Contract
No: HK/2011/07 Wanchai Development Phase II and Central Wanchai
Bypass Sampling, Field Measurement and
Testing Work (Stage 2) Environmental
Permit no. EP-364/2009/A, Further Evironmental permit nos. fep-01/364/2009,
fep-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a and FEp-07/364/2009/a Quarterly Environmental Monitoring
and Audit Report
- March to May 2012 -
|
CLIENTS: |
|
Civil
Engineering and Development Department and Highways
Department |
Lam Geotechnics Limited 11/F Centre
Point 181-185 Gloucester Road, Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED by: |
|
                         Raymond Dai Environmental Team Leader |
|
DATE: |
|
21 June 2012 |
1.1    Scope
of the Report
1.2    Structure
of the Report
2.   Project
Background
2.1    Background
2.2    Scope
of the Project and Site Description.
2.3    Division
of the Project Responsibility
2.4    Project
Organization and Contact Personnel
2.5    Principal
Work and Activities
3.   Monitoring
Requirements
3.1.    Noise
Monitoring
3.2.    Air
Monitoring
4.   Monitoring
Results
4.1.    Noise
Monitoring Results
4.2.    Real Time Noise
Monitoring Results
4.3.    Air Monitoring
Results
4.4.    Waste
Monitoring Results
5.1.    Noise
Monitoring
5.2.    Air
Monitoring
5.3.    Site
Audit
5.4.    Review
of the Reasons for and the Implications of Non-compliance
5.5.    Summary
of action taken in the event of and follow-up on non-compliance
6.   Complaints,
Notification of Summons and Prosecution
7.   Cumulative
Construction Impact due to the Concurrent Projects
lIST
OF TABLES
Table I      Principal Work Activities for Contract no.
HY/2009/17
Table II     Principal Work Activities for Contract no. HY/2009/18
Table III     Principal Work Activities for Contract no. HK/2009/01
Table IV     Principal Work Activities for Contract no. HK/2009/02
Table V     Principal Work Activities for Contract no. HY/2009/15
Table VI     Principal Work Activities for Contract no. HY/2009/19
Table 2.1    Schedule 2 Designated Projects under this Project
Table 2.2   Details of Individual Contracts under the Project
Table 2.3   Contact Details of Key Personnel
Table 2.4    Principal Work Activities for Contract no. HY/2009/17
Table 2.5    Principal Work Activities for Contract no. HY/2009/18
Table 2.6    Principal Work Activities for Contract no. HK/2009/01
Table 2.7    Principal Work Activities for Contract no. HK/2009/02
Table 2.8    Principal Work Activities for Contract no. HY/2009/15
Table 2.9    Principal Work Activities for Contract no. HY/2009/19
Table 3.1   Noise Monitoring Station
Table 3.2   Real Time Noise Monitoring Station
Table 3.3   Air Monitoring Stations
Table 4.1    Noise Monitoring Stations for Contract no. HY/2009/17
Table 4.2    Noise Monitoring Station for Contract no. HY/2009/18
Table 4.3    Noise Monitoring Stations for Contract nos. HK/2009/01 and
HK/2009/02
Table 4.4    Noise Monitoring Station for Contract nos. HY/2009/15
Table 4.5    Noise Monitoring Stations for Contract no. HY/2009/19
Table 4.6   Real Time Noise Monitoring Station for Contract no.
HY/2009/17
Table 4.7   Real Time Noise Monitoring Stations for Contract no.
HY/2009/19
Table 4.8    Air Monitoring Stations for Contract no. HY/2009/17
Table 4.7    Air Monitoring Stations for Contract no. HY/2009/18
Table 4.10   Air Monitoring Stations for Contract no. HK/2009/01
Table 4.11   Air Monitoring Station for Contract no. HK/2009/02
Table 4.12   Air Monitoring Station for Contract no. HY/2009/15
Table 4.13   Air Monitoring Stations for Contract no. HY/2009/19
Table 4.14  Details of Waste Disposal for Contract no. HY/2009/17
Table 4.15  Details of Waste Disposal for Contract no. HK/2009/01
Table 4.16  Details of Waste Disposal for Contract no. HK/2009/02
Table 4.17  Details of Waste Disposal for Contract no. HY/2009/18
Table 4.18  Details of Waste Disposal for Contract no. HY/2009/15
Table 4.19  Details of Waste Disposal for Contract no. HY/2009/19
Table 6.1   Cumulative Statistics on Complaints
Table 6.2   Cumulative Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure 2.1     Project Layout
Figure
2.2     Project Organization Chart
Figure 3.1      Locations of Environmental
Monitoring Stations
lIST OF APPENDIces
Appendix
2.1   Environmental
Mitigation Implementation Schedule
Appendix 3.1   Action and Limit Level
Appendix
4.1   Noise
Monitoring Results and Graphical Presentations
Appendix 4.2   Real-time Noise Monitoring
Results and Graphical Presentations
Appendix
4.3   Air
Quality Monitoring Results and Graphical Presentations
Appendix 5.1   Event Action Plans
Appendix 6.1   Complaint Log
Appendix
6.2   Notification of Exceedance
Appendix 8.1   Construction Programme of
Individual Contracts
EXECUTIVE SUMMARY
Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield
Depot - Advanced piling works under FEP-03/364/2009
Major construction activities for Contract no.
HK/2009/17 have been commenced on 5 October 2010. During this reporting period,
the principal work activities for Contract no. HY/2009/17 are summarized as
below:
Table I     Principal
Work Activities for Contract no. HY/2009/17
March 2012 |
April 2012 |
May 2012 |
ELS works
for basement construction for pile cap construction |
ELS works for
basement construction for pile cap construction |
ELS works
for basement construction for pile cap construction |
Contract no. HY/2009/18 - Central - Wan
Chai Bypass (CWB) - Central Interchange
under FEP-05/364/2009/A
Table
II    Principal Work Activities for
Contract no. HY/2009/18
March 2012 |
April 2012 |
May 2012 |
Instrumentation
works for Manholes and Intake Culvert Survey
Excavation
of trial pit
Drainage
work
Site
investigation and pre-drilling works
Diaphragm
wall construction
Hoarding
erection
Roadwork
Sheet-piling
Grout
curtain
Tree
transplanting |
Trial Pit
Instrumentation
and monitoring works
Drainage
works
Site
investigation and pre-drilling works
D-wall
construction
Sheet piling
Grout
curtain
Tree
Transplantation
Earthwork
Preparation
works in existing tunnel
Stitch
coring
Utilities
bridge |
Trial Pit
Instrumentation
and monitoring works
Drainage
works
Site
investigation and pre-drilling works
D-wall
construction
Sheet piling
Grout
curtain
Tree
Transplantation
Earthwork
Preparation
works in existing tunnel
Stitch
coring
Approach
ramp structure works
Top down
slab
Road works
Tunnel works
Excavation
and Lateral Support |
Contract no.
HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009
Major construction activities for Contract no.
HK/2009/01 have been commenced on 25 August 2011. During this reporting period,
the principal work activities are summarized as below:
Table III    Principal Work
Activities for Contract no. HK/2009/01
March 2012 |
April 2012 |
May 2012 |
Diaphragm
wall construction works for CWB (stage 2) and SCL protection works.
Pre-drilling
works for CWB (stage 2).
Pre-bored H
pilling works for CWB (stage 1).
Pre-bored H
pilling for exhaust duct.
Installation
of shoring system for construction of CWB top slab at stage 1.
Installation
of shoring system for construction of exhaust duct structure at stage 1.
Installation
of shoring system for chamber construction at north bank of HKCEC Water
Channel.
Guide wall
and temporary flat slab for construction of CWB Diaphragm Wall (stage 2).
Shear pin
installation work for SCL Diaphragm wall. |
Diaphragm
wall construction works for SCL Protection Works
Diaphragm
wall construction works for CWB (Stage2)
Pre-drilling
works for CWB (Stage 2)
Pre-bored H piling
works for CWB (Stage 1)
Pre-bored H
piling works for exhaust duct have been installed and grouted.
Pre-bored H
piling works for SCL
 /span>Installation of shoring system for chamber
construction at north bank of HKCEC Water
Channel works
Excavation
for CWB top slab
Shear pin
installation work for SCL Diaphragm wall
Installation
of dewatering well, recharging well, observation well and associated system
for construction of CWB tunnel, SCL top slab and Exhaust duct at Stage 1. |
Diaphragm
wall construction works for CWB (Stage2)
 /span>Pre-drilling works for CWB (Stage 2)
 /span>Pre-bored H piling works for SCL
 /span>Construction of flowmeter chamber (FMC1)
for cross harbour watermains (CHC) at north bank of HKCEC Water Channel
 /span>Excavation for CWB top slab
 /span>Shear pin installation work for SCL
Diaphragm wall
 /span>Trimming of SCL Diaphragm wall head
 /span>Installation of dewatering well, recharging
well, observation well and associated system for construction of CWB tunnel,
SCL top slab and Exhaust duct at Stage 1 |
Contract no.
HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
Major construction activities for Contract no.
HK/2009/02 have been commenced on 26 April 2011. During this reporting period, the
principal work activities are summarized as below:
Table IV    Principal Work
Activities for Contract no. HK/2009/02
March 2012 |
April 2012 |
May 2012 |
Shear pin at
WCR1 area. |
Deep
excavation works were for western tunnel portion and for eastern tunnel
portion |
Breaking
concrete slab and excavation of trial pit at tunnel portion 3 & 4
Drilling
bored pile to rock head at tunnel portion 3 & 4
Deep
excavation works were ongoing below -8.8 mPD for western tunnel portion 1 and
below -5.8mPD for eastern tunnel portion
Tunnel bored
pile works at WCR4 area
Trial Pit
excavation of D-wall at Portion 3&4
Pre-drilling
of bored pile |
Contract no. HY/2009/15 - Central-Wanchai
Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
Major construction activities for Contract no.
HY/2009/15 has been commenced on 13 July 2011. During this reporting period,
the principal work activities are summarized as below:
Table V    Principal Work Activities for Contract no.
HY/2009/15
March 2012 |
April 2012 |
May 2012 |
Diaphragm
wall construction preparation works at TS4
ELS works at
TS1 and TPCWAE
Night time
protection works at CHT
Cut off wall
preparation works at Hung Hing Road and POC |
Diaphragm
wall construction works at TS4
ELS works at
TS1 and TPCWAE
Cut and
Cover Tunnel Construction at TS1
Night time
protection works at CHT
Cut off wall
preparation works at Hung Hing Road and POC |
Diaphragm
wall construction works at TS4
ELS works at
TPCWAE
Cut and
Cover Tunnel Construction at TS1
Night time
protection works at CHT
Cut off wall
preparation works at Hung Hing Road and POC |
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
Major construction activities for Contract no.
HY/2009/19 have been commenced on March 2011. During this reporting period, the
principal work activities are summarized as below:
Table VI    Principal Work Activities for Contract no.
HY/2009/19
March 2012 |
April 2012 |
May 2012 |
Road works
at Watson Road
Fabrication
of bored piling platform
Bored piling
(Land)
Ground
contamination assessment
Pre-drilling
works for bored pile and Diaphragm wall
D-wall Construction
(North & South Section)
Guide wall
construction for D-wall / Barette at North side
Construction
works for Box Culvert T
Marine
Piling
Preparing
for pre-bored H-pile works for Culvert U |
Road works
at Watson Road
Fabrication
of bored piling platform
Bored piling
(Land)
Ground
contamination assessment
Pre-drilling
works for bored pile and Diaphragm wall
D-wall Construction
(North & South Section)
Guide wall
construction for D-wall / Barette at North side
Construction
works for Box Culvert T
Marine
Piling
Preparing
for pre-bored H-pile works for Culvert U |
Road works
at Watson Road
Fabrication
of bored piling platform
Bored piling
(Land)
Ground
contamination assessment
Pre-drilling
works for bored pile and Diaphragm wall
D-wall Construction
(North & South Section)
Guide wall
construction for D-wall / Barette at North side
Construction
works for Box Culvert T
Marine
Piling
Construct
ion of socket-H pile for Marine works
Construction
of pre-bored H-pile works for Culvert U |
Noise Monitoring
 /span>
Air Quality
Monitoring
Complaints,
Notifications of Summons and Successful Prosecutions
1.1.1.
Lam Geotechnics Limited (LGL) has been
appointed to work as the Environmental Team (ET) under Environmental Permit no.
EP-364/2009A and Further Environmental permit nos.
FEP-01/364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A and FEP-07/364/2009/A to implement the Environmental Monitoring and Audit (EM&A)
programme as stipulated in the EM&A Manual of the approved Environmental
Impact Assessment (EIA) Report for Wan Chai Development phase II and
Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A
Manual of the approved EIA Report for Central-Wan Chai Bypass and Island
Eastern Corridor Link (Register No. AEIAR-014/2001).
1.1.2.
This report presents the environmental
monitoring and auditing work carried out in accordance to the Section 10.3 of EM&A Manual and  /span>Environmental Monitoring and Audit Requirements under
Particular Specification Section 27.
1.1.3.
This report documents the finding of
EM&A works during the period from March to May 2012.
Section 1     Introduction  details
the scope and structure of the report.
Section 2     Project Background  
summarizes background and scope of the project, site description, project
organization and contact details of key personnel during the reporting period.
Section 3     Monitoring
Requirements  summarizes all monitoring parameters, monitoring locations,
monitoring frequency, duration and action
plan.
Section 4     Monitoring
Results  summarizes the monitoring results obtained in the
reporting period.
Section 5     Compliance Audit  
summarizes the auditing
of monitoring results, all exceedances environmental parameters.
Section 6     Complaints, Notification of summons and Prosecution  
summarizes the cumulative statistics on
complaints, notification of summons and prosecution
Section 7     Cumulative Construction Impact due to the Concurrent Projects  summarizes the relevant cumulative construction impact due to the
concurrent activities of the concurrent Projects.
Section 8     Conclusion
2.1.1.
“Wan Chai Development phase II and
Central-Wan Chai Bypass and “Central-Wan Chai Bypass and Island Eastern
Corridor Link (hereafter called “the Project  are Designed Project (DP) under
the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental Impact Assessment (EIA)
Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register
No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai
Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and
11 December 2008 respectively.
2.1.2.
The key purpose of Wan Chai Development
Phase II (WDII) is to provide land at Wan Chai North and North Point for
construction of the Central-Wan Chai Bypass and Island Eastern Corridor Link
(CWB). Land formed under the project will be developed as a world-class
waterfront promenade joining that at the new Central waterfront for public
enjoyment.
2.1.3.
There is a compelling and present need
for the CWB to provide relief to the very congested east-west Connaught Road
Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is
currently operating beyond its capacity. The CWB will provide relief to the
existing congestion along the Corridor and cater for the anticipated growth of
traffic on Hong Kong Island. Without the CWB and its access roads, there will
not be sufficient capacity to serve the heavy traffic demands at both strategic
and local levels.
2.2.1.
Design and
Construction of Central  Wan Chai Bypass and Island Eastern Corridor Link
under the Project involves the construction and operation of a trunk road and its
road tunnel more than 800m in length between portals that is shown at Figure 2.1.
2.2.2.
The study area
encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:
 -
A dual
three-lane trunk road, approximately 4.5 km in length, and tunnel approximately
3.7 km in length defined from the connection with the existing Rumsey Street
Flyover in Central, through to a connection with the existing Island Eastern
Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);
 -
The Central
Interchange near the Rumsey Street Flyover to provide road connections to the
Central area;
 -
Tunnel control
buildings and ventilation buildings;
 -
Slip roads to
connect the CWB to the local road system in the Wan Chai North and Causeway Bay
area;
 -
Associated
road lighting, road signing, traffic control and surveillance system; and
 -
Other
associated works.
2.2.3.
The project also contains various
Schedule 2 DPs that, under the EIAO, require Environmental Permits (EPs) to be
granted by the DEP before they may be either constructed or operated. Table
2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations
of these Schedule 2 DPs.
Table
2.1   Schedule 2 Designated Projects
under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project,
there are a number of contracts sub-dividing the whole works area into
different work areas to be commenced. 
Contractors of individual contracts will be required by the EP holder to
apply Further Environmental Permits such that the impact
monitoring stations are sub-divided accordingly to facilitate the
implementation of EM&A programme and to streamline the EM&A reporting
for individual FEP holders correspondingly.
2.3.2.
In the reporting period, all the contracts were commenced and
contract no. 04/HY/2006 had been completed. The details of individual
contracts are summarized in Table2.2.
Table
2.2  Details of Individual Contracts
under the Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HY/2009/17 |
Central  Wan Chai Bypass (CWB) at FEHD Whitfield Depot  Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central  Wan Chai Bypass (CWB)  Central Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street |
DP1 |
September 2010 |
HK/2009/01 |
Wan Chai Development Phase II  Central  Wan Chai Bypass at Hong Kong
Convention and Exhibition Centre  Tunnel Works |
DP1, DP2 |
25 August 2011 |
HK/2009/02 |
Wan Chai Development Phase II  Central  Wan Chai Bypass at Wan Chai
East(CWB Tunnel) |
DP1 |
26 April 2011 |
HY/2009/15 |
Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) |
DP1 |
13 July 2011 |
HY/2009/19 |
Central  Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
2.4.1.
Civil
Engineering and Development Department and Highways Department are the overall
project controllers for the Wan Chai Development Phase II and Central-Wan Chai
Bypass respectively. For the construction phase of the Project, Project Engineer,
Contractor(s), Environmental Team and Independent Environmental Checker are
appointed to manage and control environmental issues.
2.4.2.
The proposed project organization and
lines of communication with respect to environmental protection works are shown
in Figure
2.2. Key personnel and contact particulars are
summarized in Table 2.3:
Table 2.3  Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer’s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer’s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3916 1818 |
3529 2829 |
|
Lam Woo & CO., LTD. |
Contractor under Contract no. HY/2009/17 |
Project Manager |
Mr. K. S. Law |
9090 1378 |
2566 7522 |
Site Agent |
Mr. Tony Au |
9725 5874 |
2566 7522 |
||
Sub Agent |
Mr. Johnny Wong |
9725 5870 |
2566 7522 |
||
Chun Wo  Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Joint Venture Board Representative |
Mr. PL Yue |
2162 9909 |
2634 1626 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Sub Agent |
Mr. Terry Wong |
9757 9846 |
|||
Construction
Manager |
Mr. Wyman Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Jack Chu |
9775 2467 |
|||
Construction
Manager |
Mr KK Yuen |
9498 1213 |
|||
Construction
Manager |
Mr. Andy Yu |
9648 4896 |
|||
Environmental
Officer (Compliance Manager) |
Mr. Andy Mak |
9103 2370 |
|||
Environmental
Supervisor |
Ms. Kiwi Chan |
6227 8840 |
|||
|
|
Environmental
Supervisor |
Mr. Yeung Sze King |
9047 9952 |
|
Environmental
Supervisor |
Mr. Les Chow |
6692 2423 |
|
||
Environmental
Supervisor |
Mr. Otto Yau |
9260 4485 |
|
||
Chun Wo  CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project Manager |
Mr. Chan Sing Cho |
3658-3002 |
2827 9996 |
Site Agent |
Mr. Mak Kam Wing |
3658-3044 |
|||
Quality & Environmental Manager |
Mr. C.P. Ho |
3658-3000 |
|||
Environmental Officer |
Ms Flora Ng |
3658-3064 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570 8013 |
Site Agent |
Mr. Cheung Kit Cheung |
6909 1555 |
|||
Assistant Site Agent |
Mr. Eric Fong |
6191 9337 |
|||
Environmental Engineer |
Mr. Simon Wong |
9281 4346 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Construction Manager (Marine) |
William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
Leighton Contractors (Asia) Limited |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Brian Gillon |
2214 7700 |
2140 6799 |
Deputy Site Agent |
Mr. Desmond Sze |
2214 7703 |
|||
Environmental Officer |
Mr. Anfernee Chow |
2214 7721 |
|||
Environmental Supervisor |
K. P. Lai |
6461 4660 |
|||
Environmental Supervisor |
Ryan Tsui |
2214 7705 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Manager |
Mr. M Y Wong |
2823 7879 |
2566 2192 |
Site Agent |
Mr. P J Fan |
3557 6368 |
|||
Head of construction |
Mr. Roger Cheung |
3557 6371 |
|||
Environmental Officer |
Mr. Daniel Sin |
3557 6215 |
|||
Environmental Supervisor |
Mr. Kelven Yip |
3557 6347 |
|||
Environmental Supervisor |
Mr. Tim Fung |
3557 6349 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team
Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.5.1.
Major
construction activities for Contract no. HK/2009/17 have been commenced on 5
October 2010. During this reporting period, the principal work activities for Contract
no. HY/2009/17 are summarized in Table2.4.
Table 2.4   Principal Work Activities for Contract no. HY/2009/17
March 2012 |
April 2012 |
May 2012 |
ELS works
for basement construction for pile cap construction |
ELS works
for basement construction for pile cap construction |
ELS works
for basement construction for pile cap construction |
Table 2.5   Principal Work Activities for Contract no.
HY/2009/18
March 2012 |
April 2012 |
May 2012 |
Instrumentation
works for Manholes and Intake Culvert Survey
Excavation
of trial pit
Drainage
work
Site
investigation and pre-drilling works
Diaphragm
wall construction
Hoarding
erection
Roadwork
Sheet-piling
Grout
curtain
Tree
transplanting |
Trial Pit
Instrumentation
and monitoring works
Drainage
works
Site investigation
and pre-drilling works
D-wall
construction
Sheet piling
Grout
curtain
Tree
Transplantation
Earthwork
Preparation
works in existing tunnel
Stitch
coring
Utilities
bridge |
Trial Pit
Instrumentation
and monitoring works
Drainage
works
Site
investigation and pre-drilling works
D-wall
construction
Sheet piling
Grout
curtain
Tree
Transplantation
Earthwork
Preparation
works in existing tunnel
Stitch
coring
Approach
ramp structure works
Top down
slab
Road works
Tunnel works
Excavation
and Lateral Support |
2.5.3.
Major
construction activities for Contract no. HK/2009/01 have been commenced on 25
August 2011. During this reporting period, the principal work activities are
summarized in Table2.6:
Table 2.6   Principal Work Activities
for Contract no. HK/2009/01
March 2012 |
April 2012 |
May 2012 |
Diaphragm
wall construction works for CWB (stage 2) and SCL protection works.
Pre-drilling
works for CWB (stage 2).
Pre-bored H
pilling works for CWB (stage 1).
Pre-bored H
pilling for exhaust duct.
Installation
of shoring system for construction of CWB top slab at stage 1.
Installation
of shoring system for construction of exhaust duct structure at stage 1.
Installation
of shoring system for chamber construction at north bank of HKCEC Water
Channel.
Guide wall
and temporary flat slab for construction of CWB Diaphragm Wall (stage 2).
Shear pin
installation work for SCL Diaphragm wall. |
Diaphragm
wall construction works for SCL Protection Works
Diaphragm
wall construction works for CWB (Stage2)
Pre-drilling
works for CWB (Stage 2)
Pre-bored H
piling works for CWB (Stage 1)
Pre-bored H
piling works for exhaust duct have been installed and grouted.
Pre-bored H
piling works for SCL
 /span>Installation of shoring system for chamber
construction at north bank of HKCEC Water
Channel works
Excavation
for CWB top slab
Shear pin
installation work for SCL Diaphragm wall
Installation
of dewatering well, recharging well, observation well and associated system
for construction of CWB tunnel, SCL top slab and Exhaust duct at Stage 1. |
Diaphragm wall
construction works for CWB (Stage2)
 /span>Pre-drilling works for CWB (Stage 2)
 /span>Pre-bored H piling works for SCL
 /span>Construction of flowmeter chamber (FMC1)
for cross harbour watermains (CHC) at north bank of HKCEC Water Channel
 /span>Excavation for CWB top slab
 /span>Shear pin installation work for SCL Diaphragm
wall
 /span>Trimming of SCL Diaphragm wall head
 /span>Installation of dewatering well, recharging
well, observation well and associated system for construction of CWB tunnel,
SCL top slab and Exhaust duct at Stage 1 |
2.5.4.
Major
construction activities for Contract no. HK/2009/02 have been commenced on 26 April 2011. During this reporting period, the principal work activities are
summarized in Table2.7:
Table
2.7   Principal Work Activities for Contract no. HK/2009/02
March 2012 |
April 2012 |
May 2012 |
Shear pin at
WCR1 area. |
Deep
excavation works were for western tunnel portion and for eastern tunnel
portion |
Breaking
concrete slab and excavation of trial pit at tunnel portion 3 & 4
Drilling
bored pile to rock head at tunnel portion 3 & 4
Deep
excavation works were ongoing below -8.8 mPD for western tunnel portion 1 and
below -5.8mPD for eastern tunnel portion
Tunnel bored
pile works at WCR4 area
Trial Pit
excavation of D-wall at Portion 3&4
Pre-drilling
of bored pile |
2.5.5.
Major
construction activities for Contract no. HY/2009/15 have been commenced on 13
July 2011. During this reporting period, the principal work activities are
summarized in Table 2.8:
Table
2.8   Principal Work Activities for
Contract no. HY/2009/15
March 2012 |
April 2012 |
May 2012 |
Diaphragm
wall construction preparation works at TS4
ELS works at
TS1 and TPCWAE
Night time
protection works at CHT
Cut off wall
preparation works at Hung Hing Road and POC |
Diaphragm
wall construction works at TS4
ELS works at
TS1 and TPCWAE
Cut and
Cover Tunnel Construction at TS1
Night time
protection works at CHT
Cut off wall
preparation works at Hung Hing Road and POC |
Diaphragm
wall construction works at TS4
ELS works at
TPCWAE
Cut and
Cover Tunnel Construction at TS1
Night time
protection works at CHT
Cut off wall
preparation works at Hung Hing Road and POC |
2.5.6.
Major
construction activities for Contract no. HY/2009/19 have been commenced on
March 2011. During this reporting period, the principal work activities are
summarized in Table 2.9:
Table
2.9   Principal Work Activities for Contract
no. HY/2009/19
March 2012 |
April 2012 |
May 2012 |
Road works
at Watson Road
Fabrication
of bored piling platform
Bored piling
(Land)
Ground
contamination assessment
Pre-drilling
works for bored pile and Diaphragm wall
D-wall Construction
(North & South Section)
Guide wall
construction for D-wall / Barette at North side
Construction
works for Box Culvert T
Marine
Piling
Preparing
for pre-bored H-pile works for Culvert U |
Road works
at Watson Road
Fabrication
of bored piling platform
Bored piling
(Land)
Ground
contamination assessment
Pre-drilling
works for bored pile and Diaphragm wall
D-wall Construction
(North & South Section)
Guide wall
construction for D-wall / Barette at North side
Construction
works for Box Culvert T
Marine
Piling
Preparing
for pre-bored H-pile works for Culvert U |
Road works
at Watson Road
Fabrication
of bored piling platform
Bored piling
(Land)
Ground
contamination assessment
Pre-drilling
works for bored pile and Diaphragm wall
D-wall Construction
(North & South Section)
Guide wall
construction for D-wall / Barette at North side
Construction
works for Box Culvert T
Marine
Piling
Construct
ion of socket-H pile for Marine works
Construction
of pre-bored H-pile works for Culvert U |
2.5.7.
Implementation status of the recommended
mitigation measures during this reporting period is presented in Appendix 2.1.
3.1.1.
The noise monitoring stations for the
Project are listed and shown in Table 3.1 and Figure 3.1.  /span>Appendix 3.1 shows the established Action/Limit Levels for the monitoring
works.
Table 3.1  Noise Monitoring Station
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun
Area |
M3a |
Tung Lo Wan
Fire Station |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist
Church Henrietta Secondary School |
M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
Real time Noise
Monitoring Stations
3.1.2.
The noise monitoring stations for the
Project are listed and shown in Table 3.2 and
Figure 3.1..
Appendix 3.1 shows the established Action/Limit Levels for the monitoring
works.
Table 3.2  Real Time Noise Monitoring Station
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section Whitefield Depot |
North Point |
RTN2 |
Oil Street Community Liaison Centre |
Noise Monitoring Parameters, Frequency and Duration
3.1.3.
The construction noise level
shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq (30 minutes)
shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For
all other time periods, Leq (5 minutes) shall be employed for
comparison with the Noise Control Ordinance (NCO) criteria. Supplementary
information for data auditing, statistical results such as L10 and L90
shall also be obtained for reference.
3.1.4.
Noise monitoring shall be carried
out at all the designated monitoring stations. The monitoring frequency shall
depend on the scale of the construction activities. The following is an initial
guide on the regular monitoring frequency for each station on a weekly basis
when noise generating activities are underway:
 -
One set of measurements between
0700 and 1900 hours on normal weekdays.
3.1.5.
Real time noise shall be carried
out at the designated monitoring stations. The following is an initial guide on
the regular monitoring frequency for each station on a 24 hours daily basis
when noise generating activities are underway:
 -
One set of measurements between
0700 and 1900 hours on normal weekdays.
 -
One set of measurements between 1900
and 2300 hours on normal weekdays and 0700 and 2300 hours on public holidays.
 -
One set of measurements between 2300
and 0700 hours on next day on everyday.
3.1.6.
If construction works are
extended to include works during the hours of 1900  0700 as well as public
holidays and Sundays, additional weekly impact monitoring shall be carried out
during respective restricted hours periods. Applicable permits under NCO shall
be obtained by the Contractor.
Monitoring Equipment
3.1.7.
As referred to in the Technical
Memorandum  issued under the NCO, sound level meters in compliance with the
International Electrotechnical Commission Publications 651: 1979 (Type 1) and
804: 1985 (Type 1) specifications shall be used for carrying out the noise
monitoring. Immediately prior to and following each noise measurement the
accuracy of the sound level meter shall be checked using an acoustic calibrator
generating a known sound pressure level at a known frequency. Measurements may
be accepted as valid only if the calibration level from before and after the
noise measurement agree to within 1.0 dB.
3.1.8.
Noise measurements shall not be
made in fog, rain, wind with a steady speed exceeding 5 m/s or wind with gusts
exceeding 10 m/s. The wind speed shall be checked with a portable wind speed
meter capable of measuring the wind speed in m/s.
3.1.9.
The sound level meter shall be
checked using an acoustic calibrator generating a known sound pressure level at
a known frequency before deployment to the site and during each site visit.
Measurements may be accepted as valid only if the calibration level from before
and after the noise measurement agree to within 1.0 dB.
Air Quality Monitoring
Stations
3.2.1.
The air monitoring stations for the
Project are listed and shown in Table 3.3 and Figure 3.1. Appendix 3.1 shows the established
Action/Limit Levels for the monitoring works.
Table 3.3  Air Monitoring Stations
Station ID |
Monitoring
Location |
Description |
CMA1b |
Oil Street Community
Liaison Centre |
North Point |
CMA2a |
Causeway Bay Community
Centre |
Causeway Bay |
CMA3a |
Future CWB site office
at Wanchai Waterfront Promenade |
Causeway Bay |
CMA4a |
Society for the
Prevention of Cruelty to Animals |
Wan Chai |
CMA5a |
Children Playgrounds
opposite to Pedestrian Plaza |
Wan Chai |
CMA6a |
Future AECOM site
office at Work Area |
Wan Chai |
MA1e |
International Finance Centre (Eastern End of Podium) |
Central |
MA1w |
International Finance Centre (Western End of Podium) |
Central |
Air Monitoring Parameters,
Frequency and Duration
3.2.2.
One-hour and 24-hour TSP levels
should be measured to indicate the impacts of construction dust on air quality.
The 24-hour TSP levels shall be measured by following the standard high volume
sampling method as set out in the Title 40 of the Code of Federal Regulations,
Chapter 1 (Part 50), Appendix B.
3.2.3.
All relevant data including
temperature, pressure, weather conditions, elapsed-time meter reading for the
start and stop of the sampler, identification and weight of the filter paper,
and any other local atmospheric factors affecting or affected by site
conditions, etc., shall be recorded down in detail.
3.2.4.
For regular impact monitoring,
the sampling frequency of at least once in every six-days, shall be strictly
observed at all the monitoring stations for 24-hour TSP monitoring. For 1-hour
TSP monitoring, the sampling frequency of at least three times in every
six-days should be undertaken when the highest dust impact occurs.
Sampling Procedure and
Monitoring Equipment
3.2.5.
High volume samplers (HVSs) in
compliance with the following specifications shall be used for carrying out the
1-hour and 24-hour TSP monitoring:
 -
0.6 - 1.7 m3 per minute
adjustable flow range;
 -
Equipped with a timing / control
device with +/- 5 minutes accuracy for 24 hours operation;
 -
Installed with elapsed-time meter
with +/- 2 minutes accuracy for 24 hours operation;
 -
Capable of providing a minimum
exposed area of 406 cm2;
 -
Flow control accuracy: +/- 2.5%
deviation over 24-hour sampling period;
 -
Equipped with a shelter to
protect the filter and sampler;
 -
Incorporated with an electronic
mass flow rate controller or other equivalent devices;
 -
Equipped with a flow recorder for
continuous monitoring;
 -
Provided with a peaked roof
inlet;
 -
Incorporated with a manometer;
 -
Able to hold and seal the filter
paper to the sampler housing at horizontal position;
 -
Easily changeable filter; and
 -
Capable of operating continuously
for a 24-hour period.
3.2.6.
Initial calibration of dust
monitoring equipment shall be conducted upon installation and thereafter at
bi-monthly intervals. The transfer standard shall be traceable to the
internationally recognized primary standard and be calibrated annually. The
concern parties such as IEC shall properly document the calibration data for
future reference. All the data should be converted into standard temperature
and pressure condition.
3.2.7.
Laboratory Measurement / Analysis
3.2.8.
A clean laboratory with constant
temperature and humidity control, and equipped with necessary measuring and
conditioning instruments to handle the dust samples collected, shall be
available for sample analysis, and equipment calibration and maintenance. The
laboratory should be HOKLAS accredited.
3.2.9.
Filter paper of size 8" x
10" shall be labelled before sampling. It shall be a clean filter paper
with no pinholes, and shall be conditioned in a humidity-controlled chamber for
over 24-hours and be pre-weighed before use for the sampling.
3.2.10. After sampling, the filter paper loaded with dust shall be kept in a
clean and tightly sealed plastic bag. The filter paper shall then be returned
to the laboratory for reconditioning in the humidity controlled chamber
followed by accurate weighing by an electronic balance with readout down to 0.1
mg. The balance shall be regularly calibrated against a traceable standard.
3.2.11. All the collected samples shall be kept in a good condition for 6 months
before disposal.
4.0.1.
Monitoring for report of review
baseline noise level was performed from 11 April 2011 to 8 June 2011. Then the report was submitted on the 20 June
2011, verified by IEC on 18 July 2011 and was approved by ER by January
2012. The new baseline is used for the
noise calculation starting from the January 2012 reporting month.
4.0.2.
The environmental monitoring will
be implemented based on the division of works areas of each designed project
managed under different contracts with separate FEP applied by individual
contractors. Overall layout showing
work areas of various contracts, latest status of work commencement and
monitoring stations is shown in Figure 2.1
and Figure 3.1. The monitoring results are
presented in according to the Individual Contract(s).
4.0.3.
In the reporting period, the concurrent
contracts are as follows:
Contract no. HY/2009/15  
Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) under
FEP-06/364/2009/A
Contract no. HY/2009/17  Central
–Wanchai Bypass (CWB) at FEHD Whitfield Depot  Advanced piling works under
FEP-03/364/2009
Contract no. HY/2009/18  Central
–Wanchai Bypass (CWB)  Central Interchange under FEP-05/364/2009/A
Contract no. HY/2009/19  Central
 Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009
Contract no. HK/2009/01 –Wanchai
Development Phase II  Central –Wanchai Bypass at Hong Kong Convention and
Exhibition Centre
Contract no. HK/2009/02 Wanchai
Development Phase II  Central- Wanchai Bypass at Wanchai East
4.1.1.
Due to adverse weather condition,
monitoring at station M4b, noise monitoring was
rescheduled from 17 April 2012 to 20 April 2012.
4.1.2.
Due to adverse weather condition,
monitoring at station M5b, noise monitoring was
rescheduled from 17 April 2012 to 20 April 2012.
4.1.3.
Due to adverse weather condition,
monitoring at station M6, noise monitoring was
rescheduled from 17 April 2012 to 20 April 2012.
4.1.4.
Due to adverse weather condition,
monitoring at station M7e, noise monitoring was
rescheduled from 17 April and 16 May 2012 to 19 April and 18 May 2012.
4.1.5.
Due to adverse weather condition,
monitoring at station M7w, noise monitoring was
rescheduled from 17 April and 16 May 2012 to 20 April and 18 May 2012.
Contract no. HY/2009/17 –Central - Wanchai Bypass (CWB) at FEHD
Whitfield Depot - Advanced piling works under FEP-03/364/2009
4.1.6.
The proposed division of noise
monitoring stations for Contract no. HY/2009/17 is summarized in Table
4.1 below:
Table 4.1   Noise Monitoring Stations for Contract no.  /span>HY/2009/17
Station |
Description |
M4b |
Victoria Centre |
4.1.7.
No exceedance was recorded in this reporting period.
4.1.8.
Noise monitoring results measured
in this reporting period are reviewed and summarized. Details of graphical presentation can be referred in Appendix 4.1. 
Contract no. HY/2009/18 - Central - Wanchai Bypass
(CWB)  Central Interchange under FEP-05/364/2009/A
4.1.9.
Noise monitoring for the Central
Interchange works under contract no. HY/2009/18 was commenced on 22 April
2011.The proposed division of noise monitoring stations for Contract no.
HY/2009/18 are summarized in Table 4.2 below.
Table 4.2   Noise Monitoring Station for Contract no. HY/2009/18
Station |
Description |
M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
Reporting month of March 2012
4.1.10. No action level exceedance and two limit level exceedances were recorded
during daytime period in the reporting month.
4.1.11. During 22 March 2012 monitoring, a limit level exceedance was
recorded. After checking with
contractor’s work schedules and investigation found that drilling by drill rigs
and breaking works for diaphragm wall construction were conducted by during
monitoring.
4.1.12. During 27 March 2012 monitoring, a limit level exceedance was
recorded. After checking with
contractor’s work schedules and investigation found that drilling by drill
rigs, breaking works for diaphragm wall construction and crane moving steel
cages were conducted during monitoring.
4.1.13. Both the limit level exceedances were considered as project-related.
Reporting month of April 2012
4.1.14. No limit and action level exceedance was recorded during daytime of
reporting month of April 2012.
Reporting month of May 2012
4.1.15.
No action level exceedance and
one limit level exceedance was recorded during daytime period
in the reporting month.
4.1.16.
During 30 April 2012 monitoring,
a limit level exceedance was recorded. 
After checking with contractor’s work schedules and investigation found
that backhoe with breaker and excavator for diaphragm wall construction were
conducted during monitoring.
4.1.17.
The limit level exceedance was considered
as project-related.
4.1.18.
Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring
results and graphical presentation can be referred in
Appendix 4.1. Details of the Notification of Exceedance
can be referred in Appendix 6.2.
Contract no. HK/2009/01 - Wanchai Development Phase II - Central -
Wanchai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works
under FEP-02/364/2009 and Contract no. HK/2009/02 - Wanchai Development Phase
II - Central - Wanchai Bypass at Wanchai East (CWB Tunnel) under
FEP-01/364/2009
4.1.19. The commencement of construction works for Contract no. HK/2009/01 under
FEP-02/364/2009 is on 25 August 2011 and HK/2009/02 under
FEP-01/364/2009 is on 26 April 2011.The proposed division of air monitoring
stations are summarized in Table 4.3 below.
Table 4.3   Noise Monitoring Stations for Contract nos. HK/2009/01 and HK/2009/02
Station |
Description |
M1a |
Harbour Road Sports Centre |
4.1.20. No exceedance was recorded in this reporting period.
4.1.21.
Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring
results and graphical presentation can be referred in
Appendix 4.1 and the complaints can be referred in
Appendix
6.1. Details of the Notification of Exceedance can be referred in
Appendix
6.2.
Contract no. HY/2009/15 - Central-Wanchai
Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
4.1.22. The commencement of construction works for Contract no. HY/2009/15 under
FEP-06/364/2009/A was on 13 July 2011. Noise monitoring was
commenced on 13 July 2011. The proposed division of noise monitoring
stations are summarized in in Table 4.4 below.
Table 4.4   Noise Monitoring Station for Contract nos. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
4.1.23. No limit level exceedance and one action level exceedance was recorded
in the reporting period as a noise impact complaint was received on 5 April
2012.
4.1.24.
Details
of noise monitoring results and graphical presentation can be referred in
Appendix 4.1 and the complaints can be referred in
Appendix
6.1. 
4.1.25. Noise monitoring for the tunnel works under contract no. HY/2009/19 was
commenced on 24 April 2011. The proposed division of noise monitoring stations
are summarized in Table 4.5 below.
Table 4.5   Noise Monitoring Stations for Contract no. HY/2009/19
Station |
Description |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist Church Henrietta Secondary School |
Reporting month of March 2012
4.1.26.
One action level exceedance was recorded
as a noise impact complaint was received on 3 March 2012.
4.1.27.
Three limit level exceedances were
recorded on 28 February, 13 and 27 March 2012 at M6  HK Baptist Church
Henrietta Secondary School in the reporting month.  /span>Major traffic jam and no major work activities were observed
during monitoring, the limit level exceedances were considered as non-project
related.
Reporting month of April 2012
4.1.28.
One action level exceedance was
recorded as a noise impact complaint was received on 15 April 2012.
4.1.29.
One limit level exceedance was
recorded on 2 April 2012 at M6  HK Baptist Church Henrietta Secondary School
in the reporting month. Major traffic
jam and no major work activities were observed during monitoring, the limit
level exceedances were considered as non-project related.
Reporting month of May 2012
4.1.30.
No action level and two limit
level exceedances were recorded on 30 April and 16 May 2012 at M6  HK Baptist
Church Henrietta Secondary School in the reporting month. Major traffic jam and no major work
activities were observed during monitoring, the limit level exceedances were
considered as non-project related.
4.1.31.
Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring
results and graphical presentation can be referred in
Appendix 4.1 and the Notification of Exceedance can be
referred in Appendix 6.2.
Contract no. HY/2009/17
–Central - Wanchai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works
under FEP-03/364/2009 and Contract no.
HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under
FEP-07/364/2009/A
4.2.1.
The proposed division of real
time noise monitoring stations are summarized in Table 4.6 below.
Real time noise monitoring for the piling works under contract no. HY/2009/17
was commenced on 5 October 2010.
Table 4.6  Real Time Noise Monitoring
Station for Contract no. HY/2009/17
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD Hong Kong Transport Section Whitefield Depot |
Real time noise
monitoring results and graphical presentation during night time period are for
information only.
4.2.2.
No project
related action and limit level exceedance were recorded in the reporting
period. Real time noise monitoring results measured in this reporting period are
reviewed and summarized. Details of real time
noise monitoring results and graphical presentation can be referred to Appendix 4.2
4.2.3.
The proposed division of noise
monitoring stations are summarized in Table 4.7 below. Real time
noise monitoring for major construction works under contract no. HY/2009/19 was
commenced on 24 April 2011.
Table 4.7  Real Time Noise Monitoring
Stations for Contract no. HY/2009/19
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD Hong Kong Transport Section Whitefield Depot |
RTN2 |
North Point |
Oil Street Community Liaison Center |
Real time noise
monitoring results and graphical presentation during night time period are for
information only.
4.2.4.
No project related
action and limit level exceedance were recorded in the reporting period. Real time noise monitoring
results measured in this reporting period are reviewed and summarized. Details
of real time noise monitoring results and graphical presentation can be
referred to Appendix 4.2
4.3.1
Due to extension of site boundary
by contractor of HY/2009/19, location of air monitoring station CMA1b  Oil
Street Community Liaison Centre has been finely adjusted on 21 April 2012.
4.3.2
Due to lack of
electricity supply at station CMA1b, 24hr-TSP was rescheduled from 13 Mar, 25 Apr and 8
May 2012 to 14 Mar, 30 Apr and 9 May 2012
4.3.3
Due to lack of
electricity supply at station CMA3a, 24hr-TSP was rescheduled from 24 Mar, 16 Apr, 20
Apr 2012 to 26 Mar, 17 Apr, 24 Apr 2012.
4.3.4
Due to lack of
electricity supply at station MA1ew, 24hr-TSP was rescheduled from 16 Apr, 20 Apr and
14 May 2012 to 17 Apr, 21 Apr and 15 May 2012
4.3.5
Due to lack of
electricity supply at station CMA5a, 24hr-TSP was rescheduled from 18 and 25 May 2012 to 9
and 26 May 2012.
Contract no. HY/2009/17
–Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling
works under FEP-03/364/2009
4.3.6
The proposed division of air
monitoring stations are summarized in Table 4.8 below. Air monitoring for
the piling works under contract no. HY/2009/17 was commenced on 8 October 2010.
Table 4.8   Air Monitoring Stations
for Contract no. HY/2009/17
Station |
Description |
CMA2a |
Causeway Bay Community Centre |
4.3.7
No exceedance was recorded in the
reporting period. Air quality monitoring results measured in this reporting
period are reviewed and summarized. 
Details of air monitoring results and graphical presentation can be
referred in Appendix 4.3. 
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB)  Central
Interchange under FEP-05/364/2009/A
4.3.8
The proposed division of air
monitoring stations are summarized in Table 4.9 below.
Table 4.7   Air Monitoring Stations
for Contract no.
HY/2009/18
Station |
Description |
MA1e |
International Finance Centre (Eastern End of Podium) |
MA1w |
International Finance Centre (Western End of Podium) |
4.3.9
Air monitoring for the Central
Interchange works under contract no. HY/2009/18 was commenced on 21 April 2011.
4.3.10
No exceedance was recorded in the
reporting period. Air quality monitoring results measured in this reporting
period are reviewed and summarized. 
Details of air monitoring results and graphical presentation can be
referred in Appendix 4.3. 
Contract no.
HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009
4.3.11
The commencement of construction
works for Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011. The proposed division of air
monitoring stations are summarized in Table 4.10 below.
Table 4.10 Air Monitoring Station for
Contract no. HK/2009/01
Station |
Description |
CMA5a |
Children Playgrounds opposite to Pedestrian Plaza |
4.3.12
No exceedance was recorded in the
reporting period. Air quality monitoring results measured in this reporting
period are reviewed and summarized. 
Details of air monitoring results and graphical presentation can be
referred in Appendix 4.3. 
Contract no.
HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
Table 4.11 Air Monitoring Station for
Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
4.3.14
No exceedance was recorded in the
reporting period. Air quality monitoring results measured in this reporting
period are reviewed and summarized. 
Details of air monitoring results and graphical presentation can be
referred in Appendix 4.3. 
Contract no. HY/2009/15 - Central-Wanchai Bypass  Tunnel (Causeway Bay
Typhoon Shelter Section) under FEP-06/364/2009/A
4.3.15
The commencement of construction
works for Contract no. HY/2009/15 under FEP-06/364/2009/A was on 13 July 2011. The proposed division of air monitoring stations
are summarized in Table 4.12 below.
Table
4.12 Air Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB site office at Wanchai
Waterfront Promenade |
4.3.16
No exceedance was recorded in the
reporting period. Air quality monitoring results measured in this reporting
period are reviewed and summarized. 
Details of air monitoring results and graphical presentation can be
referred in Appendix 4.3. 
Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link 
under FEP-07/364/2009/A
4.3.17 Air monitoring for the tunnel works was commenced on 26 April 2011 for
Contract no. HY/2009/19 under FEP-07/364/2009/A. The
proposed division of air monitoring stations are summarized in Table 4.13 below.
Table 4.13 Air Monitoring Stations for Contract no. HY/2009/19
Station |
Description |
CMA1b |
Oil St Community Liaison Centre |
CMA2a |
Causeway Bay Community Centre |
4.3.18.
No exceedance was recorded in the
reporting period. Air quality monitoring results measured in this reporting
period are reviewed and summarized. 
Details of air monitoring results and graphical presentation can be
referred in Appendix 4.3. 
Contract no. HY/2009/17 –Central - Wan Chai Bypass (CWB) at FEHD
Whitfield Depot - Advanced piling works under
FEP-03/364/2009
4.4.1.
No inert and non-inert
C&D waste was disposed in the reporting period. Details of the waste flow
table are summarized in Table 4.14
Table 4.14 Details of Waste Disposal for Contract no. HY/2009/17
Waste Type |
Quantity
this quarter, m3 |
Cumulative
Quantity-to-Date, m3 |
Disposal /
Dumping Grounds |
Inert C&D materials disposed |
NIL |
NIL |
N/A |
Inert C&D materials recycled |
N/A |
||
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
N/A |
N/A |
N/A |
Contract nos. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under
FEP-02/364/2009
4.4.2.
Inert and non-inert C&D waste
was disposed of in this reporting period. Details of the waste flow table are
summarized in Table 4.15.
Table 4.15 Details of Waste Disposal for
Contract no. HK/2009/01
Inert C&D materials disposed |
5,535.48 |
19,171.45 |
TKO137, TM38 |
Inert C&D materials recycled |
NIL |
389.96 |
N/A |
Non-inert C&D materials disposed |
138.20 |
710.92 |
SENT Landfill |
Non-inert C&D materials recycled |
4,130 |
136,324 |
N/A |
Chemical waste disposed |
670 |
6,130 |
Kwun Kee (Chemical Waste Collector) |
Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
4.4.3.
Inert and non-inert C&D waste
were disposed of in this reporting period. Details of the waste flow table are
summarized in Table 4.16.
Table 4.16 Details of Waste Disposal for
Contract no. HK/2009/02
Inert C&D materials disposed |
56,065 |
140,130 |
TKO137, TM 38 |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
103 |
284 |
SENT Landfill |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
4,186 |
N/A |
Contractor
clarified that no Inert and Non-inert C&D materials disposed in
June 2011
Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB)  Central Interchange under
FEP-05/364/2009/A
4.4.4.
Inert and non-inert C&D waste
was disposed of in this reporting period. Details of the waste flow table are
summarized in Table 4.17.
Table 4.17 Details of Waste Disposal for
Contract no. HY/2009/18
Inert C&D materials disposed |
16,735.9 |
31,935 |
T.K.O. 137 |
Inert C&D materials recycled |
7,904.5 |
7,963 |
N/A |
Non-inert C&D materials disposed |
91.2 |
311 |
SENT Landfill |
Non-inert C&D materials recycled (tonnes) |
40.3 |
40.3 |
N/A |
Chemical waste disposed |
1,400 |
2,225 |
N/A |
Contract no.
HY/2009/15 - Central-Wanchai Bypass  Tunnel (Causeway Bay Typhoon Shelter
Section) under FEP-06/364/2009/A
4.4.5.
Inert and non-inert C&D waste
was disposed of in this reporting period. Details of the waste flow table are
summarized in Table 4.18.
Table 4.18 Details of Waste Disposal for Contract no. HY/2009/15
Inert C&D materials disposed |
23,506.5 |
141,651.7 |
Tuen Mun Area 38 |
|
95,892 |
96,785.5 |
TKO137 FB |
Inert C&D materials recycled |
2.9 |
415.9 |
N/A |
Non-inert C&D materials disposed |
121.5 |
230.7 |
SENT Landfill |
Non-inert C&D materials recycled |
47.59 |
369.9 |
N/A |
Chemical waste disposed |
200 |
8200 |
N/A |
Remark:s Contractor clarified and
updated waste flow table for the reporting month of January 2012 and the
cumulative sum of inert C&D materials has been updated in the March to May
2012 Quarterly Report. 
4.4.6.
Inert
C&D materials was recycled non-inert C&D waste was disposed of in this reporting period. Details
of the waste flow table are summarized in Table 5.19.
Table 4.19 Details of Waste Disposal for
Contract no. HY/2009/19
Inert C&D materials disposed |
61,739.63 |
85,618.44 |
N/A |
NIL |
1,801.91 |
N/A |
|
Non-inert C&D materials disposed |
378.99 |
461.39 |
SENT Landfill |
Non-inert C&D materials recycled |
27.81 |
42.7 |
N/A |
Chemical waste disposed |
2.35 |
4.13 |
N/A |
5.0.1.
The Event Action Plan for
construction noise and air quality are presented in Appendix 5.1.
Contract no. HY/2009/17
 Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling
works under FEP-03/364/2009
5.1.1.
No limit or
action level exceedance was recorded in this reporting period.
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB)  Central
Interchange under FEP-05/364/2009/A
Reporting month of March 2012
5.1.2.
No action and
two limit level exceednaces were recorded at M7e on 22 and 27 March 2012 in the
reporting month.
5.1.3.
During 22 March 2012 monitoring,
a limit level exceedance was recorded. 
After checking with contractor’s work schedules and investigation found
that drilling by drill rigs and breaking works for diaphragm wall construction
were conducted during monitoring.
5.1.4.
During 27 March 2012 monitoring,
a limit level exceedance was recorded. 
After checking with contractor’s work schedules and investigation found
that drilling by drill rigs, breaking works for diaphragm wall construction and
crane moving steel cages were conducted during monitoring.
5.1.5.
Both the limit level exceedances
were considered as project-related.
Reporting month of April 2012
5.1.6.
No limit and action level
exceedance was recorded during daytime of reporting month of April 2012.
Reporting month of May 2012
5.1.7.
No action and
one limit level exceedance was recorded at M7e on 30 April 2012 in the
reporting month.
5.1.8.
During 30 April 2012 monitoring,
a limit level exceedance was recorded. 
After checking with contractor’s work schedules and investigation found
that backhoe with breaker and excavator for diaphragm wall construction were
conducted during monitoring.
5.1.9.
The limit level exceedance was
considered as project-related.
Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works 
5.1.10.
No limit and
action level exceedance was recorded during the reporting period.
Contract nos. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East(CWB Tunnel)
5.1.11. No limit and action level exceedance was
recorded during the reporting period.
Contract no. HY/2009/15 - Central-Wanchai
Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) FEP-06/364/2009/A
5.1.12. No limit level exceedance was recorded
in the reporting period.
5.1.13.
One action
level exceedance was recorded in the reporting month as a complaint regarding
noise impact was received on 5 April 2012.
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
Reporting month of
March 2012
5.1.14.
One action
level exceedance was recorded as a complaint regarding noise impact was
received on 3 March 2012.
5.1.15.
Three limit level exceedances were
recorded at M6  HK Baptist Church Henrietta Secondary School on 28 February,
13 and 27 March 2012 in the reporting month.  /span>Investigation found that major traffic noise was contributed in
the noise monitoring and not related to the Project.
Reporting month of
April 2012
5.1.16.
One action
level exceedance was recorded in the reporting month as a complaint
regarding noise impact was received on 15 April 2012.
5.1.17.
One limit
level exceedance was recorded at M6  HK Baptist Church Henrietta Secondary
School on 2 April 2012 in the reporting month.  /span>Investigation found that major traffic noise was contributed in
the noise monitoring and not related to the Project.
Reporting month of
May 2012
5.1.18.
No action
level and two limit level exceedances were recorded at M6  HK Baptist Church Henrietta
Secondary School on 30 April and 16 May 2012 in the reporting month.  /span>Investigation found that major traffic noise was contributed in
the noise monitoring and not related to the Project.
Contract no. HY/2009/17  Central - Wan Chai Bypass (CWB) at FEHD
Whitfield Depot - Advanced piling works under
FEP-03/364/2009
5.2.1.
No exceedance
was recorded in the reporting period.
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB)  Central
Interchange under FEP-05/364/2009/A
5.2.2.
No exceedance was recorded in the
reporting period.
Contract nos. HK/2009/01 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works
5.2.3.
No exceedance was recorded in the
reporting period.
Contract nos. HK/2009/02 - Wan Chai Development Phase II - Central - Wan
Chai Bypass at Wan Chai East(CWB Tunnel)
5.2.4.
No exceedance was recorded in the
reporting period.
Contract no. HY/2009/15 - Central-Wanchai
Bypass  Tunnel (Causeway Bay Typhoon Shelter Section) FEP-06/364/2009/A
5.2.5.
No exceedance was recorded in the
reporting period.
Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
5.2.1
No exceedance was recorded in the
reporting period.
Contract no. HY/2009/17  Central - Wan Chai Bypass (CWB) at FEHD
Whitfield Depot - Advanced piling works under FEP-03/364/2009
5.3.1
No exceedance was recorded in the
reporting period.
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
5.3.2
No exceedance was recorded in the
reporting period.
5.4.1.
There was no non-compliance from
the site audits in the reporting period. During environmental site inspections
conducted during the reporting quarter, minor deficiencies were noted. However, the Contractor rectified all
deficiencies after receipt of notification.
5.5.1
There was no particular action
taken since no project-related non-compliance was recorded from the site audits
and environmental monitoring in the reporting period.
5.6.1
There was exceedance of noise level
recorded on 22 March 2012 at M7e that was considered in relation to drilling by
drill rigs and breaking works for diaphragm wall construction were conducted
during monitoring.
5.6.2
There was exceedance of noise level
recorded on 27 March 2012 at M7e that was considered in relation to the drilling
by drill rigs and breaking works for diaphragm wall construction.
5.6.3
There was exceedance of noise level
recorded on 30 April 2012 at M7e that was considered in relation to backhoe
with breaker and excavator for diaphragm wall construction were conducted
during monitoring.
6.0.1.
There was one environmental
complaint regarding construction noise impact received on 3 March 2012.
6.0.2.
There was one environmental complaint
regarding construction noise impact received on 5 April 2012.
6.0.3.
There was one environmental
complaint regarding construction noise impact received on 15 April 2012.
Reporting month of March 2012
6.0.4.
A noise impact complaint was
received by ET on 5 March 2012 (ICC Ref. No.: 1-344632511 dated on 3 March 2012, forwarded by RSS). The complaint was reported by
the resident of Harbour Heights that excessive noise from construction sites
of CWB was observed outside Harbour Heights from Monday to Saturday before 8am.
The plants were frequently turned on before 7:30am creating nuisance. The
complainant requested a speedy follow-up and reply from relevant department.
6.0.5.
ET confirmed with the Resident Site Staff
that PME for diaphragm wall construction started to operate at about
7:30am whilst the other PME, including those for land bored piling work,
started to operate after 8am.
6.0.6.
After reviewing the results of noise monitoring (M4b), no
exceedance was recorded during daytime period and the noise level was below 75dB(A). Site
inspection for HY/2009/19 was conducted on 7 March 2012. The condition of noise
mitigation measures near Harbour Heights was found satisfactory. RSS confirmed that no operation was active
before 7:00am everyday. The suspected nuisance was to be considered caused by
the PME for diaphragm wall construction. A surprise check was performed on 13
March 2012 by RSS. It was found that no noisy PME was in operation by
Contractor of HY/2009/19 before 8am, and the construction noise level was
minimal and not disturbing. The noise level and operation time both complied
with statutory requirements set up in NCO.
6.0.7.
Complainant called ICC on 8 March 2012 to confirm HyD has
provided a response. No further complaint was received after the response.
Reporting
month of April 2012
6.0.8.
A noise impact complaint was
received by ET on 5 April 2012 (ICC Ref. No.: 1-349030623 dated 5 April 2012, forwarded by RSS). The complaint was reported by an anonymous complainant that excessive noise from construction sites of CBTS
was observed daily before 7:30am except on public holidays, and the noise
source was mainly from piling works. 
The complainant requested that construction works should start after
8:30am to avoid nuisance to nearby residents and a speedy follow-up and reply.
6.0.9.
ET confirmed with the Resident Site Staff
that no piling works were performed during the concerned period.
6.0.10. After
reviewing the results of noise monitoring (M2b and M3a), no exceedance was
recorded during daytime period and the noise level was below 75dB(A). Site inspection
for HY/2009/15 was conducted on 10 April 2012. 
The condition of noise mitigation measures around CBTS was found
satisfactory. RSS confirmed that no pilings were performed during the concerned
period. The major works included
drilling, diaphragm wall construction and excavations.
6.0.11. HyD made a reply to the complainant on 16 April 2012 via
1823. HyD replied that the current
works at CBTS were drilling, diaphragm wall construction and deep excavations. 
In order to minimize the noise generated from the above works, the Contractor had erected temporary
noise barriers and provided noise blankets on plants. 
RSS would continue to work with the Contractor
on the effectiveness of the environmental mitigation measures implemented on
site. No further
complaint was received after the response.
6.0.12. A noise impact complaint was received by ET on 17 April 2012  /span>(ICC Ref. No.: 1-351021108 dated 15 April 2012, forwarded by RSS). The complaint was reported by
Ms. Law, a resident of Fu Lee Loy Mansion that noise generated from a HyD project that is located at the
connection point of CWB and IEC affecting nearby residents. Lately during the middle of the night
(around 00:00 to 05:00), low frequency noise, which possibly came from the
operating power generator and the barges which were parked along the Oil Street
work site, were making a nuisance to the complainant and residents nearby. The complainant requested that relevant
department should follow-up.
6.0.13. ET confirmed
with the Resident Site Staff that there was no operation of power generators
for HY/2009/19 and HY/2009/17 (HY/2009/11 had no physical work on site) during
the concerned period. Although there were a few barges mooring at the
seafront of HY/2009/19, they were not in operation and hence no operational
noise would be emitted.
6.0.14. After
reviewing the results of noise monitoring (M4b and M5b), no exceedance was
recorded during day time period and the noise level was below 75dB(A). Site
inspection for HY/2009/19 was conducted on 18 April 2012. The condition of noise mitigation measures
near Harbour Heights were found satisfactory. RSS confirmed that no operation
of power generators for HY/2009/19 and HY/2009/17 (HY/2009/11 had no physical
work on site) during the concerned period. Although there were a few
barges mooring at the seafront of HY/2009/19, they were not in operation and
hence no operational noise would be emitted.
6.0.15. HyD made a reply to the complainant on
30 April 2012 via email. HyD replied
that the current works near Oil Street, North Point, included CWB tunnel works,
IEC connections and associated foundation works. According to RSS records, no operations were performed during the
early hours of March and April at Oil Street and the waterbody nearby, and so
it was believed that the noise nuisance was not generated from the CWB
project. Despite that, RSS would continue to monitor the Contractor on the operations and
effectiveness of the environmental mitigation measures implemented on site, as
not to affect daily life of local residents nearby. No further complaint was received after the response.
Reporting month
of May 2012
6.0.19.
No
complaint was received in the May 2012 reporting month.
6.0.16. The details of cumulative complaint log and summary of complaints are
presented in Appendix 6.1.
6.0.17. No notification
of summons or prosecution was received in the reporting period. Cumulative statistic on complaints and successful prosecutions are
summarized in Table 6.1 and Table 6.2 respectively.
Table 6.1  Cumulative
Statistics on Complaints
Reporting Period |
No. of Complaints |
Commencement
of Works up to last reporting quarter |
17 |
March
 May 2012 |
3 |
Project-to-Date |
20 |
Table 6.2  Cumulative
Statistics on Successful Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this quarter (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
7.0.1.
According to Condition 3.4 of the
EP-364/2009/A, this section addresses the relevant cumulative construction
impact due to the concurrent activities of the current projects including the
Central Reclamation Phase III (CRIII), Wan Chai Development Phase II (WDII),
Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) and Wan Chai Development Phase II  Central
 Wan Chai Bypass at Wan Chai East (CWB Tunnel).
7.0.2.
According
to the Monthly EM&A report (April 2012) of Central Reclamation Phase III
(CRIII), filling works, building construction works and pipe works were
performed in the April 2012 reporting month. The water quality monitoring was
completed in October 2011 and no exceedance was recorded for air and noise
monitoring. It can be concluded that cumulative
construction impact due to the concurrent activities of the current projects with
the Central Reclamation Phase III (CRIII) was insignificant.
7.0.3.
According
to the construction programme of Wan Chai Development Phase II, Central-Wan
Chai Bypass and Island Eastern Corridor Link projects, the major construction
activity under Wan Chai Development Phase II was marine works at HKCEC areas, cross-harbour
Watermains, Fresh Watermains, Cooling Watermains and Salt Watermains
Installations, tunnel works at Wan Chai East, diaphragm wall construction at
TS4; dredging at TS2; deep excavation at TS1 and TPCWAE TCBR1W. Advanced piling
works at FEHD Whitfield Depot, Central Interchange, and diaphragm wall
construction at North Point area. The major environmental impact was water
quality impact at Causeway Bay and Wan Chai. Land-based construction activity
were Diaphragm wall construction at TS4, Diaphragm wall
construction at TS1 and TPCWAE TCBR1W, piling works at FEHD
Whitfield Depot, Diaphragm wall at Central and North Point and tunnel works at
Wan Chai East in the reporting month.
7.0.4.
The major
environmental impacts generated from advanced piling works at FEHD Whitfield
Depot were undertaken and sheet piling, pre-drilling and sheet piling works at
Central and tunnel works at Wan Chai East, IECL and Causeway Bay typhoon
shelter in the reporting quarter. Notwithstanding, three project-related exceedances regarding
construction noise were recorded during non-restricted hours referred to
Contract no. HY/2009/18 in the reporting period. In general, it is evaluated
that the cumulative construction impact from the concurrent projects including Wan
Chai Development Phase II was mainly insignificant.
8.0.1.
The EM&A programme was
carried out in accordance with the EM&A Manual requirements, minor alterations
to the programme proposed were made in response to changing circumstances.
Air quality monitoring
8.0.2.
No exceedance
was recorded.
Noise monitoring
8.0.3.
Six non-project related limit
level exceedances were recorded at M6 on 28 February, 13 March, 27 March, 2
April, 30 April and 16 May 2012 during day time. Moreover, three project
related limit level exceedances were recorded at M7e on 22 March, 27 March and
30 April 2012.
8.0.4.
Three action levels exceedances
were recorded regarding noise complaints referring to HY/2009/19 and HY2009/15
received on 3 March, 5 and 15 April 2012.
Real time noise monitoring
8.0.5.
No exceedance
was recorded.
8.0.6.
In this reporting quarter, a
total of 3 complaints were received. 
All complaints received were regarding noise impact.
8.0.7.
The construction
works of Contract no. 04/HY/2006  Reconstruction of Bus Terminus near Man Yiu
Street and Man Kwong Street under FEP-04/364/2009/A was completed, and the FEP
was surrendered by the Contractor on 11 February 2011.
8.0.8.
The construction programmes
of individual contracts are provided in Appendix 8.1.