Contract
No: HK/2011/07 Wanchai Development Phase II and Sampling, Field Measurement and
Testing Work (Stage 2) Environmental
Permit no. EP-364/2009/B, Further Evironmental permit nos. fep-01/364/2009,
fep-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEp-07/364/2009/a,
FEp-08/364/2009/a and FEP-09/364/2009/B Quarterly Environmental Monitoring
and Audit Report
- March 2013
to may 2013 -
|
CLIENTS: |
|
Civil
Engineering and Development Department and Highways
Department |
Lam Geotechnics
Limited 11/F Centre
Point Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
27June 2013 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
2.5 Principal Work and Activities
4.2. Real Time Noise Monitoring Results
5.4. Review of the Reasons for and the Implications of
Non-compliance
5.5. Summary of action taken in the event of and follow-up
on non-compliance
6. Complaints, Notification of Summons
and Prosecution
7. Cumulative Construction Impact due to
the Concurrent Projects
lIST
OF TABLES
Table I Principal Work Activities for Contract no. HY/2009/17
Table II Principal Work Activities for Contract no. HY/2009/18
Table III Principal Work Activities for Contract no. HK/2009/01
Table IV Principal Work Activities for Contract no. HK/2009/02
Table V Principal Work Activities for Contract no. HY/2009/15
Table VI Principal Work Activities for Contract no. HY/2009/19
Table VII Principal Work
Activities for Contract no. HK/2010/06
Table VIII Principal Work
Activities for Contract no. HK/2012/08
Table 2.1 Schedule 2 Designated Projects under this Project
Table 2.2 Details of Individual Contracts under the Project
Table 2.3 Contact Details of Key Personnel
Table 2.4 Principal Work Activities for Contract no. HY/2009/17
Table 2.5 Principal Work Activities for Contract no. HY/2009/18
Table 2.6 Principal Work Activities for Contract no. HK/2009/01
Table 2.7 Principal Work Activities for Contract no. HK/2009/02
Table 2.8 Principal Work Activities for Contract no. HY/2009/15
Table 2.9 Principal Work Activities for Contract
no. HK/2010/06
Table 2.10 Principal
Work Activities for Contract no. HY/2009/19
Table 2.11 Principal Work
Activities for Contract no. HK/2012/08
Table 3.1 Noise Monitoring Station
Table 3.2 Real Time Noise Monitoring Station
Table 3.3 Air Monitoring Stations
Table 4.1 Noise Monitoring Stations for Contract no. HY/2009/17
Table 4.2
Noise Monitoring Station for Contract no.
HY/2009/18
Table 4.3
Noise Monitoring Stations for Contract nos.
HK/2009/01 and HK/2009/02
Table 4.4
Noise Monitoring Station for Contract nos.
HY/2009/15
Table 4.5 Noise
Monitoring Stations for Contract no. HY/2009/19
Table 4.6 Real Time Noise Monitoring Station for Contract no. HY/2009/17
Table 4.7 Real Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 4.8 Air Monitoring Stations for Contract no. HY/2009/17
Table 4.7 Air Monitoring Stations for Contract no. HY/2009/18
Table 4.10 Air Monitoring Stations for Contract no. HK/2009/01
Table 4.11 Air Monitoring Station for Contract no. HK/2009/02
Table 4.12 Air Monitoring Station for Contract no. HY/2009/15
Table 4.13 Air Monitoring Stations for Contract no. HY/2009/19
Table 4.14 Details of Waste Disposal for Contract no. HY/2009/17
Table 4.15 Details of Waste Disposal for Contract no. HK/2009/01
Table 4.16 Details of Waste Disposal for Contract no. HK/2009/02
Table 4.17 Details of Waste Disposal for Contract no. HY/2009/18
Table 4.18 Details of Waste Disposal for Contract no. HY/2009/15
Table 4.19 Details of Waste Disposal for Contract no. HY/2009/19
Table 4.20 Details fo Waste Disposal for Contract no.
HK/2010/06
Table 4.21 Details of Waste Disposal for Contract no. HK/2012/08
Table 6.1 Cumulative Statistics on Complaints
Table 6.2 Cumulative Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure
2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 3.1 Locations of Environmental
Monitoring Stations
lIST OF APPENDIces
Appendix
2.1 Environmental
Mitigation Implementation Schedule
Appendix 3.1 Action and Limit Level
Appendix
4.1 Noise
Monitoring Results and Graphical Presentations
Appendix 4.2 Real-time Noise Monitoring
Results and Graphical Presentations
Appendix
4.3 Air
Quality Monitoring Results and Graphical Presentations
Appendix 5.1 Event Action Plans
Appendix 6.1 Complaint Log
Appendix 6.2 Notification of Exceedance
Appendix 8.1 Construction Programme of
Individual Contracts
EXECUTIVE
SUMMARY
Contract no. HY/2009/17 - Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling
works under FEP-03/364/2009
Major construction activities
for Contract no. HK/2009/17 have been commenced on 5 October 2010. During this
reporting period, the principal work activities for Contract no. HY/2009/17 are
summarized as below:
Table I Principal
Work Activities for Contract no. HY/2009/17
March 2013 |
April 2013 |
May 2013 |
No
further work under designated project |
No
further work under designated project |
No
further work under designated project
and Further Environmental Permit surrendered on 25 Apr 2013 |
Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB)
- Central Interchange under FEP-05/364/2009/
Table II Principal Work
Activities for Contract no. HY/2009/18
March 2013 |
April 2013 |
May 2013 |
Excavation of
trial pit
Transplanting of
trees
Hoarding
erection and modification
Installation of
couplers, UU detection, trial trench, pre-drilling
Excavation
Drainage works
Tunnel works
Trough structure
construction and associated drilling and grouting
Road works
OHVD
installation
Pre-bored
H-piling
Bridges
construction
Scaffolding /
false-work erection |
Excavation of
trial pit
Transplanting of
trees
Hoarding
erection and modification
Installation of
couplers, UU detection, trial trench, pre-drilling
Excavation
Drainage works
Tunnel works
Trough structure
construction and associated drilling and grouting
Road works
OHVD installation
Pre-bored
H-piling
Bridges
construction
Scaffolding /
false-work erection |
Excavation of
trial pit
Transplanting of
trees
Hoarding
erection and modification
Installation of
couplers, UU detection, trial trench, pre-drilling
Excavation
Drainage works
Tunnel works
Trough structure
construction and associated drilling and grouting
Road works
OHVD
installation
Pre-bored
H-piling
Bridges
construction
Scaffolding /
false-work erection |
Contract no. HK/2009/01 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at
Major construction activities
for Contract no. HK/2009/01 have been commenced on 25 August 2011. During this
reporting period, the principal work activities are summarized as below:
Table III Principal Work
Activities for Contract no. HK/2009/01
March 2013 |
April 2013 |
May 2013 |
Pre-drilling works for CWB (Stage 2). Diaphragm wall construction works at
Stage 2 (North) Mobilization of 1st Piling
rig for pre-bored H piling works under atrium |
Pre-drilling works for CWB (Stage 2). Diaphragm wall construction works at
Stage 2 (North) Temporary bulkhead wall construction
works between Stage1/Stage2. Pre-bored H piling works for CWB
(Stage1b) Piling rig for pre-bored H piling
works under atrium was mobilized to Site |
Pre-drilling works for CWB (Stage 2) Diaphragm wall construction works at
Stage 2 (North) Temporary bulkhead wall construction
works between Stage1 / Stage2 Pre-bored H piling works for CWB
(Stage1b) 3rd Piling rig for pre-bored H piling works
under atrium |
Contract no. HK/2009/02 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
Major construction activities
for Contract no. HK/2009/02 have been commenced on 26 April 2011. During this reporting period, the principal work
activities are summarized as below:
Table IV Principal Work
Activities for Contract no. HK/2009/02
March 2013 |
April 2013 |
May 2013 |
Casting of Base slab Bay 4, Bay8, Bay9
& Bay10 Waterproofing installation at WCR1 of
Tunnel Portion 1 Rebar fixing for base slab Bay 11 to
Bay 14 3 nos. bored piles PN12, PC12 &
PS14 were concreted Excavation for other 4 nos. bored piles
PS13, PC14, PS18 & PS19 The outstanding sewerage works in Silt curtain installation for dredging
works at TWCR4 was completed on 5 Mar 2013. Works associated with footpath modification
and proposed sewerage works for Hung Hing Road Flyover Diversion Stage 1 implementation. |
Concreting of Eastern Bulkhead Wall,
Panel BHP1, BHP6, BHP11 and BHP15 Casting of Base slab Bay 11, Bay 12
& Bay 13 Waterproofing installation at WCR1 of
Tunnel Portion 1 Rebar fixing for base slab Bay 2 and
Bay 14 - Bay 16 Concreting of 6 nos. bored piles PN13,
PC14, PC16, PS13, PS18 & PS19. Excavation for other 6 nos. bored
piles PN14, PN15, PC13, PC15, PC17 & PS17. Extraction of the temporary sheet pile
wall at WCR2. The outstanding sewerage works in Backfilling works along Works associated with footpath modification
and proposed sewerage works for Hung Hing Road Flyover Diversion (Stage 1) implementation. |
Remedial works for P7 & P8 at WCR1
area. Excavation works for pile cap
construction Remedial works of concrete plug at Bay
1B of Salt Water Intake Culvert Reinforcement fixing at Bay 1B base
slab Steel pile cutting works at Bay 2A/2B
interface of Salt Water Culvert Casting of Base slab at Bay 2B of Salt
Water Intake Culvert and steel fixing for its wall and top slab. Installation of HDPE pipes from Bay 4
to Bay 11 (except Bay 7) The HDPE pipe at Bay 3 would be
carried out after the completion of Construction of Bay 4 base slab of Box
Culvert N1c Concreting of Eastern Bulkhead Wall,
Panel BHC4, BHC10, BHP13 and BHC14
Excavation for Panel BHC2 Preparation works for BHC12 Casting of base slab (Bay 14) Rebar fixing for base slab Bay 1 &
Bay 2 at WCR1 of Tunnel Portion 1 and that for Bay 15 & Bay 16 was in progress. Bored piles PN14, PN15, PN16, PC13,
PC15, PC17 & PS17 were concreted Excavation for bored pile PN17 |
Contract no. HY/2009/15 - Central-Wanchai Bypass
Tunnel (
Major construction activities
for Contract no. HY/2009/15 has been commenced on 13 July 2011. During this
reporting period, the principal work activities are summarized as below:
Table V Principal Work Activities for Contract no.
HY/2009/15
April
2013 |
May
2013 |
|
ELS works at TS4 Rock breaking works at TPCWAE Tunnel works at TS1 Horizontal drilling for mined tunnel Construction of Diaphragm Wall at TS2 |
ELS works at TS4 Rock trimming and concrete works at
TPCWAE Tunnel works at TS1 Horizontal drilling for mined tunnel Construction of Diaphragm Wall at TS2 |
ELS works and pipe roofing works at
TS4 RC structure works at TPCWAE Tunnel works at TS1 Excavation for mined tunnel Construction of Diaphragm Wall at TS2 |
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
Major construction activities
for Contract no. HY/2009/19 have been commenced on March 2011. During this reporting
period, the principal work activities are summarized as below:
Table VI Principal Work Activities for Contract no.
HY/2009/19
March 2013 |
April 2013 |
May 2013 |
Road works at Bored piling (Land) D-wall Construction (North & South
Section) Guide wall construction for D-wall / Barrette
at North side Construction works for Box Culvert T1 Construction of socket-H pile Construction works for Culvert U1 Construction of Pile caps &
columns (Land) Demolition of parapet at IEC Link Construction of Pile caps &
columns (Marine) Construction of dewatering well for
Cut & Cover Tunnel D8-D9 Gantry Fabrication for precast
segment ELS for Cut & Cover Tunnel |
Road works at Bored piling (Land) D-wall and Barrette Construction Construction works for Box Culvert T1 Construct ion of socket-H pile Construction works for Culvert U1 Dismantling of marine platform Construction of Pile caps &
columns (Marine) Construction of dewatering well for
Cut & Cover Tunnel D8-D9 Gantry Fabrication for precast
segment will continue ELS for Cut & Cover Tunnel will
continue Laying of 1500f pipe will continue |
Road works at Bored piling (Land) D-wall and Barrette Construction Construction works for Box Culvert T1 Construction works for Culvert U1 Construction of pile cap, column &
cross head (Marine) D8-D9 Gantry Fabrication for precast
segment ELS for Cut & Cover Tunnel Laying of 1500f pipe Portal gantry works Launching of girder Launching of segments Unloading segments from derrick Extraction of temporary pile from
marine section |
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
Table
VII
Principal Work Activities for Contract
no. HK/2010/06
March 2013 |
April 2013 |
May 2013 |
Utility
works in section 2 |
Utility works in section 2 |
Nil |
Contract
no. HK/2012/08 Wan Chai Development Phase II Central- Wan Chai Bypass at
Wan Chai West under FEP-09/364/2009B
Table VII Principal Work Activities
for Contract no. HK/2012/08
March 2013 |
April 2013 |
May 2013 |
Site preparation works Site survey |
Site preparation works Site survey |
Site preparation works Site survey |
Noise Monitoring
Real time
Noise Monitoring
Air Quality Monitoring
Complaints, Notifications of
Summons and Successful Prosecutions
1.1.1.
Lam
Geotechnics Limited (LGL) has been appointed to work as the Environmental Team
(ET) under Environmental Permit no. EP-364/2009A and Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A, FEP-08/364/2009/A and FEP-09/364/2009/B to
implement the Environmental Monitoring and Audit (EM&A) programme as stipulated
in the EM&A Manual of the approved Environmental Impact Assessment (EIA)
Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register
No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for
Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No.
AEIAR-014/2001).
1.1.2.
This
report presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.3 of
EM&A Manual and Environmental Monitoring and Audit Requirements
under Particular Specification Section 27.
1.1.3. This report documents the finding of EM&A
works during the period from March 2013 to May 2013.
Section 1 Introduction details the scope and structure of the
report.
Section 2 Project Background summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section 3 Monitoring Requirements summarizes all monitoring parameters,
monitoring locations, monitoring frequency, duration and action plan.
Section 4 Monitoring Results summarizes the monitoring results
obtained in the reporting period.
Section 5 Compliance Audit summarizes the auditing of monitoring results, all
exceedances environmental parameters.
Section 6 Complaints,
Notification of summons and Prosecution summarizes the cumulative
statistics on complaints, notification of summons and prosecution
Section 7 Cumulative
Construction Impact due to the Concurrent Projects summarizes the
relevant cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section 8 Conclusion
2.1.1.
Wan
Chai Development phase II and Central-Wan Chai Bypass and Central-Wan Chai
Bypass and Island Eastern Corridor Link (hereafter called the Project) are
Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap.
499) (EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The
key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan
Chai North and North Point for construction of the Central-Wan Chai Bypass and
Island Eastern Corridor Link (CWB). Land formed under the project will be
developed as a world-class waterfront promenade joining that at the new Central
waterfront for public enjoyment.
2.1.3.
There
is a compelling and present need for the CWB to provide relief to the very
congested
2.2.1.
Design and Construction of Central Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The
study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB)
and Island Eastern Corridor Link (IECL) includes:
·
A dual three-lane trunk road, approximately 4.5 km
in length, and tunnel approximately 3.7 km in length defined from the
connection with the existing Rumsey Street Flyover in Central, through to a
connection with the existing Island Eastern Corridor to the east of the
Causeway Bay Typhoon Shelter (CBTS);
·
The Central Interchange near the Rumsey Street
Flyover to provide road connections to the Central area;
·
Tunnel control buildings and ventilation buildings;
·
Slip roads to connect the CWB to the local road
system in the Wan Chai North and
·
Associated road lighting, road signing, traffic
control and surveillance system; and
·
Other associated works.
2.2.3.
The
project also contains various Schedule 2 DPs that, under the EIAO, require
Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five
individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table
2.1 Schedule 2 Designated Projects
under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due
to the multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be
commenced. Contractors of individual
contracts will be required by the EP holder to apply Further Environmental
Permits such
that the impact monitoring stations are sub-divided accordingly to facilitate
the implementation of EM&A programme and to streamline the EM&A
reporting for individual FEP holders correspondingly.
2.3.2.
In
the reporting period, all the contracts were commenced and contract no.
04/HY/2006 had been completed. The details of individual contracts are
summarized in Table2.2.
Table
2.2 Details of Individual Contracts
under the Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HY/2009/17 |
Central Wan Chai Bypass (CWB) at FEHD Whitfield Depot Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central Wan Chai Bypass (CWB) Central Interchange |
DP1 |
21 April 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 |
HK/2009/01 |
Wan Chai Development Phase II Central Wan Chai Bypass at |
DP1, DP2 |
25 August 2011 |
HK/2009/02 |
Wan Chai Development Phase II Central Wan Chai Bypass at Wan Chai
East(CWB Tunnel) |
DP1 |
26 April 2011 |
HY/2009/15 |
Central-Wanchai Bypass Tunnel ( |
DP1 |
13 July 2011 |
HY/2009/19 |
Central Wanchai Bypass Tunnel (North Point Section) and Island Eastern
Corridor Link |
DP1 |
24 March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
HK/2012/08 |
Wan Chai Development Phase II- Central-Wan Chai
Bypass at Wan Chai West |
DP1,DP2, DP3 |
DP works under |
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively.
For the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure
2.2. Key personnel and contact particulars are
summarized in Table 2.3:
Table 2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineers Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineers Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3916 1818 |
3529 2829 |
|
Lam
Woo & CO., LTD. |
Contractor under Contract no. HY/2009/17 |
General Manager |
Mr. Thomas Tang |
6111 5351 |
2566
7522 |
Contractors Representative |
Mr. Chung Man Shek |
2566 4866 |
2566
7522 |
||
Site Agent |
Mr. Tony Au |
9725 5874 |
2566 7522 |
||
Environmental Officer |
Dr. Priscilla Choy |
9161 7287 |
2566 7522 |
||
Environmental Supervisor |
Mr. Tam Chun Pong |
6461 3062 |
2566 7522 |
||
Chun
Wo Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Joint Venture Board Representative |
|
2162 9909 |
2634 1626 |
Sub Agent |
Mr. Terry Wong |
9757 9846 |
|||
Construction
Manager |
Mr. Wyman Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Jack Chu |
9775 2467 |
|||
Construction
Manager |
Mr. Andy Yu |
9648 4896 |
|||
Environmental
Officer (Compliance Manager) |
Mr. Andy Mak |
9103 2370 |
|||
Environmental
Supervisor |
Mr. Kwong
Weng Kit |
6253
3356 |
|||
Chun Wo CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project Manager |
Mr. Chan Sing Cho |
3658-3002 |
2827 9996 |
Quality & Environmental Manager (Environmental Officer) |
Mr. C.P. Ho |
3658-3000 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570 8013 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Environmental Engineer |
|
9286 9208 |
|||
Construction Manager (Marine) |
William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
Construction Manager (Land) |
Eric Fong |
6191 9337 |
|||
Operation Manager (Land) |
Yung Kwok Wah |
9834 1010 |
|||
Leighton Contractors ( |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Jimmy Chu |
2214
7700 |
2140 6799 |
Deputy Site Agent |
Mr Roger Wong |
2214
7703 |
|||
Environmental Officer |
Mr. Anfernee Chow |
2214 7721 |
|||
Environmental Engineer Graduate |
Phil Mak |
2214
7738 |
|||
Environmental Supervisor |
K. P. Lai |
6461 4660 |
|||
Environmental Supervisor |
Ray Cheng |
22147742 |
|||
Environmental Supervisor |
Bosco Lee |
22147711 |
|||
Environmental Supervisor |
Ryan Tsui |
2214 7705 |
|||
|
Contractor under Contract no. HY/2009/15 |
Project Director |
Mr. K C Cheung |
2823 7813 |
2566 2192 |
Site Manager |
Mr. J.H. Chen |
3557 6368 |
|||
Contractors
Representative |
Mr. Andrew Wong |
3557
6407 |
|||
Head of construction |
Mr. Roger Cheung |
3557 6371 |
|||
Environmental Officer |
Mr. Daniel Sin |
3557 6215 |
|||
Enviromental Supervisor |
Ms Esther Choi |
35576348 |
|||
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project
Manager |
Mr. Paul Lui |
9095 7922 |
2529
2880 |
Site
Agent |
Mr. Keith Tse |
2529 2068 |
|||
Environmental
Officer |
Mr. Clement Pang |
9481 6024 |
|||
Environmental
Supervisor |
Mr.
Jacky Cheung |
9735 9200 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.5.1.
Major construction activities for Contract no.
HK/2009/17 have been commenced on 5 October 2010. During
this reporting period, the principal work activities for Contract no. HY/2009/17
are summarized in Table2.4.
Table
2.4 Principal
Work Activities for Contract no. HY/2009/17
March
2013 |
April
2013 |
May
2013 |
No
further work under designated project |
No
further work under designated project |
No
further work under designated project
and Further Environmental Permit surrendered on 25 Apr 2013 |
Table 2.5 Principal Work Activities for Contract no.
HY/2009/18
March
2013 |
April
2013 |
May
2013 |
Excavation of
trial pit
Transplanting of
trees
Hoarding
erection and modification
Installation of
couplers, UU detection, trial trench, pre-drilling
Excavation
Drainage works
Tunnel works
Trough structure
construction and associated drilling and grouting
Road works
OHVD
installation
Pre-bored
H-piling
Bridges
construction
Scaffolding /
false-work erection |
Excavation of
trial pit
Transplanting of
trees
Hoarding
erection and modification
Installation of
couplers, UU detection, trial trench, pre-drilling
Excavation
Drainage works
Tunnel works
Trough structure
construction and associated drilling and grouting
Road works
OHVD installation
Pre-bored
H-piling
Bridges
construction
Scaffolding /
false-work erection |
Excavation of
trial pit
Transplanting of
trees
Hoarding
erection and modification
Installation of
couplers, UU detection, trial trench, pre-drilling
Excavation
Drainage works
Tunnel works
Trough structure
construction and associated drilling and grouting
Road works
OHVD
installation
Pre-bored
H-piling
Bridges
construction
Scaffolding /
false-work erection |
2.5.3.
Major construction activities for Contract no.
HK/2009/01 have been commenced on 25 August 2011. During this reporting period,
the principal work activities are summarized in Table2.6:
Table 2.6 Principal Work Activities for Contract no. HK/2009/01
March
2013 |
April
2013 |
May
2013 |
Pre-drilling works for CWB (Stage 2).
Diaphragm wall construction works at Stage 2 (North)
Mobilization of 1st Piling rig for pre-bored H piling works
under atrium |
Pre-drilling works for CWB (Stage 2).
Diaphragm wall construction works at Stage 2 (North)
Temporary bulkhead wall construction works between Stage1/Stage2.
Pre-bored H piling works for CWB (Stage1b)
Piling rig for pre-bored H piling works under atrium was mobilized to
Site |
Pre-drilling works for CWB (Stage 2)
Diaphragm wall construction works at Stage 2 (North)
Temporary bulkhead wall construction works between Stage1 / Stage2
Pre-bored H piling works for CWB (Stage1b)
3rd Piling rig for pre-bored H
piling works under atrium |
2.5.4.
Major construction activities for Contract no.
HK/2009/02 have been commenced on 26 April 2011. During this reporting period, the principal work activities are
summarized in Table2.7:
Table 2.7 Principal Work Activities for Contract no. HK/2009/02
March
2013 |
April
2013 |
May
2013 |
Casting of Base slab Bay 4, Bay8, Bay9 & Bay10
Waterproofing installation at WCR1 of Tunnel Portion 1
Rebar fixing for base slab Bay 11 to Bay 14
3 nos. bored piles PN12, PC12 & PS14 were concreted
Excavation for other 4 nos. bored
piles PS13, PC14, PS18 &
PS19
The outstanding sewerage works in
Silt curtain installation for dredging works at TWCR4 was completed on
5 Mar 2013.
Works associated with footpath modification and proposed sewerage
works for Hung Hing Road Flyover Diversion Stage 1 implementation. |
Concreting of Eastern Bulkhead Wall, Panel BHP1, BHP6, BHP11 and BHP15
Casting of Base slab Bay 11, Bay 12 & Bay 13
Waterproofing installation at WCR1 of Tunnel Portion 1
Rebar fixing for base slab Bay 2 and Bay 14 - Bay 16
Concreting of 6 nos. bored piles PN13, PC14, PC16, PS13, PS18 &
PS19.
Excavation for other 6 nos. bored piles PN14, PN15, PC13, PC15, PC17
& PS17.
Extraction of the temporary sheet pile wall at WCR2.
The outstanding sewerage works in
Backfilling works along
Works associated with footpath modification and proposed sewerage
works for Hung Hing Road Flyover Diversion (Stage 1) implementation. |
Remedial works for P7 & P8 at WCR1 area.
Excavation works for pile cap construction
Remedial works of concrete plug at Bay 1B of Salt Water Intake Culvert
Reinforcement fixing at Bay 1B base slab
Steel pile cutting works at Bay 2A/2B interface of Salt Water Culvert
Casting of Base slab at Bay 2B of Salt Water Intake Culvert and steel
fixing for its wall and top slab.
Installation of HDPE pipes from Bay 4 to Bay 11 (except Bay 7)
The HDPE pipe at Bay 3 would be carried out after the completion of
Construction of Bay 4 base slab of Box Culvert N1c
Concreting of Eastern Bulkhead Wall, Panel BHC4, BHC10, BHP13 and
BHC14 Excavation for Panel BHC2
Preparation works for BHC12
Casting of base slab (Bay 14)
Rebar fixing for base slab Bay 1 & Bay 2 at WCR1 of Tunnel Portion
1 and that for Bay
15 & Bay 16 was in progress.
Bored piles PN14, PN15, PN16, PC13, PC15, PC17 & PS17 were
concreted
Excavation for bored pile PN17 |
2.5.5.
Major construction activities for Contract no.
HY/2009/15 have been commenced on 13 July 2011. During this reporting period,
the principal work activities are summarized in Table
2.8:
Table 2.8 Principal Work
Activities for Contract no. HY/2009/15
March
2013 |
April
2013 |
May
2013 |
ELS works at TS4
Rock breaking works at TPCWAE
Tunnel works at TS1
Horizontal drilling for mined tunnel
Construction of Diaphragm Wall at TS2 |
ELS works at TS4
Rock trimming and concrete works at TPCWAE
Tunnel works at TS1
Horizontal drilling for mined tunnel
Construction of Diaphragm Wall at TS2 |
ELS works and pipe roofing works at TS4
RC structure works at TPCWAE
Tunnel works at TS1
Excavation for mined tunnel
Construction of Diaphragm Wall at TS2 |
2.5.6.
Major construction activities for Contract no.
HY/2009/19 have been commenced on March 2011. During this reporting period, the
principal work activities are summarized in Table
2.9:
Table 2.9 Principal Work Activities for Contract no.
HY/2009/19
March
2013 |
April
2013 |
May
2013 |
Road works at
Bored piling (Land)
D-wall Construction (North & South Section)
Guide wall construction for D-wall / Barrette at North side
Construction works for Box Culvert T1
Construction of socket-H pile
Construction works for Culvert U1
Construction of Pile caps & columns (Land)
Demolition of parapet at IEC Link
Construction of Pile caps & columns (Marine)
Construction of dewatering well for Cut & Cover Tunnel
D8-D9 Gantry Fabrication for precast segment
ELS for Cut & Cover Tunnel |
Road works at
Bored piling (Land)
D-wall and Barrette Construction
Construction works for Box Culvert T1
Construct ion of socket-H pile
Construction works for Culvert U1
Dismantling of marine platform
Construction of Pile caps & columns (Marine)
Construction of dewatering well for Cut & Cover Tunnel
D8-D9 Gantry Fabrication for precast segment will continue
ELS for Cut & Cover Tunnel will continue
Laying of 1500f pipe will continue |
Road works at
Bored piling (Land)
D-wall and Barrette Construction
Construction works for Box Culvert T1
Construction works for Culvert U1
Construction of pile cap, column & cross head (Marine)
D8-D9 Gantry Fabrication for precast segment
ELS for Cut & Cover Tunnel
Laying of 1500f pipe
Portal gantry works
Launching of girder
Launching of segments
Unloading segments from derrick
Extraction of temporary pile from marine section |
2.5.7.
Major construction activities for Contract no.
HK/2010/06 have been commenced on March 2011. During this reporting period, the
principal work activities are summarized in Table
2.10:
Table 2.10 Principal Work Activities for Contract
no. HK/2010/06
March
2013 |
April
2013 |
May
2013 |
Utility
works in section 2 |
Utility works in section 2 |
Nil |
2.5.8.
Major construction activities for Contract no.
HK/2012/08 have been commenced on March 2013. During the reporting period, the
principal work activities are summarized in Table 2.11
Table 2.11 Principal Work Activities for Contract no. HK/2012/08
March
2013 |
April
2013 |
May
2013 |
Site preparation works
Site survey |
Site preparation works
Site survey |
Site preparation works
Site survey |
2.5.9.
Implementation
status of the recommended mitigation measures during this reporting period is
presented in Appendix 2.1.
3.1.1.
The
noise monitoring stations for the Project are listed and shown in Table
3.1 and Figure 3.1. Appendix 3.1 shows
the established Action/Limit Levels for the monitoring works.
Table 3.1 Noise Monitoring Station
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun
Area |
M3a |
Tung Lo Wan
Fire Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
*M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
M8 |
City Hall |
* Remark 1: Location
ID has been updated from M7 to M8 for City Hall
* Remark 2: M7e has
become a reference station starting from 7 Aug 2012
Real time Noise Monitoring Stations
3.1.2.
The
noise monitoring stations for the Project are listed and shown in Table 3.2 and Figure 3.1.. Appendix 3.1 shows
the established Action/Limit Levels for the monitoring works.
Table
3.2 Real Time Noise Monitoring Station
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section Whitefield Depot |
North Point |
RTN2a |
Electric Centre
(Replacement of RTN2) |
North Point |
RTN3 |
Pok Leung Kuk Yu |
Tin Hau |
RTN4 |
|
* RTN2 was relocated from Oil Street Community Liaison Centre to
Electric Centre on
05 Oct 2012 and re-designated
as RTN2a.
Noise Monitoring
Parameters, Frequency and Duration
3.1.3.
The construction noise level shall be measured in terms of
the A-weighted equivalent continuous sound pressure level (Leq). Leq (30
minutes) shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For
all other time periods, Leq (5 minutes) shall be employed for
comparison with the Noise Control Ordinance (NCO) criteria.
Supplementary information for data auditing, statistical results such as L10
and L90 shall also be obtained for reference.
3.1.4.
Noise
monitoring shall be carried out at all the designated monitoring stations. The
monitoring frequency shall depend on the scale of the construction activities.
The following is an initial guide on the regular monitoring frequency for each
station on a weekly basis when noise generating activities are underway:
·
One
set of measurements between 0700 and 1900 hours on normal weekdays.
3.1.5.
Real
time noise shall be carried out at the designated monitoring stations. The
following is an initial guide on the regular monitoring frequency for each
station on a 24 hours daily basis when noise generating activities are
underway:
·
One
set of measurements between 0700 and 1900 hours on normal weekdays.
·
One
set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and
2300 hours on public holidays.
·
One
set of measurements between 2300 and 0700 hours on next day on everyday.
3.1.6.
If
construction works are extended to include works during the hours of 1900
0700 as well as public holidays and Sundays, additional weekly impact
monitoring shall be carried out during respective restricted hours periods.
Applicable permits under NCO shall be obtained by the Contractor.
Monitoring Equipment
3.1.7.
As
referred to in the Technical Memorandum issued under the NCO, sound level
meters in compliance with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be
used for carrying out the noise monitoring. Immediately prior to and following
each noise measurement the accuracy of the sound level meter shall be checked
using an acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agree to within 1.0 dB.
3.1.8.
Noise
measurements shall not be made in fog, rain, wind with a steady speed exceeding
5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with
a portable wind speed meter capable of measuring the wind speed in m/s.
3.1.9.
The
sound level meter shall be checked using an acoustic calibrator generating a
known sound pressure level at a known frequency before deployment to the site
and during each site visit. Measurements may be accepted as valid only if the
calibration level from before and after the noise measurement agree to within
1.0 dB.
Air Quality Monitoring
Stations
3.2.1. The air monitoring stations for the Project are
listed and shown in Table 3.3 and Figure 3.1. Appendix 3.1 shows the established
Action/Limit Levels for the monitoring works.
Table 3.3 Air Monitoring Stations
Station ID |
Monitoring
Location |
Description |
CMA1b |
Oil Street Site Office* |
North Point |
CMA2a |
|
|
CMA3a |
Future CWB site office
at Wanchai Waterfront Promenade |
|
CMA4a |
Society for the
Prevention of Cruelty to Animals |
Wan Chai |
CMA5a |
Children Playgrounds
opposite to |
Wan Chai |
CMA6a |
Future AECOM site
office at Work Area |
Wan Chai |
MA1e |
International Finance Centre (Eastern End of Podium) |
Central |
MA1w |
International Finance Centre (Western End of Podium) |
Central |
Remarks*: The
location ID of monitoring station CMA1b was updated as Oil Street Site Office
in
April 2013.
Air Monitoring Parameters,
Frequency and Duration
3.2.2. One-hour and 24-hour TSP levels should be measured
to indicate the impacts of construction dust on air quality. The 24-hour TSP
levels shall be measured by following the standard high volume sampling method
as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part
50), Appendix B.
3.2.3. All relevant data including temperature, pressure,
weather conditions, elapsed-time meter reading for the start and stop of the
sampler, identification and weight of the filter paper, and any other local atmospheric
factors affecting or affected by site conditions, etc., shall be recorded down
in detail.
3.2.4. For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
Sampling Procedure and
Monitoring Equipment
3.2.5. High volume samplers (HVSs) in compliance with the
following specifications shall be used for carrying out the 1-hour and 24-hour
TSP monitoring:
·
0.6
1.7 m3 per minute adjustable flow range;
·
Equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours
operation;
·
Installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
·
Capable
of providing a minimum exposed area of 406 cm2;
·
Flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
·
Equipped
with a shelter to protect the filter and sampler;
·
Incorporated
with an electronic mass flow rate controller or other equivalent devices;
·
Equipped
with a flow recorder for continuous monitoring;
·
Provided
with a peaked roof inlet;
·
Incorporated
with a manometer;
·
Able
to hold and seal the filter paper to the sampler housing at horizontal
position;
·
Easily
changeable filter; and
·
Capable
of operating continuously for a 24-hour period.
3.2.6. Initial calibration of dust monitoring equipment
shall be conducted upon installation and thereafter at bi-monthly intervals. The
transfer standard shall be traceable to the internationally recognized primary
standard and be calibrated annually. The concern parties such as IEC shall
properly document the calibration data for future reference. All the data
should be converted into standard temperature and pressure condition.
3.2.7. Laboratory Measurement / Analysis
3.2.8. A clean laboratory with constant temperature and
humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
3.2.9. Filter paper of size 8 x 10 shall be labelled
before sampling. It shall be a clean filter paper with no pinholes, and shall
be conditioned in a humidity-controlled chamber for over 24-hours and be
pre-weighed before use for the sampling.
3.2.10. After sampling, the filter paper loaded with dust
shall be kept in a clean and tightly sealed plastic bag. The filter paper shall
then be returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
readout down to 0.1 mg. The balance shall be regularly calibrated against a
traceable standard.
3.2.11. All the collected samples shall be kept in a good
condition for 6 months before disposal.
4.0.1. Per EPDs letter
dated 3 Aug 2012 (received by ET on 6 Aug 2012 through HyD), noise monitoring
at M8 City Hall commenced on 7 Aug 2012, and the monitoring station M7e International
Finance Centre (Eastern Podium) has become a reference station starting from 7
Aug 2012.
4.0.2. Due to safety
concerns, the monitoring location for M4b Victoria Centre has been finely
adjusted from 7 June 2012.
4.0.3. Monitoring for report of review baseline noise
level was performed from 11 April 2011 to 8 June 2011. Then the report was submitted on the 20 June
2011, verified by IEC on 18 July 2011 and was approved by ER by January 2012. The new baseline is used for the noise
calculation starting from the January 2012 reporting month.
4.0.4. The environmental monitoring will be implemented
based on the division of works areas of each designed project managed under
different contracts with separate FEP applied by individual contractors. Overall layout showing work areas of various
contracts, latest status of work commencement and monitoring stations is shown
in Figure
2.1 and Figure 3.1. The monitoring results
are presented in according to the Individual Contract(s).
4.0.5. In the reporting period, the concurrent contracts are
as follows:
Contract
no. HY/2009/15 Central-Wanchai Bypass Tunnel (
Contract
no. HY/2009/17 Central Wanchai Bypass (CWB) at FEHD Whitfield Depot
Advanced piling works under FEP-03/364/2009
Contract
no. HY/2009/18 Central Wanchai Bypass (CWB) Central Interchange under
FEP-05/364/2009/A
Contract
no. HY/2009/19 Central Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009
Contract
no. HK/2009/01 Wanchai Development Phase II Central Wanchai Bypass at
Contract
no. HK/2009/02 Wanchai Development Phase II Central- Wanchai Bypass at Wanchai
East
Contract
no. HY/2009/17 Central Wanchai Bypass (CWB) at FEHD Whitfield Depot
Advanced piling works under FEP-03/364/2009
4.1.1.
The
proposed division of noise monitoring stations for Contract no. HY/2009/17 is
summarized in Table 4.1 below:
Table
4.1 Noise Monitoring Stations for Contract no. HY/2009/17
Station |
Description |
M4b |
Victoria Centre |
4.1.2.
No
exceedance was recorded in this reporting
quarter.
4.1.3.
Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of graphical
presentation can be referred in Appendix 4.1.
Contract no.
HY/2009/18 Central Wanchai Bypass (CWB) Central Interchange under
FEP-05/364/2009/A
4.1.4.
Noise
monitoring for the Central Interchange works under contract no. HY/2009/18 was
commenced on 22 April 2011.The proposed division of noise monitoring stations
for Contract no. HY/2009/18 are summarized in Table 4.2 below.
Table 4.2 Noise Monitoring Station for Contract no. HY/2009/18
Station |
Description |
*M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
M8 |
City Hall |
* Remark : M7e has become a reference station starting from 7 Aug 2012
4.1.5. No exceedance was recorded in this
reporting quarter.
4.1.6. Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 4.1.
Contract no. HK/2009/01 - Wanchai Development Phase
II - Central - Wanchai Bypass at Hong Kong Convention and Exhibition Centre -
Tunnel Works under FEP-02/364/2009 and Contract no. HK/2009/02 - Wanchai
Development Phase II - Central - Wanchai Bypass at Wanchai East (CWB Tunnel)
under FEP-01/364/2009
4.1.7.
The
commencement of construction works for Contract no. HK/2009/01 under
FEP-02/364/2009 is on 25 August 2011
and HK/2009/02 under FEP-01/364/2009 is on 26 April 2011.The proposed division
of air monitoring stations are summarized in Table 4.3 below.
Table 4.3 Noise Monitoring Stations for
Contract nos. HK/2009/01 and HK/2009/02
Station |
Description |
M1a |
Harbour Road Sports Centre |
4.1.8. No exceedance was recorded in this
reporting quarter.
4.1.9. Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 4.1.
Contract no.
HY/2009/15 - Central-Wanchai Bypass Tunnel (
4.1.10.
The
commencement of construction works for Contract no. HY/2009/15 under
FEP-06/364/2009/A was on 13 July 2011. Noise
monitoring was commenced on 13 July 2011. The proposed
division of noise monitoring stations are summarized in Table 4.4 below.
Table 4.4 Noise
Monitoring Station for Contract nos. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
4.1.11. No exceedance was recorded in this
reporting quarter.
4.1.12. Details of
noise monitoring results and graphical presentation can be referred in Appendix 4.1.
4.1.13. Noise monitoring for the tunnel works under
contract no. HY/2009/19 was commenced on 24 April 2011. The proposed division
of noise monitoring stations are summarized in Table 4.5 below.
Table 4.5
Noise Monitoring Stations
for Contract no. HY/2009/19
Station |
Description |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
Reporting month of March
2013
4.1.14.
Four limit level exceedances were recorded on 7, 12, 19
and 26 March 2013 at M6 HK Baptist Church Henrietta
Secondary School in the reporting month.
4.1.15.
Major traffic noise observed during monitoring on 7, 12 and 19 March
2013 and it was considered as the major noise contribution. As such, the limit
level exceedances were concluded as non-project related.
4.1.16.
Breaking works for pile head under HY/2009/19 were observed during
monitoring on 26 March 2013. Despite nearby traffic was observed, it was
considered that the breaking operation was the major noise contribution. As
such, the limit level exceedance was concluded as project related. The
temporary noise blanket at marine platform was confirmed in place and rectification
measures including provision of additional noise screen for breakers and
reduction in the number of breakers in parallel use were implemented by the
contractor after exceedance was identified.
Reporting
month of April 2013
4.1.17.
Four limit level
exceedances were recorded on 3, 12, 16 and 23 April 2013 at M6 HK Baptist Church Henrietta Secondary School in the reporting
month.
4.1.18.
Major traffic noise observed during monitoring on 3, 16 and 23 April
2013 and it was considered as the major noise contribution. As such, the limit
level exceedances were concluded as non-project related.
4.1.19.
Breaking works for pile head under HY/2009/19 were observed during
monitoring on 12 April 2013. Despite nearby traffic was observed, it was
considered that the breaking operation was the major noise contribution. As
such, the limit level exceedance was concluded as project related. The
temporary noise blanket at marine platform was confirmed in place and rectification
measures including provision of additional noise blanket at top side of marine
pier and reduction in the number of breakers in parallel use were implemented
by the contractor after exceedance was identified.
Reporting
month of May 2013
4.1.20.
Three limit level
exceedances were recorded on 2, 7 and 21 May 2013 at M6 HK Baptist Church Henrietta
Secondary School in the reporting month.
4.1.21.
Major traffic noise observed during monitoring on 2, 7 and 21 May 2013
and it was considered as the major noise contribution. As such, the limit level
exceedances were concluded as non-project related.
4.1.22. Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 4.1 and the
Notification of Exceedance can be referred in Appendix 6.2.
Contract no. HY/2009/17 Central - Wanchai Bypass
(CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009 and Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
4.2.1.
The
proposed division of real time noise monitoring stations are summarized in Table
4.6 below. Real time noise monitoring for the piling works under
contract no. HY/2009/17 was commenced on 5 October 2010.
Table
4.6 Real Time Noise Monitoring
Station for Contract no. HY/2009/17
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD Hong Kong Transport Section Whitefield Depot |
Real
time noise monitoring results and graphical presentation during night time
period are for information only.
4.2.2.
No action and limit level exceedance was
recorded during the March reporting month.
4.2.3.
Limit level exceedances were recorded at
RTN1-FEHD Hong Kong Transport Section Whitfield Depot during restricted hours
on 28 and 30 March 2013 in the April reporting month. After checking with
contractor, no designated project work was conducted at the concerned location
during the recorded period. The exceedances were non-continuous and considered
to be contributed by nearby IEC traffic.
4.2.4.
Limit level exceedances were recorded at RTN1-FEHD Hong Kong Transport
Section Whitfield Depot during restricted hours on 28 April 2013. After
checking with contractor, no major noisy construction works was conducted at the
concerned location during the recorded period. The exceedances were
non-continuous and considered to be contributed by nearby IEC traffic.
4.2.5.
Real
time noise monitoring results measured in this reporting period are reviewed
and summarized. Details
of real time noise monitoring results and graphical presentation can be
referred to Appendix
4.2
4.2.6.
The
proposed division of noise monitoring stations are summarized in Table 4.7
below. Real time noise monitoring for major construction works under contract
no. HY/2009/19 was commenced on 24 April 2011.
Table
4.7 Real Time Noise Monitoring
Stations for Contract no. HY/2009/19
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD Hong Kong Transport Section Whitefield Depot |
RTN2a |
North Point |
Electric Centre
(Replacement of RTN2) |
RTN3 |
North Point |
Pok Leung Kuk Yu |
RTN4 |
Tin Hau |
|
* Real time noise monitoring results and graphical presentation during
night time period are for information only.
*Real-time noise monitoring results and graphical presentation for RTN3
during restricted hours are for information only as no night classes were
conducted at the educational institute.
Reporting
month of March 2013
4.2.7.
No limit level exceedance was recorded at
RTN1-FEHD Hong Kong Transport Section Whitfield Depot in this reporting month.
4.2.8.
No limit level exceedance was recorded at
RTN2a-Electric Centre in this reporting month.
4.2.9.
No limit Level exceedance was recorded at
RTN3-Yu Lee Mo Fan Memorial School in this reporting month.
4.2.10.
Limit level exceedances were recorded at
RTN4-Causeway Bay Community Centre during restricted hours on 10 March 2013.
After checking with contractor, road mark realignment was conducted during the
recorded period. However, no PMEs were used for performing such works. The
exceedances were non-continuous and considered to be contributed by nearby IEC
traffic.
Reporting
month of April 2013
4.2.11.
Limit level exceedances were recorded at RTN1-FEHD
Hong Kong Transport Section Whitfield Depot during restricted hours on 28 and
30 March 2013. After checking with contractor, no noisy construction works was
conducted at the concerned location during the recorded period. The exceedances
were non-continuous and considered to be contributed by nearby IEC traffic.
4.2.12.
Limit level exceedance was recorded at
RTN2a-Electric Centre during restricted hours on 28 March 2013. After checking
with contractor, no construction work was conducted at the concerned location
during the recorded period. The exceedances were non-continuous and considered
to be contributed by near by IEC traffic.
4.2.13.
No limit Level exceedance was recorded at
RTN3-Yu Lee Mo Fan Memorial School in this reporting month.
Limit level
exceedances were recorded at RTN4-Causeway Bay Community Centre during
restricted hours on 28 March 2013. After checking with contractor, no
construction work was conducted at the concerned location during the recorded
period. The exceedances were non-continuous and considered to be contributed by
near by IEC traffic.
Reporting month
of May 2013
4.2.14.
Limit level exceedances were recorded at
RTN1-FEHD Hong Kong Transport Section Whitfield Depot during restricted hours
on 28 April 2013. After checking with contractor, no major noisy construction
works was conducted at the concerned location during the recorded period. The
exceedances were non-continuous and considered to be contributed by nearby IEC
traffic.
4.2.15.
Limit level exceedance was recorded at
RTN2a-Electric Centre during restricted hours on 20 May 2013 and during daytime
on 21 May 2013. After checking with contractor, no construction work was
conducted 20 May 2013 at the concerned location during the recorded period and
no major noisy construction work was conducted at the concerned location on 21
May 2013. The exceedances were non-continuous and considered to be contributed
by near by IEC traffic.
4.2.16.
Limit Level exceedance was recorded at
RTN3-Yu Lee Mo Fan Memorial School during daytime on 21 May 2013. After
checking with the contractor, rebar fixing and concrete pile head breaking
works were conducted during the recorded period. Mitigation measures including
erection of noise barrier was confirmed in place. The exceedance was
non-continuous and considered to be contributed by nearby IEC traffic.
4.2.17.
No Limit level exceedance was recorded at
RTN4-Causeway Bay Community Centre in the reporting month.
4.2.18.
Real
time noise monitoring results measured in this reporting quarter are reviewed
and summarized. Details of real time noise monitoring results and graphical
presentation can be referred to Appendix
4.2
4.3.1
Due to extension of site boundary by contractor of HY/2009/19, location
of air monitoring station CMA1b Oil Street Community Liaison Centre has been
finely adjusted on 21 April 2012.
4.3.2
Due to lack of electricity supply, the 24hr-TSP monitoring at CMA2a were
rescheduled from 4 Mar 2013 to 5 Mar 2013.
4.3.3
Due to lack of electricity supply, the
24hr-TSP monitoring at CMA1b and CMA3a were rescheduled from 19 April 2013 to
20 April 2013 and from 8, 9 April 2013 to 25, 26 April 2013 respectively.
4.3.4
Due to lack of electricity supply, the
24hr-TSP monitoring at CMA3a and CMA4a were rescheduled from 1 May 2013 to 2
May 2013 and from 18 May 2013 to 20 May 2013 respectively.
Contract no. HY/2009/17 Central - Wan Chai Bypass
(CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009
4.3.5
The
proposed divisions of air monitoring stations are summarized in Table
4.8 below. Air monitoring for the piling works under contract no.
HY/2009/17 was commenced on 8 October 2010.
Table
4.8 Air Monitoring Stations
for Contract no. HY/2009/17
Station |
Description |
CMA1b |
Oil
Street Site Office |
CMA2a |
|
4.3.6
Two action level and no limit level exceedances were recorded at CMA1b-
Oil Street Site Office on 15 April 2013 during 1hr- TSP monitoring in the April
reporting month. After investigation, it was found that the high ambient air
pollutant concentration was the major contribution to air quality impact and no
designated project construction work was conducted during monitoring. As such,
the exceedances were considered as non- project related. Air quality monitoring results measured in this
reporting period are reviewed and summarized.
Details of air monitoring results and graphical presentation can be
referred in Appendix 4.3.
Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB) Central Interchange under
FEP-05/364/2009/A
4.3.7
The
proposed division of air monitoring stations are summarized in Table
4.9 below.
Table
4.7 Air Monitoring Stations
for Contract no.
HY/2009/18
Station |
Description |
MA1e |
International Finance Centre (Eastern End of Podium) |
MA1w |
International Finance Centre (Western End of Podium) |
4.3.8
Air
monitoring for the Central Interchange works under contract no. HY/2009/18 was
commenced on 21 April 2011.
4.3.9
Two action level and one limit level exceedances
were recorded at MA1e- International Finance Centre (Eastern Wing) on 15 April
2013 during 1hr- TSP monitoring in the April reporting month. After
investigation, it was found that the high ambient air pollutant concentration
was the major contribution to air quality impact and contractor dust mitigation
measures were confirmed in place. As such, the exceedances were considered as
non- project related.
4.3.10
Three action level and no limit level
exceedances were recorded at MA1w- International Finance Centre (Western Wing)
on 15 April 2013 during 1hr- TSP monitoring in the April reporting month. After
investigation, it was found that the high ambient air pollutant concentration
was the major contribution to air quality impact and contractor dust mitigation
measures were confirmed in place. As such, the exceedances were considered as
non- project related.
Details of air monitoring results and graphical
presentation can be referred in Appendix 4.3.
Contract no. HK/2009/01 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at
4.3.11
The
commencement of construction works for Contract no. HK/2009/01 under
FEP-02/364/2009 is on 25 August 2011. The
proposed division of air monitoring stations are summarized in Table
4.10 below.
Table
4.10 Air Monitoring Station
for Contract no. HK/2009/01
Station |
Description |
CMA5a |
Children Playgrounds opposite to |
4.3.12
No
exceedance was recorded in the reporting quarter. Air quality monitoring
results measured in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 4.3.
Contract no. HK/2009/02 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
Table 4.11 Air Monitoring Station
for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
4.3.14
No
exceedance was recorded in the reporting period. Air quality monitoring results
measured in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 4.3.
Contract no.
HY/2009/15 - Central-Wanchai Bypass Tunnel (
4.3.15
The
commencement of construction works for Contract no. HY/2009/15 under
FEP-06/364/2009/A was on 13 July 2011. The proposed division of air
monitoring stations are summarized in Table 4.12
below.
Table
4.12
Air
Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB site office at Wanchai
Waterfront Promenade |
4.3.16
Two action level and no limit level exceedances were recorded at CMA3a-
CWB PRE Site Office on 15 April 2013 during 1hr- TSP monitoring in the April
reporting month. After investigation, it was found that the high ambient air
pollutant concentration was the major contribution to air quality impact and
contractor dust mitigation measures were confirmed in place. As such, the
exceedances were considered as non-project related. Details of air
monitoring results and graphical presentation can be referred in Appendix 4.3.
Contract no.
HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under
FEP-07/364/2009/A
4.3.17 Air monitoring for the tunnel works was commenced
on 26 April 2011 for Contract no. HY/2009/19 under FEP-07/364/2009/A.
The proposed division of air monitoring stations are summarized in Table 4.13
below.
Table 4.13 Air Monitoring Stations for Contract no. HY/2009/19
Station |
Description |
CMA1b |
Oil St Community Liaison Centre |
CMA2a |
|
4.3.18.
Two action level and no limit level exceedances were recorded at CMA1b-
Oil Street Site Office on 15 April 2013 during 1hr- TSP monitoring in the April
reporting month. After investigation, it was found that the high ambient air
pollutant concentration was the major contribution to air quality impact and
contractor dust mitigation measure was confirmed in place. As such, the
exceedances were considered as non-project related. Details of air
monitoring results and graphical presentation can be referred in Appendix 4.3.
Contract no. HY/2009/17 Central
- Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009
4.4.1.
No inert and non-inert C&D waste was disposed in
the reporting period. Details of the waste flow table are summarized in Table
4.14
Table
4.14 Details of Waste Disposal for Contract no. HY/2009/17
Waste Type |
Quantity
this quarter, m3 |
Cumulative
Quantity-to-Date, m3 |
Disposal /
Dumping Grounds |
Inert C&D materials disposed |
NIL |
NIL |
CWBP/TKO137 |
Inert C&D materials recycled |
N/A |
||
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
N/A |
N/A |
N/A |
Contract nos. HK/2009/01 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at
4.4.2.
Inert
and non-inert C&D waste was disposed of in this reporting period. Details
of the waste flow table are summarized in Table 4.15.
Table 4.15 Details of Waste Disposal for Contract no. HK/2009/01
Inert C&D materials disposed |
5561.5 |
27810.845 |
TKO137, TM38 |
Inert C&D materials recycled |
Nil |
5104.5 |
N/A |
Non-inert C&D materials disposed |
80.5 |
1273.5 |
SENT Landfill |
Non-inert C&D materials recycled |
Nil |
205943 |
N/A |
Chemical waste disposed |
450 |
9550 |
Kwun Kee (Chemical Waste Collector) |
Contract no. HK/2009/02 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009
4.4.3.
Inert
and non-inert C&D waste were disposed of in this reporting period. Details
of the waste flow table are summarized in Table 4.16.
Table 4.16 Details of Waste Disposal for
Contract no. HK/2009/02
Inert C&D materials disposed |
7174.86 |
236556.94 |
TKO137, TM 38 |
Inert C&D materials recycled |
Nil |
18161 |
WCR2 |
Non-inert C&D materials disposed |
113.335 |
922.19 |
SENT Landfill |
Non-inert C&D materials recycled |
NIL |
N/A |
N/A |
Chemical waste disposed |
1400 |
7971 |
N/A |
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) Central
Interchange under FEP-05/364/2009/A
4.4.4.
Inert
and non-inert C&D waste was disposed of in this reporting period. Details
of the waste flow table are summarized in Table 4.17.
Table 4.17 Details of Waste Disposal for
Contract no. HY/2009/18
Inert C&D materials disposed |
9982 |
94015 |
T.K.O. 137 |
Inert C&D materials recycled |
2009 |
55989 |
N/A |
Non-inert C&D materials disposed |
226 |
1160 |
SENT Landfill |
Non-inert C&D materials recycled (tonnes) |
Nil |
77.84 |
N/A |
Chemical waste disposed |
Nil |
3565 |
N/A |
Contract no. HY/2009/15 - Central-Wanchai Bypass Tunnel (
4.4.5.
Inert
and non-inert C&D waste was disposed of in this reporting period. Details
of the waste flow table are summarized in Table 4.18.
Table 4.18 Details of Waste Disposal for Contract no. HY/2009/15
Inert C&D materials disposed |
88096.3 33209.6 |
333973.3 197189.6 |
Tuen Mun Area 38 TKO137 FB |
Inert C&D materials recycled |
8567.8 |
217596.2 |
HY/2009/11 ex-PCWA TS4 |
Non-inert C&D materials disposed |
137.8 |
809 |
SENT Landfill |
Non-inert C&D materials recycled |
191.4 |
543000.8 |
Xun Xiang Metal ware Skylight Recycle (paper) |
Chemical waste disposed |
4490 |
17211 |
Dunwell Group |
Remarks:
Contractor clarified and updated the Non-inert C&D material recycled for
the reporting quarter.
Contract
no. HY/2009/19 Central Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/A
4.4.6.
Inert C&D materials was recycled
non-inert C&D waste was disposed of in this reporting period. Details of
the waste flow table are summarized in Table 4.19.
Table 4.19 Details of Waste Disposal for
Contract no. HY/2009/19
Inert C&D materials
disposed |
29408.24 |
295116.71 |
N/A |
39544.72 |
49264.18 |
N/A |
|
Non-inert C&D
materials disposed |
85.18 |
827.79 |
SENT Landfill |
Non-inert C&D
materials recycled |
57.34 |
282.03 |
N/A |
Chemical waste disposed |
0.17 |
4.59 |
N/A |
Remarks: Contractor clarified and updated the inert
C&D material recycled disposed in for the reporting quarter.
Contract no. HK/2010/06 Wan Chai Development Phase
II - Central-Wan Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
4.4.7.
No
inert and Non-inert C&D wastes were disposed of in this reporting period.
Details of the waste flow table are summarized in Table 4.20.
Table 4.20 Details of Waste Disposal for Contract no. HK/2010/06
Inert C&D materials disposed |
NIL |
NIL |
TM38 |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
Recyclers |
Chemical waste disposed |
NIL |
NIL |
N/A |
Contract no.
HK/2012/08 Wan Chai Development Phase II - Central-Wan Chai Bypass at Wan Chai
West under FEP-09/364/2009/B
4.4.8.
No inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 4.21.
Table 4.21 Details of Waste Disposal for Contract no. HK/2012/08
Waste
Type* |
Quantity
this month, m3 |
Cumulative-to-Date,
m3 |
Disposal
/ Dumping Grounds |
Inert
C&D materials disposed |
NIL |
NIL |
N/A |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
5.0.1. The Event Action Plan for construction noise and air
quality are presented in Appendix 5.1.
Contract no. HY/2009/17 Central - Wan Chai Bypass (CWB) at FEHD
Whitfield Depot - Advanced piling works under FEP-03/364/2009
5.1.1.
No limit or action level exceedance was
recorded in this reporting quarter.
Contract no. HY/2009/18 - Central - Wan Chai Bypass
(CWB) Central Interchange under FEP-05/364/2009/A
5.1.2.
No limit or action level exceedance was
recorded in this reporting quarter.
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at
5.1.3.
No limit or action level exceedance was
recorded in this reporting quarter.
Contract no. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East(CWB Tunnel)
5.1.4.
No limit or action level exceedance was
recorded in this reporting quarter.
Contract no. HY/2009/15 - Central-Wanchai Bypass
Tunnel (
5.1.5. No limit
or action level exceedance was recorded in this reporting quarter.
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
Reporting month of March 2013
6.1.1. Four limit level
exceedances were recorded on 7, 12. 19 and 26 March 2013 at M6 HK Baptist Church Henrietta
Secondary School in the reporting month. Investigations found that on 7, 12 and 19
March 2013, major traffic noise was contributed in the noise monitoring and exceedances
were not related to the Project. On 26 March 2013, investigation found that
breaking works operation was the major noise contribution despite nearby IEC traffic
and the exceedance was considered as Project-related.
Reporting month of April 2013
6.1.2. Four limit level
exceedances were recorded on 3, 12, 16 and 23 April 2013 at M6 HK Baptist Church Henrietta
Secondary School in the reporting month. Investigations found that on 3, 16 and 23
April 2013, major traffic noise was contributed in the noise monitoring and exceedances
were not related to the Project. On 12 April 2013, investigation found that
breaking works operation was the major noise contribution despite nearby IEC traffic
and the exceedance was considered as Project-related.
Reporting month of May 2013
5.1.1
Three limit level
exceedances were recorded on 2, 7 and 21 May 2013 at M6 HK Baptist Church Henrietta
Secondary School in the reporting month. Investigations found that on 2, 7 and 21 May
2013, major traffic noise was contributed in the noise monitoring and exceedances
were not related to the Project.
Contract no. HY/2009/17 Central
- Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced piling works under FEP-03/364/2009
Reporting month of April 2013
6.2.1.
Two action level exceedances were recorded at
CMA1b- Oil Street Site Office on 15 April 2013 during 1hr TSP monitoring in the
reporting month. Ambient air pollutant concentration was considered as the
contribution to air quality impact. As such, the exceedances were concluded as
non project related.
Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB) Central Interchange under
FEP-05/364/2009/A
Reporting month of April 2013
6.2.2.
Two action level and one limit level exceedances
were recorded at MA1e- International Finance Centre (Eastern Wing) on 15 April
2013 during 1hr TSP monitoring in the reporting month. Ambient air pollutant
concentration was considered as the contribution to air quality impact. As
such, the exceedances were concluded as non project related.
6.2.3.
Three action level exceedances were recorded at
MA1w- International Finance Centre on 15 April 2013 (Western Wing) during 1hr
TSP monitoring in the reporting month. Ambient air pollutant concentration was
considered as the contribution to air quality impact. As such, the exceedances
were concluded as non project related.
Contract no.
HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
5.2.1.
No
exceedance was recorded in the reporting quarter.
Contract nos.
HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan
Chai East(CWB Tunnel)
5.2.2.
No
exceedance was recorded in the reporting quarter.
Contract no. HY/2009/15 - Central-Wanchai Bypass Tunnel (
Reporting month of April 2013
5.2.3.
Two action level exceedances were recorded at
CMA3a- CWB PRE Site Office on 15 April 2013 during 1hr-TSP monitoring in the
reporting month. Ambient air pollutant concentration was considered as the
contribution to air quality impact. As such, the exceedances were concluded as
non project related.
Contract no.
HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under FEP-07/364/2009/A
Reporting month of
April 2013
5.2.1
Two action level exceedances were recorded at
CMA1b- Oil Street Site Office on 15 April 2013 during 1hr-TSP monitoring in the
reporting month. Ambient air pollutant concentration was considered as the
contribution to air quality impact. As such, the exceedances were concluded as
non project related.
Contract
no. HY/2009/17 Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot -
Advanced piling works under FEP-03/364/2009
Reporting month of March 2013
Reporting month of April 2013
6.1.4. Non project
related limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport
Section Whitfield Depot on 28 and 30 March 2013. Investigation found that
exceedances were contributed by IEC traffic.
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/A
Reporting month of March 2013
6.1.5. No limit level
exceedance was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield
Depot in this reporting month.
6.1.6. No limit level
exceedance was recorded at RTN2a-Electric Centre in this reporting month.
6.1.7. No limit level
exceedance was recorded at RTN3- Yu Lee Mo Fan Memorial School in this
reporting month.
6.1.8. Non project
related exceedances were recorded at RTN4- Causeway Bay Community Centre on 10
March 2013. Investigation found that exceedances were contributed by IEC
traffic.
Reporting month of April 2013
6.1.9. Non project
related limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport
Section Whitfield Depot on 28 and 30 March 2013. Investigation found that
exceedances were contributed by IEC traffic.
6.1.10. Non project
related limit level exceedance was recorded at RTN2a- Electric Centre on 28
March 2013. Investigation found that exceedances were contributed by IEC
traffic.
6.1.11. No limit level
exceedance was recorded at RTN3- Yu Lee Mo Fan Memorial School in this
reporting month.
6.1.12. Non project
related exceedances were recorded at RTN4- Causeway Bay Community Centre on 28
March 2013. Investigation found that exceedances were contributed by IEC
traffic.
Reporting month of May 2013
6.1.13. Non project
related limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport
Section Whitfield Depot on 28 Apr 2013. Investigation found that exceedances
were contributed by IEC traffic.
6.1.14.
Non project related limit level
exceedance was recorded at RTN2a- Electric Centre on 20 and 21 May 2013.
Investigation found that exceedances were contributed by IEC traffic.
6.1.15. Non project
related limit level exceedance was recorded at RTN3- Yu Lee Mo Fan Memorial
School on 21 May 2013. Investigation found that the exceedance was contributed
by IEC traffic.
6.1.16. No limit level
exceedances were recorded at RTN4- Causeway Bay Community Centre in this
reporting month.
5.4.1. There was no non-compliance from the site audits in
the reporting period. During environmental site inspections conducted during
the reporting quarter, minor deficiencies were noted. However, the Contractor rectified all
deficiencies after receipt of notification.
5.5.1
There was no particular action taken since no project-related
non-compliance was recorded from the site audits and environmental monitoring
in the reporting period.
5.5.2
One project related exceedances from noise monitoring
was recorded in the March reporting month within the reporting quarter.
5.5.3
One project related exceedances from noise monitoring
was recorded in the April reporting month within the reporting quarter.
5.6.1
One limit level exceedances of noise
monitoring recorded on 26 March 2013 at M6- HK Henrietta Secondary School that
was considered in relation to pile head breaking works conducted during monitoring.
5.6.2
Following the Event and Action Plan,
additional noise monitoring was conducted on 27 March 2013 and a proposal for
remediation measures was submitted by the contractor after the exceedance was identified.
5.6.3
The temporary noise blanket at marine platform was confirmed in place
and rectification measures including provision of additional noise screen for
breakers and reduction in the number of breakers in parallel use were
implemented by the contractor.
5.6.4
One limit level exceedances of noise
monitoring recorded on 12 April 2013 at M6- HK Henrietta Secondary School that
was considered in relation to pile head breaking works conducted during
monitoring.
5.6.5
Following the Event and Action Plan,
additional noise monitoring was conducted on 15 April 2013 and a proposal for
remediation measures was submitted by the contractor after the exceedance was identified.
5.6.6
The temporary noise blanket at marine platform was confirmed in place
and rectification measures including provision of additional noise blanket at
top side of marine pier and reduction in the number of breakers in parallel use
were implemented by the contractor.
6.0.1.
There was no environmental complaint received in this reporting period.
6.0.2. The details of cumulative complaint log and summary of
complaints are presented in Appendix
6.1.
6.0.3. No notification of summons or prosecution was received in the reporting
period. Cumulative statistic
on complaints and successful prosecutions are summarized in Table
6.1 and Table 6.2 respectively.
Table 6.1 Cumulative
Statistics on Complaints
Reporting Period |
No. of Complaints |
Commencement
of Works up to last reporting quarter |
20 |
March 2012 May 2013 |
0 |
Project-to-Date |
20 |
Table 6.2 Cumulative
Statistics on Successful Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this quarter (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
7.0.1.
According to Condition 3.4 of the
EP-364/2009/B, this section addresses the relevant cumulative construction
impact due to the concurrent activities of the current projects including the
Central Reclamation Phase III (CRIII), Wan Chai Development Phase II (WDII),
Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) and
Wan Chai Development Phase II Central Wan Chai Bypass at Wan Chai East (CWB
Tunnel).
7.0.2.
According to the Monthly EM&A report (April
2013) of Central Reclamation Phase III (CRIII), Installation of cable wall at
PLA berth, footpath construction and Modification
to the junction of Road D8 and Road P2 were performed in the May 2013 reporting
month. The water quality monitoring was completed in
October 2011 and no Project-related exceedance was recorded for air and noise
monitoring. It can be concluded that
cumulative construction impact due to the concurrent activities of the current
projects with the Central Reclamation Phase III (CRIII) was insignificant.
7.0.3.
According to the construction programme of
Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern
Corridor Link projects, the major construction activity under Wan Chai Development
Phase II were marine works at HKCEC areas, cross-harbour Watermains, Fresh
Watermains and Cooling Watermains Installations, tunnel works at Wan Chai East,
ELS work at TS4 and deep excavation at TPCWAE TCBR1W. Excavation
and tunnel works at Central Interchange, ELS and box culvert construction at
North Point area. The major environmental impact was water quality impact at
7.0.4.
The major environmental impacts generated
from tunnel works at Central and tunnel works at Wan Chai East, IECL and
Causeway Bay Typhoon Shelter were undertaken in the reporting month. No
significant air impact from construction activities was anticipated in the
reporting month. Besides, there were two project-related
exceedances were recorded during the noise environmental monitoring events in
the reporting quarter and rectification measures have been implemented by the
contractor. Thus, it is evaluated that the cumulative construction impact from
the concurrent projects including Wan Chai Development Phase II was
insignificant.
8.0.1. The EM&A programme was carried out in
accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
Air quality monitoring
Contract no. HY/2009/17 Central Wan Chai Bypass
(CWB) at FEHD Whitfield Depot Advanced piling works under FEP-03/364/2009
8.0.2.
Two action level exceedances were recorded at CMA1b- Oil Street Site
Office on 15 April 2013 during 1hr TSP monitoring in the April reporting month.
Ambient air pollutant concentration was considered as the contribution to air
quality impact. As such, the exceedances were concluded as non project related.
Contract no. HY/2009/18 Central Wan Chai Bypass
(CWB) Central Interchange under FEP-05/364/2009/A
8.0.3.
Two action level and one limit level exceedances
were recorded at MA1e- International Finance Centre (Eastern Wing) on 15 April
2013 during 1hr TSP monitoring in the April reporting month. Ambient air pollutant concentration was considered as
the contribution to air quality impact. As such, the exceedances were concluded
as non project related.
8.0.4.
Three action level exceedances were recorded at
MA1w- International Finance Centre on 15 April 2013 (Western Wing) during 1hr
TSP monitoring in the April reporting month. Ambient air pollutant concentration was considered as
the contribution to air quality impact. As such, the exceedances were concluded
as non project related.
Contract no. HY/2009/15 Central-Wanchai Bypass
Tunnel (
8.0.5.
Two action level exceedances were recorded at
CMA3a- CWB PRE Site Office on 15 April 2013 during 1hr-TSP monitoring in the April reporting month.
Ambient air pollutant concentration was considered as the contribution to air
quality impact. As such, the exceedances were concluded as non project related.
Contract no. HY/2009/19 Central Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
8.0.6.
Two action level exceedances were recorded at
CMA1b- Oil Street Site Office on 15 April 2013 during 1hr-TSP monitoring in the
April reporting month.
Ambient air pollutant concentration was considered as the contribution to air
quality impact. As such, the exceedances were concluded as non project related.
Noise monitoring
8.0.7. Three non-project related limit level
exceedances were recorded on 7, 12 and 19 March 2013 at M6 HK Baptist Church
Henrietta Secondary School in the March reporting month. Meanwhile, one limit
level exceedances at M6 HK Baptist Church Henrietta Secondary School was
recorded on 26 March 2013 was considered as related to project works.
8.0.8. Three non-project related limit level
exceedances were recorded on 3, 16 and 23 April 2013 at M6 HK Baptist Church
Henrietta Secondary School in the April reporting month. Meanwhile, one limit
level exceedances at M6 HK Baptist Church Henrietta Secondary School was
recorded on 12 April 2013 was considered as related to project works.
8.0.9.
Three non-project related limit level exceedances were recorded on 2, 7
and 21 May 2013 at M6 HK Baptist Church Henrietta Secondary School in the May
reporting month.
Real
time noise monitoring
8.0.10.
No limit level exceedance was recorded at
RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the March month.
8.0.11.
No limit level exceedance was recorded at
RTN2a-Electric Centre in the March month.
8.0.12.
No limit level exceedance was recorded at
RTN3- Yu Lee Mo Fan Memorial School in the March reporting month.
8.0.13.
Non project related exceedances were recorded
at RTN4- Causeway Bay Community Centre on 10 March 2013. Investigation found
that exceedances were contributed by IEC traffic.
8.0.14. Non project related limit level
exceedance was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield
Depot on 28 and 30 March 2013 in the April reporting month. Investigation found
that exceedances were contributed by IEC traffic.
8.0.15. Non project related limit level
exceedance was recorded at RTN2a- Electric Centre on 28 March 2013 in the April
reporting month. Investigation found that exceedances were contributed by IEC
traffic.
8.0.16. No limit level exceedance was recorded
at RTN3- Yu Lee Mo Fan Memorial School in the April reporting month.
8.0.17.
Non project related exceedances were recorded at RTN4- Causeway Bay
Community Centre on 28 March 2013 in the April reporting month. Investigation
found that exceedances were contributed by IEC traffic.
8.0.18.
Non project related limit level exceedance
was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot on 28 Apr
2013 in the
May reporting month. Investigation found that exceedances were
contributed by IEC traffic.
8.0.19.
Non project related limit level exceedance
was recorded at RTN2a- Electric Centre on 20 and 21 May 2013 in the May reporting month. Investigation
found that exceedances were contributed by IEC traffic.
8.0.20.
Non project related limit level exceedance
was recorded at RTN3- Yu Lee Mo Fan Memorial School on 21 May 2013 in the May
reporting month. Investigation found that the exceedance was contributed by IEC
traffic.
8.0.21.
No limit level exceedances were recorded at
RTN4- Causeway Bay Community Centre in the May reporting month.
8.0.22.
No environmental
complaint was received in this reporting quarter.
8.0.23. The construction programmes
of individual contracts are provided in Appendix 8.1.