Contract
No: HK/2011/07 Wanchai Development Phase II and Sampling, Field Measurement and
Testing Work (Stage 2) Environmental
Permit no. EP-364/2009/B, Further Evironmental permit nos. fep-01/364/2009,
fep-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEp-07/364/2009/a,
FEp-08/364/2009/a , FEP-09/364/2009/B and fep-10/364/2009/B Quarterly Environmental Monitoring
and Audit Report
- June 2013 to
August 2013 -
|
CLIENTS: |
|
Civil
Engineering and Development Department and Highways
Department |
Lam Geotechnics
Limited 11/F Centre
Point Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
September 2013 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
2.5 Principal Work and Activities
4.2. Real Time Noise Monitoring Results
5.4. Review of the Reasons for and the Implications of
Non-compliance
5.5. Summary of action taken in the event of and follow-up
on non-compliance
6. Complaints, Notification of Summons
and Prosecution
7. Cumulative Construction Impact due to
the Concurrent Projects
lIST
OF TABLES
Table I Principal Work Activities for Contract no.
HY/2009/18
Table II Principal Work Activities for Contract no. HK/2009/01
Table III Principal Work Activities for Contract no. HK/2009/02
Table IV Principal
Work Activities for Contract no. HY/2009/15
Table V Principal Work Activities for Contract no. HY/2009/19
Table
VI Principal Work Activities for Contract no.
HK/2010/06
Table
VII Principal Work Activities for Contract no.
HK/2012/08
Table VIII Principal Work Activities for Contract no. HY/2010/08
Table 2.1 Schedule
2 Designated Projects under this Project
Table 2.2 Details
of Individual Contracts under the Project
Table 2.3 Contact
Details of Key Personnel
Table 2.4 Principal
Work Activities for Contract no. HY/2009/18
Table 2.5 Principal
Work Activities for Contract no. HK/2009/01
Table 2.6 Principal
Work Activities for Contract no. HK/2009/02
Table 2.7 Principal
Work Activities for Contract no. HY/2009/15
Table 2.8 Principal
Work Activities for Contract no. HY/2009/19
Table 2.9 Principal Work Activities for Contract
no. HK/2010/06
Table 2.10 Principal
Work Activities for Contract no. HK/2012/08
Table 2.11 Principal Work Activities for Contract no. HY/2010/08
Table 3.1 Noise
Monitoring Station
Table 3.2 Real
Time Noise Monitoring Station
Table 3.3 Air
Monitoring Stations
Table 4.1
Noise
Monitoring Station for Contract no. HY/2009/18
Table 4.2
Noise
Monitoring Stations for Contract nos. HK/2009/01 and HK/2009/02
Table 4.3
Noise
Monitoring Station for Contract nos. HY/2009/15
Table 4.4 Noise Monitoring
Stations for Contract no. HY/2009/19
Table 4.5 Real
Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 4.6 Air
Monitoring Stations for Contract no. HY/2009/18
Table 4.7 Air
Monitoring Stations for Contract no. HK/2009/01
Table 4.8 Air
Monitoring Station for Contract no. HK/2009/02
Table 4.9 Air
Monitoring Station for Contract no. HY/2009/15
Table 4.10 Air
Monitoring Stations for Contract no. HY/2009/19
Table 4.11 Details
of Waste Disposal for Contract no. HK/2009/01
Table 4.12 Details
of Waste Disposal for Contract no. HK/2009/02
Table 4.13 Details
of Waste Disposal for Contract no. HY/2009/18
Table 4.14 Details
of Waste Disposal for Contract no. HY/2009/15
Table 4.15 Details of Waste
Disposal for Contract no. HY/2009/19
Table
4.16 Details of Waste Disposal for
Contract no. HK/2010/06
Table 4.17 Details of Waste
Disposal for Contract no. HK/2012/08
Table
4.18 Details of Waste Disposal for
Contract no. HY/2012/08
Table 6.1 Cumulative
Statistics on Complaints
Table 6.2 Cumulative
Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure
2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 3.1 Locations of Environmental Monitoring
Stations
lIST OF APPENDIces
Appendix
2.1 Environmental
Mitigation Implementation Schedule
Appendix 3.1 Action and Limit Level
Appendix
4.1 Noise
Monitoring Results and Graphical Presentations
Appendix 4.2 Real-time Noise Monitoring
Results and Graphical Presentations
Appendix
4.3 Air
Quality Monitoring Results and Graphical Presentations
Appendix 5.1 Event Action Plans
Appendix 6.1 Complaint Log
Appendix 6.2 Notification of Exceedance
Appendix 8.1 Construction Programme of
Individual Contracts
EXECUTIVE
SUMMARY
Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB)
- Central Interchange under FEP-05/364/2009/
Major construction activities for Contract no. HY/2009/18 have been
commenced on 21
Table I Principal Work
Activities for Contract no. HY/2009/18
June 2013 |
July 2013 |
August 2013 |
Excavation of
trial pit
Transplanting of
trees
Hoarding
erection and modification
Installation of
couplers, UU detection, trial trench, pre-drilling
Excavation
Drainage works
Tunnel works
Trough structure
construction and associated drilling and grouting
Road works
OHVD
installation
Pre-bored
H-piling
Bridges
construction
Scaffolding /
false-work erection |
Excavation of
trial pit
Transplanting of
trees
Hoarding
erection and modification
Installation of
couplers, UU detection, trial trench, pre-drilling
Excavation
Drainage works
Tunnel works
Trough structure
construction and associated drilling and grouting
Road works
OHVD
installation
Pre-bored
H-piling
Bridges
construction
Scaffolding /
false-work erection |
Excavation of
trial pit
Transplanting of
trees
Drainage works
Tunnel works
including scaffolding erection, excavation, OHVD installation, roadside barriers,
top and base slab construction
Trough structure
construction and associated drilling and grouting
Road works
Bridges
construction |
Contract no. HK/2009/01 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at
Major construction activities
for Contract no. HK/2009/01 have been commenced on 25 August 2011. During this
reporting period, the principal work activities are summarized as below:
Table II Principal Work Activities for Contract no.
HK/2009/01
June 2013 |
July 2013 |
August 2013 |
Pre-drilling
works for CWB (Stage 2).
Diaphragm wall
construction works at Stage 2 (North).
Temporary
bulkhead wall construction works at CH3129 (between Stage2 / Stage3).
Pre-bored H
piling works for CWB (Stage1b).
Excavation and
grouting of Pre-bored H-pile.
Pre-bored H
piling works for CWB (Stage2).
Installation of
dewatering well at CWB (Stage 1 & 1b). |
Installation of
pre-bored H-pile in CWB Stage 1 underneath Atrium Link (from CH80 to CH120)
Installation of
pre-bored H-pile in CWB Stage 2 Atrium Link (from CH120 to CH220) would be
continued. 14 nos. pre-bored H-piles had been excavated. 2 nos. pre-bored
H-piles were grouted
Construction of
bulkhead wall at CH3129 (18 panels)
Filling of the
existing open water channel at CH260.
Construction of
the Common D-wall
Demolition of
the Promenade Deck
Installation of
dewatering wells, observation wells and piezometers at CWB Stage 1
|
Installation of
pre-bored H-pile in CWB Stage 2 Atrium Link (from CH120 to CH220) was carried
on. 23 nos. pre-bored H-piles had been excavated. 6 nos. pre-bored H-piles
were grouted
Construction of
Common D-wall was commenced.
Filling of the existing open water channel
from CH100 to CH206
Demolition of
the Promenade Deck
ELS at bottom-up
area. Fabrication of steel strutting members was in order |
Contract no. HK/2009/02 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
Major construction activities
for Contract no. HK/2009/02 have been commenced on 26
Table III Principal Work
Activities for Contract no. HK/2009/02
June 2013 |
July 2013 |
August 2013 |
Base Slab for Tunnel Portion 1
Bored piles PN17 was concreted
Casting Base slab for silo setup
Desander setup and its mud pit construction for D-Wall construction at
Tunnel Portion 2 Ground treatment for D-wall at WCR2 was commenced on 10 Jun
2013.
Backfilling works for pipe trenches and the road modification works along
Casting of Base slab at Bay 4 of Box Culvert N.
Sheet pile cutting works at Bay5 / Bay 6 interface for subsequent
construction of water plug beneath the installed precast unit (Bay 6)
Panel (BHC2) of Eastern Bulkhead Wall was concreted
Excavation for P129 and the remaining panel of Eastern Bulkhead Wall
BHC12 |
ELS removal of strut S5 Rebar fixing for the center wall Bay 4
and Bay 5 Formwork delivery Installation of waterproofing for side
wall at Bay 4 & Bay 5 Total 123 nos. out of 290 nos. of
pre-grouting at WCR2 Total 66 m guide wall for D-wall
construction at WCR2 was casted Silo installation and pipe connect
from desander to silo was in progress. Desander setup for D-Wall construction
at Tunnel Portion 2 at WCR2 area |
Casting of the center wall Bay 2 and
Bay 3 Installation of waterproofing for both
side walls and rebar fixing for wall construction Total 165 nos. out of 290 nos. of
pre-grouting at WCR2 Casting of Total D-Wall Panel P90 and P98 was concreted
on 12 Aug 2013 and 17 Aug 2013 respectively. Concreting of D-wall for Tunnel
Portion 2. Steel cage installation for Panel BH4.
Excavation for Panel P91 and P99 were
on-going. |
Contract no. HY/2009/15 - Central-Wanchai Bypass
Tunnel (
Major construction activities
for Contract no. HY/2009/15 has been commenced on 13 July 2011. During this
reporting period, the principal work activities are summarized as below:
Table IV Principal Work
Activities for Contract no. HY/2009/15
July
2013 |
August
2013 |
|
ELS works and pipe roofing works at
TS4 Cut and cover tunnel construction at
TPCWAE Construction of OHVD at TS1 Excavation for mined tunnel Construction of Diaphragm Wall at TS2 |
ELS works and pipe roofing works at
TS4 Cut and cover tunnel construction at
TPCWAE Construction of OHVD at TS1 Excavation and tunnel lining
construction for mined tunnel Construction of Diaphragm Wall, Post
Diaphragm Wall Works and Installation of King Post at TS2 |
ELS works, pipe roofing works and
tunnel construction at TS4 Cut and cover tunnel construction at
TPCWAE Construction of OHVD at TS1 Excavation and tunnel lining
construction for mined tunnel Post Diaphragm Wall Works, ELS works and
Installation of King Post at TS2 |
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
Major construction activities
for Contract no. HY/2009/19 have been commenced on March 2011. During this
reporting period, the principal work activities are summarized as below:
Table V Principal Work Activities for Contract no.
HY/2009/19
June 2013 |
July 2013 |
August 2013 |
Road works at Bored piling (Land) D-wall and Barrette Construction Construction works for Box Culvert T1 Construction works for Culvert U1 Construction of Pile cap (Land) Demolition of parapet at IEC Link Construction of dewatering well for
Cut & Cover Tunnel Removal of marine platform Construction of pile cap, column &
cross head (Marine) ELS for Cut & Cover Tunnel Laying of 1500 pipe Launching of segments Unloading segments from derrick Extraction of temporary pile from
marine section |
Road works at Bored piling (Land) D-wall and Barrette Construction Construction works for Box Culvert T1 Construction works for Culvert U1 Construction of Pile cap (Land) Construction of dewatering well for
Cut & Cover Tunnel Removal of marine platform Construction of pile cap, column &
cross head (Marine) ELS for Cut & Cover Tunnel Laying of 1500 pipe Launching of segments Unloading segments from derrick Extraction of temporary pile from
marine section |
Road works at Bored piling (Land) D-wall and Barrette Construction Construction works for Box Culvert T1 Construction works for Box Culvert U1 Construction of Pile cap (Land) Demolition of parapet at IEC Link Removal of marine platform Construction of pile cap, column &
cross head (Marine) ELS for Cut & Cover Tunnel Installation of dewatering well Laying of 1500f pipe Launching of segments Extraction of temporary pile from
marine section Installation of temporary lighting at
IEC link commenced Construction of bridge truss TA1
commenced Breaking of barrette piles at Cut
& Cover tunnel commenced Demolition of parapet at IEC link |
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
Table
VI Principal Work Activities for
Contract no. HK/2010/06
June 2013 |
July 2013 |
August 2013 |
Nil |
Installation Works of Precast Concrete
Box Unit Installation of 150T anchors |
Stitching Works Grouting Works |
Contract
no. HK/2012/08 Wan Chai Development Phase II Central- Wan Chai Bypass at
Wan Chai West under FEP-09/364/2009B
Table VII Principal Work Activities
for Contract no. HK/2012/08
June 2013 |
July 2013 |
August 2013 |
Site preparation works Site survey Hoarding erection |
Site preparation works Site survey Hoarding erection |
Site preparation works Site survey Hoarding erection |
Contract
no. HY/2010/08 Central and WanChai Bypass Slip road 8 section under
FEP-10/364/2009B
Table VIII Principal Work Activities
for Contract no. HY/2010/08
June 2013 |
July 2013 |
August 2013 |
Nil |
Tree Pruning works Tree removal works, Tree transplanting works, Instrumentation works, Ground investigation works and Erection of site hoarding. |
Tree Pruning works Tree removal works Tree transplanting works Tree works within off-site nursery
compound Instrumentation works Ground investigation works Chain link fence demarcation works and Erection of site hoarding. |
Noise Monitoring
Real
time Noise Monitoring
Air Quality
Monitoring
No action level and no limit level
exceedances were recorded in this reporting quarter.
Complaints, Notifications of Summons and
Successful Prosecutions
A follow-up joint
inspection with RSS and Landscape specialist was conducted on 10 June2013, it
was considered that the withered and yellow leaves of the affected trees
(T1674,T1675,T1676,T1677,T1678,T1679,T1680,T1681,T1683,T1644,T1643,T1641,T1639)
at the concerned planter area were contributed by natural life cycle of the
affected trees and the health condition of the affected trees were considered
to be fair. It was also noted that an active CEDD works area was located within
the concerned planter area in close proximity to few of the concerned trees
(T1644, T1643, T1641, and T1639)
According to tree
inspection records from Jan 2013 to May 2013 confirmed by RSS (Document Ref:
CI-F1-043b, CI-F1-044b, CI-F1-045b, CI-F1-046b, CI-F1-047b), the affected tree
(T1712) at the concerned planter area was considered to show sign of withering
and considered to be in poor health condition in latest tree survey report
confirmed by RSS.
During the follow-up
inspection on 10 June 2013, it was observed those construction material and oil
drums were placed near the roots area of other trees within the CEDD works.
Despite the above observation, no direct evidence was found on site which
indicates the work front have contributed to the poor health condition of the
affected tree (T1712) at the time of investigation.
Nevertheless, regular
inspection to check the health condition of the trees and regular removal of
withered leaves or dead branches which deemed appropriate to maintain the
overall tree appearance were implemented by the contractor.
xxvi.
One environmental complaint under EP-364//2009/B was received on 11 June 2013 (EPD
Ref.:H04/RS/00011587-13) dated 11 June 2013) regarding noise impact near
Central Piers in the reporting month.
The complaint
reported that the noise was emanated from the construction site near the
Central Piers at around 0900 hrs on 30 May 2013 and other days and requested
follow up action by relevant department. RSS confirmed that major noise
generating construction activities undertaken at works area near Central Pier
during the concerned time include breaking up existing D-wall concrete and
excavation at portion 4B, 4C and sheet pilling works at Portion VI (
Total 1 no. of
Backhoe with breaker, 1 no. of Backhoe with vibratory hammer and 4 no.s of
pneumatic breakers were deployed for the above construction activities.
Reviewing the noise
monitoring data at monitoring stations (M7e- International Finance Centre
Eastern End of Podium and M7w- International Finance Centre Western End of
Podium), no limit level exceedances were recorded during routine noise
monitoring event on 28 May 2013 and 03 June 2013. As similar construction works
activities conducted on 30 May 2013 was continued across the above monitoring
period, the noise emanated from the construction activities under Contract
HY/2009/18 was considered complied with the statutory requirement.
In addition, weekly
environmental site inspection was conducted on 30 May 2013 at around 10:00.
According to the inspection record, no particular observation regarding noise
impact was recorded and the mitigation measures including erection of temporary
noise barrier was observed in place.
Nevertheless, the contractor was recommended to review the need of
additional noise mitigation measures to
further reduce the noise emanated during construction works for pier side
public area.
1.1.1.
Lam
Geotechnics Limited (LGL) has been appointed to work as the Environmental Team
(ET) under Environmental Permit no. EP-364/2009A and Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A, FEP-08/364/2009/A and FEP-09/364/2009/B to implement
the Environmental Monitoring and Audit (EM&A) programme as stipulated in
the EM&A Manual of the approved Environmental Impact Assessment (EIA)
Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register
No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for
Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No.
AEIAR-014/2001).
1.1.2.
This
report presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.3 of EM&A
Manual and Environmental Monitoring and Audit Requirements
under Particular Specification Section 27.
1.1.3. This report documents the finding of EM&A
works during the period from June 2013 to August 2013.
Section 1 Introduction details the scope and structure of the
report.
Section 2 Project Background summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section 3 Monitoring Requirements summarizes all monitoring parameters,
monitoring locations, monitoring frequency, duration and action plan.
Section 4 Monitoring Results summarizes the monitoring results
obtained in the reporting period.
Section 5 Compliance Audit summarizes the auditing of monitoring results, all
exceedances environmental parameters.
Section 6 Complaints,
Notification of summons and Prosecution summarizes the cumulative
statistics on complaints, notification of summons and prosecution
Section 7 Cumulative
Construction Impact due to the Concurrent Projects summarizes the
relevant cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section 8 Conclusion
2.1.1.
Wan
Chai Development phase II and Central-Wan Chai Bypass and Central-Wan Chai
Bypass and Island Eastern Corridor Link (hereafter called the Project) are
Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap.
499) (EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The
key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan
Chai North and North Point for construction of the Central-Wan Chai Bypass and
Island Eastern Corridor Link (CWB). Land formed under the project will be
developed as a world-class waterfront promenade joining that at the new Central
waterfront for public enjoyment.
2.1.3.
There
is a compelling and present need for the CWB to provide relief to the very
congested
2.2.1.
Design and Construction of Central Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The
study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB)
and Island Eastern Corridor Link (IECL) includes:
·
A dual three-lane trunk road, approximately 4.5 km
in length, and tunnel approximately 3.7 km in length defined from the
connection with the existing Rumsey Street Flyover in Central, through to a
connection with the existing Island Eastern Corridor to the east of the
Causeway Bay Typhoon Shelter (CBTS);
·
The Central Interchange near the Rumsey Street
Flyover to provide road connections to the Central area;
·
Tunnel control buildings and ventilation buildings;
·
Slip roads to connect the CWB to the local road
system in the Wan Chai North and
·
Associated road lighting, road signing, traffic
control and surveillance system; and
·
Other associated works.
2.2.3.
The
project also contains various Schedule 2 DPs that, under the EIAO, require
Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five
individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table
2.1 Schedule 2 Designated Projects
under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due
to the multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be
commenced. Contractors of individual
contracts will be required by the EP holder to apply Further Environmental
Permits such
that the impact monitoring stations are sub-divided accordingly to facilitate
the implementation of EM&A programme and to streamline the EM&A
reporting for individual FEP holders correspondingly.
2.3.2.
In
the reporting period, all the contracts were commenced and contract no.
04/HY/2006 had been completed. The details of individual contracts are
summarized in Table2.2.
Table
2.2 Details of Individual Contracts
under the Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HY/2009/17 |
Central Wan Chai Bypass (CWB) at FEHD Whitfield Depot Advanced
piling works. |
DP1 |
5 October 2010 (Completed) |
HY/2009/18 |
Central Wan Chai Bypass (CWB) Central Interchange |
DP1 |
21 |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II Central Wan Chai Bypass at |
DP1, DP2 |
25 August 2011 |
HK/2009/02 |
Wan Chai Development Phase II Central Wan Chai Bypass at Wan Chai
East(CWB Tunnel) |
DP1 |
26 |
HY/2009/15 |
Central-Wanchai Bypass Tunnel ( |
DP1 |
13 July 2011 |
HY/2009/19 |
Central Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
HK/2012/08 |
Wan Chai Development Phase II- Central-Wan Chai
Bypass at Wan Chai West |
DP1,DP2, DP3 |
DP works under |
HY/2010/08 |
Central- Wanchai Bypass Tunnel Tunnel (Slip
Road 8) |
DP1, DP2, DP3 |
21 March 2013 |
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively.
For the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure
2.2. Key personnel and contact particulars are
summarized in Table 2.3:
Table 2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineers Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineers Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3916 1818 |
3529 2829 |
|
Lam
Woo & CO., LTD. |
Contractor under Contract no. HY/2009/17 |
General Manager |
Mr. Thomas Tang |
6111 5351 |
2566
7522 |
Contractors Representative |
Mr. Chung Man Shek |
2566 4866 |
2566
7522 |
||
Site Agent |
Mr. Tony Au |
9725 5874 |
2566 7522 |
||
Environmental Officer |
Dr. Priscilla Choy |
9161 7287 |
2566 7522 |
||
Environmental Supervisor |
Mr. Tam Chun Pong |
6461 3062 |
2566 7522 |
||
Chun
Wo Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Joint Venture Board Representative |
|
2162 9909 |
2634 1626 |
Sub Agent |
Mr. Terry Wong |
9757 9846 |
|||
Construction
Manager |
Mr. Wyman Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Jack Chu |
9775 2467 |
|||
Construction
Manager |
Mr. Andy Yu |
9648 4896 |
|||
Environmental
Officer (Compliance Manager) |
Mr. Andy Mak |
9103 2370 |
|||
Environmental
Supervisor |
Mr. Kwong
Weng Kit |
6253
3356 |
|||
Chun Wo CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project Manager |
Mr. Chan Sing Cho |
3658-3002 |
2827 9996 |
Quality & Environmental Manager (Environmental Officer) |
Mr. C.P. Ho |
3658-3000 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570 8013 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Environmental Engineer |
|
9286 9208 |
|||
Construction Manager (Marine) |
William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
Construction Manager (Land) |
Eric Fong |
6191 9337 |
|||
Operation Manager (Land) |
Yung Kwok Wah |
9834 1010 |
|||
Leighton Contractors ( |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Jimmy Chu |
2214
7700 |
2140 6799 |
Deputy Site Agent |
Mr Roger Wong |
2214
7703 |
|||
Environmental Officer |
Mr. Anfernee Chow |
2214 7721 |
|||
Environmental Engineer Graduate |
Phil Mak |
2214
7738 |
|||
Environmental Supervisor |
K. P. Lai |
6461 4660 |
|||
Environmental Supervisor |
Ray Cheng |
22147742 |
|||
Environmental Supervisor |
Bosco Lee |
22147711 |
|||
Environmental Supervisor |
Ryan Tsui |
2214 7705 |
|||
|
Contractor under Contract no. HY/2009/15 |
Project Director |
Mr. K C Cheung |
2823 7813 |
2566 2192 |
Site Manager |
Mr. J.H. Chen |
3557 6368 |
|||
Contractors
Representative |
Mr. Andrew Wong |
3557
6407 |
|||
Head of construction |
Mr. Roger Cheung |
3557 6371 |
|||
Environmental Officer |
Mr. Daniel Sin |
3557 6215 |
|||
Enviromental Supervisor |
Ms Esther Choi |
35576348 |
|||
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project
Manager |
Mr. Paul Lui |
9095 7922 |
2529
2880 |
Site
Agent |
Mr. Keith Tse |
2529 2068 |
|||
Environmental
Officer |
Mr. Clement Pang |
9481 6024 |
|||
Environmental
Supervisor |
Mr.
Jacky Cheung |
9735 9200 |
|||
|
Contractor under Contract no.HY/2010/08 |
Project
Director |
Cheung
Kit Cheung |
3557
6399 |
3465 2899 |
Project
Manager |
Chan
Ying Lun |
9812
0592 |
|||
Deputy
Project Manager |
Chris
Leung |
3467
4299 |
|||
Site
Agent |
Dave
Chan |
3467
4277 |
|||
Environmental
Officer |
C.M.
Wong |
3557
6464 |
|||
Environmental
Supervisor |
Louis
Lam Tsz Kwan |
3557
6470 |
|||
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.5.1.
Major construction activities for Contract no.
HY/2009/18 have been commenced on 21
Table 2.4 Principal Work Activities
for Contract no. HY/2009/18
June
2013 |
July
2013 |
August
2013 |
Excavation of
trial pit
Transplanting of
trees
Hoarding
erection and modification
Installation of
couplers, UU detection, trial trench, pre-drilling
Excavation
Drainage works
Tunnel works
Trough structure
construction and associated drilling and grouting
Road works
OHVD
installation
Pre-bored
H-piling
Bridges
construction Scaffolding / false-work erection |
Excavation of
trial pit
Transplanting of
trees
Hoarding
erection and modification
Installation of
couplers, UU detection, trial trench, pre-drilling
Excavation
Drainage works
Tunnel works
Trough structure
construction and associated drilling and grouting
Road works
OHVD
installation
Pre-bored
H-piling
Bridges
construction Scaffolding / false-work erection |
Excavation of
trial pit
Transplanting of
trees
Drainage works
Tunnel works
including scaffolding erection, excavation, OHVD installation, roadside barriers,
top and base slab construction
Trough structure
construction and associated drilling and grouting
Road works
Bridges
construction |
2.5.2.
Major construction activities for Contract no.
HK/2009/01 have been commenced on 25 August 2011. During this reporting period,
the principal work activities are summarized in Table2.5:
Table 2.5 Principal Work Activities for Contract no. HK/2009/01
June
2013 |
July
2013 |
August
2013 |
Pre-drilling
works for CWB (Stage 2).
Diaphragm wall
construction works at Stage 2 (North).
Temporary
bulkhead wall construction works at CH3129 (between Stage2 /Stage3).
Pre-bored H
piling works for CWB (Stage1b).
Excavation and
grouting of Pre-bored H-pile.
Pre-bored H
piling works for CWB (Stage2).
Installation of
dewatering well at CWB (Stage 1 & 1b). |
Installation of
pre-bored H-pile in CWB Stage 1 underneath Atrium Link (from CH80 to CH120)
Installation of
pre-bored H-pile in CWB Stage 2 Atrium Link (from CH120 to CH220) would be
continued. 14 nos. pre-bored H-piles had been excavated. 2 nos. pre-bored
H-piles were grouted
Construction of
bulkhead wall at CH3129 (18 panels)
Filling of the
existing open water channel at CH260.
Construction of
the Common D-wall
Demolition of
the Promenade Deck
Installation of
dewatering wells, observation wells and piezometers at CWB Stage 1
|
Installation of
pre-bored H-pile in CWB Stage 2 Atrium Link (from CH120 to CH220) was carried
on. 23 nos. pre-bored H-piles had been excavated. 6 nos. pre-bored H-piles
were grouted
Construction of
Common D-wall was commenced.
Filling of the existing open water channel
from CH100 to CH206
Demolition of
the Promenade Deck
ELS at bottom-up
area. Fabrication of steel strutting members was in order |
2.5.3.
Major construction activities for Contract no.
HK/2009/02 have been commenced on 26
Table 2.6 Principal Work Activities for Contract no. HK/2009/02
June
2013 |
July
2013 |
August
2013 |
Base Slab for Tunnel Portion 1
Bored piles PN17 was concreted
Casting Base slab for silo setup
Desander setup and its mud pit construction for D-Wall construction at
Tunnel Portion 2 Ground treatment for D-wall at WCR2 was commenced on 10 Jun
2013.
Backfilling works for pipe trenches and the road modification works along
Casting of Base slab at Bay 4 of Box Culvert N.
Sheet pile cutting works at Bay5 / Bay 6 interface for subsequent
construction of water plug beneath the installed precast unit (Bay 6)
Panel (BHC2) of Eastern Bulkhead Wall was concreted
Excavation for P129 and the remaining panel of Eastern Bulkhead Wall
BHC12 |
ELS removal of strut S5
Rebar fixing for the center wall Bay 4 and Bay 5
Formwork delivery
Installation of waterproofing for side wall at Bay 4 & Bay 5
Total 123 nos. out of 290 nos. of pre-grouting at WCR2
Total 66 m guide wall for D-wall construction at WCR2 was casted
Silo installation and pipe connect from desander to silo was in
progress.
Desander setup for D-Wall construction at Tunnel Portion 2 at WCR2
area |
Casting of the center wall Bay 2 and Bay 3
Installation of waterproofing for both side walls and rebar fixing for
wall construction
Total 165 nos. out of 290 nos. of pre-grouting at WCR2
Casting of Total
D-Wall Panel P90 and P98 was concreted on 12 Aug 2013 and 17 Aug 2013
respectively.
Concreting of D-wall for Tunnel Portion 2.
Steel cage installation for Panel BH4.
Excavation for Panel P91 and P99 were on-going. |
2.5.4.
Major construction activities for Contract no.
HY/2009/15 have been commenced on 13 July 2011. During this reporting period,
the principal work activities are summarized in Table
2.7:
Table 2.7 Principal Work Activities for Contract no.
HY/2009/15
June
2013 |
July
2013 |
August
2013 |
ELS works and pipe roofing works at TS4
Cut and cover tunnel construction at TPCWAE
Construction of OHVD at TS1
Excavation for mined tunnel
Construction of Diaphragm Wall at TS2 |
ELS works and pipe roofing works at TS4
Cut and cover tunnel construction at TPCWAE
Construction of OHVD at TS1
Excavation and tunnel lining construction for mined tunnel
Construction of Diaphragm Wall, Post Diaphragm Wall Works and
Installation of King Post at TS2 |
ELS works, pipe roofing works and tunnel construction at TS4
Cut and cover tunnel construction at TPCWAE
Construction of OHVD at TS1
Excavation and tunnel lining construction for mined tunnel
Post Diaphragm Wall Works, ELS works and Installation of King Post at
TS2 |
2.5.5.
Major construction activities for Contract no.
HY/2009/19 have been commenced on March 2011. During this reporting period, the
principal work activities are summarized in Table
2.8:
Table
2.8 Principal Work Activities for Contract no.
HY/2009/19
June
2013 |
July
2013 |
August
2013 |
Road works at
Bored piling (Land)
D-wall and Barrette Construction
Construction works for Box Culvert T1
Construction works for Culvert U1
Construction of Pile cap (Land)
Demolition of parapet at IEC Link
Construction of dewatering well for Cut & Cover Tunnel
Removal of marine platform
Construction of pile cap, column & cross head (Marine)
ELS for Cut & Cover Tunnel
Laying of 1500 pipe
Launching of segments
Unloading segments from derrick
Extraction of temporary pile from marine section |
Road works at
Bored piling (Land)
D-wall and Barrette Construction
Construction works for Box Culvert T1
Construction works for Culvert U1
Construction of Pile cap (Land)
Construction of dewatering well for Cut & Cover Tunnel
Removal of marine platform
Construction of pile cap, column & cross head (Marine)
ELS for Cut & Cover Tunnel
Laying of 1500 pipe
Launching of segments
Unloading segments from derrick
Extraction of temporary pile from marine section |
Road works at
Bored piling (Land)
D-wall and Barrette Construction
Construction works for Box Culvert T1
Construction works for Box Culvert U1
Construction of Pile cap (Land)
Demolition of parapet at IEC Link
Removal of marine platform
Construction of pile cap, column & cross head (Marine)
ELS for Cut & Cover Tunnel
Installation of dewatering well
Laying of 1500f pipe
Launching of segments
Extraction of temporary pile from marine section
Installation of temporary lighting at IEC link commenced
Construction of bridge truss TA1 commenced
Breaking of barrette piles at Cut & Cover tunnel commenced
Demolition of parapet at IEC link |
2.5.6.
Major construction activities for Contract no.
HK/2010/06 have been commenced on March 2011. During this reporting period, the
principal work activities are summarized in Table
2.9
Table 2.9 Principal Work Activities for Contract
no. HK/2010/06
June
2013 |
July
2013 |
August
2013 |
Nil |
Installation Works of Precast Concrete Box Unit
Installation of 150T anchors |
Stitching Works
Grouting Works |
2.5.7.
Major construction activities for Contract no.
HK/2012/08 have been commenced on March 2013. During the reporting period, the
principal work activities are summarized in Table 2.10
Table 2.10 Principal Work Activities for Contract no. HK/2012/08
June
2013 |
July
2013 |
August
2013 |
Site preparation works
Site survey
Hoarding erection |
Site preparation works
Site survey
Hoarding erection |
Site preparation works
Site survey
Hoarding erection |
2.5.8.
Major
construction activities for Contract no.HY/2010/08 have been commenced on March
2013. During the reporting period, the principal work activities are summarized
in Table
2.11
Table 2.11 Principal Work Activities for Contract no. HY/2010/08
June
2013 |
July
2013 |
August
2013 |
Nil |
Tree Pruning works
Tree removal works,
Tree transplanting works,
Instrumentation works,
Ground investigation works and
Erection of site hoarding. |
Tree Pruning works
Tree removal works
Tree transplanting works
Tree works within off-site nursery compound
Instrumentation works
Ground investigation works
Chain link fence demarcation works and
Erection of site hoarding. |
2.5.9.
Implementation
status of the recommended mitigation measures during this reporting period is
presented in Appendix 2.1.
3.1.1.
The
noise monitoring stations for the Project are listed and shown in Table
3.1 and Figure 3.1. Appendix 3.1 shows
the established Action/Limit Levels for the monitoring works.
Table 3.1 Noise Monitoring Station
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun
Area |
M3a |
Tung Lo Wan
Fire Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
*M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
M8 |
City Hall |
* Remark 1: Location
ID has been updated from M7 to M8 for City Hall
* Remark 2: M7e has
become a reference station starting from 7 Aug 2012
Real time Noise Monitoring Stations
3.1.2.
The
noise monitoring stations for the Project are listed and shown in Table 3.2 and Figure 3.1.. Appendix 3.1
shows the established Action/Limit Levels for the monitoring works.
Table
3.2 Real Time Noise Monitoring Station
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section Whitefield Depot |
North Point |
RTN2a |
Electric Centre
(Replacement of RTN2) |
North Point |
RTN3 |
Pok Leung Kuk Yu |
Tin Hau |
RTN4 |
|
* RTN2 was relocated from Oil Street Community Liaison Centre to
Electric Centre on
05 Oct 2012 and re-designated
as RTN2a.
Noise Monitoring
Parameters, Frequency and Duration
3.1.3.
The construction noise level shall be measured in terms of
the A-weighted equivalent continuous sound pressure level (Leq). Leq (30
minutes) shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For
all other time periods, Leq (5 minutes) shall be employed for
comparison with the Noise Control Ordinance (NCO) criteria.
Supplementary information for data auditing, statistical results such as L10
and L90 shall also be obtained for reference.
3.1.4.
Noise
monitoring shall be carried out at all the designated monitoring stations. The
monitoring frequency shall depend on the scale of the construction activities.
The following is an initial guide on the regular monitoring frequency for each
station on a weekly basis when noise generating activities are underway:
·
One
set of measurements between 0700 and 1900 hours on normal weekdays.
3.1.5.
Real
time noise shall be carried out at the designated monitoring stations. The
following is an initial guide on the regular monitoring frequency for each
station on a 24 hours daily basis when noise generating activities are
underway:
·
One
set of measurements between 0700 and 1900 hours on normal weekdays.
·
One
set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and
2300 hours on public holidays.
·
One
set of measurements between 2300 and 0700 hours on next day on everyday.
3.1.6.
If
construction works are extended to include works during the hours of 1900
0700 as well as public holidays and Sundays, additional weekly impact
monitoring shall be carried out during respective restricted hours periods.
Applicable permits under NCO shall be obtained by the Contractor.
Monitoring Equipment
3.1.7.
As
referred to in the Technical Memorandum issued under the NCO, sound level
meters in compliance with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be
used for carrying out the noise monitoring. Immediately prior to and following
each noise measurement the accuracy of the sound level meter shall be checked
using an acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agree to within 1.0 dB.
3.1.8.
Noise
measurements shall not be made in fog, rain, wind with a steady speed exceeding
5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with
a portable wind speed meter capable of measuring the wind speed in m/s.
3.1.9.
The
sound level meter shall be checked using an acoustic calibrator generating a
known sound pressure level at a known frequency before deployment to the site
and during each site visit. Measurements may be accepted as valid only if the
calibration level from before and after the noise measurement agree to within
1.0 dB.
Air Quality Monitoring
Stations
3.2.1. The air monitoring stations for the Project are
listed and shown in Table 3.3 and Figure 3.1. Appendix 3.1 shows the established
Action/Limit Levels for the monitoring works.
Table 3.3 Air Monitoring Stations
Station ID |
Monitoring
Location |
Description |
CMA1b |
Oil Street Site Office* |
North Point |
CMA2a |
|
|
CMA3a |
Future CWB site office
at Wanchai Waterfront Promenade |
|
CMA4a |
Society for the
Prevention of Cruelty to Animals |
Wan Chai |
CMA5a |
Children Playgrounds
opposite to |
Wan Chai |
CMA6a |
Future AECOM site office
at Work Area |
Wan Chai |
MA1e |
International Finance Centre (Eastern End of Podium) |
Central |
MA1w |
International Finance Centre (Western End of Podium) |
Central |
Remarks*: The
location ID of monitoring station CMA1b was updated as Oil Street Site Office
in
Air Monitoring Parameters,
Frequency and Duration
3.2.2. One-hour and 24-hour TSP levels should be measured
to indicate the impacts of construction dust on air quality. The 24-hour TSP
levels shall be measured by following the standard high volume sampling method
as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part
50), Appendix B.
3.2.3. All relevant data including temperature, pressure,
weather conditions, elapsed-time meter reading for the start and stop of the
sampler, identification and weight of the filter paper, and any other local
atmospheric factors affecting or affected by site conditions, etc., shall be
recorded down in detail.
3.2.4. For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
Sampling Procedure and
Monitoring Equipment
3.2.5. High volume samplers (HVSs) in compliance with the
following specifications shall be used for carrying out the 1-hour and 24-hour
TSP monitoring:
·
0.6
1.7 m3 per minute adjustable flow range;
·
Equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours
operation;
·
Installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
·
Capable
of providing a minimum exposed area of 406 cm2;
·
Flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
·
Equipped
with a shelter to protect the filter and sampler;
·
Incorporated
with an electronic mass flow rate controller or other equivalent devices;
·
Equipped
with a flow recorder for continuous monitoring;
·
Provided
with a peaked roof inlet;
·
Incorporated
with a manometer;
·
Able
to hold and seal the filter paper to the sampler housing at horizontal
position;
·
Easily
changeable filter; and
·
Capable
of operating continuously for a 24-hour period.
3.2.6. Initial calibration of dust monitoring equipment
shall be conducted upon installation and thereafter at bi-monthly intervals.
The transfer standard shall be traceable to the internationally recognized
primary standard and be calibrated annually. The concern parties such as IEC
shall properly document the calibration data for future reference. All the data
should be converted into standard temperature and pressure condition.
3.2.7. Laboratory Measurement / Analysis
3.2.8. A clean laboratory with constant temperature and
humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
3.2.9. Filter paper of size 8 x 10 shall be labelled
before sampling. It shall be a clean filter paper with no pinholes, and shall
be conditioned in a humidity-controlled chamber for over 24-hours and be
pre-weighed before use for the sampling.
3.2.10. After sampling, the filter paper loaded with dust
shall be kept in a clean and tightly sealed plastic bag. The filter paper shall
then be returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
readout down to 0.1 mg. The balance shall be regularly calibrated against a
traceable standard.
3.2.11. All the collected samples shall be kept in a good
condition for 6 months before disposal.
4.0.1. Per EPDs letter
dated 3 Aug 2012 (received by ET on 6 Aug 2012 through HyD), noise monitoring
at M8 City Hall commenced on 7 Aug 2012, and the monitoring station M7e
International Finance Centre (Eastern Podium) has become a reference station
starting from 7 Aug 2012.
4.0.2. Due to safety
concerns, the monitoring location for M4b Victoria Centre has been finely adjusted
from 7 June 2012.
4.0.3. Monitoring for report of review baseline noise
level was performed from 11
4.0.4. The environmental monitoring will be implemented
based on the division of works areas of each designed project managed under
different contracts with separate FEP applied by individual contractors. Overall layout showing work areas of various
contracts, latest status of work commencement and monitoring stations is shown
in Figure
2.1 and Figure 3.1. The monitoring results
are presented in according to the Individual Contract(s).
4.0.5. In the reporting period, the concurrent contracts are
as follows:
Contract
no. HY/2009/15 Central-Wanchai Bypass Tunnel (
Contract
no. HY/2009/18 Central Wanchai Bypass (CWB) Central Interchange under
FEP-05/364/2009/A
Contract
no. HY/2009/19 Central Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009
Contract
no. HK/2009/01 Wanchai Development Phase II Central Wanchai Bypass at
Contract
no. HK/2009/02 Wanchai Development Phase II Central- Wanchai Bypass at Wanchai
East
Contract
no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan Chai Bypass over
MTR Tsuen Wan Line under FEP-08/364/2009/A
Contract
no. HK/2012/08 Wan Chai Development Phase II Central- Wan Chai Bypass at
Wan Chai West under FEP-09/364/2009B
Contract
no. HY/2010/08 Central and WanChai Bypass Slip road 8 Section under
FEP-10/364/2009B
Contract no.
HY/2009/18 Central Wanchai Bypass (CWB) Central Interchange under
FEP-05/364/2009/A
4.1.1.
Noise
monitoring for the Central Interchange works under contract no. HY/2009/18 was
commenced on 22
Table 4.1 Noise Monitoring Station for Contract no. HY/2009/18
Station |
Description |
*M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
M8 |
City Hall |
* Remark : M7e has become a reference station starting from 7 Aug 2012
4.1.2. No exceedance was recorded in this
reporting quarter.
4.1.3. Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 4.1.
Contract no. HK/2009/01 - Wanchai Development Phase
II - Central - Wanchai Bypass at Hong Kong Convention and Exhibition Centre -
Tunnel Works under FEP-02/364/2009 and Contract no. HK/2009/02 - Wanchai
Development Phase II - Central - Wanchai Bypass at Wanchai East (CWB Tunnel)
under FEP-01/364/2009
4.1.4.
The
commencement of construction works for Contract no. HK/2009/01 under FEP-02/364/2009
is on 25 August 2011
and HK/2009/02 under FEP-01/364/2009 is on 26
Table 4.2 Noise Monitoring Stations for
Contract nos. HK/2009/01 and HK/2009/02
Station |
Description |
M1a |
Harbour Road Sports Centre |
4.1.5. No exceedance was recorded in this
reporting quarter.
4.1.6. Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 4.1.
Contract no.
HY/2009/15 - Central-Wanchai Bypass Tunnel (
4.1.7.
The
commencement of construction works for Contract no. HY/2009/15 under
FEP-06/364/2009/A was on 13 July 2011. Noise
monitoring was commenced on 13 July 2011. The proposed
division of noise monitoring stations are summarized in Table 4.3 below.
Table 4.3 Noise
Monitoring Station for Contract nos. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
4.1.8. No exceedance was recorded in this
reporting quarter.
4.1.9. Details of
noise monitoring results and graphical presentation can be referred in Appendix 4.1.
4.1.10. Noise monitoring for the tunnel works under
contract no. HY/2009/19 was commenced on 24
Table 4.4
Noise Monitoring
Stations for Contract no. HY/2009/19
Station |
Description |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
Reporting month of June
2013
4.1.11.
Two limit level
exceedances were recorded on 3 and 13 June 2013 at M6 HK Baptist Church Henrietta Secondary School in the reporting
month.
4.1.12.
Major traffic noise observed during monitoring on 3 and 13 June 2013 and
it was considered as the major noise contribution. As such, the limit level
exceedances were concluded as non-project related.
Reporting
month of July 2013
4.1.13.
Two limit level
exceedances were recorded on 9 and 16 July 2013 at M6 HK Baptist Church Henrietta Secondary School in the reporting
month.
4.1.14.
Major traffic noise observed during monitoring on 9 and 16 2013 and it
was considered as the major noise contribution. As such, the limit level
exceedances were concluded as non-project related.
Reporting
month of August 2013
4.1.15.
Three limit level
exceedances were recorded on 6, 20 and 27 August 2013 at M6 HK Baptist Church Henrietta
Secondary School in the reporting month.
4.1.16.
Major traffic noise observed during monitoring on 6, 20 and 27
August 2013 and it was considered as the major noise contribution. As such,
the limit level exceedances were concluded as non-project related.
4.1.17. Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 4.1 and the
Notification of Exceedance can be referred in Appendix 6.2.
Contract no.
HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under FEP-07/364/2009/A
4.2.1.
Real
time noise monitoring results measured in this reporting period are reviewed
and summarized. Details
of real time noise monitoring results and graphical presentation can be
referred to Appendix
4.2
4.2.2.
The
proposed division of noise monitoring stations are summarized in Table 4.5
below. Real time noise monitoring for major construction works under contract
no. HY/2009/19 was commenced on 24
Table
4.5 Real Time Noise Monitoring
Stations for Contract no. HY/2009/19
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD Hong Kong Transport Section Whitefield Depot |
RTN2a |
North Point |
Electric Centre
(Replacement of RTN2) |
RTN3 |
North Point |
Pok Leung Kuk Yu |
RTN4 |
Tin Hau |
|
* Real time noise monitoring results and graphical presentation during
night time period are for information only.
*Real-time noise monitoring results and graphical presentation for RTN3
during restricted hours are for information only as no night classes were
conducted at the educational institute.
Reporting
month of June 2013
4.2.3.
Limit level exceedances were recorded at
RTN1-FEHD Hong Kong Transport Section Whitfield Depot during restricted hours
on 15 June 2013. After checking with contractor, no major noisy construction
works with only one mobile crane was in operation at the concerned location
during the recorded period. As such, the exceedances were considered not
contributed by the project works but due to the nearby IEC traffic.
4.2.4.
Limit level exceedance was recorded at
RTN2a-Electric Centre during restricted hours on 4 June 2013. After checking
with contractor, no construction work was conducted 4 June 2013 at the
concerned location during the recorded period. As such, the exceedances were
considered to be contributed by near by IEC traffic.
4.2.5.
No limit Level exceedance was recorded at
RTN3-Yu Lee Mo Fan Memorial School in the reporting month.
4.2.6.
No limit level exceedance was recorded at
RTN4-Causeway Bay Community Centre in the reporting month.
Reporting
month of July 2013
4.2.7.
Limit level exceedances were recorded at
RTN1-FEHD Hong Kong Transport Section Whitfield Depot during restricted hours
on 14 July 2013. After checking with contractor, no construction works was
conducted at the concerned location during the recorded period. As such, the
exceedances were considered not contributed by the project works but due to the
nearby IEC traffic.
4.2.8.
Limit level exceedance was recorded at
RTN2a-Electric Centre during restricted hours on 14 July 2013. After checking
with contractor, no construction work was conducted at the concerned location
during the recorded period. As such, the exceedances were considered to be
contributed by near by IEC traffic.
4.2.9.
Limit level exceedance was recorded at RTN3-Yue
Lee Mo Fan Memorial School during restricted hours on 14 July 2013. After
checking with contractor, no construction work was conducted at the concerned
location during the recorded period. As such, the exceedances were considered
to be contributed by near by IEC traffic.
4.2.10.
No limit level exceedance was recorded at
RTN4-Causeway Bay Community Centre in the reporting month.
Reporting month
of August 2013
4.2.11.
No limit level exceedance was recorded at
RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the reporting month.
4.2.12.
Limit level exceedance was recorded at
RTN2a-Electric Centre during restricted hours on 2 August 2013. After checking
with contractor, no major noisy construction activity was conducted at the
concerned location during the recorded period and the exceedance was
non-continuous. As such, the exceedances were considered to be contributed by
nearby IEC traffic.
4.2.13.
No limit level exceedance was recorded at
RTN3-Yue Lee Mo Fan Memorial School in the reporting month.
4.2.14.
No limit level exceedance was recorded at
RTN4-Causeway Bay Community Centre in the reporting month.
4.2.15.
Real
time noise monitoring results measured in this reporting quarter are reviewed
and summarized. Details of real time noise monitoring results and graphical
presentation can be referred to Appendix
4.2
4.3.1
Due to extension of site boundary by contractor of HY/2009/19, location
of air monitoring station CMA1b Oil Street Community Liaison Centre has been
finely adjusted on 21
Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB) Central Interchange under
FEP-05/364/2009/A
4.3.2
The
proposed division of air monitoring stations are summarized in Table
4.6 below.
Table
4.6 Air Monitoring Stations
for Contract no.
HY/2009/18
Station |
Description |
MA1e |
International Finance Centre (Eastern End of Podium) |
MA1w |
International Finance Centre (Western End of Podium) |
4.3.3
Air
monitoring for the Central Interchange works under contract no. HY/2009/18 was
commenced on 21
4.3.4
No exceedance was recorded in the reporting period. Air quality
monitoring results measured in this reporting period are reviewed and
summarized. Details of air monitoring results and graphical presentation can be
referred in Appendix 4.3.
Contract no. HK/2009/01 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at
4.3.5
The
commencement of construction works for Contract no. HK/2009/01 under
FEP-02/364/2009 is on 25 August 2011. The
proposed division of air monitoring stations are summarized in Table
4.7 below.
Table
4.7 Air Monitoring Station
for Contract no. HK/2009/01
Station |
Description |
CMA5a |
Children Playgrounds opposite to |
4.3.6
No
exceedance was recorded in the reporting quarter. Air quality monitoring
results measured in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 4.3.
Contract no. HK/2009/02 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
4.3.7 The commencement of construction works for
HK/2009/02 under FEP-01/364/2009 is on 26
Table 4.8 Air Monitoring Station
for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
4.3.8
No
exceedance was recorded in the reporting period. Air quality monitoring results
measured in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 4.3.
Contract no.
HY/2009/15 - Central-Wanchai Bypass Tunnel (
4.3.9
The
commencement of construction works for Contract no. HY/2009/15 under
FEP-06/364/2009/A was on 13 July 2011. The proposed division of air
monitoring stations are summarized in Table 4.9
below.
Table
4.9
Air
Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB site office at Wanchai
Waterfront Promenade |
4.3.10
No exceedance was recorded in the reporting period. Air quality
monitoring results measured in this reporting period are reviewed and
summarized. Details of air
monitoring results and graphical presentation can be referred in Appendix 4.3.
Contract no.
HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under
FEP-07/364/2009/A
4.3.11 Air monitoring for the tunnel works was commenced
on 26
Table 4.10 Air Monitoring Stations for Contract no. HY/2009/19
Station |
Description |
CMA1b |
Oil St Community Liaison Centre |
CMA2a |
|
4.3.18.
No exceedance was recorded in the reporting period. Air quality
monitoring results measured in this reporting period are reviewed and
summarized. Details of air
monitoring results and graphical presentation can be referred in Appendix 4.3.
Contract no. HK/2009/01 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at
4.4.1.
Inert
and non-inert C&D waste was disposed of in this reporting period. Details
of the waste flow table are summarized in Table 4.11.
Table 4.11 Details of Waste Disposal for Contract no. HK/2009/01
Inert C&D materials disposed |
2045.27 |
29856.115 |
TKO137, TM38 |
Inert C&D materials recycled |
Nil |
5104.5 |
N/A |
Non-inert C&D materials disposed |
96.88 |
1370.38 |
SENT Landfill |
Non-inert C&D materials recycled |
Nil |
205943 |
N/A |
Chemical waste disposed |
500 |
10050 |
Kwun Kee (Chemical Waste Collector) |
Contract no. HK/2009/02 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
4.4.2.
Inert
and non-inert C&D waste were disposed of in this reporting period. Details
of the waste flow table are summarized in Table 4.12.
Table 4.12 Details of Waste Disposal for
Contract no. HK/2009/02
Inert C&D materials disposed |
2948.985 |
239505.925 |
TKO137, TM 38 |
Inert C&D materials recycled |
Nil |
18161 |
WCR2 |
Non-inert C&D materials disposed |
131.63 |
1053.82 |
SENT Landfill |
Non-inert C&D materials recycled |
NIL |
N/A |
N/A |
Chemical waste disposed |
1400 |
9371 |
N/A |
Remarks: The cumulative
amount of Inert C&D materials in the reporting quarter was updated.
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) Central
Interchange under FEP-05/364/2009/A
4.4.3.
Inert
and non-inert C&D waste was disposed of in this reporting period. Details
of the waste flow table are summarized in Table 4.13.
Table 4.13 Details of Waste Disposal for Contract no. HY/2009/18
Inert C&D materials disposed |
5312 |
99327 |
T.K.O. 137 |
Inert C&D materials recycled |
234 |
56223 |
N/A |
Non-inert C&D materials disposed |
144 |
1304 |
SENT Landfill |
Non-inert C&D materials recycled (tonnes) |
0.74 |
78.58 |
N/A |
Chemical waste disposed |
650 |
4215 |
N/A |
Contract no. HY/2009/15 - Central-Wanchai Bypass Tunnel (
4.4.4.
Inert
and non-inert C&D waste was disposed of in this reporting period. Details
of the waste flow table are summarized in Table 4.14.
Table 4.14 Details of Waste Disposal for Contract no. HY/2009/15
Inert C&D materials disposed |
42757.9 15058.8 |
376731.2 212248.4 |
Tuen Mun Area 38 TKO137 FB |
Inert C&D materials recycled |
5054 |
222650.2 |
HY/2009/11 ex-PCWA TS4 |
Non-inert C&D materials disposed |
156.4 |
965.4 |
SENT Landfill |
Non-inert C&D materials recycled |
603.4 |
543604.2 |
Xun Xiang Metal ware Skylight Recycle (paper) |
Chemical waste disposed |
744 |
17955 |
Dunwell Group |
Contract
no. HY/2009/19 Central Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/A
4.4.5.
Inert C&D materials was recycled
non-inert C&D waste was disposed of in this reporting period. Details of
the waste flow table are summarized in Table 4.15.
Table 4.15 Details of Waste Disposal for
Contract no. HY/2009/19
Inert C&D materials
disposed |
49677.92 |
344794.63 |
N/A |
6675.62 |
55939.8 |
N/A |
|
Non-inert C&D
materials disposed |
68.91 |
896.7 |
SENT Landfill |
Non-inert C&D
materials recycled |
41.2 |
323.23 |
N/A |
Chemical waste disposed |
0.29 |
4.88 |
N/A |
Marine Sediment (Tunnel) (Type 1- Open Sea
Disposal (Dedicated Sites) & Type 2 Confined Marine Disposal), m3 |
825 |
4976 |
East
of Sha Chau |
Contract no. HK/2010/06 Wan Chai Development Phase
II - Central-Wan Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
4.4.6.
No
inert and Non-inert C&D wastes were disposed of in this reporting period.
Details of the waste flow table are summarized in Table 4.16.
Table 4.16 Details of Waste Disposal for Contract no. HK/2010/06
Inert C&D materials disposed |
NIL |
NIL |
TM38 |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
19.13 |
19.13 |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
Recyclers |
Chemical waste disposed |
NIL |
NIL |
N/A |
Contract no.
HK/2012/08 Wan Chai Development Phase II - Central-Wan Chai Bypass at Wan Chai
West under FEP-09/364/2009/B
4.4.7.
No inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 4.17.
Table 4.17 Details of Waste Disposal for Contract no. HK/2012/08
Waste
Type* |
Quantity
this month, m3 |
Cumulative-to-Date,
m3 |
Disposal
/ Dumping Grounds |
Inert
C&D materials disposed |
NIL |
NIL |
N/A |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
Contract no. HY/2010/08
Central Wan Chai Bypass (CWB)
Tunnel (Slip Road 8) under FEP-10/364/2009/B
4.4.8.
No inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 4.18.
Table 4.18 Details
of Waste Disposal for Contract no. HY/2010/08
Waste Type* |
Quantity this month, m3 |
Cumulative-to-Date, m3 |
Disposal / Dumping Grounds |
Inert
C&D materials disposed |
12 |
15 |
TM 38 |
Inert C&D materials recycled |
Nil |
Nil |
Nil |
Non-inert C&D materials disposed |
2 |
16 |
SENT |
Non-inert C&D materials recycled |
Nil |
Nil |
Nil |
Chemical waste disposed |
Nil |
Nil |
Nil |
5.0.1. The Event Action Plan for construction noise and air
quality are presented in Appendix 5.1.
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) Central
Interchange under FEP-05/364/2009/A
Reporting Month of June 2013
5.1.1. One
action level exceedance regarding noise complaint concerning location near
Central Pier area was received by ET on 11 June 2013. After investigation, no
non-compliance was identified.
Reporting
Month of July 2013
5.1.2. No action
or limit level exceedance was recorded in the reporting month.
Reporting
Month of August 2013
5.1.3.
No action or limit level exceedance was
recorded in the reporting month.
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at
5.1.4.
No limit or action level exceedance was
recorded in this reporting quarter.
Contract no. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East(CWB Tunnel)
5.1.5.
No limit or action level exceedance was
recorded in this reporting quarter.
Contract no. HY/2009/15 - Central-Wanchai Bypass
Tunnel (
5.1.6. No limit
or action level exceedance was recorded in this reporting quarter.
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
Reporting month of June 2013
5.1.7.
Two limit level exceedances were
recorded on 3 and 13 June 2013 at M6 HK Baptist Church Henrietta Secondary
School in the reporting month. Investigations found that on 3 and 13 June
2013, major traffic noise was contributed in the noise monitoring and exceedances
were not related to the Project.
Reporting month of July 2013
5.1.8.
Two limit level exceedances were
recorded on 9 and 16 July 2013 at M6 HK Baptist Church Henrietta Secondary
School in the reporting month. Investigations found that on 9 and 16 July
2013, major traffic noise was contributed in the noise monitoring and exceedances
were not related to the Project.
Reporting month of August 2013
5.1.9.
Three limit level exceedances were
recorded on 6, 20 and 27 August 2013 at M6 HK Baptist Church Henrietta
Secondary School in the reporting month. Investigations found that on 6, 20 and 27
August 2013, major traffic noise was contributed in the noise monitoring and exceedances
were not related to the Project.
5.2.1.
No
exceedance was recorded in the reporting quarter.
Contract no.
HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
5.2.2.
No
exceedance was recorded in the reporting quarter.
Contract nos.
HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan
Chai East(CWB Tunnel)
5.2.3.
No
exceedance was recorded in the reporting quarter.
Contract no. HY/2009/15 - Central-Wanchai Bypass Tunnel (
5.2.4.
No
exceedance was recorded in the reporting quarter.
Contract no.
HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under FEP-07/364/2009/A
5.2.5. No exceedance was recorded in the reporting
quarter.
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/A
Reporting month of June 2013
5.3.1
Non project related limit level exceedance
was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot on 15
June 2013. Investigation found that exceedances were contributed by IEC
traffic.
5.3.2
Non project related limit level
exceedance was recorded at RTN2a- Electric Centre on 4 June 2013. Investigation
found that exceedances were contributed by IEC traffic.
5.3.3
No limit level exceedance was recorded at
RTN3- Yu Lee Mo Fan Memorial School in this reporting month.
5.3.4
No limit level exceedances were recorded at
RTN4- Causeway Bay Community Centre in this reporting month.
Reporting month of July 2013
5.3.5
Non project related limit level exceedance
was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot on 14
July 2013. Investigation found that exceedances were contributed by IEC
traffic.
5.3.6
Non project related limit level exceedance
was recorded at RTN2a- Electric Centre on 14 July 2013. Investigation found
that exceedances were contributed by IEC traffic.
5.3.7
Non project related limit level exceedance
was recorded at RTN3- Yue Lee Mo Fan Memorial School on 14 July 2013.
Investigation found that exceedances were contributed by IEC traffic.
5.3.8
No limit level exceedances were recorded at
RTN4- Causeway Bay Community Centre in this reporting month.
Reporting month of August 2013
5.3.9
No limit level exceedance was recorded at
RTN1-FEHD Hong Kong Transport Section Whitfield Depot on 14 July 2013.
Investigation found that exceedances were contributed by IEC traffic.
5.3.10
Non project related limit level
exceedance was recorded at RTN2a- Electric Centre on 2 August 2013.
Investigation found that exceedances were contributed by IEC traffic.
5.3.11
No limit level exceedance was recorded at
RTN3- Yue Lee Mo Fan Memorial School on 14 July 2013. Investigation found that
exceedances were contributed by IEC traffic.
5.3.12
No limit level exceedances were recorded at
RTN4- Causeway Bay Community Centre in this reporting month.
5.4.1. There was no non-compliance from the site audits in
the reporting period. During environmental site inspections conducted during
the reporting quarter, minor deficiencies were noted. However, the Contractor rectified all deficiencies
after receipt of notification.
5.5.1
There was no particular action taken since no project-related
non-compliance was recorded from the site audits and environmental monitoring
in the reporting period.
5.6.1 As no project related exceedance and non-compliance was recorded in this
reporting period, no action or follow-up was required in this reporting period.
6.0.1.
There was no environmental complaint received in this reporting period.
6.0.2. The details of cumulative complaint log and summary of
complaints are presented in Appendix
6.1.
6.0.3. No notification of summons or prosecution was received in the reporting
period. Cumulative statistic
on complaints and successful prosecutions are summarized in Table
6.1 and Table 6.2 respectively.
Table 6.1 Cumulative
Statistics on Complaints
Reporting Period |
No. of Complaints |
Commencement
of Works up to last reporting quarter |
20 |
June 2012 August 2013 |
2 |
Project-to-Date |
22 |
Table 6.2 Cumulative
Statistics on Successful Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this quarter (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
7.0.1.
According to Condition 3.4 of the EP-364/2009/B,
this section addresses the relevant cumulative construction impact due to the
concurrent activities of the current projects including the Central Reclamation
Phase III (CRIII), Wan Chai Development Phase II (WDII), Central-WanChai Bypass
(CWB), Island Eastern Corridor Link projects (IECL) and Wan Chai Development
Phase II Central Wan Chai Bypass at Wan Chai East (CWB Tunnel).
7.0.2.
According to the Monthly EM&A report (July
2013) of Central Reclamation Phase III (CRIII), surface drainage and
footpath construction adjacent to GPO, modification to the junction of Road D8
and Road P2 and modification of timber decks at advance promenade were
performed in the August 2013 reporting month. The water
quality monitoring was completed in October 2011 and no Project-related exceedance
was recorded for air and noise monitoring.
It can be concluded that cumulative construction impact due to the
concurrent activities of the current projects with the Central Reclamation
Phase III (CRIII) was insignificant.
7.0.3.
According to the construction programme of
Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern
Corridor Link projects, the major construction activity under Wan Chai
Development Phase II were marine works at HKCEC areas, cross-harbour
Watermains, Fresh Watermains and Cooling Watermains Installations, tunnel works
at Wan Chai East, ELS work and pipe roofing works at TS4 and
cut and cover tunnel construction at TPCWAE. Excavation
and tunnel works at Central Interchange, ELS and box culvert construction at
North Point area. The major environmental impact was water quality impact at
7.0.4.
The major environmental impacts generated
from tunnel works at Central and tunnel works at Wan Chai East, IECL and
Causeway Bay Typhoon Shelter were undertaken in the reporting month. No
significant air impact from construction activities was anticipated in the
reporting month.
8.0.1. The EM&A programme was carried out in
accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
Air quality monitoring
8.0.2.
No action or limit level exceedance was recorded.
Noise monitoring
8.0.3.
Two limit level exceedances were
recorded on 3 and 13 June 2013 at M6 HK Baptist Church Henrietta Secondary
School in the reporting month. Investigations found that on 3 and 13 June
2013, major traffic noise was contributed in the noise monitoring and exceedances
were not related to the Project.
8.0.4.
One action level exceedances was
recorded on 11 June 2013 for Contract HY/2009/18 regarding noise emission at
Central Pier area. After investigation, the noise emanated
from the construction activities under Contract HY/2009/18 was considered complied
with the statutory requirement.
8.0.5.
Two limit level exceedances were
recorded on 9 and 16 July 2013 at M6 HK Baptist Church Henrietta Secondary
School in the reporting month. Investigations found that on 9 and 16 July
2013, major traffic noise was contributed in the noise monitoring and exceedances
were not related to the Project.
8.0.6.
Three limit level exceedances were
recorded on 6, 20 and 27 August 2013 at M6 HK Baptist Church Henrietta
Secondary School in the reporting month. Investigations found that on 6, 20 and 27
August 2013, major traffic noise was contributed in the noise monitoring and exceedances
were not related to the Project.
Real
time noise monitoring
8.0.7.
Limit level exceedances were recorded at
RTN1-FEHD Hong Kong Transport Section Whitfield Depot during restricted hours
on 15 June 2013. After checking with contractor, no major noisy construction
works with only one mobile crane was in operation at the concerned location
during the recorded period. As such, the exceedances were considered not
contributed by the project works but due to the nearby IEC traffic.
8.0.8.
Limit level exceedance was recorded at
RTN2a-Electric Centre during restricted hours on 4 June 2013. After checking
with contractor, no construction work was conducted 4 June 2013 at the
concerned location during the recorded period. As such, the exceedances were
considered to be contributed by near by IEC traffic.
8.0.9.
No limit Level exceedance was recorded
at RTN3-Yu Lee Mo Fan Memorial School in the reporting month.
8.0.10.
No limit level exceedance was recorded
at RTN4-Causeway Bay Community Centre in the reporting month.
8.0.11.
Non project related limit level exceedance
was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot on 14
July 2013. Investigation found that exceedances were contributed by IEC
traffic.
8.0.12.
Non project related limit level exceedance
was recorded at RTN2a- Electric Centre on 14 July 2013. Investigation found
that exceedances were contributed by IEC traffic.
8.0.13.
Non project related limit level exceedance
was recorded at RTN3- Yue Lee Mo Fan Memorial School on 14 July 2013.
Investigation found that exceedances were contributed by IEC traffic.
8.0.14.
No limit level exceedances were recorded at
RTN4- Causeway Bay Community Centre in this reporting month.
8.0.15.
No limit level exceedance was recorded at
RTN1-FEHD Hong Kong Transport Section Whitfield Depot on 14 July 2013.
Investigation found that exceedances were contributed by IEC traffic.
8.0.16.
Non project related limit level exceedance
was recorded at RTN2a- Electric Centre on 2 August 2013. Investigation found
that exceedances were contributed by IEC traffic.
8.0.17.
No limit level exceedance was recorded at
RTN3- Yue Lee Mo Fan Memorial School on 14 July 2013. Investigation found that
exceedances were contributed by IEC traffic.
8.0.18.
No limit level exceedances were recorded at
RTN4- Causeway Bay Community Centre in this reporting month.
8.0.19.
One environmental complaint under EP-364/2009/B was received on 6 June
2013 (ICC Ref: No: #1-430164728 dated 30 May 2013) regarding landscape aspect
along
8.0.20.
One environmental complaint under EP-364//2009/B was received on 11 June 2013 (EPD
Ref.:H04/RS/00011587-13) dated 11 June 2013) regarding noise impact near
Central Piers in the reporting quarter.
8.0.21. The construction programmes
of individual contracts are provided in Appendix 8.1.