Contract
No: HK/2011/07 Wanchai Development Phase II and Sampling, Field Measurement and
Testing Work (Stage 2) Environmental
Permit no. EP-364/2009/B, Further Evironmental permit nos. fep-01/364/2009,
fep-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEp-07/364/2009/a and
FEp-08/364/2009/a Quarterly Environmental Monitoring
and Audit Report
- DeCEMBER
2012 to February 2013 -
|
CLIENTS: |
|
Civil
Engineering and Development Department and Highways
Department |
Lam Geotechnics
Limited 11/F Centre
Point Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
27 March 2013 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
2.5 Principal Work and Activities
4.2. Real Time Noise Monitoring Results
5.4. Review of the Reasons for and the Implications of
Non-compliance
5.5. Summary of action taken in the event of and follow-up
on non-compliance
6. Complaints, Notification of Summons
and Prosecution
7. Cumulative Construction Impact due to
the Concurrent Projects
lIST
OF TABLES
Table I Principal Work Activities for Contract no. HY/2009/17
Table II Principal Work Activities for Contract no. HY/2009/18
Table III Principal Work Activities for Contract no. HK/2009/01
Table IV Principal Work Activities for Contract no. HK/2009/02
Table V Principal Work Activities for Contract no. HY/2009/15
Table VI Principal Work Activities for Contract no. HY/2009/19
Table 2.1 Schedule 2 Designated Projects under this Project
Table 2.2 Details of Individual Contracts under the Project
Table 2.3 Contact Details of Key Personnel
Table 2.4 Principal Work Activities for Contract no. HY/2009/17
Table 2.5 Principal Work Activities for Contract no. HY/2009/18
Table 2.6 Principal Work Activities for Contract no. HK/2009/01
Table 2.7 Principal Work Activities for Contract no. HK/2009/02
Table 2.8 Principal Work Activities for Contract no. HY/2009/15
Table 2.9 Principal
Work Activities for Contract no. HY/2009/19
Table 3.1 Noise Monitoring Station
Table 3.2 Real Time Noise Monitoring Station
Table 3.3 Air Monitoring Stations
Table 4.1 Noise Monitoring Stations for Contract no. HY/2009/17
Table 4.2
Noise Monitoring Station for Contract no.
HY/2009/18
Table 4.3
Noise Monitoring Stations for Contract nos.
HK/2009/01 and HK/2009/02
Table 4.4
Noise Monitoring Station for Contract nos.
HY/2009/15
Table 4.5 Noise Monitoring Stations for Contract no. HY/2009/19
Table 4.6 Real Time Noise Monitoring Station for Contract no. HY/2009/17
Table 4.7 Real Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 4.8 Air Monitoring Stations for Contract no. HY/2009/17
Table 4.9 Air Monitoring Stations for Contract no. HY/2009/18
Table 4.10 Air Monitoring Stations for Contract no. HK/2009/01
Table 4.11 Air Monitoring Station for Contract no. HK/2009/02
Table 4.12 Air Monitoring Station for Contract no. HY/2009/15
Table 4.13 Air Monitoring Stations for Contract no. HY/2009/19
Table 4.14 Details of Waste Disposal for Contract no. HY/2009/17
Table 4.15 Details of Waste Disposal for Contract no. HK/2009/01
Table 4.16 Details of Waste Disposal for Contract no. HK/2009/02
Table 4.17 Details of Waste Disposal for Contract no. HY/2009/18
Table 4.18 Details of Waste Disposal for Contract no. HY/2009/15
Table 4.19 Details of Waste Disposal for Contract no. HY/2009/19
Table 4.20 Details of
Waste Disposal for Contract no. HK/2010/06
Table 6.1 Cumulative Statistics on Complaints
Table 6.2 Cumulative Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure
2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 3.1 Locations of Environmental
Monitoring Stations
lIST OF APPENDIces
Appendix
2.1 Environmental
Mitigation Implementation Schedule
Appendix 3.1 Action and Limit Level
Appendix
4.1 Noise
Monitoring Results and Graphical Presentations
Appendix 4.2 Real-time Noise Monitoring
Results and Graphical Presentations
Appendix
4.3 Air
Quality Monitoring Results and Graphical Presentations
Appendix 5.1 Event Action Plans
Appendix 6.1 Complaint Log
Appendix 6.2 Notification of Exceedance
Appendix 8.1 Construction Programme of
Individual Contracts
EXECUTIVE
SUMMARY
Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling
works under FEP-03/364/2009
Major construction activities
for Contract no. HK/2009/17 have been commenced on 5 October 2010. During this
reporting period, the principal work activities for Contract no. HY/2009/17 are
summarized as below:
Table I Principal
Work Activities for Contract no. HY/2009/17
December 2012 |
January 2013 |
February 2013 |
No
further work under designated project |
No
further work under designated project |
No
further work under designated project |
Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB)
- Central Interchange under FEP-05/364/2009/A
Table II Principal Work
Activities for Contract no. HY/2009/18
December 2012 |
January 2013 |
February 2013 |
Excavation of
trial pit
Transplanting
of trees
Hoarding
erection and modification
Installation of
couplers, UU detection, trial trench, pre-drilling
Excavation
Sheet Piling
Drainage works
Tunnel works
Trough
structure construction and associated drilling and grouting
Road works
OHVD
installation
Pipe-piling
works
Pre-bored
H-piling
Bridge
construction |
Excavation of
trial pit
Transplanting
of trees
Hoarding
erection and modification
Installation of
couplers, UU detection, trial trench, pre-drilling
Excavation
Sheet Piling
Drainage works
Tunnel works
Trough
structure construction and associated drilling and grouting
Road works
OHVD
installation
Cooling main
bridge construction
Pre-bored
H-piling
Bridge
construction |
Excavation of trial pit Transplanting of trees Hoarding erection and modification Installation of couplers, UU
detection, trial trench, pre-drilling Excavation Sheet Piling Drainage works Tunnel works Trough structure construction and
associated drilling and grouting Road works OHVD installation Cooling main bridge construction Pre-bored H-piling Bridges construction |
Contract no. HK/2009/01 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at
Major construction activities
for Contract no. HK/2009/01 have been commenced on 25 August 2011. During this
reporting period, the principal work activities are summarized as below:
Table III Principal Work
Activities for Contract no. HK/2009/01
December 2012 |
January 2013 |
February 2013 |
Backfilling works on top of SCL
protection works. Jet grouting to HKCEC new extension
foundation. Plant mobilization for installation
of pre-bored H-pile works at Stage 1b & Stage 2 Pre-drilling works for CWB (Stage 2). |
Backfilling works on top of SCL
protection works Pre-bored H piling works for the
proposed CWB. Pre-drilling works for CWB (Stage 2) Ground treatment works for proposed
CWB diaphragm wall. Plant Mobilization for diaphragm wall
construction works at Stage 2. |
Backfilling works on top of SCL
protection works Pre-bored H piling works for the
proposed CWB stage 1b and pre-bored H piles excavation and grouting. Pre-drilling works for CWB (Stage 2). Diaphragm wall construction works at
Stage 2. Removal of remaining guide wall along
|
Contract no. HK/2009/02 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
Major construction activities
for Contract no. HK/2009/02 have been commenced on 26 April 2011. During this reporting period, the principal work
activities are summarized as below:
Table IV Principal Work
Activities for Contract no. HK/2009/02
December 2012 |
January 2013 |
February 2013 |
Trimming of pile head and blinding
laying construction at WCR1 of Tunnel Portion 1 Waterproofing installation at WCR1 of
Tunnel Portion 1 Bay 2 - Bay 7 together with Bay 8 Bay 16 Preparation works for extract the
western temporary sheetpile wall Diaphragm wall of panel P106, C107,
P108, C109, P110, C111, P112, P114, C115 & P116. Panel P113. Preparation works of saw cut Southern
Diaphragm wall for the connection between existing drainage and Bay 1 of Box
Culvert N1. Trial excavation, Footpath Set back,
UU Diversion and preparation works for Hung Hing Road Diversion Stage. Installation of precast concrete
short pipe extended from the existing 1800 drainage at Box Culvert N
landside. |
Placing concrete of the final portion
for precast scission seawall 2X Trimming of pile head at WCR1 of
Tunnel Portion 1 Blinding laying construction at WCR1
of Tunnel Portion 1 Waterproofing installation at WCR1 of
Tunnel Portion 1 Bay 1 - Bay 7 Rebar fixing for base slab. Backfilling of temporary sheet pile
seawall Extraction of total 150 nos. of
western temporary sheet piling. Casting of Diaphragm wall of panel
P106, C107, P108, C109, P110, C111, P112, C113, P114, C115 & P116. Total
11 out of 19 D-wall panels were completed. Panel BHP3 and BHP7 in Zone 3. Trial excavation, Footpath Set back,
UU Diversion and preparation works for Hung Hing Road Flyover Diversion Stage
1. |
Concrete surround for 1800 dia. concrete
pipe connecting between Bay 1 and the existing drainage. Concreting of base slab Bay3, Bay5 &
Bay7 was casted on 6 Feb 2013, 29 Jan 2013 & 19 Feb 2013 respectively. Waterproofing installation at WCR1 of
Tunnel Portion 1 Bay 11-16. Rebar fixing for base slab at WCR1 of
Tunnel Portion 1 Bay 3 - Bay 7. Bored piling works at WCR2 of Tunnel
Portion 2. Diaphragm wall of panel P106, C107,
P108, C109, P110, C111, P112, C113, P114, C115 & P116. Bored piles no. PN34, PC34, PC35 and PC36. Works associated with footpath modification
and proposed sewerage works for Hung Hing Road Flyover Diversion Stage 1. |
Contract no. HY/2009/15 - Central-Wanchai Bypass
Tunnel (
Major construction activities
for Contract no. HY/2009/15 has been commenced on 13 July 2011. During this
reporting period, the principal work activities are summarized as below:
Table V Principal Work Activities for Contract no.
HY/2009/15
January
2013 |
February
2013 |
|
Excavation and Lateral Support works
at TS4 Rock breaking works at TPCWAE Tunnel works at TS1 Bored piling at eastern breakwater Horizontal drilling for mined tunnel Pipe roofing installation |
Excavation and Lateral Support works
at TS4 Rock breaking works at TPCWAE Tunnel works at TS1 Horizontal drilling for mined tunnel Pipe roofing installation Construction of diaphragm at TS2 |
ELS works at TS4 Rock breaking works at TPCWAE Tunnel works at TS1 Horizontal drilling for mined tunnel Construction of Diaphragm Wall at TS2 |
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
Major construction activities
for Contract no. HY/2009/19 have been commenced on March 2011. During this
reporting period, the principal work activities are summarized as below:
Table VI Principal Work Activities for Contract no.
HY/2009/19
December 2012 |
January 2013 |
February 2013 |
Road works at
Bored piling
(Land)
Pre-drilling
works for bored pile and Diaphragm wall
D-wall Construction
(North & South Section)
Guide wall
construction for D-wall / Barrette at North side
Construction
works for Box Culvert T1
Marine Piling
Construct ion
of socket-H pile
Construction
works for Culvert U1
Construction of
1500f drainage pipe
Construction of
Pile cap & column (Land)
Dismantling of
marine platform
Cut & Cover
Tunnel sheet piling works
Construction of
dewatering well for Cut & Cover Tunnel
|
Road works at Bored piling (Land) Pre-drilling works for bored pile and
Diaphragm wall D-wall Construction (North &
South Section) Guide wall construction for D-wall /
Barrette at North side Construction works for Box Culvert T1 Marine Piling Construct ion of socket-H pile Construction works for Culvert U1 Construction of Pile cap & column
(Land) Dismantling of marine platform Demolition of parapet at IEC Link Construction of Pile caps &
columns (Marine) Cut & Cover Tunnel sheet piling
works and installation of King Post Construction of dewatering well for
Cut & Cover Tunnel |
Road works at Bored piling (Land) Pre-drilling works for bored pile and
Diaphragm wall D-wall Construction (North &
South Section) Guide wall construction for D-wall / Barrette
at North side Construction works for Box Culvert T1 Construct ion of socket-H pile Construction works for Culvert U1 Construction of Pile cap & column
(Land) Demolition of parapet at IEC Link Cut & Cover Tunnel sheet piling
works and installation of King Post D8-D9 Gantry Fabrication for precast
segment will continue Construction of dewatering well for
Cut & Cover Tunnel ELS for Cut & Cover Tunnel |
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
Table
VII
Principal Work Activities for Contract
no. HK/2010/06
December 2012 |
January 2013 |
February 2013 |
Construction
of pre-cast unit in |
Utility works in section 2 |
Utility works in section 2 |
Noise Monitoring
Real
time Noise Monitoring
Air Quality Monitoring
Complaints, Notifications of
Summons and Successful Prosecutions
1.1.1.
Lam
Geotechnics Limited (LGL) has been appointed to work as the Environmental Team
(ET) under Environmental Permit no. EP-364/2009A and Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A and FEP-08/364/2009/A to
implement the Environmental Monitoring and Audit (EM&A) programme as stipulated
in the EM&A Manual of the approved Environmental Impact Assessment (EIA)
Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register
No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for
Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No.
AEIAR-014/2001).
1.1.2.
This
report presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.3 of
EM&A Manual and Environmental Monitoring and Audit Requirements
under Particular Specification Section 27.
1.1.3.
This
report documents the finding of EM&A works during the period from December 2012 to February 2013.
Section 1 Introduction details the scope and structure of the
report.
Section 2 Project Background summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section 3 Monitoring Requirements summarizes all monitoring parameters,
monitoring locations, monitoring frequency, duration and action plan.
Section 4 Monitoring Results summarizes the monitoring results
obtained in the reporting period.
Section 5 Compliance Audit summarizes the auditing of monitoring results, all
exceedances environmental parameters.
Section 6 Complaints,
Notification of summons and Prosecution summarizes the cumulative
statistics on complaints, notification of summons and prosecution
Section 7 Cumulative
Construction Impact due to the Concurrent Projects summarizes the
relevant cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section 8 Conclusion
2.1.1.
Wan
Chai Development phase II and Central-Wan Chai Bypass and Central-Wan Chai
Bypass and Island Eastern Corridor Link (hereafter called the Project) are
Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap.
499) (EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The
key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan
Chai North and North Point for construction of the Central-Wan Chai Bypass and
Island Eastern Corridor Link (CWB). Land formed under the project will be
developed as a world-class waterfront promenade joining that at the new Central
waterfront for public enjoyment.
2.1.3.
There
is a compelling and present need for the CWB to provide relief to the very
congested
2.2.1.
Design and Construction of Central Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The
study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB)
and Island Eastern Corridor Link (IECL) includes:
·
A dual three-lane trunk road, approximately 4.5 km
in length, and tunnel approximately 3.7 km in length defined from the
connection with the existing Rumsey Street Flyover in Central, through to a
connection with the existing Island Eastern Corridor to the east of the
Causeway Bay Typhoon Shelter (CBTS);
·
The Central Interchange near the Rumsey Street
Flyover to provide road connections to the Central area;
·
Tunnel control buildings and ventilation buildings;
·
Slip roads to connect the CWB to the local road
system in the Wan Chai North and
·
Associated road lighting, road signing, traffic
control and surveillance system; and
·
Other associated works.
2.2.3.
The
project also contains various Schedule 2 DPs that, under the EIAO, require
Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five
individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table
2.1 Schedule 2 Designated Projects
under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due
to the multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be
commenced. Contractors of individual
contracts will be required by the EP holder to apply Further Environmental Permits such that the impact monitoring stations are
sub-divided accordingly to facilitate the implementation of EM&A programme
and to streamline the EM&A reporting for individual FEP holders
correspondingly.
2.3.2.
In
the reporting period, all the contracts were commenced and contract no.
04/HY/2006 had been completed. The details of individual contracts are
summarized in Table2.2.
Table
2.2 Details of Individual Contracts
under the Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HY/2009/17 |
Central Wan Chai Bypass (CWB) at FEHD Whitfield Depot Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central Wan Chai Bypass (CWB) Central Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 |
HK/2009/01 |
Wan Chai Development Phase II Central Wan Chai Bypass at |
DP1, DP2 |
25 August 2011 |
HK/2009/02 |
Wan Chai Development Phase II Central Wan Chai Bypass at Wan Chai
East(CWB Tunnel) |
DP1 |
26 April 2011 |
HY/2009/15 |
Central-Wanchai Bypass Tunnel ( |
DP1 |
13 July 2011 |
HY/2009/19 |
Central Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively.
For the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure
2.2. Key personnel and contact particulars are
summarized in Table 2.3:
Table 2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineers Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineers Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3916 1818 |
3529 2829 |
|
Lam
Woo & CO., LTD. |
Contractor under Contract no. HY/2009/17 |
General Manager |
Mr. Thomas Tang |
6111 5351 |
2566
7522 |
Contractors Representative |
Mr. Chung Man Shek |
2566 4866 |
2566
7522 |
||
Site Agent |
Mr. Tony Au |
9725 5874 |
2566 7522 |
||
Environmental Officer |
Dr. Priscilla Choy |
9161 7287 |
2566 7522 |
||
Environmental Supervisor |
Mr. Tam Chun Pong |
6461 3062 |
2566 7522 |
||
Chun
Wo Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Joint Venture Board Representative |
|
2162 9909 |
2634 1626 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Sub Agent |
Mr. Terry Wong |
9757 9846 |
|||
Construction
Manager |
Mr. Wyman Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Jack Chu |
9775 2467 |
|||
Construction
Manager |
Mr. Andy Yu |
9648 4896 |
|||
Environmental
Officer (Compliance Manager) |
Mr. Andy Mak |
9103 2370 |
|||
Chun Wo CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project Manager |
Mr. Chan Sing Cho |
3658-3002 |
2827 9996 |
Quality & Environmental Manager (Environmental Officer) |
Mr. C.P. Ho |
3658-3000 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570 8013 |
Site Agent |
Mr. Cheung Kit Cheung |
6909 1555 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Environmental Engineer |
|
9286 9208 |
|||
Construction Manager (Marine) |
William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
Construction Manager (Land) |
Eric Fong |
6191 9337 |
|||
Operation Manager (Land) |
Yung Kwok Wah |
9834 1010 |
|||
Leighton Contractors ( |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Brian Gillon |
2214
7700 |
2140 6799 |
Deputy Site Agent |
Mr Roger Wong |
2214
7703 |
|||
Environmental Officer |
Mr. Anfernee Chow |
2214 7721 |
|||
Environmental Engineer Graduate |
Phil Mak |
2214
7738 |
|||
Environmental Supervisor |
K. P. Lai |
6461 4660 |
|||
Environmental Supervisor |
Ray Cheng |
22147742 |
|||
Environmental Supervisor |
Bosco Lee |
22147711 |
|||
Environmental Supervisor |
Ryan Tsui |
2214 7705 |
|||
|
Contractor under Contract no. HY/2009/15 |
Project Director |
Mr. Chan Wai Hung |
2823 7879 |
2566 2192 |
Site Agent |
Mr. P J Fan |
3557 6368 |
|||
Contractors
Representative |
Mr. David Lau |
3557
6358 |
|||
Head of construction |
Mr. Roger Cheung |
3557 6371 |
|||
Environmental Officer |
Mr. Daniel Sin |
3557 6215 |
|||
Enviromental Supervisor |
Ms Esther Choi |
35576348 |
|||
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project
Manager |
Mr. Paul Lui |
9095 7922 |
2529
2880 |
Site
Agent |
Mr. Keith Tse |
2529 2068 |
|||
Environmental
Officer |
Mr. Lee
Wai Man |
9481 6024 |
|||
Environmental
Supervisor |
Mr.
Clement Pang |
9735 9200 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.5.1.
Major construction activities for Contract no.
HK/2009/17 have been commenced on 5 October 2010. During
this reporting period, the principal work activities for Contract no. HY/2009/17
are summarized in Table2.4.
Table
2.4 Principal
Work Activities for Contract no. HY/2009/17
December
2012 |
January
2013 |
February
2013 |
No further work under designated
project |
No further work under designated
project |
No further work under designated
project |
Table 2.5 Principal Work Activities for Contract no.
HY/2009/18
December
2012 |
January
2013 |
February
2013 |
Excavation of
trial pit
Transplanting
of trees
Hoarding
erection and modification
Installation of
couplers, UU detection, trial trench, pre-drilling
Excavation
Sheet Piling
Drainage works
Tunnel works
Trough
structure construction and associated drilling and grouting
Road works
OHVD
installation
Pipe-piling
works
Pre-bored
H-piling
Bridge
construction |
Excavation of
trial pit
Transplanting
of trees
Hoarding
erection and modification
Installation of
couplers, UU detection, trial trench, pre-drilling
Excavation
Sheet Piling
Drainage works
Tunnel works
Trough
structure construction and associated drilling and grouting
Road works
OHVD
installation
Cooling main
bridge construction
Pre-bored
H-piling
Bridge
construction |
Excavation of trial pit
Transplanting of trees
Hoarding erection and modification
Installation of couplers, UU detection, trial trench, pre-drilling
Excavation
Sheet Piling
Drainage works
Tunnel works
Trough structure construction and associated drilling and grouting
Road works
OHVD installation
Cooling main bridge construction
Pre-bored H-piling
Bridges construction |
2.5.3.
Major construction activities for Contract no.
HK/2009/01 have been commenced on 25 August 2011. During this reporting period,
the principal work activities are summarized in Table2.6:
Table 2.6 Principal Work Activities for Contract no. HK/2009/01
December
2012 |
January
2013 |
February
2013 |
Backfilling works on top of SCL protection works.
Jet grouting to HKCEC new extension foundation.
Plant mobilization for installation of pre-bored H-pile works at Stage
1b & Stage 2
Pre-drilling works for CWB (Stage 2). subsequent pre-bored H piling works |
Backfilling works on top of SCL protection works
Pre-bored H piling works for the proposed CWB.
Pre-drilling works for CWB (Stage 2)
Ground treatment works for proposed CWB diaphragm wall.
Plant Mobilization for diaphragm wall construction works at Stage 2. |
Backfilling works on top of SCL protection works
Pre-bored H piling works for the proposed CWB stage 1b and pre-bored H
piles excavation and grouting.
Pre-drilling works for CWB (Stage 2).
Diaphragm wall construction works at Stage 2. Removal of remaining guide wall along
|
2.5.4.
Major construction activities for Contract no.
HK/2009/02 have been commenced on 26 April 2011. During this reporting period, the principal work activities are
summarized in Table2.7:
Table 2.7 Principal Work Activities for Contract no. HK/2009/02
December
2012 |
January
2013 |
February
2013 |
Trimming of pile head and blinding laying construction at WCR1 of
Tunnel Portion 1
Waterproofing installation at WCR1 of Tunnel Portion 1 Bay 2 - Bay 7
together with Bay 8 Bay 16
Preparation works for extract the western temporary sheetpile wall
Diaphragm wall of panel P106, C107, P108, C109, P110, C111, P112,
P114, C115 & P116. Panel P113.
Preparation works of saw cut Southern Diaphragm wall for the
connection between existing drainage and Bay 1 of Box Culvert N1.
Trial excavation, Footpath Set back, UU Diversion and preparation
works for Hung Hing Road Diversion Stage.
Installation of precast concrete short pipe extended from the existing
1800 drainage at Box Culvert N landside. |
Placing concrete of the final portion for precast scission seawall 2X
Trimming of pile head at WCR1 of Tunnel Portion 1
Blinding laying construction at WCR1 of Tunnel Portion 1
Waterproofing installation at WCR1 of Tunnel Portion 1 Bay 1 - Bay 7
Rebar fixing for base slab.
Backfilling of temporary sheet pile seawall
Extraction of total 150 nos. of western temporary sheet piling.
Casting of Diaphragm wall of panel P106, C107, P108, C109, P110, C111,
P112, C113, P114, C115 & P116. Total 11 out of 19 D-wall panels were
completed.
Panel BHP3 and BHP7 in Zone 3.
Trial excavation, Footpath Set back, UU Diversion and preparation
works for Hung Hing Road Flyover Diversion Stage 1. |
Concrete surround for 1800 dia. concrete pipe connecting between Bay 1
and the existing drainage.
Concreting of base slab Bay3,
Bay5 & Bay7 was casted on 6 Feb 2013, 29 Jan 2013 & 19 Feb 2013
respectively.
Waterproofing installation at
WCR1 of Tunnel Portion 1 Bay 11-16.
Rebar fixing for base slab at WCR1 of Tunnel Portion 1 Bay 3 - Bay 7.
Bored piling works at WCR2 of Tunnel Portion 2.
Diaphragm wall of panel P106, C107, P108, C109, P110, C111, P112,
C113, P114, C115 & P116.
Bored piles no. PN34, PC34,
PC35 and PC36.
Works associated with footpath modification
and proposed sewerage works for Hung Hing Road Flyover Diversion Stage 1. |
2.5.5.
Major construction activities for Contract no.
HY/2009/15 have been commenced on 13 July 2011. During this reporting period,
the principal work activities are summarized in Table
2.8:
Table 2.8 Principal Work
Activities for Contract no. HY/2009/15
December 2012 |
January 2013 |
February 2013 |
Excavation and Lateral Support works at TS4
Rock breaking works at TPCWAE
Tunnel works at TS1
Bored piling at eastern breakwater
Horizontal drilling for mined tunnel
Pipe roofing installation |
Excavation and Lateral Support works at TS4
Rock breaking works at TPCWAE
Tunnel works at TS1
Horizontal drilling for mined tunnel
Pipe roofing installation
Construction of diaphragm at TS2 |
ELS works at TS4
Rock breaking works at TPCWAE
Tunnel works at TS1
Horizontal drilling for mined tunnel
Construction of Diaphragm Wall at TS2 |
2.5.6.
Major construction activities for Contract no.
HY/2009/19 have been commenced on March 2011. During this reporting period, the
principal work activities are summarized in Table
2.9:
Table 2.9 Principal Work Activities for Contract no.
HY/2009/19
December
2012 |
January
2013 |
February
2013 |
Road works at
Bored piling
(Land)
Pre-drilling
works for bored pile and Diaphragm wall
D-wall Construction
(North & South Section)
Guide wall
construction for D-wall / Barrette at North side
Construction
works for Box Culvert T1
Marine Piling
Construct ion
of socket-H pile
Construction
works for Culvert U1
Construction of
1500f drainage pipe
Construction of
Pile cap & column (Land)
Dismantling of
marine platform
Cut & Cover
Tunnel sheet piling works
Construction of
dewatering well for Cut & Cover Tunnel
|
Road works at
Bored piling (Land)
Pre-drilling works for bored pile and Diaphragm wall
D-wall Construction (North & South Section)
Guide wall construction for D-wall / Barrette at North side
Construction works for Box Culvert T1
Marine Piling
Construct ion of socket-H pile
Construction works for Culvert U1
Construction of Pile cap & column (Land)
Dismantling of marine platform
Demolition of parapet at IEC Link
Construction of Pile caps & columns (Marine)
Cut & Cover Tunnel sheet piling works and installation of King
Post
Construction of dewatering well for Cut & Cover Tunnel |
Road works at
Bored piling (Land)
Pre-drilling works for bored pile and Diaphragm wall
D-wall Construction (North & South Section)
Guide wall construction for D-wall / Barrette at North side
Construction works for Box Culvert T1
Construct ion of socket-H pile
Construction works for Culvert U1
Construction of Pile cap & column (Land)
Demolition of parapet at IEC Link
Cut & Cover Tunnel sheet piling works and installation of King
Post
D8-D9 Gantry Fabrication for precast segment will continue
Construction of dewatering well for Cut & Cover Tunnel
ELS for Cut & Cover Tunnel
|
2.5.7.
Major construction activities for Contract no.
HK/2010/06 have been commenced on March 2011. During this reporting period, the
principal work activities are summarized in Table
2.10:
Table 2.10 Principal Work Activities for Contract no. HK/2010/06
December
2012 |
January
2013 |
February
2013 |
Construction
of pre-cast unit in |
Utility works in section 2 |
Utility works in section 2 |
2.5.8.
Implementation
status of the recommended mitigation measures during this reporting period is
presented in Appendix 2.1.
3.1.1.
The
noise monitoring stations for the Project are listed and shown in Table
3.1 and Figure 3.1. Appendix 3.1 shows
the established Action/Limit Levels for the monitoring works.
Table 3.1 Noise Monitoring Station
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun
Area |
M3a |
Tung Lo Wan
Fire Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
*M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
M8 |
City Hall |
* Remark 1: Location
ID has been updated from M7 to M8 for City Hall
* Remark 2: M7e has
become a reference station starting from 7 Aug 2012
Real time Noise Monitoring Stations
3.1.2.
The
noise monitoring stations for the Project are listed and shown in Table 3.2 and Figure 3.1.. Appendix 3.1
shows the established Action/Limit Levels for the monitoring works.
Table
3.2 Real Time Noise Monitoring Station
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section Whitefield Depot |
North Point |
RTN2a |
Electric Centre
(Replacement of RTN2) |
North Point |
RTN3 |
Pok Leung Kuk Yu |
Tin Hau |
RTN4 |
|
* RTN2 was relocated from Oil Street Community Liaison Centre to
Electric Centre on
05 Oct 2012 and re-designated
as RTN2a.
Noise Monitoring Parameters,
Frequency and Duration
3.1.3.
The construction noise level shall be measured in terms of
the A-weighted equivalent continuous sound pressure level (Leq). Leq (30
minutes) shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For
all other time periods, Leq (5 minutes) shall be employed for
comparison with the Noise Control Ordinance (NCO) criteria.
Supplementary information for data auditing, statistical results such as L10
and L90 shall also be obtained for reference.
3.1.4.
Noise
monitoring shall be carried out at all the designated monitoring stations. The
monitoring frequency shall depend on the scale of the construction activities.
The following is an initial guide on the regular monitoring frequency for each
station on a weekly basis when noise generating activities are underway:
·
One
set of measurements between 0700 and 1900 hours on normal weekdays.
3.1.5.
Real
time noise shall be carried out at the designated monitoring stations. The
following is an initial guide on the regular monitoring frequency for each
station on a 24 hours daily basis when noise generating activities are
underway:
·
One
set of measurements between 0700 and 1900 hours on normal weekdays.
·
One
set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and
2300 hours on public holidays.
·
One
set of measurements between 2300 and 0700 hours on next day on everyday.
3.1.6.
If
construction works are extended to include works during the hours of 1900
0700 as well as public holidays and Sundays, additional weekly impact
monitoring shall be carried out during respective restricted hours periods.
Applicable permits under NCO shall be obtained by the Contractor.
Monitoring Equipment
3.1.7.
As
referred to in the Technical Memorandum issued under the NCO, sound level
meters in compliance with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be
used for carrying out the noise monitoring. Immediately prior to and following
each noise measurement the accuracy of the sound level meter shall be checked
using an acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agree to within 1.0 dB.
3.1.8.
Noise
measurements shall not be made in fog, rain, wind with a steady speed exceeding
5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with
a portable wind speed meter capable of measuring the wind speed in m/s.
3.1.9.
The
sound level meter shall be checked using an acoustic calibrator generating a
known sound pressure level at a known frequency before deployment to the site
and during each site visit. Measurements may be accepted as valid only if the
calibration level from before and after the noise measurement agree to within
1.0 dB.
Air Quality Monitoring
Stations
3.2.1. The air monitoring stations for the Project are
listed and shown in Table 3.3 and Figure 3.1. Appendix 3.1 shows the established
Action/Limit Levels for the monitoring works.
Table 3.3 Air Monitoring Stations
Station ID |
Monitoring
Location |
Description |
CMA1b |
Oil Street Community
Liaison Centre |
North Point |
CMA2a |
|
|
CMA3a |
Future CWB site office
at Wanchai Waterfront Promenade |
|
CMA4a |
Society for the
Prevention of Cruelty to Animals |
Wan Chai |
CMA5a |
Children Playgrounds
opposite to |
Wan Chai |
CMA6a |
Future AECOM site
office at Work Area |
Wan Chai |
MA1e |
International Finance Centre (Eastern End of Podium) |
Central |
MA1w |
International Finance Centre (Western End of Podium) |
Central |
Air Monitoring Parameters,
Frequency and Duration
3.2.2. One-hour and 24-hour TSP levels should be measured
to indicate the impacts of construction dust on air quality. The 24-hour TSP
levels shall be measured by following the standard high volume sampling method
as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part
50), Appendix B.
3.2.3. All relevant data including temperature, pressure,
weather conditions, elapsed-time meter reading for the start and stop of the
sampler, identification and weight of the filter paper, and any other local
atmospheric factors affecting or affected by site conditions, etc., shall be
recorded down in detail.
3.2.4. For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
Sampling Procedure and
Monitoring Equipment
3.2.5. High volume samplers (HVSs) in compliance with the
following specifications shall be used for carrying out the 1-hour and 24-hour
TSP monitoring:
·
0.6
1.7 m3 per minute adjustable flow range;
·
Equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours
operation;
·
Installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
·
Capable
of providing a minimum exposed area of 406 cm2;
·
Flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
·
Equipped
with a shelter to protect the filter and sampler;
·
Incorporated
with an electronic mass flow rate controller or other equivalent devices;
·
Equipped
with a flow recorder for continuous monitoring;
·
Provided
with a peaked roof inlet;
·
Incorporated
with a manometer;
·
Able
to hold and seal the filter paper to the sampler housing at horizontal
position;
·
Easily
changeable filter; and
·
Capable
of operating continuously for a 24-hour period.
3.2.6. Initial calibration of dust monitoring equipment
shall be conducted upon installation and thereafter at bi-monthly intervals.
The transfer standard shall be traceable to the internationally recognized
primary standard and be calibrated annually. The concern parties such as IEC
shall properly document the calibration data for future reference. All the data
should be converted into standard temperature and pressure condition.
3.2.7. Laboratory Measurement / Analysis
3.2.8. A clean laboratory with constant temperature and
humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be HOKLAS
accredited.
3.2.9. Filter paper of size 8 x 10 shall be labelled
before sampling. It shall be a clean filter paper with no pinholes, and shall
be conditioned in a humidity-controlled chamber for over 24-hours and be
pre-weighed before use for the sampling.
3.2.10. After sampling, the filter paper loaded with dust
shall be kept in a clean and tightly sealed plastic bag. The filter paper shall
then be returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
readout down to 0.1 mg. The balance shall be regularly calibrated against a
traceable standard.
3.2.11. All the collected samples shall be kept in a good
condition for 6 months before disposal.
4.0.1. Per EPDs letter
dated 3 Aug 2012 (received by ET on 6 Aug 2012 through HyD), noise monitoring
at M8 City Hall commenced on 7 Aug 2012, and the monitoring station M7e
International Finance Centre (Eastern Podium) has become a reference station
starting from 7 Aug 2012.
4.0.2. Due to safety
concerns, the monitoring location for M4b Victoria Centre has been finely
adjusted from 7 June 2012.
4.0.3. Monitoring for report of review baseline noise
level was performed from 11 April 2011 to 8 June 2011. Then the report was submitted on the 20 June
2011, verified by IEC on 18 July 2011 and was approved by ER by January
2012. The new baseline is used for the
noise calculation starting from the January 2012 reporting month.
4.0.4. The environmental monitoring will be implemented
based on the division of works areas of each designed project managed under
different contracts with separate FEP applied by individual contractors. Overall layout showing work areas of various
contracts, latest status of work commencement and monitoring stations is shown
in Figure
2.1 and Figure 3.1. The monitoring results
are presented in according to the Individual Contract(s).
4.0.5. In the reporting period, the concurrent contracts are
as follows:
Contract
no. HY/2009/15 Central-Wanchai Bypass Tunnel (
Contract
no. HY/2009/17 Central Wanchai Bypass (CWB) at FEHD Whitfield Depot
Advanced piling works under FEP-03/364/2009
Contract
no. HY/2009/18 Central Wanchai Bypass (CWB) Central Interchange under
FEP-05/364/2009/A
Contract
no. HY/2009/19 Central Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009
Contract
no. HK/2009/01 Wanchai Development Phase II Central Wanchai Bypass at
Contract
no. HK/2009/02 Wanchai Development Phase II Central- Wanchai Bypass at Wanchai
East
Contract
no. HY/2009/17 Central Wanchai Bypass (CWB) at FEHD Whitfield Depot
Advanced piling works under FEP-03/364/2009
4.1.1.
The
proposed division of noise monitoring stations for Contract no. HY/2009/17 is
summarized in Table 4.1 below:
Table
4.1 Noise Monitoring Stations for Contract no. HY/2009/17
Station |
Description |
M4b |
Victoria Centre |
4.1.2.
No
exceedance was recorded in this reporting quarter.
4.1.3.
Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of graphical
presentation can be referred in Appendix 4.1.
Contract no.
HY/2009/18 Central Wanchai Bypass (CWB) Central Interchange under
FEP-05/364/2009/A
4.1.4.
Noise
monitoring for the Central Interchange works under contract no. HY/2009/18 was
commenced on 22 April 2011.The proposed division of noise monitoring stations
for Contract no. HY/2009/18 are summarized in Table 4.2 below.
Table 4.2 Noise Monitoring Station for Contract no. HY/2009/18
Station |
Description |
*M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
M8 |
City Hall |
* Remark : M7e has become a reference station starting from 7 Aug 2012
Reporting month of December 2012
4.1.5.
No action level and one limit level exceedance was recorded at M8- City Hall on 27 Dec 2012 in the
reporting month. Tourist gathering at City Hall and no
major construction activities were observed during monitoring. As such, the exceedance
was considered as non project related.
4.1.6. Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 4.1.
Contract no. HK/2009/01 - Wanchai Development Phase
II - Central - Wanchai Bypass at Hong Kong Convention and Exhibition Centre -
Tunnel Works under FEP-02/364/2009 and Contract no. HK/2009/02 - Wanchai
Development Phase II - Central - Wanchai Bypass at Wanchai East (CWB Tunnel)
under FEP-01/364/2009
4.1.7.
The
commencement of construction works for Contract no. HK/2009/01 under
FEP-02/364/2009 is on 25 August 2011
and HK/2009/02 under FEP-01/364/2009 is on 26 April 2011.The proposed division
of air monitoring stations are summarized in Table 4.3 below.
Table 4.3 Noise Monitoring Stations for
Contract nos. HK/2009/01 and HK/2009/02
Station |
Description |
M1a |
Harbour Road Sports Centre |
Reporting
month of January 2013
4.1.8.
No action level and one limit level exceedance was recorded on 24 Jan 2013 in the reporting month. Non-CWB project drilling works nearby was observed during noise
monitoring and considered as the major noise contribution. As such, the exceedance was not related to
the Project.
Reporting
month of February 2013
4.1.9.
No action level and one limit level exceedances
was recorded on 29 Jan 2013 in the reporting month. Non-CWB project drilling
works nearby was observed during noise monitoring and considered as the major
noise contribution. As such, the exceedance was not related to the Project.
4.1.10. Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 4.1.
Contract no.
HY/2009/15 - Central-Wanchai Bypass Tunnel (
4.1.11.
The
commencement of construction works for Contract no. HY/2009/15 under
FEP-06/364/2009/A was on 13 July 2011. Noise
monitoring was commenced on 13 July 2011. The proposed
division of noise monitoring stations are summarized in in Table 4.4 below.
Table 4.4 Noise
Monitoring Station for Contract nos. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
4.1.12. No exceedance was recorded in this
reporting quarter.
4.1.13. Details of
noise monitoring results and graphical presentation can be referred in Appendix 4.1.
4.1.14. Noise monitoring for the tunnel works under
contract no. HY/2009/19 was commenced on 24 April 2011. The proposed division
of noise monitoring stations are summarized in Table 4.5 below.
Table
4.5
Noise Monitoring Stations
for Contract no. HY/2009/19
Station |
Description |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
Reporting
month of December 2012
4.1.15.
No action level and four limit level exceedances were recorded on 29 Nov, 11, 17 and 27 Dec 2012
at M6 HK Baptist Church Henrietta Secondary School during the reporting month.
Major traffic was observed during
monitoring and considered as the major noise contribution, the limit level
exceedances were considered as non-project related.
Reporting
month of January 2013
4.1.16.
No action level and four limit level exceedances were recorded on 3,8,15 and 24 January 2013 at
M6 HK Baptist Church Henrietta Secondary School during the reporting month. Major traffic was observed during monitoring
and considered as the major noise contribution, the limit level exceedances
were considered as non-project related.
Reporting
month of February 2013
4.1.17.
No action level and five limit level exceedance was recorded on 29 Jan,
7, 15, 19 and 26 2013 at M6 HK Baptist Church Henrietta
Secondary School in the reporting month.
Major traffic was observed during
monitoring and considered as the major noise contribution, the limit level
exceedances were considered as non-project related.
4.1.18. Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 4.1 and the
Notification of Exceedance can be referred in Appendix 6.2.
Contract no. HY/2009/17 Central - Wanchai Bypass
(CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009 and Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
4.2.1.
The
proposed division of real time noise monitoring stations are summarized in Table
4.6 below. Real time noise monitoring for the piling works under
contract no. HY/2009/17 was commenced on 5 October 2010.
Table
4.6 Real Time Noise Monitoring
Station for Contract no. HY/2009/17
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD Hong Kong Transport Section Whitefield Depot |
Real
time noise monitoring results and graphical presentation during night time
period are for information only.
4.2.2.
No action and limit level exceedance was recorded
during the December reporting month.
4.2.3.
Limit level Exceedances were recorded at
RTN1-FEHD Hong Kong Transport Section Whitfield Depot on 3 Jan 2013 and 16 Jan
2013. After checking with contractor, no noisy activities were undertaken
during monitoring and exceedances were contributed by non-designated project
works and nearby IEC traffic. As such, the exceedances were concluded as non
project related.
4.2.4.
Limit level Exceedances were recorded at
RTN1-FEHD Hong Kong Transport Section Whitfield Depot during daytime on 2 Feb
2013 and during restricted hours on 11 and 25 Feb 2013. After checking with
contractor, on 2 Feb 2013 no construction activities under designated project
were undertaken during the recorded period and exceedances were considered to
be contributed by non-designated project works at nearby construction site. On 11
Feb 2013, no construction activities were conducted and the exceedances were
contributed by Chinese New Year pyrotechnic display. On 25 Feb 2013, no
construction activities under designated project were conducted and the exceedances
were contributed by nearby IEC traffic. As such, the exceedances were concluded
as non project related.
4.2.5.
Real
time noise monitoring results measured in this reporting period are reviewed
and summarized. Details
of real time noise monitoring results and graphical presentation can be
referred to Appendix
4.2
4.2.6.
The
proposed division of noise monitoring stations are summarized in Table 4.7
below. Real time noise monitoring for major construction works under contract
no. HY/2009/19 was commenced on 24 April 2011.
Table
4.7 Real Time Noise Monitoring
Stations for Contract no. HY/2009/19
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD Hong Kong Transport Section Whitefield Depot |
RTN2a |
North Point |
Electric Centre
(Replacement of RTN2) |
RTN3 |
North Point |
Pok Leung Kuk Yu |
RTN4 |
Tin Hau |
|
* Real time noise monitoring results and graphical presentation during
night time period are for information only.
*Real-time noise monitoring results and graphical presentation for RTN3
during restricted hours are for information only as no night classes were
conducted at the educational institute.
Reporting
month of December 2012
4.2.7.
No action or limit level exceedance was
recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the December
reporting month.
4.2.8.
A limit level exceedance was recorded at
RTN2a-Electric Centre on 7 Dec 2012 in the reporting month. After checking with
contractor, no major noisy construction works were conducted during the time
period and the non CWB project construction activities near Electric Centre was
considered to be the major source of noise impact. As such, the exceedance was
concluded as non-project related.
Reporting
month of January 2013
4.2.9.
Limit level Exceedances were recorded at
RTN1-FEHD Hong Kong Transport Section Whitfield Depot on 3 and 16 Jan 2013 in
the reporting month. After checking with contractor, no noisy activities were
undertaken during monitoring and exceedances were contributed by no designated
project works and nearby IEC traffic. As such, the exceedances were concluded
as non project related.
4.2.10.
No action and limit level exceedance was
recorded at RTN2a-Electric Centre during the reporting month.
Reporting month
of February 2013
4.2.11.
Limit level exceedances were recorded at RTN1-FEHD Hong Kong Transport
Section Whitfield Depot during daytime on 2 Feb 2013 and during restricted
hours on 11 and 25 Feb 2013. After checking with contractor, on 2 Feb 2013 no
noisy activities were undertaken during the recorded period and exceedances
were contributed by non-designated project works at nearby construction site.
On 11 Feb 2013, no construction activities were conducted and the exceedances
were contributed by pyrotechnic display during Chinese New Year holiday. On 25
Feb 2013, no noisy construction activities were undertaken during the recorded
period. The exceedances were non-continuous and contributed by nearby IEC
traffic. As such, the exceedances were concluded as non project related.
4.2.12.
Limit level exceedances were recorded at RTN2a-Electric Centre during
daytime on 31 Jan 2013 and during restricted hours on 5, 11 and 12 Feb 2013.
After checking with contractor, on 31 Jan 2013, no noisy construction
activities were undertaken during the recorded period. The exceedance was
non-continuous and considered to be contributed by the IEC traffic. On 11 and
12 Feb 2013, no construction activities were conducted and the exceedances were
considered to be contributed by the Chinese New Year pyrotechnic display and
IEC traffic respectively. As such, the exceedances were concluded as
non-project related.
4.2.13.
Limit Level exceedances were recorded at RTN3-Yu Lee Mo Fan Memorial
School during daytime on 4 Feb 2013. After checking with contractor, on 4 Feb
2013, no construction activities were conducted on IEC bridge deck during the
recorded period and the exceedances were considered to be contributed by nearby
IEC traffic. As such, the exceedances recorded were considered as non project
related.
4.2.14.
Limit level exceedances were recorded at RTN4-Causeway Bay Community
Centre during restricted hours on 3 and 11 Feb 2013. After checking with
contractor, on 3 Feb 2013, road mark realignment was conducted during the
recorded period. However, no PMEs were used for performing such works. The
exceedances were non-continuous and considered to be contributed by nearby IEC
traffic. On 11 Feb 2013, no construction activities on IEC bridge deck and the
exceedances were contributed by the Chinese New Year pyrotechnic display. As
such, the exceedances recorded were considered as non project related.
4.2.15.
Real
time noise monitoring results measured in this reporting quarter are reviewed
and summarized. Details of real time noise monitoring results and graphical
presentation can be referred to Appendix
4.2
4.3.1
Due to extension of site boundary by contractor of HY/2009/19, location
of air monitoring station CMA1b Oil Street Community Liaison Centre has been
finely adjusted on 21 April 2012.
4.3.2 Due to
lack of electricity supply at station CMA2a, 24hr-TSP was rescheduled from 12 December 2012 to 14 December 2012.
4.3.3 Due to
lack of electricity supply at station CMA3a, 24hr-TSP was rescheduled from 22
December 2012 and 26 January 2013 to 24 December 2012 and 28 January 2013
respectively.
4.3.4 Due to
lack of electricity supply at station CMA5a, 24hr-TSP was rescheduled from 26 February 2013 to 27 February 2013.
Contract no. HY/2009/17 Central - Wan Chai Bypass
(CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009
4.3.5
The
proposed divisions of air monitoring stations are summarized in Table
4.8 below. Air monitoring for the piling works under contract no.
HY/2009/17 was commenced on 8 October 2010.
Table
4.8 Air Monitoring Stations
for Contract no. HY/2009/17
Station |
Description |
CMA2a |
|
4.3.6
No
exceedance was recorded in the reporting period. Air quality monitoring results
measured in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 4.3.
Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB) Central Interchange under
FEP-05/364/2009/A
4.3.7
The
proposed division of air monitoring stations are summarized in Table
4.9 below.
Table
4.9 Air Monitoring Stations
for Contract no.
HY/2009/18
Station |
Description |
MA1e |
International Finance Centre (Eastern End of Podium) |
MA1w |
International Finance Centre (Western End of Podium) |
4.3.8
Air
monitoring for the Central Interchange works under contract no. HY/2009/18 was
commenced on 21 April 2011.
4.3.9
No
exceedance was recorded in the reporting period. Air quality monitoring results
measured in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 4.3.
Contract no. HK/2009/01 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at
4.3.10
The
commencement of construction works for Contract no. HK/2009/01 under
FEP-02/364/2009 is on 25 August 2011. The
proposed division of air monitoring stations are summarized in Table
4.10 below.
Table
4.10 Air Monitoring Station
for Contract no. HK/2009/01
Station |
Description |
CMA5a |
Children Playgrounds opposite to |
4.3.11
No
exceedance was recorded in the reporting period. Air quality monitoring results
measured in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 4.3.
Contract no. HK/2009/02 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
Table 4.11 Air Monitoring Station
for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
4.3.13
No
exceedance was recorded in the reporting period. Air quality monitoring results
measured in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 4.3.
Contract no.
HY/2009/15 - Central-Wanchai Bypass Tunnel (
4.3.14
The
commencement of construction works for Contract no. HY/2009/15 under
FEP-06/364/2009/A was on 13 July 2011. The proposed division of air
monitoring stations are summarized in Table 4.12
below.
Table
4.12
Air
Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB site office at Wanchai
Waterfront Promenade |
4.3.15
No
exceedance was recorded in the reporting period. Air quality monitoring results
measured in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 4.3.
Contract no.
HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under
FEP-07/364/2009/A
4.3.16 Air monitoring for the tunnel works was commenced
on 26 April 2011 for Contract no. HY/2009/19 under FEP-07/364/2009/A.
The proposed division of air monitoring stations are summarized in Table 4.13
below.
Table 4.13 Air Monitoring Stations for Contract no. HY/2009/19
Station |
Description |
CMA1b |
Oil St Community Liaison Centre |
CMA2a |
|
4.3.18.
No
exceedance was recorded in the reporting period. Air quality monitoring results
measured in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 4.3.
Contract no. HY/2009/17 Central
- Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009
4.4.1.
No inert and non-inert C&D waste was disposed in
the reporting period. Details of the waste flow table are summarized in Table
4.14
Table
4.14 Details of Waste Disposal for Contract no. HY/2009/17
Waste Type |
Quantity
this quarter, m3 |
Cumulative
Quantity-to-Date, m3 |
Disposal /
Dumping Grounds |
Inert C&D materials disposed |
NIL |
NIL |
CWBP/TKO137 |
Inert C&D materials recycled |
N/A |
||
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
N/A |
N/A |
N/A |
Contract nos. HK/2009/01 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at
4.4.2.
Inert
and non-inert C&D waste was disposed of in this reporting period. Details
of the waste flow table are summarized in Table 4.15.
Table 4.15 Details of Waste Disposal for Contract no. HK/2009/01
Inert C&D materials disposed |
Nil |
22249.345 |
TKO137, TM38 |
Inert C&D materials recycled |
Nil |
5104.5 |
N/A |
Non-inert C&D materials disposed |
142.4 |
1193 |
SENT Landfill |
Non-inert C&D materials recycled |
Nil |
205943 |
N/A |
Chemical waste disposed |
750 |
9100 |
Kwun Kee (Chemical Waste Collector) |
Contract no. HK/2009/02 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
4.4.3.
Inert
and non-inert C&D waste were disposed of in this reporting period. Details
of the waste flow table are summarized in Table 4.16.
Table 4.16 Details of Waste Disposal for
Contract no. HK/2009/02
Inert C&D materials disposed |
9,965.05 |
229,382.08 |
TKO137, TM 38 |
Inert C&D materials recycled |
Nil |
18,161 |
WCR2 |
Non-inert C&D materials disposed |
111.485 |
808.855 |
SENT Landfill |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
350 |
6571 |
N/A |
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) Central
Interchange under FEP-05/364/2009/A
4.4.4.
Inert
and non-inert C&D waste was disposed of in this reporting period. Details
of the waste flow table are summarized in Table 4.17.
Table 4.17 Details of Waste Disposal for
Contract no. HY/2009/18
Inert C&D materials disposed |
17665 |
84033 |
T.K.O. 137 |
Inert C&D materials recycled |
20612 |
53980 |
N/A |
Non-inert C&D materials disposed |
180 |
934 |
SENT Landfill |
Non-inert C&D materials recycled (tonnes) |
4.63 |
77.84 |
N/A |
Chemical waste disposed |
Nil |
3565 |
N/A |
Contract no. HY/2009/15 - Central-Wanchai Bypass Tunnel (
4.4.5.
Inert
and non-inert C&D waste was disposed of in this reporting period. Details
of the waste flow table are summarized in Table 4.18.
Table 4.18 Details of Waste Disposal for Contract no. HY/2009/15
Inert C&D materials disposed |
62510.1 13545.7 |
245877 163980 |
Tuen Mun Area 38 TKO137 FB |
Inert C&D materials recycled |
125834.1 |
209028.4 |
HY/2009/11 ex-PCWA TS4 |
Non-inert C&D materials disposed |
109.5 |
671.2 |
SENT Landfill |
Non-inert C&D materials recycled |
217.9 |
542809.4 |
Xun Xiang Metal ware Skylight Recycle (paper) |
Chemical waste disposed |
685 |
12721 |
Dunwell Group |
Remarks: Contractor clarified and updated waste
flow table for the reporting quarter.
Contract
no. HY/2009/19 Central Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/A
4.4.6.
Inert C&D materials was recycled
non-inert C&D waste was disposed of in this reporting period. Details of
the waste flow table are summarized in Table 4.19.
Table 4.19 Details of Waste Disposal for
Contract no. HY/2009/19
Inert C&D materials
disposed |
60323.69 |
265708.47 |
N/A |
Nil |
3124.91 |
N/A |
|
Non-inert C&D
materials disposed |
106.83 |
742.61 |
SENT Landfill |
Non-inert C&D
materials recycled |
70.66 |
224.69 |
N/A |
Chemical waste disposed |
Nil |
4.42 |
N/A |
Contract no. HK/2010/06 Wan Chai Development Phase
II - Central-Wan Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
4.4.7.
No
inert and Non-inert C&D wastes were disposed of in this reporting period.
Details of the waste flow table are summarized in Table 4.20.
Table 4.20 Details of Waste Disposal for Contract no. HK/2010/06
Inert C&D materials disposed |
NIL |
NIL |
TM38 |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
Recyclers |
Chemical waste disposed |
NIL |
NIL |
N/A |
5.0.1. The Event Action Plan for construction noise and air
quality are presented in Appendix 5.1.
Contract no. HY/2009/17 Central - Wan Chai Bypass (CWB) at FEHD
Whitfield Depot - Advanced piling works under FEP-03/364/2009
5.1.1.
No limit or action level exceedance was recorded in
this reporting period.
Contract no. HY/2009/18 - Central - Wan Chai Bypass
(CWB) Central Interchange under FEP-05/364/2009/A
Reporting month of
December 2012
5.1.2.
One limit level exceedance was recorded on 27 Dec 2012 at M8- City Hall
in the reporting month. Investigation found that noise from tourist gathering
was contributed in the noise monitoring an exceedance was not related to the project.
Contract no. HK/2009/01 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at
Reporting month of
January 2013
5.1.3.
One limit level exceedance was recorded on 24 Jan 2013 at M1a- Habour
Road Sports Centre in the reporting month. Investigation found that non- CWB
project drilling works nearby was the major noise contribution during
monitoring. As such the exceedance was not related to the Project.
Reporting month of
February 2013
5.1.4.
One limit level exceedance was recorded on 29 Jan 2013 at M1a- Habour
Road Sports Centre in the reporting month. Investigation found that non- CWB
project drilling works nearby was the major noise contribution during
monitoring. As such the exceedance was not related to the Project.
Contract no. HK/2009/02 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at Wan Chai East(CWB Tunnel)
Reporting month of
January 2013
5.1.5.
One limit level exceedance was recorded on 24 Jan 2013 at M1a- Habour
Road Sports Centre in the reporting month. Investigation found that non- CWB
project drilling works nearby was the major noise contribution during
monitoring. As such the exceedance was not related to the Project.
Reporting month of
February 2013
5.1.6.
One limit level exceedance was recorded on 29 Jan 2013 at M1a- Habour
Road Sports Centre in the reporting month. Investigation found that non- CWB
project drilling works nearby was the major noise contribution during
monitoring. As such the exceedance was not related to the Project.
Contract no. HY/2009/15 - Central-Wanchai Bypass Tunnel (
5.1.7.
No limit and action level exceedance was recorded during the reporting
period.
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
Reporting month of December
2012
5.1.8.
Four limit level
exceedances were recorded on 29 November, 11 December 2012, 17 December 2012 and
27 December 2012 at M6 HK Baptist Church Henrietta
Secondary School in the reporting month. Investigations found that major traffic noise
was contributed in the noise monitoring and exceedances were not related to the
Project.
Reporting month of January
2013
5.1.9.
Four limit level
exceedances were recorded on 3, 8, 15 and 24 January 2013 at M6 HK Baptist Church Henrietta
Secondary School in the reporting month. Investigations found that major traffic noise
was contributed in the noise monitoring and exceedances were not related to the
Project.
Reporting month of February
2013
5.1.10.
Five limit level
exceedances were recorded on 29 Jan, 7, 15, 24 and 26 Feb 2013 at M6 HK Baptist Church Henrietta
Secondary School in the reporting month. Investigations found that major traffic noise
was contributed in the noise monitoring and exceedances were not related to the
Project.
Contract no. HY/2009/17 Central
- Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009
5.2.1.
No exceedance was recorded in the reporting period.
Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB) Central Interchange under
FEP-05/364/2009/A
5.2.2.
No
exceedance was recorded in the reporting period.
Contract nos.
HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
5.2.3.
No
exceedance was recorded in the reporting period.
Contract nos.
HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan
Chai East(CWB Tunnel)
5.2.4.
No
exceedance was recorded in the reporting period.
Contract no. HY/2009/15 - Central-Wanchai Bypass Tunnel (
5.2.5.
No
exceedance was recorded in the reporting period.
Contract no.
HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under FEP-07/364/2009/A
5.2.1 No exceedance was recorded in the reporting period.
Contract
no. HY/2009/17 Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot -
Advanced piling works under FEP-03/364/2009
Reporting month of December 2012
5.3.1
No action and limit level exceedance was
recorded at RTN1- FEHD Hong Kong Transport Section Whitfield Depot during the December reporting month.
Reporting month of January 2013
5.3.2
Non project related exceedances were recorded at RTN1-FEHD Hong Kong Transport
Section Whitfield Depot on 3 Jan 2013 and 16 Jan 2013. Investigation found that
exceedances were contributed by non designated project works and nearby IEC
traffic.
Reporting month of February 2013
5.3.3
Non project related exceedances were recorded at RTN1-FEHD Hong Kong Transport
Section Whitfield Depot on 2, 11 and 25 Feb 2013. Investigation found that
exceedances were contributed by non designated project works and Chinese New
Year pyrotechnic display and nearby IEC traffic.
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/A
Reporting month of December 2012
5.3.4
No action and limit level exceedances was
recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Deport in the
reporting month.
5.3.5
Non-project related limit level exceedance was recorded at RTN2a-Hong
Kong Electric Centre on 7 Dec 2012 in the reporting month.
Reporting month of January 2013
5.3.6
Non project related exceedances were recorded at RTN1-FEHD Hong Kong Transport
Section Whitfield Depot on 3 Jan 2013 and 16 Jan 2013 in the reporting month.
Investigation found that exceedances were contributed by non designated project
works and nearby IEC traffic.
5.3.7
No action and limit level exceedance was recorded at RTN2-Hong Kong
Electric Centre in the reporting month.
Reporting month of February 2013
5.3.8
Non project related exceedances were recorded
at RTN1-FEHD Hong Kong Transport Section Whitfield Depot on 2, 11 and 25 Feb
2013. Investigation found that exceedances were contributed by non-designated
project works and pyrotechnic display and nearby IEC traffic.
5.3.9
Non project related exceedances were recorded
at RTN2a-Electric Centre on 31 Jan, 5, 11 and 12 Feb 2013. Investigation found
that exceedances were contributed by IEC traffic and Chinese New Year
pyrotechnic display.
5.3.10
Non project related exceedances were recorded
at RTN3- Yu Lee Mo Fan Memorial School on 4 Feb 2013. Investigation found that
exceedances were contributed by IEC traffic and Chinese New Year pyrotechnic
display.
5.3.11
Non project related exceedances were recorded
at RTN4- Causeway Bay Community Centre on 3 and 11 Feb 2013. Investigation
found that exceedances were contributed by IEC traffic and Chinese New Year
pyrotechnic display.
5.4.1. There was no non-compliance from the site audits in
the reporting period. During environmental site inspections conducted during
the reporting quarter, minor deficiencies were noted. However, the Contractor rectified all
deficiencies after receipt of notification.
5.5.1
There was no particular action taken since no project-related
non-compliance was recorded from the site audits and environmental monitoring
in the reporting period.
5.6.1 As no project related exceedance and non-compliance was recorded in this
reporting period, no action or follow-up was required in this reporting period.
6.0.1.
There was no environmental complaint received in this reporting period.
6.0.2. The details of cumulative complaint log and summary of
complaints are presented in Appendix
6.1.
6.0.3. No notification of summons or prosecution was received in the reporting
period. Cumulative statistic
on complaints and successful prosecutions are summarized in Table
6.1 and Table 6.2 respectively.
Table 6.1 Cumulative
Statistics on Complaints
Reporting Period |
No. of Complaints |
Commencement
of Works up to last reporting quarter |
20 |
December 2012 February 2013 |
0 |
Project-to-Date |
20 |
Table 6.2 Cumulative
Statistics on Successful Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this quarter (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
7.0.1.
According
to Condition 3.4 of the EP-364/2009/B, this section addresses the relevant
cumulative construction impact due to the concurrent activities of the current
projects including the Central Reclamation Phase III (CRIII), Wan Chai
Development Phase II (WDII), Central-WanChai Bypass (CWB), Island Eastern
Corridor Link projects (IECL) and Wan Chai Development Phase II
Central Wan Chai Bypass at Wan Chai East (CWB Tunnel).
7.0.2.
According to the Monthly EM&A report (January
2013) of Central Reclamation Phase III (CRIII), filling works, road works,
landscape works, building construction works and drainage works were performed
in the February 2013 reporting month. The water
quality monitoring was completed in October 2011 and no project-related exceedance
was recorded for air and noise monitoring during the reporting quarter. It can
be concluded that cumulative construction impact due to the concurrent
activities of the current projects with the Central Reclamation Phase III
(CRIII) was insignificant
7.0.3.
According to the construction programme of
Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern
Corridor Link projects, the major construction activity under Wan Chai
Development Phase II were marine works at HKCEC areas, cross-harbour
Watermains, Fresh Watermains and Cooling Watermains Installations, tunnel works
at Wan Chai East, ELS work at TS4 and deep excavation at
TPCWAE TCBR1W. Excavation at Central Interchange, and marine pilling and box
culvert construction at North Point area. The major environmental impact was
water quality impact at
7.0.4.
The major environmental impacts generated from excavation at Central and
tunnel works at Wan Chai East, IECL and Causeway Bay Typhoon Shelter were
undertaken in the reporting quarter. No significant air impact was anticipated
in the reporting quarter. Besides, no project-related exceedances were recorded
during the environmental monitoring events in the reporting month. Thus, it is evaluated that the cumulative
construction impact from the concurrent projects including Wan Chai Development
Phase II was insignificant.
8.0.1. The EM&A programme was carried out in
accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
Air quality monitoring
8.0.2.
No action or limit level exceedance was recorded.
Noise monitoring
8.0.3. No action and 4 non-project related limit
level exceedances at M6 HK Baptist Church Henrietta Secondary School were
recorded on 29 November 2012, 11 December 2012, 17 December 2012 and 27 December
2012 in the December reporting month.
8.0.4. No action and 1 non-project limit level
exceedances at M8- City Hall was recorded on 27 Dec 2012 in the December
reporting month.
8.0.5. No action and 4 non-project related limit
level exceedances at M6 HK Baptist Church Henrietta Secondary School were
recorded on 3,8,15 and 24 January 2013 in the January month.
8.0.6. No action and 1 non-project related
limit level exceedances at M1a- Habour Road Sports Centre was recorded on 24
January 2013 in the January reporting month.
8.0.7.
No action and 5 non-project
related limit level exceedances at M6 HK Baptist Church Henrietta Secondary
School were recorded on 29 Jan, 7, 15, 19 and 26 Feb 2013 in the February
reporting month.
8.0.8.
No action and 1 non-project related limit level exceedances at M1a-
Habour Road Sports Centre was recorded on 29 January 2013 in the February
reporting month.
8.0.9.
Real time noise monitoring
8.0.10.
No limit level exceedance was recorded
at RTN1- FEHD Hong
Kong Transport Section Whitfield Depot in December reporting month.
8.0.11.
Non-project related exceedance was recorded on 7 Dec 2012 at RTN2a Hong
Kong Electric Centre in the December reporting month.
8.0.12.
Non-project related exceedance was recorded at RTN1- FEHD Hong Kong Transport Section Whitfield
Depot on 3 and 16 Jan 2013 in the January reporting month.
8.0.13.
No limit level exceedance was recorded at RTN2a Hong Kong Electric Centre in the January
reporting month.
8.0.14.
Non-project related limit level Exceedances were recorded at RTN1-FEHD
Hong Kong Transport Section Whitfield Depot during daytime on 2 Feb 2013 and
during restricted hours on 11 and 25 Feb 2013.
8.0.15.
Non-project related limit level exceedances were recorded at
RTN2a-Electric Centre during daytime on 31 Jan 2013 and during restricted hours
on 5, 11 and 12 Feb 2013.
8.0.16.
Non-project related limit Level exceedances were recorded at RTN3-Yu Lee
Mo Fan Memorial School during daytime on 4 Feb 2013.
8.0.17.
Non-project related limit level exceedances were recorded at
RTN4-Causeway Bay Community Centre during restricted hours on 3 and 11 Feb
2013.
8.0.18.
No environmental
complaint was received in this reporting quarter.
8.0.19. The construction programmes
of individual contracts are provided in Appendix 8.1.