under contract no.
HY/2009/17 was commenced on 5 October 2010.
Table
4.6  Real
Time Noise Monitoring Station for Contract
no. HY/2009/17
Location
ID |
District |
Description |
RTN1 |
Tin
Hau |
FEHD Hong Kong Transport Section
Whitefield Depot |
Real time noise
monitoring results and graphical presentation during night time period are for
information only.
4.2.4.
No project related action and limit level exceedance were recorded in
the reporting period. Real time noise monitoring
results measured in this reporting period are reviewed and summarized. Details of real time noise monitoring results and
graphical presentation can be referred to
Appendix 4.2
4.2.5.
The proposed
division of noise monitoring stations are summarized in Table 4.7
below. Real time noise monitoring for major construction works under contract
no. HY/2009/19 was commenced on 24 April 2011.
Table
4.7  Real
Time Noise Monitoring Stations for Contract
no. HY/2009/19
Location
ID |
District |
Description |
RTN1 |
Tin
Hau |
FEHD Hong Kong Transport Section
Whitefield Depot |
RTN2 |
North Point |
|
Real time noise
monitoring results and graphical presentation during night time period are for
information only.
4.2.6.
No project related action and limit level exceedance were recorded in
the reporting period. Real time noise monitoring
results measured in this reporting period are reviewed and summarized. Details of
real time noise monitoring results and graphical presentation can be referred
to
Appendix 4.2
4.3.1
Due to lack of electricity supply at station MA1w, 24 hr and 1 hr TSP
were rescheduled to conduct on 22 June 2011 and 23 June 2011, respectively.
4.3.2
Due to lack of electricity supply at station MA1w and CMA3a, both 24
hr-TSPs were rescheduled to conduct on 27 July 2011.
4.3.3
Due to lack of electricity supply at station CMA1b, CMA2a CMA4a, the 24
hr-TSP monitoring were rescheduled to conduct on 2 August 2011, 19 August 2011,
8 August 2011 and 25 August 2011.
Contract no. HY/2009/17 –Central - Wan Chai Bypass (CWB) at FEHD
Whitfield Depot - Advanced piling works under
FEP-03/364/2009
4.3.1.
The proposed
division of air monitoring stations are summarized in Table 4.8 below. Air
monitoring for the piling works under contract no. HY/2009/17 was commenced on
8 October 2010.
Table
4.8   Air Monitoring Stations for Contract
no. HY/2009/17
Station |
Description |
CMA2a |
|
4.3.2.
No exceedance
was recorded in the reporting period. Air quality monitoring results measured
in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 4.3. 
Contract no. 04/HY/2006  /span>
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A and
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB)  Central Interchange
under FEP-05/364/2009/A
4.3.3.
The proposed
division of air monitoring stations are summarized in Table 4.9 below.
Table
4.97 Air Monitoring Stations for Contract
no. 04/HY/2006
and HY/2009/18
Station |
Description |
MA1e |
International
Finance Centre (Eastern End of Podium) |
MA1w |
International
Finance Centre (Western End of Podium) |
4.3.4.
Construction
activity under contract no. 04/HY/2006 was completed, no air monitoring for the
contract was conducted in this reporting period.
4.3.5.
Air monitoring
for the Central Interchange works under contract no. HY/2009/18 was commenced
on 21 April 2011.
4.3.6.
No exceedance
was recorded in the reporting period. Air quality monitoring results measured
in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in
Appendix 4.3. 
Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at
4.3.7.
The commencement
of construction works for Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011. The proposed division of air
monitoring stations are summarized in Table 4.10 below.
Table
4.10 Air Monitoring Stations for Contract
no. HK/2009/01
Station |
Description |
CMA5a |
Children
Playgrounds opposite to |
4.3.8.
Air quality
monitoring was commenced on 25 August 2011. Only 1-hr TSP monitoring was
conducted in the reporting period.
4.3.9.
No exceedance
was recorded in the reporting period. Air quality monitoring results measured
in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in
Appendix 4.3. 
Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
Table 4.11 Air Monitoring Station for Contract
no. HK/2009/02
Station |
Description |
CMA4a |
Society
for the Prevention of Cruelty to Animals |
4.3.11.
No exceedance
was recorded in the reporting period. Air quality monitoring results measured
in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in
Appendix 4.3. 
Contract no. HY/2009/15 - Central-Wanchai Bypass
 Tunnel (
4.3.12. The commencement of construction works for Contract
no. HY/2009/15 under FEP-06/364/2009/A was on 13 July 2011. The proposed division of air monitoring
stations are summarized in Table 4.12 below.
Table 4.12
Air
Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB site
office at Wanchai Waterfront Promenade |
4.3.13.
No exceedance
was recorded in the reporting period. Air quality monitoring results measured
in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 4.3. 
Contract no. HY/2009/19 - Central
- Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
4.3.14.
Air monitoring
for the tunnel works was commenced on 26 April 2011 for Contract no. HY/2009/19
under FEP-07/364/2009/A. The proposed
division of air monitoring stations are summarized in Table 4.13 below.
Table 4.13 Air
Monitoring Stations for Contract
no. HY/2009/19
Station |
Description |
CMA1b |
Oil St
Community Liaison Centre |
CMA2a |
|
4.3.15.
No exceedance
was recorded in the reporting period. Air quality monitoring results measured
in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 4.3. 
Contract no. HY/2009/17 –Central - Wan Chai Bypass
(CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009
4.4.1.
No inert C&D
waste was recycled in the reporting period. Details of the waste flow table are
summarized in Table 4.14
Table
4.14 Details
of Waste Disposal for
Contract no.
HY/2009/17
Waste
Type |
Quantity this quarter, m3 |
Cumulative Quantity-to-Date, m3 |
Disposal / Dumping Grounds |
Inert C&D materials disposed |
NIL |
NIL |
N/A |
Inert C&D materials recycled |
N/A |
||
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
N/A |
N/A |
N/A |
Contract no. 04/HY/2006  /span> Reconstruction
of Bus Terminus near Man Yiu Street and Man Kwong Street under
FEP-04/364/2009/A
4.4.2.
No inert C&D
waste was disposed of in this reporting period. Details of the waste flow table
are summarized in Table 4.15.
Table
4.15 Details
of Waste Disposal for Contract
no. 04/HY/2006
Inert C&D materials disposed |
NIL |
1288.5 |
Chai Wan and T.K.O. 137 |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
Contract nos. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at
4.4.3.
Inert and
non-inert C&D waste was disposed of in this reporting period. Details of
the waste flow table are summarized in Table 4.16.
Table 4.16 Details of Waste Disposal for Contract no. HK/2009/01
Inert C&D materials disposed |
206.67 |
206.67 |
TKO137 |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
35.92 |
35.92 |
SENT Landfill |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
4.4.4.
Inert C&D and
chemical waste were disposed of in this reporting period. Details of the waste
flow table are summarized in Table 4.17.
Table 4.17 Details of Waste Disposal for Contract no.
HK/2009/02
Inert C&D materials disposed |
29,259 |
29,259 |
TM 38 |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
NIL |
NIL |
SENT Landfill |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
1,104 |
1,104 |
N/A |
Contract no. HY/2009/18 -
Central - Wan Chai Bypass (CWB)  Central Interchange under FEP-05/364/2009/A
4.4.5.
Inert and non-inert
C&D waste was disposed of in this reporting period. Details of the waste
flow table are summarized in Table 4.18.
Table
4.18 Details
of Waste Disposal for Contract no. HY/2009/18
Inert C&D materials disposed |
2013.2 |
T.K.O. 137 |
|
Inert C&D materials recycled |
NIL |
N/A |
|
Non-inert C&D materials disposed |
16.7 |
SENT Landfill |
|
Non-inert C&D materials recycled |
NIL |
N/A |
|
Chemical waste disposed |
NIL |
N/A |
Contract no. HY/2009/15 - Central-Wanchai
Bypass  Tunnel (
4.4.6.
Inert and non-inert
C&D waste was disposed of in this reporting period. Details of the waste flow
table are summarized in Table 4.19.
Table 4.19 Details
of Waste Disposal for Contract no. HY/2009/15
Inert C&D materials disposed |
1,952 |
1,952 |
Tuen Mun Area 38 |
Inert C&D materials recycled |
29 |
29 |
N/A |
Non-inert C&D materials disposed |
38.1 |
38.1 |
SENT Landfill |
Non-inert C&D materials recycled |
61.3 |
61.3 |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
4.4.7.
No inert and non-inert
C&D waste was disposed of in this reporting period. Details of the waste
flow table are summarized in Table 5.20.
Table
5.20 Details
of Waste Disposal for Contract no. HY/2009/19
Inert C&D materials disposed |
NIL |
NIL |
N/A |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
1.805 |
1.805 |
SENT Landfill |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
5.0.1.
The Event Action
Plan for construction noise and air quality are presented in
Appendix 5.1.
Contract
no. HY/2009/17  Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot -
Advanced piling works under FEP-03/364/2009
5.1.1.
No exceedance was recorded in the reporting period.
Contract no. 04/HY/2006  /span> Reconstruction
of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A
5.1.2.
No noise monitoring was undertaken in the reporting period.
Contract no. HY/2009/18 - Central - Wan Chai
Bypass (CWB)  Central Interchange under FEP-05/364/2009/A
5.1.3.
A limit level exceedance was recorded during day time on 19 July 2011 in
the reporting month. After checking contractor’s work schedules and investigation
found that sheet piling works were conducted during monitoring.
5.1.4.
One action level and no limit level exceedance was recorded due to a
recorded noise complaint on 30 July 2011
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at
5.1.5.
No noise monitoring was undertaken in the reporting period.
5.1.6.
One action level
exceedance was recorded at M1a  Harbour Road Sports Centre due to recorded noise complaint on 26 August 2011.
Contract nos. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East(CWB Tunnel)
5.1.7.
Four limit level and no action level exceedances were recorded at M1a -
Harbour Road Sports Centre on 2, 8,
14 and 24 June 2011 during restricted hour. Investigation found that major traffic noise was
contributed in the noise monitoring and not related
to the Project.
5.1.8.
Five limit level and no action level exceedances were recorded at M1a -
Harbour Road Sports Centre on 29
June, 5, 13, 19 and 25 July 2011 during restricted hour. Investigation found that major traffic noise was
contributed in the noise monitoring and not related
to the Project.
5.1.9.
One limit level and no action level exceedance were recorded at M1a  
Harbour Road Sports Centre on 22
August 2011 during restricted hour. Investigation found that major traffic noise was
contributed in the noise monitoring and not related
to the Project.
Contract no. HY/2009/15 - Central-Wanchai
Bypass  Tunnel (
5.1.10. No limit level and four Action level
exceedances and no limit level exceedance were recorded during day time and restricted hour period due to four recorded noise complaints on 23 and 27 July 2011
in the reporting month.
5.1.11.
No
limit level and one action level exceedance and no limit level exceedance was
recorded during day time
and restricted hour period due to a recorded noise
complaint on 7 August 2011 in the reporting month.
Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
5.1.12. Three limit level exceedances
were recorded at M6 - HK Baptist Church Henrietta Secondary School on 2, 8, 14 June 2011 during day time of
examination period. After checking contractor’s work schedules and investigation found that only
minor works was conducted during monitoring and traffic noises in IECL as major
noise sources contributed in the noise monitoring. It was considered the
exceedances were not related to the Project.
5.1.13. A limit level exceedance was
recorded at M6 - HK Baptist Church Henrietta Secondary School on 13 July 2011 during day time period. After checking contractor’s work schedules and investigation
found that no major construction works were conducted during monitoring and traffic
noises in IECL as major noise sources contributed in the noise monitoring. It
was considered the exceedance was not related to the Project.
5.1.14. Two limit level and no action level exceedances were recorded at M6
 HK Baptist Church Henrietta Secondary School on 10 and 16 August 2011 during day time period. After checking contractor’s work
schedules and investigation found that no major construction works was
conducted during monitoring on 10 August 2011 and per drilling work was
conducted with noise barrier deployed and traffic noises in IECL as major noise
sources contributed in the noise monitoring. It was considered the exceedance
was not related to the Project.
Contract no. HY/2009/17  Central - Wan Chai Bypass
(CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009
5.2.1.
No exceedance was recorded in the reporting period.
Contract no. 04/HY/2006  /span> Reconstruction of Bus Terminus near Man Yiu
Street and Man Kwong Street under FEP-04/364/2009/A
5.1.15.
No air monitoring was undertaken in the reporting period.
Contract no. HY/2009/18 - Central - Wan Chai
Bypass (CWB)  Central Interchange under FEP-05/364/2009/A
5.2.2.
No exceedance
was recorded in the reporting period.
Contract nos. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at
5.2.3.
No exceedance
was recorded in the reporting period.
Contract nos. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East(CWB Tunnel)
5.2.4.
No exceedance
was recorded in the reporting period.
Contract no. HY/2009/15 - Central-Wanchai
Bypass  Tunnel (
5.2.5.
No exceedance
was recorded in the reporting period.
Contract no. HY/2009/19 - Central
- Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
5.2.1
No exceedance
was recorded in the reporting period.
Contract no. HY/2009/17  Central
- Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009
5.3.1
No exceedance
was recorded in the reporting period.
Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
5.3.2
No exceedance
was recorded in the reporting period.
5.4.1.
There was no
non-compliance from the site audits in the reporting period. During
environmental site inspections conducted during the reporting quarter, minor
deficiencies were noted. However, the
Contractor rectified all deficiencies after receipt of notification.
5.5.1
There was exceedance
of noise level recorded during day time on 19 July 2011 at M7w that was
considered in relation to the sheeting piling during monitoring.
5.6.1
According to the
Event and Action Plan stated in Appendix 6.1, repeated measurement for noise
monitoring station (M7w) would be conducted immediately once Limit Level
exceedance recorded in relation to Contract no. HY/2009/18, site investigations
would be arranged accordingly to observe and record the sources of the
exceedance(s). Sheet piling was suspended from 19 July 2011 to 21 July 2011 and
mitigation measures subjected to the works were recommended to the contractor
to implement. An additional monitoring was conducted on 21 July 2011 to
investigation the effectiveness of the mitigation measures. No exceedance was
recorded during the monitoring.
5.6.2
Further
investigation of the effectiveness of the mitigation measures of the sheet
piling works was conducted on 4 August 2011 during day time noise monitoring at
the same location. No exceedance was recorded.
6.0.1.
No complaint received in June 2011.
6.0.2.
There are four complaints were received in July 2011.
6.0.3.
A noise impact
complaint ICC no. 1  03887687 was received by ET on 28 July 2011. It was complained
by a resident Ms. Law at Block 1, Victoria Centre on 23 July 2011. She
concerned that Highways Department published a notice in their Management
Office about construction works will be conducted at 0700 hours during July to
December 2011 including Saturday, Sunday and public holiday. RSS confirmed that
the notice was prepared by Victoria Centre‘s Management office to their
resident and advice was only given on the extension construction works to
7am-9pm Monday to Saturday except Public Holidays and Sundays. As a mitigation measure
to minimize the noise nuisance in the vicinity of the residents, rock breaking
activities will be started at 8am and is expected to be completed by mid-August
2011. The complainant was satisfied with the arrangement and no further
complaint was received after proposed measures. Further investigation revealed
that no construction noise exceedance was recorded at noise monitoring station
of Victoria Centre on 19 and 25 July 2011 during daytime period while breaking
and excavation works were undertaken during monitoring. In conclusion, it was related
to the construction works under Contract HY/2009/15 and mitigation measure was provided.
No further complaint from complainant was received after proposed the
mitigation measure.
6.0.4.
A noise impact
complaint ICC no. 1  04616162 was received by ET on 28 July 2011. It was complained
by Mr. Law from Victoria Centre Management Office on 27 July 2011 regarding construction
noise generated by the construction operations of Central-Wanchai Bypass at noon
rather than in morning at 7am. RSS confirmed to start the rock breaking
activities at 8m as a mitigation measure to minimize the noise nuisance in the
vicinity of the residents. Further investigation revealed that no construction
noise exceedance was recorded at noise monitoring station of Victoria Centre on
25 July and 4 August 2011 during daytime period while breaking and excavation
works were undertaken during monitoring. In conclusion, it was related to the
construction works under Contract HY/2009/15 and mitigation measure was provided.
No further complaint from complainant was received after proposed the
mitigation measure.
6.0.5.
A noise impact
complaint ICC no. 1-304013959 was received by ET on 8 August 2011. It was complained
by Ms. Yau from Block 2 at Victoria Centre on 23 July 2011 regarding construction
noise generated by the construction operations of Central-Wanchai Bypass at noon
rather than in morning at 7am. RSS confirmed to start the rock breaking
activities at 8m as a mitigation measure to minimize the noise nuisance in the
vicinity of the residents. Further investigation revealed that no construction
noise exceedance was recorded at noise monitoring station of Victoria Centre on
19 and 25 July 2011 during daytime period while breaking and excavation works
were undertaken during monitoring. In conclusion, it was related to the
construction works under Contract HY/2009/15 and mitigation measure was provided.
No further complaint from complainant was received after proposed the
mitigation measure.
6.0.6.
A noise impact
complaint ICC no.1-304615409 by Ms. Chiu on 27 July 2011 referred by RSS to
Environmental Team on 28 July 2011. A further complaint was made by her on 7
August 2011. Details shall be referred to section 6.0.9.
6.0.7.
There were five complaints received in August 2011.
6.0.8.
A noise impact
complaint ICC complaint no.1-305074350 by Mr. TSUI on 30 July 2011 referred by
RSS to Environmental
Team on 1 August 2011. He complained on the construction noise generated by the
construction operations of Central-Interchange which is near the spa room. In
addition, Mr. TSUI enquired the commencement
time of the construction on Saturday. RSS confirmed the noisiest plant from 2
vibratory hammers has been conducted in alternating manner for sheet piling
works to minimize noise due to current plant operation as one of the mitigation
measures implemented by contractor for noise reduction. Further investigation
revealed that no construction noise exceedance was recorded at noise monitoring
station of IFC Western End of Podium on 25 July 2011 and 4 August 2011 during
daytime period while sheet piling and excavation works were undertaken during
monitoring. No further complaint from complainant was received after the
liaison. In conclusion, it was related to the construction works under Contract
HY/2009/18 and mitigation measure was provided.
6.0.9.
A noise impact
complaint ICC complaint no.1-304615409 by Ms. Chiu on 27 July 2011 referred by
RSS to Environmental Team on 28 July 2011. She complained on the construction
noise generated from the construction operations of Central-Wanchai Bypass in
morning at 7am rather than at noon. RSS confirmed to start the rock breaking
activities at 8m as a mitigation measure to minimize the noise nuisance in the
vicinity of the residents. Further investigation revealed that no construction noise exceedance was recorded at noise monitoring
station of Victoria Centre on 4 and 10 August 2011 during daytime period while breaking
and excavation works were undertaken during monitoring. However, complainant did not satisfy with the
response on the noise nuisance from the rock-breaking during morning in front
of Victoria Centre and then further complained via 1823 on 7 August 2011. Highways contacted the complainant on 15 August 2011
that the noisy rock breaking operation had been completed. No further
complaint from complainant was received after the liaison. In conclusion, it was
related to the construction works under Contract HY/2009/15 and mitigation
measure was provided.
6.0.10. An ICC complaint no. 1  306740207 was received on
10 August 2011. The complainant, Mr. Yip complained that muddy
water was discharged from work site to the seafront near
6.0.11. A visual complaint, ICC no. 1-307657681, was
received on 23 August 2011. The complainant from
6.0.12.
A noise complaint was
raised by Grand Hyatt and a complainant via 1823 on 26 August 2011 regarding construction
noise and vibration nuisance generated from the works at
6.0.13. Investigation revealed that the erected noise
barriers (
6.0.14. The details of cumulative complaint log and summary
of complaints are presented in
Appendix 6.1.
6.0.15. No notification
of summons or prosecution was received in the reporting period. Cumulative statistic on complaints and successful
prosecutions are summarized in Table 6.1 and Table 6.2 respectively.
Table 6.1  Cumulative
Statistics on Complaints
Reporting Period |
No. of Complaints |
Commencement of Works
up to last reporting quarter |
0 |
June 2011  August 2011 |
9 |
Project-to-Date |
9 |
Table 6.2  Cumulative
Statistics on Successful Prosecutions
Environmental
Parameters |
Cumulative
No. Brought Forward |
No. of
Successful Prosecutions this quarter (Offence Date) |
Cumulative
No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
7.0.1.
According to
Condition 3.4 of the EP-364/2009/A, this section addresses the relevant
cumulative construction impact due to the concurrent activities of the current
projects including the Central Reclamation Phase III (CRIII), Wan Chai
Development Phase II (WWDII), Central-WanChai Bypass (CWB) and Island Eastern
Corridor Link projects (IECL).
7.0.2.
According to the
construction programme of Wan Chai Development Phase II, Central-Wan Chai
Bypass and Island Eastern Corridor Link projects, the major construction
activity under Wan Chai Development Phase II was the seawall block construction
at TCBR1w, reclamation works of HKCEC Water Channel, dredging for submarine
outfall pipe, Advanced piling works at FEHD Whitfield Depot, Central
Interchange, cross-harbour water mains and marine pre-drilling in the reporting
month. The major environmental impact was water quality impact at
7.0.3.
The major environmental
impacts generated from advanced
piling works at FEHD Whitfield Depot were undertaken and sheet piling, pre-drilling and sheet piling works at Central
and tunnel works at Wan Chai East
in the reporting period. No significant air impact was anticipated in the
reporting month. However, one Limit Level exceedance was recorded during
construction noise monitoring in relation to Contract no. HY/2009/18 for the
project Central-Wan Chai Bypass in July 2011. Mitigation measures were
implemented shortly by the Contractor according to the Event and Action and no
further exceedance was recorded afterwards. Thus, it is evaluated that the
cumulative construction impact from the concurrent projects including Wan Chai
Development Phase II was mainly insignificant.
8.0.1.
The EM&A
programme was carried out in accordance with the EM&A Manual requirements,
minor alterations to the programme proposed were made in response to changing
circumstances.
8.0.2.
One project
related limit level exceedance at noise monitoring recorded in 19 July 2011, and
no non-compliances were noted and no prosecutions were received during the
reporting quarter.
8.0.3.
No exceedance was recorded in air and real time noise monitoring.
8.0.4.
Four
limit level exceedances were recorded at M1a
- Harbour Road Sports Centre on 2, 8, 14 and 24 June 2011 during restricted hour and three
limit level exceedances were recorded at M6 - HK Baptist Church Henrietta Secondary School on 2, 8, 14 June 2011 during day time of examination period. The limit exceedances were considered not related
to project.
8.0.5.
Five
limit level exceedances were recorded at M1a - Harbour Road Sports Centre on 29
June, 5, 13, 19 and 25 July 2011 during restricted hour; a limit level
exceedance was recorded at M6 - HK Baptist Church Henrietta Secondary School on 13 July 2011
during day time. The limit level exceedances were considered not
related to project. Also,
four Action levels were recorded due to four recorded noise complaints on 23
and 27 July 2011.
8.0.6.
One
limit level exceedance was recorded at M1a - Harbour Road Sports Centre on 22
August 2011 during restricted hour. Two limit level exceedances were
recorded at M6 - HK Baptist Church Henrietta Secondary School on 10 & 16 August 2011
during day time. The limit level exceedances were considered not
related to project. Also,
three Action levels were recorded due to three recorded noise complaints on 30
July, 7 and 26 August 2011.
8.0.7.
Nine complaints were recorded on 23 July, 27 July 2011, 30 July, 7, 10, 17 and 26 August 2011. No further complaint was received after follow-up
action and investigation.
8.0.8.
Construction works were completed and a duly signed report on Completion
of Works was issued by the Engineer dated on 1 March 2011. In addition, acknowledge of FEP surrender was
under preparation by the Contractor
8.0.9.
The
construction programmes of individual contracts are provided in
Appendix 8.1.