Contract
No: HK/2011/07 Wanchai Development Phase II and Sampling, Field Measurement and
Testing Work (Stage 2) Environmental
Permit no. EP-364/2009/B, Further Evironmental permit nos. fep-01/364/2009,
fep-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEp-07/364/2009/a,
FEp-08/364/2009/a , FEP-09/364/2009/B, fep-10/364/2009/B and
fep-11/364/2009/B Quarterly Environmental Monitoring
and Audit Report
- March 2014
to May 2014 -
|
CLIENTS: |
|
Civil
Engineering and Development Department and Highways
Department |
Lam Geotechnics
Limited 11/F Centre
Point Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
23 June 2014 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
2.5 Principal Work and Activities
4.2. Real Time Noise Monitoring Results
5.4. Review of the Reasons for and the Implications of Non-compliance
5.5. Summary of action taken in the event of and follow-up
on non-compliance
6. Complaints, Notification of Summons
and Prosecution
7. Cumulative Construction Impact due to
the Concurrent Projects
lIST
OF TABLES
Table I Principal Work Activities for Contract no.
HY/2009/18
Table II Principal Work Activities for Contract no. HK/2009/01
Table III Principal Work Activities for Contract no. HK/2009/02
Table IV Principal
Work Activities for Contract no. HY/2009/15
Table V Principal Work Activities for Contract no. HY/2009/19
Table
VI Principal Work Activities for
Contract no. HK/2010/06
Table
VII Principal Work Activities for
Contract no. HK/2012/08
Table VIII Principal Work Activities for Contract no. HY/2010/08
Table
IV Principal Work Activities for Contract no. HY/2011/08
Table 2.1 Schedule
2 Designated Projects under this Project
Table 2.2 Details
of Individual Contracts under the Project
Table 2.3 Contact
Details of Key Personnel
Table 2.4 Principal
Work Activities for Contract no. HY/2009/18
Table 2.5 Principal
Work Activities for Contract no. HK/2009/01
Table 2.6 Principal
Work Activities for Contract no. HK/2009/02
Table 2.7 Principal
Work Activities for Contract no. HY/2009/15
Table 2.8 Principal
Work Activities for Contract no. HY/2009/19
Table 2.9 Principal Work Activities for Contract
no. HK/2010/06
Table 2.10 Principal
Work Activities for Contract no. HK/2012/08
Table 2.11 Principal Work Activities for Contract no. HY/2010/08
Table 2.12 Principal Work
Activities for Contract no. HY/2011/08
Table 3.1 Noise
Monitoring Station
Table 3.2 Real
Time Noise Monitoring Station
Table 3.3 Air
Monitoring Stations
Table 4.1
Noise
Monitoring Station for Contract no. HY/2009/18
Table 4.2
Noise
Monitoring Stations for Contract nos. HK/2009/01 and HK/2009/02
Table 4.3
Noise
Monitoring Station for Contract nos. HY/2009/15
Table 4.4 Noise Monitoring
Stations for Contract no. HY/2009/19
Table 4.5 Real
Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 4.6 Air
Monitoring Stations for Contract no. HY/2009/18
Table 4.7 Air
Monitoring Stations for Contract no. HK/2009/01
Table 4.8 Air
Monitoring Station for Contract no. HK/2009/02
Table 4.9 Air
Monitoring Station for Contract no. HY/2009/15
Table 4.10 Air
Monitoring Stations for Contract no. HY/2009/19
Table 4.11 Details
of Waste Disposal for Contract no. HK/2009/01
Table 4.12 Details
of Waste Disposal for Contract no. HK/2009/02
Table 4.13 Details
of Waste Disposal for Contract no. HY/2009/18
Table 4.14 Details
of Waste Disposal for Contract no. HY/2009/15
Table 4.15 Details
of Waste Disposal for Contract no. HY/2009/19
Table
4.16 Details of Waste Disposal for
Contract no. HK/2010/06
Table 4.17 Details of Waste
Disposal for Contract no. HK/2012/08
Table
4.18 Details of Waste Disposal for
Contract no. HY/2012/08
Table 6.1 Cumulative
Statistics on Complaints
Table 6.2 Cumulative
Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure
2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 3.1 Locations of Environmental
Monitoring Stations
lIST OF APPENDIces
Appendix
2.1 Environmental
Mitigation Implementation Schedule
Appendix 3.1 Action and Limit Level
Appendix
4.1 Noise
Monitoring Results and Graphical Presentations
Appendix 4.2 Real-time Noise Monitoring
Results and Graphical Presentations
Appendix
4.3 Air
Quality Monitoring Results and Graphical Presentations
Appendix 5.1 Event Action Plans
Appendix 6.1 Complaint Log
Appendix 6.2 Notification of Exceedance
Appendix 8.1 Construction Programme of
Individual Contracts
EXECUTIVE
SUMMARY
Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB)
- Central Interchange under FEP-05/364/2009/
Major construction activities for Contract no. HY/2009/18 have been
commenced on 21
Table I Principal Work
Activities for Contract no. HY/2009/18
March 2013 |
April 2014 |
May 2014 |
Excavation of
trial pit
Transplanting of
trees
Drainage works
Tunnel works
including scaffolding erection, excavation, OHVD installation, roadside
barriers, top and base slab construction
Trough structure
construction and associated drilling and grouting
Road works
Bridges
construction |
Excavation of trial
pit
Transplanting of
trees
Drainage works
Tunnel works
including scaffolding erection, excavation, OHVD installation, roadside
barriers, top and base slab construction
Trough structure
construction and associated drilling and grouting
Road works
Bridges
construction |
Excavation of
trial pit
Transplanting of
trees
Drainage works
Tunnel works
including scaffolding erection, excavation, OHVD installation, roadside
barriers, top and base slab construction
Trough structure
construction and associated drilling and grouting
Road works
Bridges
construction |
Contract no. HK/2009/01 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at
Major construction activities
for Contract no. HK/2009/01 have been commenced on 25 August 2011. During this
reporting period, the principal work activities are summarized as below:
Table II Principal Work Activities for Contract no.
HK/2009/01
March 2013 |
April 2014 |
May 2014 |
Stage 1 tunnel excavation work to -5.5
mPD including ELS works for 2nd layer Bay 5 and Bay 6 blinding layers Ground treatment works and guide wall
construction at the promenade deck area demolition of the existing pump
house. Installation of pre-bored H-piles Construction of D wall at C1/C2
interface and CSD for pipe pile wall P2 Plant demobilization Removal of silos Road diversion works for the
construction of temporary road at Expo Drive East UU diversion at both south and north
junction. |
New temporary road for diversion of
Expo Drive East Stage 1 tunnel excavation work Installation of pre-bored H-piles Construction of D-wall for the remaining
south D-wall panels at Stage 2 Discharge cooling main laying works
for BI, BG & BF Saltwater main laying works for S8B at
Zone A5-4 and A5-6 at Harbor Road Tree transplanting at the planter
areas near Hong Kong Culture Centre at Tsim Sha Tsui Trimming works at Fairway |
Demolition work of the existing Expo
Drive East Bridge Trench excavation at both northern and
southern ends of existing Expo Drive East Bridge Stage 1 tunnel blinding layer Stage 1 tunnel structure work Excavation & fabrication at tunnel Installation of pre-bored H-piles at
the HKCEC water channel by t Installation of pre-bored H-piles at
the area adjacent to new temporary road Construction of D-wall for the
remaining south D-wall panels at Stage 2 Discharge cooling main laying works
for BI, BG & BF Saltwater main laying works for S8B Trimming works at Fairway The removal work for abandoned
equipment at lower portion of existing P3 & P4 pump houses The removal work for abandoned
equipment for existing P7 & P9 pump houses |
Contract no. HK/2009/02 - Wan
Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB
Tunnel) under FEP-01/364/2009
Major construction activities
for Contract no. HK/2009/02 have been commenced on 26
Table III Principal Work
Activities for Contract no. HK/2009/02
March 2013 |
April 2014 |
May 2014 |
Casting of OHVD and upper side wall at
Westbound are as follows: Casting for roof slab at Bay 1 , Bay
3, Bay 4 and Bay 7 Rebar fixing at Bay 6. Scaffolding removal of Bay 2 Concreting of D-wall Panel at Tunnel
Portion 2 Casting of bored pile nos. PC 28, PC
30, PC 32 and PN29 Installation of Bored Pile Nos. PN28. Ground treatment for D-wall
construction at Panel Nos. P97 C105 Guide wall and ground treatment for
D-wall construction at Panel Nos. C
Concreting of 2 nos. D-wall Panels for Tunnel Portion 6 |
Casting of roof Slab at Bay 4a, Bay 5, Bay 6 and Bay 8 Water testing on cracks at roof
slab. The crack mapping for tunnel top slab
from Bay 2 to Bay 4. Removal of ELS at S3 Level. Removal at Bay 4 was now in progress. Eastbound scaffolding removal of Bay 1
to Bay 4 Westbound scaffolding removal at Bay 3
and Bay 4 Concreting and grouting of 6 nos.
D-wall Panel Complete demobilization of D-Wall
plant, including the silo at northern seawall near Box Culvert N1 outfall. Casting of 4 nos. bored pile nos.
PN28, PN32, PN33 and PC29. Completing total 60.7% (17 out of 28
nos.) Installation of Bored Pile Nos. PS30 Ground treatment for D-wall
construction at Panel Nos. P97 C105 Plant mobilization for D-Wall
construction |
Water test on cracks at roof slab Removal of ELS at S3 Level The crack mapping for tunnel top slab Loading Transfer for King Post at top
slab Preparation works for horizontal CJ
slab construction at Bay 1 Dismantling of scaffolding along the
eastbound base slab and 50% along westbound base slab Scaffolding removal at OHVD of
eastbound and westbound Toe grouting & interfacing coring
for southern D-Wall Transferal of D-Wall plant from Tunnel
Portion 2 to Tunnel Portion 3 & 4, including the BC-Cutter and Crane Removal of silo at northern seawall
near Box Culvert N1 outfall Excavation for remaining 2 bored pile
nos. PS15 and PS16 3 nos. D-wall Panel were concreted in
the report period P99, P130 and P145 Critical D-wall interfacing with the
footprint of temporary bridges for HHR Flyover Diversion (Stage 2)
implementation Construction of D-wall panels P98,
P131 and P146 |
Contract no. HY/2009/15 - Central-Wanchai Bypass
Tunnel (
Major construction activities
for Contract no. HY/2009/15 has been commenced on 13 July 2011. During this
reporting period, the principal work activities are summarized as below:
Table IV Principal Work
Activities for Contract no. HY/2009/15
April
2014 |
May
2014 |
|
Tunnel construction at TS2, TS4 &
TPCWAE Dismantling of struts at TS4 &
TPCWAE Mined Tunnel drill-and-break works and
installation of steel ribs at East and West Portal. Mined tunnel lining construction |
Tunnel construction at TS2, TS4 &
TPCWAE Dismantling of struts at TS4 &
TPCWAE Mined Tunnel drill-and-break works and
installation of steel ribs at East and West Portal. Mined tunnel lining construction |
Tunnel construction (shaft) at TPCWAE Dismantling of struts at TS2, TS4
& TPCWAE Mined Tunnel drill-and-break works and
installation of steel ribs at East and West Portal. Mined tunnel lining construction |
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/A
Major construction activities
for Contract no. HY/2009/19 have been commenced on March 2011. During this
reporting period, the principal work activities are summarized as below:
Table V Principal Work Activities for Contract no.
HY/2009/19
March 2013 |
April 2014 |
May 2014 |
Road works at Watson Road Bored piling (Land) Removal of strut at ELS Construction of Pile cap, column and
cross-head (Land) Removal of marine platform Construction of Dolphin Cap ELS, EVB and Cut & Cover Tunnel Installation of dewatering well Laying of 1500 pipe Launching of segments Extraction of temporary pile from
marine section Construction of bridge TA1 Pre-bored H-pile for Admin. Building
commenced |
Road works at Watson Road Bored piling (Land) Removal of strut at ELS Construction of Pile cap, column and
cross-head (Land) Removal of marine platform Construction of Dolphin Cap ELS, EVB and Cut & Cover Tunnel Installation of dewatering well Laying of 1500 pipe Launching of segments Extraction of temporary pile from
marine section Construction of bridge TA1 Pre-bored H-pile for Admin. Building
commenced U-beam installation commenced Parapet construction commenced Wing slab extension for segment
commenced Construction of TD bridge commenced |
Road works at Watson Road Bored piling (Land) Removal of strut at ELS Removal of marine platform Construction of Dolphin Cap ELS, EVB and Cut & Cover Tunnel Installation of dewatering well Laying of 1500 pipe Launching of segments Extraction of temporary pile from
marine section Construction of bridge TA1 Pre-bored H-pile for Admin. Building
commenced U-beam installation commenced Parapet construction commenced Wing slab extension for segment
commenced Construction of TD bridge commenced |
Contract no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan
Chai Bypass over MTR Tsuen Wan Line under FEP-08/364/2009/A
Table
VI Principal Work Activities for
Contract no. HK/2010/06
March 2013 |
April 2014 |
May 2014 |
Installation of protection layer for
precast unit |
Installation of protection layer for
precast unit |
Completion of laying protection board Preparation works for sealing of cross
wall opening Diversion of power supply |
Contract
no. HK/2012/08 Wan Chai Development Phase II Central- Wan Chai Bypass at
Wan Chai West under FEP-09/364/2009B
Table VII Principal Work Activities
for Contract no. HK/2012/08
March 2013 |
April 2014 |
May 2014 |
Site preparation works Site survey |
Site preparation works Site survey |
Diaphragm wall construction Site survey |
Contract
no. HY/2010/08 Central and WanChai Bypass Slip road 8 section under
FEP-10/364/2009B
Table VIII Principal Work Activities for Contract
no. HY/2010/08
March 2013 |
April 2014 |
May 2014 |
Tree & root pruning works Tree
& root pruning works Tree transplanting works, Tree works within off-site nursery
compound, Drainage improvement works, Sheet piling works, Demarcation of graphics, Erection of noise absorption
sheetings, Installation of site hoardings, Pipe pile & pre-boring works, Re-provisional of turtle pond peddle
path, Loop detector installation works & UMP installation works. . |
Tree & root pruning works Tree transplanting works, Tree works within off-site nursery
compound, Drainage improvement works, Sheet piling works, Demarcation of graphics, Erection of noise absorption
sheetings, Installation of site hoardings, Sheet piling, pipe piling, ground
pre-treatment & pre-boring works, Re-provisional of turtle pond peddle
path & Construction of Bowling Green Office. |
Tree & root pruning works Tree transplanting works, Tree works within off-site nursery
compound, Drainage improvement works, Sheet piling works, Demarcation of graphics, Erection of noise absorption
sheetings, Installation of site hoardings and
provision of concrete bund under the site hoardings, Pipe piling, ground pre-treatment
& pre-boring works, Re-provisional of turtle pond peddle
path & Construction of Bowling Green Office |
Contract
no. HY/2011/08 Central - Wan Chai Bypass (CWB) Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B
Table IV Principal Work Activities for Contract
no. HY/2011/08
March 2013 |
April 2014 |
May 2014 |
N/A . |
N/A |
No physical construction activity on
site |
Remarks: The FEP for
Contract no. HY/2011/08 was granted in May 2014 reporting month.
Noise Monitoring
Real
time Noise Monitoring
Air Quality
Monitoring
No action level and no limit level
exceedances were recorded in this reporting quarter.
Complaints, Notifications of Summons and
Successful Prosecutions
Nevertheless, in view of the concern
regarding noise nuisance raised by public, it is considered desirable for the
Contractor to review and strengthen the noise mitigation measures around the
concerned location.
1.1.1.
Lam
Geotechnics Limited (LGL) has been appointed to work as the Environmental Team
(ET) under Environmental Permit no. EP-364/2009A and Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-03/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A, FEP-08/364/2009/A and FEP-09/364/2009/B to
implement the Environmental Monitoring and Audit (EM&A) programme as stipulated
in the EM&A Manual of the approved Environmental Impact Assessment (EIA)
Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register
No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for
Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No.
AEIAR-014/2001).
1.1.2.
This
report presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.3 of
EM&A Manual and Environmental Monitoring and Audit Requirements
under Particular Specification Section 27.
1.1.3. This report documents the finding of EM&A
works during the period from March 2014 to May 2014.
Section 1 Introduction details the scope and structure of the
report.
Section 2 Project Background summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section 3 Monitoring Requirements summarizes all monitoring parameters,
monitoring locations, monitoring frequency, duration and action plan.
Section 4 Monitoring Results summarizes the monitoring results
obtained in the reporting period.
Section 5 Compliance Audit summarizes the auditing of monitoring results, all
exceedances environmental parameters.
Section 6 Complaints,
Notification of summons and Prosecution summarizes the cumulative
statistics on complaints, notification of summons and prosecution
Section 7 Cumulative
Construction Impact due to the Concurrent Projects summarizes the
relevant cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section 8 Conclusion
2.1.1.
Wan
Chai Development phase II and Central-Wan Chai Bypass and Central-Wan Chai
Bypass and Island Eastern Corridor Link (hereafter called the Project) are
Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap.
499) (EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The
key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan
Chai North and North Point for construction of the Central-Wan Chai Bypass and
Island Eastern Corridor Link (CWB). Land formed under the project will be
developed as a world-class waterfront promenade joining that at the new Central
waterfront for public enjoyment.
2.1.3.
There
is a compelling and present need for the CWB to provide relief to the very
congested
2.2.1.
Design and Construction of Central Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The
study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB)
and Island Eastern Corridor Link (IECL) includes:
·
A dual three-lane trunk road, approximately 4.5 km
in length, and tunnel approximately 3.7 km in length defined from the
connection with the existing Rumsey Street Flyover in Central, through to a
connection with the existing Island Eastern Corridor to the east of the Causeway
Bay Typhoon Shelter (CBTS);
·
The Central Interchange near the Rumsey Street
Flyover to provide road connections to the Central area;
·
Tunnel control buildings and ventilation buildings;
·
Slip roads to connect the CWB to the local road
system in the Wan Chai North and
·
Associated road lighting, road signing, traffic
control and surveillance system; and
·
Other associated works.
2.2.3.
The
project also contains various Schedule 2 DPs that, under the EIAO, require
Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five
individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table
2.1 Schedule 2 Designated Projects
under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due
to the multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be
commenced. Contractors of individual
contracts will be required by the EP holder to apply Further Environmental
Permits such
that the impact monitoring stations are sub-divided accordingly to facilitate
the implementation of EM&A programme and to streamline the EM&A
reporting for individual FEP holders correspondingly.
2.3.2.
In
the reporting period, all the contracts were commenced and contract no.
04/HY/2006 had been completed. The details of individual contracts are
summarized in Table2.2.
Table
2.2 Details of Individual Contracts
under the Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HY/2009/17 |
Central Wan Chai Bypass (CWB) at FEHD Whitfield Depot Advanced
piling works. |
DP1 |
5 October 2010 (Completed) |
HY/2009/18 |
Central Wan Chai Bypass (CWB) Central Interchange |
DP1 |
21 |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II Central Wan Chai Bypass at |
DP1, DP2 |
25 August 2011 |
HK/2009/02 |
Wan Chai Development Phase II Central Wan Chai Bypass at Wan Chai
East(CWB Tunnel) |
DP1 |
26 |
HY/2009/15 |
Central-Wanchai Bypass Tunnel ( |
DP1 |
13 July 2011 |
HY/2009/19 |
Central Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
HK/2012/08 |
Wan Chai Development Phase II- Central-Wan Chai
Bypass at Wan Chai West |
DP1,DP2, DP3 |
DP works under |
HY/2010/08 |
Central- Wanchai Bypass Tunnel Tunnel (Slip
Road 8) |
DP1, DP2, DP3 |
21 March 2013 |
HY/2011/08 |
Central - Wan Chai Bypass (CWB) Tunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning |
DP1 |
To be commenced tentatively on 4th
quarter in 2014. |
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively.
For the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure
2.2. Key personnel and contact particulars are
summarized in Table 2.3:
Table 2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineers Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineers Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3916 1818 |
3529 2829 |
|
Chun
Wo Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Site Agent |
Mr. Simon Liu |
2162 9909 |
2634 1626 |
Deputy Site Agent |
Mr. Andy Yu |
9648 4896 |
|||
Construction
Manager |
Mr. Wyman
Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Jack
Chu |
9775 2467 |
|||
Environmental
Officer |
Mr. Terry
Wong |
9757 9846 |
|||
Environmental
Supervisor |
Mr. Stanley Chan |
9047 6148 |
|||
Chun Wo CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. K.K. Yuen |
3658-3002 |
2827 9996 |
Project Manager |
Mr. Alfred Leung |
3658-3022 |
|||
Quality & Environmental Manager (Environmental Officer) |
Mr. C.P. Ho |
3658-3000 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. David Lau |
3758 8879 |
2570 8013 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Environmental Engineer |
|
9286 9208 |
|||
Construction Manager (Marine) |
William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
Construction Manager (Land) |
Eric Fong |
6191 9337 |
|||
Operation Manager (Land) |
Yung Kwok Wah |
9834 1010 |
|||
Leighton Contractors ( |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Desmond Sze |
2214
7700 |
2140 6799 |
Deputy Site Agent |
Mr Roger Wong |
2214
7703 |
|||
Environmental Officer |
Ms. |
2823
1161 |
|||
Environmental Engineer |
Mr. Donald Yip |
2214 7721 |
|||
Assistant Environmental Engineer |
Mr. Penny Yiu |
2214
7738 |
|||
Environmental Supervisor |
K. P. Lai |
6461 4660 |
|||
Environmental Supervisor |
Ray Cheng |
22147742 |
|||
Environmental Supervisor |
Bosco Lee |
22147711 |
|||
Environmental Supervisor |
Ryan Tsui |
2214 7705 |
|||
|
Contractor under Contract no. HY/2009/15 |
Project Director |
Mr. K C Cheung |
2823 7813 |
2566 2192 |
Site Manager |
Mr. J.H. Chen |
3557 6368 |
|||
Contractors
Representative |
Mr. Gene Cheung |
3557
6395 |
|||
Head of construction |
Mr. Roger Cheung |
3557 6371 |
|||
Environmental Officer |
Mr. Andy Mak |
3557 6215 |
|||
Environmental Supervisor |
Ms Esther Choi |
35576348 |
|||
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project
Manager |
Mr. Paul Lui |
9095 7922 |
2529
2880 |
Site
Agent |
Mr. Keith Tse |
2529 2068 |
|||
Environmental
Officer |
Mr. Clement Pang |
9481 6024 |
|||
Environmental
Supervisor |
Mr.
Jacky Cheung |
9735 9200 |
|||
|
Contractor under Contract no.HY/2010/08 |
Project
Director |
Cheung
Kit Cheung |
3557
6399 |
3465 2899 |
Project
Manager |
Chan
Ying Lun |
9812
0592 |
|||
Deputy
Project Manager |
Chris
Leung |
3467
4299 |
|||
Site
Agent |
Dave
Chan |
3467
4277 |
|||
Environmental
Officer |
C.M.
Wong |
3557
6464 |
|||
Environmental
Supervisor |
Louis
Lam Tsz Kwan |
3557
6470 |
|||
Leighton Joint Venture |
Contractor under Contract no. HY/2011/08 |
Project
Manager |
Paul
Evans |
2823
1111 |
21406799 |
Site
Agent |
Colman Wong |
9730
0806 |
|||
Environmental
Officer |
Donald Ip |
6461
8635 |
|||
Environmental
Supervisor |
Penny Yiu |
2214
7738 |
|||
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
2.5.1.
Major construction activities for Contract no.
HY/2009/18 have been commenced on 21
Table 2.4 Principal Work Activities
for Contract no. HY/2009/18
March
2013 |
April
2014 |
May
2014 |
Excavation of
trial pit
Transplanting of
trees
Drainage works
Tunnel works
including scaffolding erection, excavation, OHVD installation, roadside
barriers, top and base slab construction
Trough structure
construction and associated drilling and grouting
Road works
Bridges
construction |
Excavation of
trial pit
Transplanting of
trees
Drainage works
Tunnel works
including scaffolding erection, excavation, OHVD installation, roadside
barriers, top and base slab construction
Trough structure
construction and associated drilling and grouting
Road works
Bridges
construction |
Excavation of
trial pit
Transplanting of
trees
Drainage works
Tunnel works
including scaffolding erection, excavation, OHVD installation, roadside
barriers, top and base slab construction
Trough structure
construction and associated drilling and grouting
Road works
Bridges
construction |
2.5.2. Major
construction activities for Contract no. HK/2009/01 have been commenced on 25
August 2011. During this reporting period, the principal work activities are
summarized in Table2.5:
Table 2.5 Principal Work Activities for Contract no. HK/2009/01
March
2013 |
April
2014 |
May
2014 |
Stage 1 tunnel excavation work to -5.5 mPD including ELS works for 2nd
layer
Bay 5 and Bay 6 blinding layers
Ground treatment works and guide wall construction at the promenade
deck area demolition of the existing pump house.
Installation of pre-bored H-piles
Construction of D wall at C1/C2 interface and CSD for pipe pile wall
P2
Plant demobilization
Removal of silos
Road diversion works for the construction of temporary road at Expo
Drive East
UU diversion at both south and north junction. |
New temporary road for diversion of Expo Drive East
Stage 1 tunnel excavation work
Installation of pre-bored H-piles
Construction of D-wall for the remaining south D-wall panels at Stage
2
Discharge cooling main laying works for BI, BG & BF
Saltwater main laying works for S8B at Zone A5-4 and A5-6 at Harbor
Road
Tree transplanting at the planter areas near Hong Kong Culture Centre
at Tsim Sha Tsui
Trimming works at Fairway |
Demolition work of the existing Expo Drive East Bridge
Trench excavation at both northern and southern ends of existing Expo
Drive East
Bridge
Stage 1 tunnel blinding layer
Stage 1 tunnel structure work
Excavation & fabrication at tunnel
Installation of pre-bored H-piles at the HKCEC water channel by t
Installation of pre-bored H-piles at the area adjacent to new
temporary road
Construction of D-wall for the remaining south D-wall panels at Stage
2
Discharge cooling main laying works for BI, BG & BF
Saltwater main laying works for S8B
Trimming works at Fairway
The removal work for abandoned equipment at lower portion of existing
P3 & P4
pump houses
The removal work for abandoned equipment for existing P7 & P9 pump
houses |
2.5.3. Major
construction activities for Contract no. HK/2009/02 have been commenced on 26
Table 2.6 Principal Work Activities for Contract no. HK/2009/02
March
2013 |
April
2014 |
May
2014 |
Casting of OHVD and upper side wall at Westbound are as follows:
Casting for roof slab at Bay 1 , Bay 3, Bay 4 and Bay 7
Rebar fixing at Bay 6.
Scaffolding removal of Bay 2
Concreting of D-wall Panel at Tunnel Portion 2
Casting of bored pile nos. PC 28, PC 30, PC 32 and PN29
Installation of Bored Pile Nos. PN28.
Ground treatment for D-wall construction at Panel Nos. P97 C105
Guide wall and ground treatment for D-wall construction at Panel Nos.
C Concreting of 2 nos. D-wall Panels for
Tunnel Portion 6 |
Casting of roof Slab at Bay 4a,
Bay 5, Bay 6 and Bay 8
Water testing on cracks at roof slab.
The crack mapping for tunnel top slab from Bay 2 to Bay 4.
Removal of ELS at S3 Level.
Removal at Bay 4 was now in progress.
Eastbound scaffolding removal of Bay 1 to Bay 4
Westbound scaffolding removal at Bay 3 and Bay 4
Concreting and grouting of 6 nos. D-wall Panel
Complete demobilization of D-Wall plant, including the silo at
northern seawall near Box Culvert N1 outfall.
Casting of 4 nos. bored pile nos. PN28, PN32, PN33 and PC29.
Completing total 60.7% (17 out of 28 nos.)
Installation of Bored Pile Nos. PS30
Ground treatment for D-wall construction at Panel Nos. P97 C105
Plant mobilization for D-Wall construction |
Water test on cracks at roof slab
Removal of ELS at S3 Level
The crack mapping for tunnel top slab
Loading Transfer for King Post at top slab
Preparation works for horizontal CJ slab construction at Bay 1
Dismantling of scaffolding along the eastbound base slab and 50% along
westbound base slab
Scaffolding removal at OHVD of eastbound and westbound
Toe grouting & interfacing coring for southern D-Wall
Transferal of D-Wall plant from Tunnel Portion 2 to Tunnel Portion 3
& 4, including the BC-Cutter and Crane
Removal of silo at northern seawall near Box Culvert N1 outfall
Excavation for remaining 2 bored pile nos. PS15 and PS16
3 nos. D-wall Panel were concreted in the report period P99, P130 and
P145 Critical D-wall interfacing with the footprint of temporary bridges for
HHR Flyover Diversion (Stage 2) implementation
Construction of D-wall panels P98, P131 and P146 |
2.5.4. Major
construction activities for Contract no. HY/2009/15 have been commenced on 13
July 2011. During this reporting period, the principal work activities are
summarized in Table 2.7:
Table 2.7 Principal Work Activities for Contract no.
HY/2009/15
March
2013 |
April
2014 |
May
2014 |
Tunnel construction at TS2, TS4 & TPCWAE
Dismantling of struts at TS4 & TPCWAE
Mined Tunnel drill-and-break works and installation of steel ribs at
East and West Portal.
Mined tunnel lining construction |
Tunnel construction at TS2, TS4 & TPCWAE
Dismantling of struts at TS4 & TPCWAE
Mined Tunnel drill-and-break works and installation of steel ribs at
East and West Portal.
Mined tunnel lining construction |
Tunnel construction (shaft) at TPCWAE
Dismantling of struts at TS2, TS4 & TPCWAE
Mined Tunnel drill-and-break works and installation of steel ribs at
East and West Portal.
Mined tunnel lining construction |
2.5.5. Major
construction activities for Contract no. HY/2009/19 have been commenced on March
2011. During this reporting period, the principal work activities are
summarized in Table 2.8:
Table 2.8 Principal Work Activities for Contract no.
HY/2009/19
March
2013 |
April
2014 |
May
2014 |
Road works at Watson Road
Bored piling (Land)
Removal of strut at ELS
Construction of Pile cap, column and cross-head (Land)
Removal of marine platform
Construction of Dolphin Cap
ELS, EVB and Cut & Cover Tunnel
Installation of dewatering well
Laying of 1500 pipe
Launching of segments
Extraction of temporary pile from marine section
Construction of bridge TA1
Pre-bored H-pile for Admin. Building commenced |
Road works at Watson Road
Bored piling (Land)
Removal of strut at ELS
Construction of Pile cap, column and cross-head (Land)
Removal of marine platform
Construction of Dolphin Cap
ELS, EVB and Cut & Cover Tunnel
Installation of dewatering well
Laying of 1500 pipe
Launching of segments
Extraction of temporary pile from marine section
Construction of bridge TA1
Pre-bored H-pile for Admin. Building commenced
U-beam installation commenced
Parapet construction commenced
Wing slab extension for segment commenced
Construction of TD bridge commenced |
Road works at Watson Road
Bored piling (Land)
Removal of strut at ELS
Removal of marine platform
Construction of Dolphin Cap
ELS, EVB and Cut & Cover Tunnel
Installation of dewatering well
Laying of 1500 pipe
Launching of segments
Extraction of temporary pile from marine section
Construction of bridge TA1
Pre-bored H-pile for Admin. Building commenced
U-beam installation commenced
Parapet construction commenced
Wing slab extension for segment commenced
Construction of TD bridge commenced |
2.5.6.
Major construction activities for
Contract no. HK/2010/06 have been commenced on March 2011. During this
reporting period, the principal work activities are summarized in Table 2.9
Table 2.9 Principal Work Activities for Contract
no. HK/2010/06
March
2013 |
April
2014 |
May
2014 |
Installation of protection layer for precast unit |
Installation of protection layer for precast unit |
Completion of laying protection board
Preparation works for sealing of cross wall opening
Diversion of power supply |
2.5.7.
Major construction activities for
Contract no. HK/2012/08 have been commenced on March 2013. During the reporting
period, the principal work activities are summarized in Table 2.10
Table
2.10 Principal Work Activities for
Contract no. HK/2012/08
March
2013 |
April
2014 |
May
2014 |
Site preparation works
Site survey |
Site preparation works
Site survey |
Diaphragm wall construction
Site survey |
2.5.8.
Major construction activities for Contract no.HY/2010/08 have been commenced
on March 2013. During the reporting period, the principal work activities are
summarized in Table 2.11
Table
2.11 Principal Work Activities for
Contract no. HY/2010/08
March
2013 |
April
2014 |
May
2014 |
Tree & root pruning works Tree & root pruning works
Tree transplanting works,
Tree works within off-site nursery compound,
Drainage improvement works,
Sheet piling works,
Demarcation of graphics,
Erection of noise absorption sheetings,
Installation of site hoardings,
Pipe pile & pre-boring works,
Re-provisional of turtle pond peddle path,
Loop detector installation works &
UMP installation works. . |
Tree & root pruning works
Tree transplanting works,
Tree works within off-site nursery compound,
Drainage improvement works,
Sheet piling works,
Demarcation of graphics,
Erection of noise absorption sheetings,
Installation of site hoardings,
Sheet piling, pipe piling, ground pre-treatment & pre-boring
works,
Re-provisional of turtle pond peddle path &
Construction of Bowling Green Office. |
Tree & root pruning works
Tree transplanting works,
Tree works within off-site nursery compound,
Drainage improvement works,
Sheet piling works,
Demarcation of graphics,
Erection of noise absorption sheetings,
Installation of site hoardings and provision of concrete bund under
the site hoardings,
Pipe piling, ground pre-treatment & pre-boring works,
Re-provisional of turtle pond peddle path &
Construction of Bowling Green Office |
2.5.9.
Contract no. HY/2011/08 Central - Wan Chai Bypass (CWB) Tunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning
under FEP-11/364/2009B
Table 2.12 Principal
Work Activities for Contract no. HY/2011/08
March
2013 |
April
2014 |
May
2014 |
N/A . |
N/A |
No physical construction activity on site |
Remarks: The FEP for Contract no. HY/2011/08 was
granted in May 2014 reporting month.
2.5.10.
Implementation status of the recommended mitigation measures
during this reporting period is presented in Appendix 2.1.
3.1.1.
The
noise monitoring stations for the Project are listed and shown in Table
3.1 and Figure 3.1. Appendix 3.1 shows
the established Action/Limit Levels for the monitoring works.
Table 3.1 Noise Monitoring Station
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun
Area |
M3a |
Tung Lo Wan
Fire Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
*M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
M8 |
City Hall |
* Remark 1: Location
ID has been updated from M7 to M8 for City Hall
* Remark 2: M7e has
become a reference station starting from 7 Aug 2012
Real time Noise Monitoring Stations
3.1.2.
The
noise monitoring stations for the Project are listed and shown in Table 3.2 and Figure 3.1.. Appendix 3.1
shows the established Action/Limit Levels for the monitoring works.
Table
3.2 Real Time Noise Monitoring Station
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section Whitefield Depot |
North Point |
RTN2a |
Electric Centre |
North Point |
RTN3 |
Pok Leung Kuk Yu |
Tin Hau |
RTN4 |
|
* RTN2 was relocated from Oil Street Community Liaison Centre to
Electric Centre on
05 Oct 2012 and re-designated
as RTN2a.
Noise Monitoring
Parameters, Frequency and Duration
3.1.3.
The construction noise level shall be measured in terms of
the A-weighted equivalent continuous sound pressure level (Leq). Leq (30
minutes) shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For
all other time periods, Leq (5 minutes) shall be employed for
comparison with the Noise Control Ordinance (NCO) criteria.
Supplementary information for data auditing, statistical results such as L10
and L90 shall also be obtained for reference.
3.1.4.
Noise
monitoring shall be carried out at all the designated monitoring stations. The
monitoring frequency shall depend on the scale of the construction activities.
The following is an initial guide on the regular monitoring frequency for each
station on a weekly basis when noise generating activities are underway:
·
One
set of measurements between 0700 and 1900 hours on normal weekdays.
3.1.5.
Real
time noise shall be carried out at the designated monitoring stations. The
following is an initial guide on the regular monitoring frequency for each
station on a 24 hours daily basis when noise generating activities are
underway:
·
One
set of measurements between 0700 and 1900 hours on normal weekdays.
·
One
set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and
2300 hours on public holidays.
·
One
set of measurements between 2300 and 0700 hours on next day on everyday.
3.1.6.
If
construction works are extended to include works during the hours of 1900
0700 as well as public holidays and Sundays, additional weekly impact
monitoring shall be carried out during respective restricted hours periods.
Applicable permits under NCO shall be obtained by the Contractor.
Monitoring Equipment
3.1.7.
As
referred to in the Technical Memorandum issued under the NCO, sound level
meters in compliance with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be
used for carrying out the noise monitoring. Immediately prior to and following
each noise measurement the accuracy of the sound level meter shall be checked
using an acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agree to within 1.0 dB.
3.1.8.
Noise
measurements shall not be made in fog, rain, wind with a steady speed exceeding
5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with
a portable wind speed meter capable of measuring the wind speed in m/s.
3.1.9.
The
sound level meter shall be checked using an acoustic calibrator generating a
known sound pressure level at a known frequency before deployment to the site
and during each site visit. Measurements may be accepted as valid only if the
calibration level from before and after the noise measurement agree to within
1.0 dB.
Air Quality Monitoring
Stations
3.2.1. The air monitoring stations for the Project are
listed and shown in Table 3.3 and Figure 3.1. Appendix 3.1 shows the established
Action/Limit Levels for the monitoring works.
Table
3.3 Air Monitoring Stations
Station ID |
Monitoring
Location |
Description |
CMA1b |
Oil Street Site Office* |
North Point |
CMA2a |
|
|
CMA3a |
Future CWB site office
at Wanchai Waterfront Promenade |
|
CMA4a |
Society for the
Prevention of Cruelty to Animals |
Wan Chai |
CMA5a |
Children Playgrounds
opposite to |
Wan Chai |
CMA6a |
Future AECOM site
office at Work Area |
Wan Chai |
MA1e |
International Finance Centre (Eastern End of Podium) |
Central |
MA1w |
International Finance Centre (Western End of Podium) |
Central |
Remarks*: The location
ID of monitoring station CMA1b was updated as Oil Street Site Office in
Air Monitoring Parameters,
Frequency and Duration
3.2.2. One-hour and 24-hour TSP levels should be measured
to indicate the impacts of construction dust on air quality. The 24-hour TSP
levels shall be measured by following the standard high volume sampling method
as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part
50), Appendix B.
3.2.3. All relevant data including temperature, pressure,
weather conditions, elapsed-time meter reading for the start and stop of the
sampler, identification and weight of the filter paper, and any other local
atmospheric factors affecting or affected by site conditions, etc., shall be
recorded down in detail.
3.2.4. For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
Sampling Procedure and
Monitoring Equipment
3.2.5. High volume samplers (HVSs) in compliance with the
following specifications shall be used for carrying out the 1-hour and 24-hour
TSP monitoring:
·
0.6
1.7 m3 per minute adjustable flow range;
·
Equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours
operation;
·
Installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
·
Capable
of providing a minimum exposed area of 406 cm2;
·
Flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
·
Equipped
with a shelter to protect the filter and sampler;
·
Incorporated
with an electronic mass flow rate controller or other equivalent devices;
·
Equipped
with a flow recorder for continuous monitoring;
·
Provided
with a peaked roof inlet;
·
Incorporated
with a manometer;
·
Able
to hold and seal the filter paper to the sampler housing at horizontal
position;
·
Easily
changeable filter; and
·
Capable
of operating continuously for a 24-hour period.
3.2.6. Initial calibration of dust monitoring equipment
shall be conducted upon installation and thereafter at bi-monthly intervals.
The transfer standard shall be traceable to the internationally recognized
primary standard and be calibrated annually. The concern parties such as IEC
shall properly document the calibration data for future reference. All the data
should be converted into standard temperature and pressure condition.
3.2.7. Laboratory Measurement / Analysis
3.2.8. A clean laboratory with constant temperature and
humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
3.2.9. Filter paper of size 8 x 10 shall be labelled
before sampling. It shall be a clean filter paper with no pinholes, and shall
be conditioned in a humidity-controlled chamber for over 24-hours and be
pre-weighed before use for the sampling.
3.2.10. After sampling, the filter paper loaded with dust
shall be kept in a clean and tightly sealed plastic bag. The filter paper shall
then be returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
readout down to 0.1 mg. The balance shall be regularly calibrated against a
traceable standard.
3.2.11. All the collected samples shall be kept in a good
condition for 6 months before disposal.
4.0.1. Per EPDs letter
dated 3 Aug 2012 (received by ET on 6 Aug 2012 through HyD), noise monitoring
at M8 City Hall commenced on 7 Aug 2012, and the monitoring station M7e
International Finance Centre (Eastern Podium) has become a reference station
starting from 7 Aug 2012.
4.0.2. Due to safety
concerns, the monitoring location for M4b Victoria Centre has been finely
adjusted from 7 June 2012.
4.0.3. Monitoring for report of review baseline noise
level was performed from 11
4.0.4. The environmental monitoring will be implemented
based on the division of works areas of each designed project managed under
different contracts with separate FEP applied by individual contractors. Overall layout showing work areas of various
contracts, latest status of work commencement and monitoring stations is shown
in Figure
2.1 and Figure 3.1. The monitoring results
are presented in according to the Individual Contract(s).
4.0.5. In the reporting period, the concurrent contracts are
as follows:
Contract
no. HY/2009/15 Central-Wanchai Bypass Tunnel (
Contract
no. HY/2009/18 Central Wanchai Bypass (CWB) Central Interchange under
FEP-05/364/2009/A
Contract
no. HY/2009/19 Central Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009
Contract
no. HK/2009/01 Wanchai Development Phase II Central Wanchai Bypass at
Contract
no. HK/2009/02 Wanchai Development Phase II Central- Wanchai Bypass at Wanchai
East
Contract
no. HK/2010/06 - Wan Chai Development Phase II - Central - Wan Chai Bypass over
MTR Tsuen Wan Line under FEP-08/364/2009/A
Contract
no. HK/2012/08 Wan Chai Development Phase II Central- Wan Chai Bypass at
Wan Chai West under FEP-09/364/200/B
Contract
no. HY/2010/08 Central and WanChai Bypass Slip road 8 Section under
FEP-10/364/2009/B
Contract no. HY/2011/08 Central - Wan Chai Bypass (CWB) Tunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning
under FEP-11/364/2009/B
Contract no.
HY/2009/18 Central Wanchai Bypass (CWB) Central Interchange under
FEP-05/364/2009/A
4.1.1.
Noise
monitoring for the Central Interchange works under contract no. HY/2009/18 was
commenced on 22
Table 4.1 Noise Monitoring Station for Contract no. HY/2009/18
Station |
Description |
*M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
M8 |
City Hall |
* Remark : M7e has become a reference station starting from 7 Aug 2012
4.1.2. No exceedance was recorded in the
reporting quarter.
4.1.3. Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 4.1.
Contract no. HK/2009/01 - Wanchai Development Phase
II - Central - Wanchai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel
Works under FEP-02/364/2009 and Contract no. HK/2009/02 - Wanchai Development
Phase II - Central - Wanchai Bypass at Wanchai East (CWB Tunnel) under
FEP-01/364/2009
4.1.4.
The
commencement of construction works for Contract no. HK/2009/01 under
FEP-02/364/2009 is on 25 August 2011
and HK/2009/02 under FEP-01/364/2009 is on 26
Table 4.2 Noise Monitoring Stations for
Contract nos. HK/2009/01 and HK/2009/02
Station |
Description |
M1a |
Harbour Road Sports Centre |
4.1.5. No exceedance was recorded in this
reporting quarter.
4.1.6. Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 4.1.
Contract no.
HY/2009/15 - Central-Wanchai Bypass Tunnel (
4.1.7.
The
commencement of construction works for Contract no. HY/2009/15 under
FEP-06/364/2009/A was on 13 July 2011. Noise
monitoring was commenced on 13 July 2011. The proposed
division of noise monitoring stations are summarized in Table 4.3 below.
Table 4.3 Noise
Monitoring Station for Contract nos. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
4.1.8. No exceedance was recorded in this
reporting quarter.
4.1.9. Details of
noise monitoring results and graphical presentation can be referred in Appendix 4.1.
4.1.10. Noise monitoring for the tunnel works under
contract no. HY/2009/19 was commenced on 24
Table 4.4
Noise Monitoring
Stations for Contract no. HY/2009/19
Station |
Description |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
Reporting month of March
2014
4.1.11.
Two limit level exceedances were recorded on 5 and 11 March 2014 at M6
HK Baptist Church Henrietta Secondary School in the reporting month.
4.1.12.
Major traffic noise observed during monitoring on 5 and 11 March 2014
and it was considered as the major noise contribution. As such, the limit level
exceedances were concluded as non-project related.
Reporting
month of April 2014
4.1.13.
Three limit level exceedances were recorded on 2, 8 and 15 April
2014 at M6 HK Baptist Church Henrietta Secondary School in the
reporting month.
4.1.14.
Major traffic noise observed during monitoring on 2, 8 and 15 April 2014
and it was considered as the major noise contribution. As such, the limit level
exceedances were concluded as non-project related.
Reporting
month of May 2014
4.1.15.
Two limit level exceedances were recorded on 7 and 14 May 2014 at M6
HK Baptist Church Henrietta Secondary School in the reporting month.
4.1.16.
Major traffic noise observed during monitoring on 7 and 14 May
2014 and it was considered as the major noise contribution. As such, the
limit level exceedances were concluded as non-project related.
4.1.17. Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 4.1 and the
Notification of Exceedance can be referred in Appendix 6.2.
Contract no. HY/2010/08 Central-Wanchai Bypass Wanchai Bypass Tunnel
(Slip Raod 8 Section) under FEP-09/364/2009/B
4.1.18. The commencement of construction works
for Contract no. HY/2010/08 under FEP-10/364/2009/B was on 02 September 2013.
Noise monitoring was commenced on 02 September 2013. The proposed divisions of
noise monitoring stations are summarized in Table 5.5 below.
Table
5.5
Noise Monitoring Stations
for Contract
no. HY/2010/08
Station |
Description |
M3a |
Tung
Lo Wan Fire Station |
4.1.19.
No action or limit level exceedance was recorded in this reporting quarter.
4.1.20.
Noise monitoring results measured in this reporting period are reviewed
and summarized. Details of noise
monitoring results and graphical presentation can be referred in Appendix 5.2.
Contract no.
HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under FEP-07/364/2009/A
4.2.1.
Real
time noise monitoring results measured in this reporting period are reviewed
and summarized. Details
of real time noise monitoring results and graphical presentation can be
referred to Appendix
4.2
4.2.2.
The
proposed division of noise monitoring stations are summarized in Table 4.5
below. Real time noise monitoring for major construction works under contract
no. HY/2009/19 was commenced on 24
Table
4.5 Real Time Noise Monitoring
Stations for Contract no. HY/2009/19
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD Hong Kong Transport Section Whitefield Depot |
RTN2a |
North Point |
Electric Centre
(Replacement of RTN2) |
RTN3 |
North Point |
Pok Leung Kuk Yu |
RTN4 |
Tin Hau |
|
* Real time noise monitoring results and graphical presentation during
night time period are for information only.
*Real-time noise monitoring results and graphical presentation for RTN3
during restricted hours are for information only as no night classes were
conducted at the educational institute.
Reporting
month of March 2014
4.2.3.
No limit level exceedance was recorded at
RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the reporting month.
4.2.4.
Limit level exceedances were recorded at
RTN2a-Electric Centre during daytime on 28 February 2014 and 4 March 2014 and
during restricted hours on 23 March 2014.
After checking with contractor, no construction activities were conducted
at the concerned location during daytime on 28 February 2014 and 4 March 2014 and
no construction activities were conducted at the concerned location during
restricted hours on 23 March 2014. As such, the exceedances were considered as
non-project related and contributed by nearby IEC traffic and nearby non-CWB
Project.
4.2.5.
No limit level exceedance was recorded at
RTN3-Yue Lee Mo Fan Memorial School in the reporting month.
4.2.6.
No limit level exceedance was recorded at
RTN4-Causeway Bay Community Centre in the
reporting month.
Reporting month of April
2014
4.2.7.
Limit level exceedances were recorded at
RTN1-FEHD Hong Kong Transport Section Whitfield Depot during restricted hours
on 31 March 2014 in the reporting month. After checking with Contractor, no
construction activities were conducted at the concerned location during the
recorded. The exceedances were considered to be contributed by the adverse
weather condition during the hoisting period of black rainstorm signal and
hence considered as non-project related.
4.2.8.
Limit level exceedances were recorded at
RTN2a-Electric Centre during restricted hours on 31 March 2014 and 6 April 2014
in the reporting month. After checking
with Contractor, no construction activities were conducted at the concerned
location during the recorded. The exceedances were considered to be contributed
by the adverse weather condition during the hoisting period of black rainstorm
signal on 31 March 2014 and mainly due to nearby traffic on 6 April 2014. As
such the exceedances were considered as non-project related.
4.2.9.
Limit level exceedances were recorded at
RTN3-Yue Lee Mo Fan Memorial School during restricted hours on 31 March 2014 in
the reporting month. After checking with Contractor, no construction activities
were conducted at the concerned location during the recorded. The exceedances
were considered to be contributed by the adverse weather condition during the
hoisting period of black rainstorm signal and hence considered as non-project
related.
4.2.10.
Limit level exceedances were recorded at
RTN4-Causeway Bay Community Centre during restricted hours on 31 March 2014 in
the reporting month. After checking with Contractor, no construction activities
were conducted at the concerned location during the recorded. The exceedances
were considered to be contributed by the adverse weather condition during the
hoisting period of black rainstorm signal and hence considered as non-project
related
Reporting month
of May 2014
4.2.11.
Limit level exceedances were recorded at
RTN1-FEHD Hong Kong Transport Section Whitfield Depot during restricted hours
on 8, 9 and 11 May 2014 in the reporting month. After checking with Contractor,
no noisy construction activities were conducted at the concerned location on 8,
9 and 11 May 2014 during the recorded period and the exceedances were
considered to be contributed by the adverse weather condition during the
hoisting period of rainstorm signal. As such, the exceedances were considered
as non-project related.
4.2.12.
Limit level exceedances were recorded at
RTN2a-Electric Centre during restricted hours on 8, 9 and 11 May 2014 and
during daytime on 10 May 2014 in the reporting month. After checking with
Contractor, no construction activities were conducted at the concerned location
on 8, 9 and 11 May 2014 during the recorded period and the exceedances were
considered to be contributed by the adverse weather condition during the
hoisting period of rainstorm signal. On 10 May 2014, despite socket H-piling
activities was conducted at the concerned location on the monitoring day,
contractor mitigation measures including erection of temporary noise barrier
was confirmed in place. Piling works was also observed at nearby non-CWB
Projects. In view of the exceedance was non-continuous, it was considered that the exceedances were considered as
non-project related.
4.2.13.
Limit level exceedances were recorded at
RTN3-Yue Lee Mo Fan Memorial School during daytime on 16 and 23 May 2014. After
checking with Contractor, no noisy construction activities were conducted at
the concerned location during the recorded period on 16 and 23 May 2014. As the
exceedances recorded were non-continuous, the exceedances were considered to be
contributed by nearby IEC traffic.
4.2.14.
Limit level exceedances were recorded at
RTN4-Causeway Bay Community Centre during restricted hours on 11 May 2014 in
the reporting month. After checking with Contractor, no noisy construction
activities were conducted at the concerned location during the recorded period
on 11 May 2014 and the exceedances were considered to be contributed by the
adverse weather condition during the hoisting period of rainstorm signal. As
such the exceedance was considered as non-project related.
4.2.15.
Real
time noise monitoring results measured in this reporting quarter are reviewed
and summarized. Details of real time noise monitoring results and graphical
presentation can be referred to Appendix
4.2
4.3.1
Due to extension of site boundary by contractor of HY/2009/19, location
of air monitoring station CMA1b Oil Street Community Liaison Centre has been
finely adjusted on 21
Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB) Central Interchange under
FEP-05/364/2009/A
4.3.2
The
proposed division of air monitoring stations are summarized in Table
4.6 below.
Table
4.6 Air Monitoring Stations
for Contract no.
HY/2009/18
Station |
Description |
MA1e |
International Finance Centre (Eastern End of Podium) |
MA1w |
International Finance Centre (Western End of Podium) |
4.3.3
Air
monitoring for the Central Interchange works under contract no. HY/2009/18 was
commenced on 21
4.3.4
No exceedance was recorded in the reporting period. Air quality
monitoring results measured in this reporting period are reviewed and
summarized. Details of air monitoring results and graphical presentation can be
referred in Appendix 4.3.
Contract no. HK/2009/01 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at
4.3.5
The
commencement of construction works for Contract no. HK/2009/01 under
FEP-02/364/2009 is on 25 August 2011. The
proposed division of air monitoring stations are summarized in Table
4.7 below.
Table
4.7 Air Monitoring Station
for Contract no. HK/2009/01
Station |
Description |
CMA5a |
Children Playgrounds opposite to |
4.3.6
No
exceedance was recorded in the reporting quarter. Air quality monitoring
results measured in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 4.3.
Contract no. HK/2009/02 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
4.3.7 The commencement of construction works for
HK/2009/02 under FEP-01/364/2009 is on 26
Table 4.8 Air Monitoring Station
for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
4.3.8
No
exceedance was recorded in the reporting period. Air quality monitoring results
measured in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 4.3.
Contract no.
HY/2009/15 - Central-Wanchai Bypass Tunnel (
4.3.9
The
commencement of construction works for Contract no. HY/2009/15 under
FEP-06/364/2009/A was on 13 July 2011. The proposed division of air
monitoring stations are summarized in Table 4.9
below.
Table
4.9
Air
Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB site office at Wanchai
Waterfront Promenade |
4.3.10
No exceedance was recorded in the reporting period. Air quality
monitoring results measured in this reporting period are reviewed and
summarized. Details of air
monitoring results and graphical presentation can be referred in Appendix 4.3.
Contract no.
HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under FEP-07/364/2009/A
4.3.11 Air monitoring for the tunnel works was commenced
on 26
Table 4.10 Air Monitoring Stations for Contract no. HY/2009/19
Station |
Description |
CMA1b |
Oil Street Site Office |
CMA2a |
|
4.3.18.
No exceedance was recorded in the reporting period. Air quality
monitoring results measured in this reporting period are reviewed and
summarized. Details of air
monitoring results and graphical presentation can be referred in Appendix 4.3.
Contract no. HK/2009/01 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at
4.4.1.
Inert
and non-inert C&D waste was disposed of in this reporting period. Details
of the waste flow table are summarized in Table 4.11.
Table 4.11 Details of Waste Disposal for Contract no. HK/2009/01
Inert C&D materials
disposed |
32.9 |
53235.885 |
TKO137, TM38 |
Inert C&D materials
recycled |
Nil |
10104.5 |
N/A |
Non-inert C&D
materials disposed |
68.4 |
1603.73 |
SENT Landfill |
Non-inert C&D
materials recycled |
Nil |
205943 |
N/A |
Chemical waste disposed |
Nil |
10350 |
Kwun Kee (Chemical Waste Collector) |
Remarks: The cumulative amount of
Non-inert C&D material disposed has been updated in May 2014 reporting
month.
Contract no. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
4.4.2.
Inert and non-inert C&D waste were disposed of in this reporting
period. Details of the waste flow table are summarized in Table 4.12.
Table 4.12 Details of Waste Disposal for
Contract no. HK/2009/02
Inert C&D materials
disposed |
7470.825 |
263012.487 |
TKO137, TM 38 |
Inert C&D materials
recycled |
Nil |
18161 |
WCR2 |
Non-inert C&D
materials disposed |
128.42 |
1473.413 |
SENT Landfill |
Non-inert C&D
materials recycled |
Nil |
N/A |
N/A |
Chemical waste disposed |
1124 |
13195 |
N/A |
Remarks: The cumulative amount of inert C&D material disposed has
been clarified in this quarter report.
Contract no. HY/2009/18 - Central - Wan Chai Bypass
(CWB) Central Interchange under FEP-05/364/2009/A
4.4.3.
Inert and non-inert C&D waste was disposed of in this reporting
period. Details of the waste flow table are summarized in Table 4.13.
Table 4.13 Details of Waste Disposal for
Contract no. HY/2009/18
Inert C&D materials
disposed |
4346.95 |
107430.95 |
T.K.O. 137 |
Inert C&D materials
recycled |
111 |
56685 |
N/A |
Non-inert C&D
materials disposed |
286.87 |
2165.87 |
SENT Landfill |
Non-inert C&D materials recycled (tonnes) |
302.67 |
385.15 |
N/A |
Chemical waste disposed |
Nil |
4440 |
N/A |
Contract no. HY/2009/15 - Central-Wanchai Bypass
Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
4.4.4.
Inert and non-inert C&D waste was disposed of in this reporting
period. Details of the waste flow table are summarized in Table 4.14.
Table 4.14 Details of Waste Disposal for Contract no. HY/2009/15
Inert C&D materials
disposed |
1444.89 414.3 |
491219.88 243352.01 |
Tuen Mun Area 38 TKO137 FB |
Inert C&D materials
recycled |
13133.8 |
284962.3 |
HY/2009/11 ex-PCWA TS4 |
Non-inert C&D
materials disposed |
334.79 |
1938.17 |
SENT Landfill |
Non-inert C&D
materials recycled |
2068 |
549122.2 |
Xun Xiang Metal ware Skylight Recycle (paper) |
Chemical waste disposed |
200 |
22155 |
Dunwell Group |
Marine Sediment (Type1-Open Sea Disposal (Dedicate
Sites) &Type 2 Confined Marine Disposal), m3 |
Nil |
5684 |
South of the Brothers |
Contract no. HY/2009/19 Central Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
4.4.5.
Inert C&D materials was recycled non-inert C&D waste was disposed of in this reporting period. Details
of the waste flow table are summarized in Table 4.15.
Table 4.15 Details of Waste Disposal for
Contract no. HY/2009/19
Inert C&D materials
disposed |
11706 |
484786.69 |
N/A |
4840.32 |
66944.75 |
N/A |
|
Non-inert C&D
materials disposed |
113.36 |
1205.06 |
SENT Landfill |
Non-inert C&D
materials recycled |
11.59 |
363.33 |
N/A |
Chemical waste disposed |
0.73 |
6.69 |
N/A |
Marine Sediment (Tunnel) (Type 1- Open Sea
Disposal), m3 |
14016 |
16977 |
South of Cheung Chau |
Marine Sediment (Tunnel) (Type 1- Open Sea
Disposal (Dedicated Sites) & Type 2 Confined Marine Disposal), m3 |
16238 |
26968 |
East
of Sha Chau |
Remarks: The cumulative amount of marine sediment (Typ1- Open Sea
Disposal) and (Type 1 Open sea Disposal (dedicated Site) & Type 2
Confined Marine Disposal have been clarified in May 2014 monthly report.
** The cumulative amount of
non-inert C&D material disposed have been clarified in May 2014 reporting
month.
*** The cumulative amount of
chemical waste disposed was updated in April 2014 reporting month.
*** The cumulative amount inert C&D
material disposed has been clarified in this quarterly report.
Contract no. HK/2010/06 Wan Chai
Development Phase II - Central-Wan Chai Bypass over MTR Tsuen Wan Line under
FEP-08/364/2009/A
4.4.6.
No inert and Non-inert C&D wastes were disposed of in this reporting
period. Details of the waste flow table are summarized in Table 4.16.
Table 4.16 Details of Waste Disposal for Contract no. HK/2010/06
Inert C&D materials disposed |
NIL |
NIL |
TM38 |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
33.61 |
337.21 |
N/A |
Non-inert C&D materials recycled |
74440 |
79510 |
Recyclers |
Chemical waste disposed |
Nil |
0.2 |
N/A |
Remarks: Contractor clarified the
amount of Non-inert C&D material recycled of the reporting quarter in May
2014. As such, the cumulative amount of non-inert C&D material recycled as
of May 2014 has been updated.
Contract no.
HK/2012/08 Wan Chai Development Phase II - Central-Wan Chai Bypass at Wan Chai
West under FEP-09/364/2009/B
4.4.7.
No inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 4.17.
Table 4.17 Details of Waste Disposal for Contract no. HK/2012/08
Waste
Type* |
Quantity
this month, m3 |
Cumulative-to-Date,
m3 |
Disposal
/ Dumping Grounds |
Inert
C&D materials disposed |
511 |
511 |
N/A |
Inert C&D materials recycled |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
Contract no. HY/2010/08
Central Wan Chai Bypass (CWB)
Tunnel (Slip Road 8) under FEP-10/364/2009/B
4.4.8.
No inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 4.18.
Table 4.18 Details
of Waste Disposal for Contract no. HY/2010/08
Waste Type* |
Quantity this month, m3 |
Cumulative-to-Date, m3 |
Disposal / Dumping Grounds |
Inert
C&D materials disposed |
3284 234 |
6328.4 303.029 |
TM 38 |
Inert C&D materials recycled |
Nil |
Nil |
Nil |
Non-inert C&D materials disposed |
84 |
425 |
SENT |
Non-inert C&D materials recycled |
Nil |
Nil |
Nil |
Chemical waste disposed |
Nil |
60 |
Nil |
Remarks: The cumulative amount of Inert
C&D material disposed as of May 2014 was updated as cumulative amount if
inert C&D material disposed in Jan 2014 have been clarified.
5.0.1. The Event Action Plan for construction noise and air
quality are presented in Appendix 5.1.
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) Central
Interchange under FEP-05/364/2009/A
5.1.1. No
exceedance was recorded in the reporting quarter.
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at
5.1.2.
No limit or action level exceedance was
recorded in this reporting quarter.
Contract no. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel)
5.1.3.
No limit or action level exceedance was
recorded in this reporting quarter.
Contract no. HY/2009/15 - Central-Wanchai Bypass
Tunnel (
5.1.4. No limit
or action level exceedance was recorded in this reporting quarter.
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
Reporting month of March 2014
5.1.5.
Two limit level
exceedances were recorded on 5 and 11 March 2014 at M6 HK Baptist Church Henrietta
Secondary School in the reporting month. Investigations found that on 5 and 11 March
2014, traffic noise was major contribution in the noise monitoring and exceedances
were not related to the Project.
Reporting month of April 2014
5.1.6.
Three limit level
exceedances were recorded on 2, 8 and 15 April 2014 at M6 HK Baptist Church Henrietta
Secondary School in the reporting month. Investigations found that on 2, 8 and 15
April 2014, traffic noise was major contribution in the noise monitoring and exceedances
were not related to the Project
Reporting month of May 2014
5.1.7.
Two limit level
exceedances were recorded on 7 and 14 May 2014 at M6 HK Baptist Church Henrietta
Secondary School in the reporting month. Investigations found that on 7 and 14 May
2014, traffic noise was major contribution in the noise monitoring and exceedances
were not related to the Project.
5.2.1.
No
exceedance was recorded in the reporting quarter.
Contract no.
HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
5.2.2.
No
exceedance was recorded in the reporting quarter.
Contract nos.
HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan
Chai East (CWB Tunnel)
5.2.3.
No
exceedance was recorded in the reporting quarter.
Contract no. HY/2009/15 - Central-Wanchai Bypass Tunnel (
5.2.4.
No
exceedance was recorded in the reporting quarter.
Contract no.
HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under FEP-07/364/2009/A
5.2.5. No exceedance was recorded in the reporting
quarter.
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/A
Reporting month of March 2014
5.3.1.
No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport
Section Whitfield Depot during restricted hours in the reporting month.
5.3.2.
Limit level exceedances were recorded at RTN2a-Electric Centre during
daytime on 28 February 2014 and 4 March 2014 and during restricted hours on 23
March 2014. After checking with
contractor, no construction activities were conducted at the concerned location
during daytime on 28 February 2014 and 4 March 2014 and no construction activities
were conducted at the concerned location during restricted hours on 23 March
2014. As such, the exceedances were considered as non-project related and
contributed by nearby IEC traffic and nearby non-CWB Project.
5.3.3.
No limit level exceedances were recorded at RTN3-Yue Lee Mo Fan Memorial
School in the reporting month.
5.3.4.
No limit level exceedance was recorded at RTN4-Causeway Bay Community
Centre in the reporting month.
Reporting month of April
2014
5.3.5.
Limit level exceedances were recorded at RTN1-FEHD Hong Kong Transport
Section Whitfield Depot during restricted hours on 31 March 2014 in the
reporting month. After checking with Contractor, no construction activities
were conducted at the concerned location during the recorded. The exceedances
were considered to be contributed by the adverse weather condition during the
hoisting period of black rainstorm signal and hence considered as non-project
related.
5.3.6.
Limit level exceedances were recorded at RTN2a-Electric Centre during
restricted hours on 31 March 2014 and 6 April 2014 in the reporting month. After checking with Contractor, no
construction activities were conducted at the concerned location during the
recorded. The exceedances were considered to be contributed by the adverse
weather condition during the hoisting period of black rainstorm signal on 31
March 2014 and mainly due to nearby traffic on 6 April 2014. As such the
exceedances were considered as non-project related.
5.3.7.
Limit level exceedances were recorded at RTN3-Yue Lee Mo Fan Memorial
School during restricted hours on 31 March 2014 in the reporting month. After
checking with Contractor, no construction activities were conducted at the
concerned location during the recorded. The exceedances were considered to be
contributed by the adverse weather condition during the hoisting period of
black rainstorm signal and hence considered as non-project related.
5.3.8.
Limit level exceedances were recorded at RTN4-Causeway Bay Community
Centre during restricted hours on 31 March 2014 in the reporting month. After
checking with Contractor, no construction activities were conducted at the
concerned location during the recorded. The exceedances were considered to be
contributed by the adverse weather condition during the hoisting period of
black rainstorm signal and hence considered as non-project related.
Reporting month of May 2014
5.3.9.
Limit level exceedances were recorded at RTN1-FEHD Hong Kong Transport
Section Whitfield Depot during restricted hours on 8, 9 and 11 May 2014 in the
reporting month. After checking with Contractor, no noisy construction
activities were conducted at the concerned location on 8, 9 and 11 May 2014 during
the recorded period and the exceedances were considered to be contributed by
the adverse weather condition during the hoisting period of rainstorm signal.
As such, the exceedances were considered as non-project related.
5.3.10.
Limit level exceedances were recorded at RTN2a-Electric Centre during
restricted hours on 8, 9 and 11 May 2014 and during daytime on 10 May 2014 in
the reporting month. After checking with Contractor, no construction activities
were conducted at the concerned location on 8, 9 and 11 May 2014 during the
recorded period and the exceedances were considered to be contributed by the
adverse weather condition during the hoisting period of rainstorm signal. On 10
May 2014, despite socket H-piling activities was conducted at the concerned
location on the monitoring day, contractor mitigation measures including
erection of temporary noise barrier was confirmed in place. Piling works was
also observed at nearby non-CWB Projects. In view of the exceedance was
non-continuous, it was considered that the exceedances were considered as
non-project related.
5.3.11.
Limit level exceedances were recorded at RTN3-Yue Lee Mo Fan Memorial
School during daytime on 16 and 23 May 2014. After checking with Contractor, no
noisy construction activities were conducted at the concerned location during
the recorded on 16 and 23 May 2014. As the exceedances recorded were
non-continuous, the exceedances were considered to be contributed by nearby IEC
traffic.
5.3.12.
Limit level exceedances were recorded at RTN4-Causeway Bay Community Centre
during restricted hours on 11 May 2014 in the reporting month. After checking
with Contractor, no noisy construction activities were conducted at the
concerned location during the recorded period on 11 May 2014 and the
exceedances were considered to be contributed by the adverse weather condition
during the hoisting period of rainstorm signal. As such the exceedance was
considered as non-project related.
5.4.1. There was no non-compliance from the site audits in
the reporting period. During environmental site inspections conducted during
the reporting quarter, minor deficiencies were noted. However, the Contractor rectified all
deficiencies after receipt of notification.
5.5.1 There was no particular action taken
since no project-related non-compliance was recorded from the site audits and
environmental monitoring in the reporting period.
5.6.1 As no project related exceedance and non-compliance was recorded in this
reporting period, no action or follow-up was required in this reporting period.
6.0.1.
There was no environmental complaint received in this reporting period.
6.0.2. The details of cumulative complaint log and summary of
complaints are presented in Appendix
6.1.
6.0.3. No notification of summons or prosecution was received in the reporting
period. Cumulative statistic
on complaints and successful prosecutions are summarized in Table
6.1 and Table 6.2 respectively.
Table 6.1 Cumulative
Statistics on Complaints
Reporting Period |
No. of Complaints |
Commencement
of Works up to last reporting quarter |
27 |
March 2014 May 2014 |
1 |
Project-to-Date |
28 |
Table 6.2 Cumulative
Statistics on Successful Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this quarter (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
7.0.1.
According to Condition 3.4 of the
EP-364/2009/B, this section addresses the relevant cumulative construction
impact due to the concurrent activities of the current projects including the
Central Reclamation Phase III (CRIII), Wan Chai Development Phase II (WDII),
Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) and
Wan Chai Development Phase II Central Wan Chai Bypass at Wan Chai East (CWB
Tunnel).
7.0.2.
According to the Final
EM&A Report of Central Reclamation Phase III (CRIII) for Contract HK 12/02,
the major construction activities were completed by end of January 2014 and no
construction activities were undertaken thereafter and the water
quality monitoring was completed in October 2011. As such, it is considered that there were no
cumulative construction impact due to the concurrent activities of the current
projects with the Central Reclamation Phase III (CRIII) undertaken by
contractor HK12/02 in the reporting month.
7.0.3.
According to the construction programme of
Central-Wanchai Bypass at Wanchai West at the Central Reclamation Phase III
area, Diaphragm wall construction, Guide wall construction were performed in
May 2014 reporting month. As no exceedances were recorded during the reporting
period, cumulative construction impact due to the concurrent activities of the
current projects with the Central Reclamation Phase III (CRIII) was considered
as insignificant.
7.0.4.
According to the construction programme of
Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern
Corridor Link projects, the major construction activity under Wan Chai
Development Phase II were marine works at HKCEC areas, cross-harbour
Watermains, Fresh Watermains and Cooling Watermains Installations, tunnel works
at Wan Chai East and filling
works at Wan Chai West. The major construction activities under Central-Wan
Chai Bypass and Island Eastern Corridor Link Projects were tunnel construction at
TS4 and tunnel construction and dismantling of struts at TPCWAE. Bridge
construction and tunnel works at Central Interchange, ELS, segment launching
works and tunnel works at North Point area. The major environmental impact was
water quality impact at Causeway Bay and Wan Chai. Land-based construction
activities were tunnel construction at TS2, TS4 and TPCWAE, tunnel works at
Central and ELS and tunnel works at North Point and tunnel works at Wan Chai
East in the reporting month.
7.0.5.
The major environmental impacts generated
from tunnel works at Central and tunnel works at Wan Chai East, IECL and
Causeway Bay Typhoon Shelter were undertaken in the reporting month. No
significant air impact from construction activities was anticipated in the
reporting month.
8.0.1. The EM&A programme was carried out in
accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
Air quality monitoring
8.0.2.
No action or limit level exceedance was recorded in
the reporting quarter.
Noise monitoring
Reporting month of March 2014
8.0.3.
Two limit level exceedances were recorded on 5 and 11 March 2014 at M6 HK Baptist Church Henrietta
Secondary School in the reporting month. Investigations found that on 5 and 11 March
2014, traffic
noise was major contribution in the noise monitoring and exceedances were not
related to the Project.
Reporting month of April 2014
8.0.4.
Three limit level
exceedances were recorded on 2, 8 and 15 April 2014 at M6 HK Baptist Church Henrietta
Secondary School in the reporting month. Investigations found that on 2, 8 and 15
April 2014, traffic
noise was major contribution in the noise monitoring and exceedances were not
related to the Project
Reporting month of May 2014
8.0.5.
Two limit level exceedances were recorded on 7 and 14 May 2014 at M6 HK Baptist Church Henrietta
Secondary School in the reporting month. Investigations found that on 7 and 14 May
2014, traffic
noise was major contribution in the noise monitoring and exceedances were not
related to the Project.
Real
time noise monitoring
Reporting month of March 2014
8.1.1. No limit level exceedance
was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot during
restricted hours in the reporting month.
8.1.2. Limit level exceedances were recorded at
RTN2a-Electric Centre during daytime on 28 February 2014 and 4 March 2014 and
during restricted hours on 23 March 2014.
After checking with contractor, no construction activities were
conducted at the concerned location during daytime on 28 February 2014 and 4
March 2014 and no construction activities were conducted at the concerned
location during restricted hours on 23 March 2014. As such, the exceedances
were considered as non-project related and contributed by nearby IEC traffic
and nearby non-CWB Project.
8.1.3. Limit level exceedances were recorded at
RTN3-Yue Lee Mo Fan Memorial School in the reporting month.
8.1.4. No limit level exceedance was recorded
at RTN4-Causeway Bay Community Centre in the reporting month.
Reporting month of April
2014
8.1.5. Limit level exceedances were recorded at
RTN1-FEHD Hong Kong Transport Section Whitfield Depot during restricted hours
on 31 March 2014 in the reporting month. After checking with Contractor, no
construction activities were conducted at the concerned location during the
recorded. The exceedances were considered to be contributed by the adverse
weather condition during the hoisting period of black rainstorm signal and
hence considered as non-project related.
8.1.6. Limit level exceedances were recorded at
RTN2a-Electric Centre during restricted hours on 31 March 2014 and 6 April 2014
in the reporting month. After checking
with Contractor, no construction activities were conducted at the concerned
location during the recorded. The exceedances were considered to be contributed
by the adverse weather condition during the hoisting period of black rainstorm
signal on 31 March 2014 and mainly due to nearby traffic on 6 April 2014. As
such the exceedances were considered as non-project related.
8.1.7. Limit level exceedances were recorded at
RTN3-Yue Lee Mo Fan Memorial School during restricted hours on 31 March 2014 in
the reporting month. After checking with Contractor, no construction activities
were conducted at the concerned location during the recorded. The exceedances
were considered to be contributed by the adverse weather condition during the
hoisting period of black rainstorm signal and hence considered as non-project
related.
8.1.8. Limit level exceedances were recorded at
RTN4-Causeway Bay Community Centre during restricted hours on 31 March 2014 in
the reporting month. After checking with Contractor, no construction activities
were conducted at the concerned location during the recorded. The exceedances
were considered to be contributed by the adverse weather condition during the
hoisting period of black rainstorm signal and hence considered as non-project
related.
Reporting month of May 2014
8.1.9. Limit level exceedances were recorded at
RTN1-FEHD Hong Kong Transport Section Whitfield Depot during restricted hours
on 8, 9 and 11 May 2014 in the reporting month. After checking with Contractor,
no noisy construction activities were conducted at the concerned location on 8,
9 and 11 May 2014 during the recorded period and the exceedances were
considered to be contributed by the adverse weather condition during the
hoisting period of rainstorm signal. As such, the exceedances were considered
as non-project related.
8.1.10. Limit level exceedances were recorded at
RTN2a-Electric Centre during restricted hours on 8, 9 and 11 May 2014 and
during daytime on 10 May 2014 in the reporting month. After checking with
Contractor, no construction activities were conducted at the concerned location
on 8, 9 and 11 May 2014 during the recorded period and the exceedances were
considered to be contributed by the adverse weather condition during the
hoisting period of rainstorm signal. On 10 May 2014, despite socket H-piling
activities was conducted at the concerned location on the monitoring day,
contractor mitigation measures including erection of temporary noise barrier
was confirmed in place. Piling works was also observed at nearby non-CWB
Projects. In view of the exceedance was non-continuous, it was considered that
the exceedances were considered as non-project related.
8.1.11. Limit level exceedances were recorded at
RTN3-Yue Lee Mo Fan Memorial School during daytime on 16 and 23 May 2014. After
checking with Contractor, no noisy construction activities were conducted at
the concerned location during the recorded on 16 and 23 May 2014. As the
exceedances recorded were non-continuous, the exceedances were considered to be
contributed by nearby IEC traffic.
8.1.12. Limit level exceedances were recorded at
RTN4-Causeway Bay Community Centre during restricted hours on 11 May 2014 in
the reporting month. After checking with Contractor, no noisy construction
activities were conducted at the concerned location during the recorded period
on 11 May 2014 and the exceedances were considered to be contributed by the
adverse weather condition during the hoisting period of rainstorm signal. As
such the exceedance was considered as non-project related.
8.1.13. One environmental complaints under
FEP-05/364/2009/B were received in the reporting quarter.
8.1.14. A public complaint regarding
construction noise impact referred by EPD was received by ET on 11 March 2014 (Ref: H04/RS/0004232-14 dated11 March 2014) under FEP-05/364/2009/B.
8.1.15. The construction programmes
of individual contracts are provided in Appendix 8.1.