Contract
No: HK/2011/07 Wanchai Development Phase II and Sampling, Field Measurement and
Testing Work (Stage 2) Environmental
Permit no. EP-364/2009/C, Further Evironmental permit nos. fep-01/364/2009,
fep-02/364/2009, FEP-05/364/2009/A,
FEp-06/364/2009/a, FEp-07/364/2009/a, FEP-09/364/2009/B, fep-10/364/2009/B
and fep-11/364/2009/B Quarterly Environmental Monitoring
and Audit Report
- march 2015
to may 2015 -
|
CLIENTS: |
|
Civil
Engineering and Development Department and Highways
Department |
Lam Geotechnics
Limited 11/F Centre
Point Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
18 June 2015 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
2.5 Principal Work and Activities
4.2. Real Time Noise Monitoring Results
5.4. Review of the Reasons for and the Implications of
Non-compliance
5.5. Summary of action taken in the event of and follow-up
on non-compliance
6. Complaints, Notification of Summons
and Prosecution
7. Cumulative Construction Impact due to
the Concurrent Projects
lIST
OF TABLES
Table I Principal Work
Activities for Contract no. HY/2009/18
Table II Principal
Work Activities for Contract no. HK/2009/01
Table III Principal Work Activities for
Contract no. HK/2009/02
Table IV Principal Work Activities for
Contract no. HY/2009/15
Table V Principal
Work Activities for Contract no. HY/2009/19
Table VI Principal Work Activities for Contract
no. HK/2012/08
Table VII Principal Work Activities for Contract
no. HY/2010/08
Table VIII Principal Work Activities for Contract no.
HY/2011/08
Table 2.1 Schedule
2 Designated Projects under this Project
Table 2.2 Details
of Individual Contracts under the Project
Table 2.3 Contact
Details of Key Personnel
Table 2.4 Principal Work Activities for
Contract no. HY/2009/18
Table 2.5 Principal Work Activities for
Contract no. HK/2009/01
Table 2.6 Principal
Work Activities for Contract no. HK/2009/02
Table 2.7 Principal
Work Activities for Contract no. HY/2009/15
Table 2.8 Principal
Work Activities for Contract no. HY/2009/19
Table 2.9 Principal
Work Activities for Contract no. HK/2012/08
Table 2.10 Principal Work
Activities for Contract no. HY/2010/08
Table 2.11 Principal Work
Activities for Contract no. HY/2011/08
Table 3.1 Noise
Monitoring Stations
Table 3.2 Real
Time Noise Monitoring Stations
Table 3.3 Air
Monitoring Stations
Table 4.1 Noise Monitoring Station
for Contract no. HY/2009/18
Table 4.2 Noise Monitoring Stations
for Contract nos. HK/2009/01 and HK/2009/02
Table 4.3 Noise Monitoring Station
for Contract nos. HY/2009/15
Table 4.4 Noise
Monitoring Stations for Contract no. HY/2009/19
Table 4.5 Noise Monitoring Stations for Contract
no. HY/2010/08
Table 4.6 Noise Monitoring Stations for Contract no.
HY/2011/08
Table 4.7 Real
Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 4.8 Air
Monitoring Stations for Contract no. HY/2009/18
Table 4.9 Air
Monitoring Stations for Contract no. HK/2009/01
Table 4.10 Air
Monitoring Station for Contract no. HK/2009/02
Table 4.11 Air
Monitoring Station for Contract no. HY/2009/15
Table 4.12 Air
Monitoring Stations for Contract no. HY/2009/19
Table 4.13 Air
Monitoring Stations for Contract no. HK/2012/08
Table 4.14 Air
Monitoring Stations for Contract no. HY/2010/08
Table 4.15 Air Monitoring Stations for Contract
no. HY/2011/08
Table 4.16 Details
of Waste Disposal for Contract no. HK/2009/01
Table 4.17 Details
of Waste Disposal for Contract no. HK/2009/02
Table 4.18 Details
of Waste Disposal for Contract no. HY/2009/18
Table 4.19 Details
of Waste Disposal for Contract no. HY/2009/15
Table 4.20 Details
of Waste Disposal for Contract no. HY/2009/19
Table 4.21 Details of Waste Disposal
for Contract no. HK/2012/08
Table 4.22 Details of Waste Disposal for Contract no.
HY/2012/08
Table 4.23 Details of
Waste Disposal for Contract no. HY/2011/08
Table 6.1 Cumulative
Statistics on Complaints
Table 6.2 Cumulative
Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure
2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure 3.1 Locations of Environmental
Monitoring Stations
lIST OF APPENDIces
Appendix
2.1 Environmental
Mitigation Implementation Schedule
Appendix 3.1 Action and Limit Level
Appendix 4.1 Noise Monitoring Results and
Graphical Presentations
Appendix 4.2 Real-time Noise Monitoring
Results and Graphical Presentations
Appendix 4.3 Air Quality Monitoring Results
and Graphical Presentations
Appendix 5.1 Event Action Plans
Appendix 6.1 Complaint Log
Appendix 6.2 Notification of Exceedance
Appendix 8.1 Construction Programme of
Individual Contracts
EXECUTIVE
SUMMARY
Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB)
- Central Interchange under FEP-05/364/2009/
Major construction activities for Contract no. HY/2009/18 have been
commenced on 21
Table I Principal Work Activities for Contract
no. HY/2009/18
March 2015 |
April 2015 |
May 2015 |
Planting trees and shrubs Transplanting of trees Drainage works Trough structure construction
including excavation, concreting and waterproofing and backfill Road works Bridges construction |
Planting trees and shrubs Transplanting of trees Drainage works Trough structure construction
including excavation, concreting and waterproofing and backfill Road works Bridges construction |
Planting trees and shrubs Transplanting of trees Drainage works Trough structure construction
including excavation, concreting and waterproofing and backfill Road works Bridges construction |
Contract no.
HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009
Major construction activities
for Contract no. HK/2009/01 have been commenced on 25 August 2011. During this
reporting period, the principal work activities are summarized as below:
Table II Principal Work
Activities for Contract no. HK/2009/01
March 2015 |
April 2015 |
May 2015 |
Stage 1 Construction of roadside
barrier Stage 1 Demolition of temporary
upstand Stage 1 Construction of retaining wall
RW1 at slip road 2 Stage 2 ELS works Stage 2 Removal of 2nd layer of
strut/waling at Bay 7 Stage 2 Steel fixing and formwork
erection at Bay 7, 8 and 9 Stage 2 Rebar fixing of exhaust duct Stage 3 ELS excavation and strut
installing works Stage 3 Construction of box culvert
Bay 2 (base slab) and S5A and 5B salt water-main connection Stage 3 Construction of box culvert
Bay 3 to 6 Trench excavation works at A3-5B for sewage
pipeline at Fenwick Pier Street Cooling Main Installation (BI/BG/BF)
at Expo Drive East Outfall and BF at Fleming Road Installation works for Cooling Main
(BF)/ Salt Watermain (S3) / Fresh Watermain (F3) Work zone X1-1 to X1-3 Construction of C3-1 Outfall Reinstatement of cable draw pits at Lung
King Street was in progress |
Stage 1 Construction of roadside
barrier and defect rectification Stage 2 Backfilling of retaining wall
RW1 at slip road 2 Stage 2 ELS and demolition works of
bulkhead wall at Bay 10 Stage 2 Steel fixing and formwork
erection at Bay 7, 8 and 9 OHVD Stage 2 Construction of exhaust duct
at slip road 3 Stage 3 ELS excavation and strut
installing works Stage 3 Base slab construction of box
culvert Bay 2 and Bay 7 Stage 3 Construction of box culvert
Bay 1 Stage 3 Construction of Outfall at
Expo Drive East and backfilling work Sewerage pipeline at Fenwick Pier
Street Pipe laying works for Cooling Main
(BI/BG/BF) Work zone X1-1 to X1-4 at Fleming Road Pipe laying works of C3-1B and
backfilling works of C3-1A |
Stage 1 Construction of roadside
barrier was completed and defect rectification Stage 2 Construction of exhaust duct Stage 2 Construction of base slab Bay
10 Stage 3 ELS excavation and strut
installing work Stage 3 Box culvert diversion Stage 3 Base slab construction of box
culvert Stage 3 Construction works of Outfall
at Expo Drive East Cooling Main Installation (BI/BG) at
Expo Drive East Removal of abandoned cooling main
(P7/P8) at Convention Avenue Sewerage Pipeline A3-4B at Fenwick
Pier Street Installation works for Cooling Main
(BI/BG) / Salt Watermain (S3)/ Fresh Watermain (F3) Reinstatement of Expo Drive East |
Contract no.
HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
Major construction activities
for Contract no. HK/2009/02 have been commenced on 26
Table III Principal Work Activities for Contract no.
HK/2009/02
March 2015 |
April 2015 |
May 2015 |
Core hole at -19mPD for bulk head wall
demolition and wire cut Blinding layer application for base
slab
Waterproofing application for base slab Concreting for base slab Struts dismantling Construction of capping beam at the
west side Excavation at the west side Installation of observation well, dewatering
well, piezometer at the east side Grouting and shear pin installation
for all D-wall panels at the east side Packer tests |
Bulkhead wall breakthrough by Robot at
the north side Bulkhead wall breakthrough by saw cut
and wire cut Waterproofing application for north
and south walls Rebar fixing at the north wall from
Bay 1 to Bay 4 Rebar fixing at the south wall of Bay
3 and Bay 4 Formworks erection was now in progress
at central wall of Bay 4, at south wall and north wall of Bay 1 Concrete cast for central wall at Bay
1, Bay 2 and Bay 3 Excavation at the west side and struts
installation. Packer tests at the east side Excavation at the east side and
welding for struts installation Installation of observation well, dewatering
well, piezometer at the east side Pump test set up and schedule for pump
test |
Removal of scaffolding and clearance
works Bulkhead wall breakthrough by Robot at
-12.9mPD upper part Dismantling of temporary working
platform Preparation for breakthrough the lower
part by Robot Concrete cast for central wall at Bay
4 Concrete cast for south side wall at
Bay 1, Bay 2, Bay 3 and Bay 4 Concrete cast for north side wall at
Bay 1, Bay 2, Bay 3 and Bay 4 Concrete cast for OHVD base slab at
Bay 1 Rebar fixing and formworks erection
for OHVD side wall at Bay 1 Pump test Excavation at Strut Layer S2 of the
west side Excavation at Strut Layer S2 of the
east side |
Contract no. HY/2009/15 - Central-Wanchai
Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
Major construction activities
for Contract no. HY/2009/15 has been commenced on 13 July 2011. During this
reporting period, the principal work activities are summarized as below:
Table IV Principal Work Activities for Contract no.
HY/2009/15
April
2015 |
May
2015 |
|
Mined Tunnel drill-and-break works at
East and West Portal Permanent lining structure at Mined
Tunnel Construction of diaphragm wall at
TPCWAW |
Mined Tunnel drill-and-break works at
East and West Portal Permanent lining structure at Mined
Tunnel Construction of diaphragm wall at
TPCWAW Fabrication of first layer of ELS for
TPCWAW |
Mined Tunnel drill-and-break works at
East and West Portal Permanent lining structure at Mined
Tunnel Construction of diaphragm wall at
TPCWAW |
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/A
Major construction activities
for Contract no. HY/2009/19 have been commenced on March 2011. During this
reporting period, the principal work activities are summarized as below:
Table V Principal Work
Activities for Contract no. HY/2009/19
March 2015 |
April 2015 |
May 2015 |
Bored piling (Land) Demolition of ELS for Cut &Cover
Tunnel and EVB Laying of 1350f pipe Pre-bored H-pile for Admin. Building
continue Construction of Bridge E Installation of Noise
Barrier/enclosure IECL Road modification and removal of
Median Barrier Construction of TB Bridge Abutment D12 construction Saw cut of parapet at IEC East bound Construction for TA2 bridge Construction of temporary steel tower
for IEC demolition JBI Gantry Installation |
Demolition of ELS for Cut &Cover
Tunnel and EVB Pre-bored H-pile for Approach Ramp IECL Road modification and removal of
Median Barrier Abutment D12 construction Saw cut of parapet at IEC East bound Construction of TA2 bridge Construction of temporary steel tower
for IEC demolition Saw cut of existing west fast lane of
IEC bridge Demolition of bulk head wall between
C15 to C19 Column modification at F1 to F8 |
Demolition of ELS for EVB Pre-bored H-pile for Pier 23 Construction of TA2 bridge Construction of temporary steel tower
for IEC demolition Saw cut of existing west fast lane of
IEC bridge Demolition of bulk head wall between
C15 to C19 Column modification at F1 to F8 |
Contract
no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at
Wan Chai West under FEP-09/364/2009B
Table VI Principal
Work Activities for Contract no. HK/2012/08
March 2015 |
April 2015 |
May 2015 |
Diaphragm wall construction Installation of dewatering wells Grouting Construction of ELS at MVB Construction of ELS at Zone A1 |
Diaphragm wall construction Installation of dewatering wells Grouting Construction of ELS at MVB Excavation and installation of lateral
support at top-down area Pre-bored H-pile construction |
Diaphragm wall construction Installation of dewatering wells Grouting Construction of ELS at MVB Construction of top-down slab Pre-bored H-pile construction |
Contract
no. HY/2010/08 – Central and WanChai Bypass – Slip road 8 section under
FEP-10/364/2009B
Table VII Principal Work
Activities for Contract no. HY/2010/08
March 2015 |
April 2015 |
May 2015 |
Tree transplanting works next to W1, Drainage improvement works, Sheet piling works, Excavation and Lateral Support for
U-structure works, Erection of noise absorption
sheetings, Pipe piling & grouting works, Utility diversion works, Waterproofing works, Construction of Bowling Green Office
& Construction of ramp for TTA stage II –
eastbound |
Drainage improvement works, Sheet piling works, Excavation and Lateral Support for
U-structure works, Erection of noise absorption
sheetings, Pipe piling & grouting works, Utility diversion works, Waterproofing works, Provisional of Bowling Green, Milling & paving works for TTA
stage II – westbound &. Construction of ramp for TTA stage II
– eastbound |
Tree protection works next to existing
BGO Drainage improvement works, Sheet piling works, Excavation and Lateral Support for
U-structure works, Erection of noise absorption
sheetings, Pipe piling & grouting works, Utility diversion works, Waterproofing works, Renovation works for Bowling Green
Office, Reprovisional of Bowling Green & Demolition of an existing bowling
green office |
Contract
no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B
Table VIII Principal Work
Activities for Contract no. HY/2011/08
March 2015 |
April 2015 |
May 2015 |
West Ventilation Building structure construction
Install VE panels bracket and thermal
barrier for Tunnel Site preparation for East Vent Shaft |
West Ventilation Building structure
construction Install VE panels bracket and thermal
barrier for Tunnel Construct reinforcement concrete
structure for EVS |
West Ventilation Building structure
construction Install VE panels bracket and thermal
barrier for Tunnel Construct reinforcement concrete
structure for EVS |
Noise Monitoring
Real
time Noise Monitoring
Air Quality Monitoring
Complaints, Notifications of
Summons and Successful Prosecutions
“I live in a building next to Gloucester
Road in Causeway Bay. Recently, I am suffering from unnecessary light source
from the construction site. The banners of the construction companies are
always illuminated with very bright lights.”
1.1.1.
Lam
Geotechnics Limited (LGL) has been appointed to work as the Environmental Team
(ET) under Environmental Permit no. EP-364/2009C and Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/A, FEP-09/364/2009/B, FEP-10/364/2009/B and
FEP-11/364/2009/B to implement the Environmental Monitoring and
Audit (EM&A) programme as stipulated in the EM&A Manual of the approved
Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A
Manual of the approved EIA Report for Central-Wan Chai Bypass and Island
Eastern Corridor Link (Register No. AEIAR-041/2001).
1.1.2.
This
report presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.3 of
EM&A Manual and “Environmental Monitoring and Audit Requirements”
under Particular Specification Section 27.
1.1.3. This report documents the finding of EM&A
works during the period from March
2015 to May 2015.
Section 1 Introduction – details the scope and structure of the
report.
Section 2 Project Background – summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section 3 Monitoring Requirements – summarizes all monitoring parameters,
monitoring locations, monitoring frequency, duration and action plan.
Section 4 Monitoring Results – summarizes the monitoring results
obtained in the reporting period.
Section 5 Compliance Audit – summarizes the auditing of monitoring results, all
exceedances environmental parameters.
Section 6 Complaints,
Notification of summons and Prosecution – summarizes the cumulative
statistics on complaints, notification of summons and prosecution
Section 7 Cumulative
Construction Impact due to the Concurrent Projects – summarizes the
relevant cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section 8 Conclusion
2.1.1.
“Wan
Chai Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai
Bypass and Island Eastern Corridor Link” (hereafter called “the Project”) are
Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap.
499) (EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The
key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan
Chai North and North Point for construction of the Central-Wan Chai Bypass and
Island Eastern Corridor Link (CWB). Land formed under the project will be
developed as a world-class waterfront promenade joining that at the new Central
waterfront for public enjoyment.
2.1.3.
There
is a compelling and present need for the CWB to provide relief to the very
congested
2.2.1.
Design and Construction of Central – Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The
study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB)
and Island Eastern Corridor Link (IECL) includes:
·
A dual three-lane trunk road, approximately 4.5 km
in length, and tunnel approximately 3.7 km in length defined from the
connection with the existing Rumsey Street Flyover in Central, through to a
connection with the existing Island Eastern Corridor to the east of the
Causeway Bay Typhoon Shelter (CBTS);
·
The Central Interchange near the Rumsey Street
Flyover to provide road connections to the Central area;
·
Tunnel control buildings and ventilation buildings;
·
Slip roads to connect the CWB to the local road
system in the Wan Chai North and
·
Associated road lighting, road signing, traffic
control and surveillance system; and
·
Other associated works.
2.2.3.
The
project also contains various Schedule 2 DPs that, under the EIAO, require Environmental
Permits (EPs) to be granted by the DEP before they may be either constructed or
operated. Table 2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table 2.1 Schedule 2 Designated Projects under this
Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due
to the multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be
commenced. Contractors of individual
contracts will be required by the EP holder to apply Further Environmental
Permits such
that the impact monitoring stations are sub-divided accordingly to facilitate
the implementation of EM&A programme and to streamline the EM&A
reporting for individual FEP holders correspondingly.
2.3.2.
In
the reporting period, all the contracts were commenced and contract no.
04/HY/2006 had been completed. The details of individual contracts are
summarized in Table2.2.
Table 2.2 Details of Individual Contracts under the
Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HY/2009/17 |
Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced
piling works. |
DP1 |
5 October 2010 (Completed) |
HY/2009/18 |
Central – Wan Chai Bypass (CWB) – Central Interchange |
DP1 |
21 |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II – Central – Wan Chai Bypass at |
DP1, DP2 |
25 August 2011 |
HK/2009/02 |
Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai
East(CWB Tunnel) |
DP1 |
26 |
HY/2009/15 |
Central-Wanchai Bypass – Tunnel ( |
DP1 |
13 July 2011 |
HY/2009/19 |
Central – Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 (Completed) |
HK/2012/08 |
Wan Chai Development Phase II- Central-Wan Chai
Bypass at Wan Chai West |
DP1,DP2, DP3 |
DP works under |
HY/2010/08 |
Central- Wanchai Bypass Tunnel – Tunnel (Slip
Road 8) |
DP1, DP2, DP3 |
21 March 2013 |
HY/2011/08 |
Central - Wan Chai Bypass (CWB) –Tunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning |
DP1 |
8 October 2014 |
2.3.3.
The construction works of Contract no.
04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street under FEP-04/364/2009/A was completed, and the FEP was surrendered by
the Contractor on 11 February 2011.
2.3.4.
Construction of bored pile E3B under HY/2009/17 was confirmed
completed and the respective work area under FEP-03/364/2009 was handover and inspected
under HY/2009/19 from 19 Dec 2012 onwards. Subsequently, the FEP-03/364/2009
was surrendered by the Contractor on 28 March 2013.
2.3.5.
Construction works under HK/2010/06 was confirmed completed and the
respective work area under FEP-08/364/2009/A was handover and inspected under
HK/2012/08 from 22 Sep 2014 onwards. Subsequently, the FEP-08/364/2009/A was
surrendered by the Contractor on 3 October 2014.
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively.
For the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure 2.2. Key
personnel and contact particulars are summarized in Table 2.3.
Table
2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer’s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer’s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3916 1818 |
3529 2829 |
|
Chun
Wo – Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Site Agent |
Mr. Simon Liu |
2162 9909 |
2634 1626 |
Deputy Site Agent |
Mr. Andy Yu |
9648 4896 |
|||
Construction
Manager |
Mr. Wyman
Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Jack
Chu |
9775 2467 |
|||
Environmental
Officer |
Mr. Wendy
Ng |
9803 0057 |
|||
Environmental
Supervisor |
Mr. Connie Chan |
2162 9935 |
|||
Chun Wo – CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. K.K. Yuen |
3658-3002 |
2827 9996 |
Project Manager |
Mr. Alfred Leung |
3658-3022 |
|||
Quality & Environmental Manager (Environmental Officer) |
Mr. C.P. Ho |
3658-3000 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. David Lau |
3758 8879 |
2570 8013 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Environmental Engineer |
|
9286 9208 |
|||
Construction Manager (Marine) |
William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
Construction Manager (Land) |
Eric Fong |
6191 9337 |
|||
Operation Manager (Land) |
Yung Kwok Wah |
9834 1010 |
|||
Leighton Contractors ( |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Jimmy Chu |
2214
7700 |
2140 6799 |
Deputy Site Agent |
Mr Roger Wong |
2214
7703 |
|||
Environmental Officer |
Ms. |
2823
1161 |
|||
Environmental Engineer |
Mr. Chris Chan |
2214 7721 |
|||
Assistant Environmental Engineer |
Mr. Penny Yiu |
2214
7738 |
|||
Environmental Supervisor |
K. P. Lai |
6461 4660 |
|||
Environmental Supervisor |
Ray Cheng |
22147742 |
|||
Environmental Supervisor |
Bosco Lee |
22147711 |
|||
Environmental Supervisor |
Ryan Tsui |
2214 7705 |
|||
|
Contractor under Contract no. HY/2009/15 |
Project Director |
Mr. K C Cheung |
2823 7813 |
2566 2192 |
Site Manager |
Mr. Y.Huo |
3557 6368 |
|||
Contractor’s
Representative |
Mr. Gene Cheung |
3557
6395 |
|||
Head of construction |
Mr. Roger Cheung |
3557 6371 |
|||
Environmental Officer |
Mr. Andy Mak |
3557 6215 |
|||
Environmental Supervisor |
Ms Esther Choi |
35576348 |
|||
China State- Leader JV |
Contractor under Contract no. HK/2012/08 |
Project
Director |
Mr. C.N.
Lai |
9137
1811 |
2877
1522 |
Project
Manager |
Mr. Eddie
Chung |
9193
8871 |
|||
Site
Agent |
Mr. Keith
Tse |
9095
7922 |
|||
Environmental
Officer |
Mr. James
MA |
9130
9549 |
|||
Environmental
Supervisor |
Mr. Y.L.
Ho |
6050
4919 |
|
||
China |
Contractor under Contract no.HY/2010/08 |
Project
Director |
Cheung
Kit Cheung |
3557
6399 |
3465 2899 |
Project
Manager |
Chan
Ying Lun |
9812
0592 |
|||
Deputy
Project Manager |
Chris
Leung |
3467
4299 |
|||
Site
Agent |
Dave
Chan |
3467
4277 |
|||
Environmental
Officer |
C.M.
Wong |
3557
6464 |
|||
Environmental
Supervisor |
Louis
Lam Tsz Kwan |
3557
6470 |
|||
Leighton Joint Venture |
Contractor under Contract no. HY/2011/08 |
Project
Manager |
Paul
Evans |
2823
1111 |
21406799 |
Site
Agent |
Colman Wong |
9730
0806 |
|||
Environmental
Officer |
Chris Chan |
9765
6151 |
|||
Environmental
Supervisor |
Penny Yiu |
2214
7738 |
|||
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
2.5.1.
Major construction activities for Contract no.
HY/2009/18 have been commenced on 21
Table 2.4 Principal Work Activities
for Contract no. HY/2009/18
March
2015 |
April
2015 |
May
2015 |
Planting trees and shrubs
Transplanting of trees
Drainage works
Trough structure construction including excavation, concreting and
waterproofing and backfill
Road works
Bridges construction |
Planting trees and shrubs
Transplanting of trees
Drainage works
Trough structure construction including excavation, concreting and
waterproofing and backfill
Road works
Bridges construction |
Planting trees and shrubs
Transplanting of trees
Drainage works
Trough structure construction including excavation, concreting and
waterproofing and backfill
Road works
Bridges construction |
2.5.2. Major
construction activities for Contract no. HK/2009/01 have been commenced on 25
August 2011. During this reporting period, the principal work activities are
summarized in Table2.5:
Table 2.5 Principal Work Activities
for Contract no. HK/2009/01
March
2015 |
April
2015 |
May
2015 |
Stage 1 Construction of roadside barrier
Stage 1 Demolition of temporary upstand
Stage 1 Construction of retaining wall RW1 at slip road 2
Stage 2 ELS works
Stage 2 Removal of 2nd layer of strut/waling at Bay 7
Stage 2 Steel fixing and formwork erection at Bay 7, 8 and 9
Stage 2 Rebar fixing of exhaust duct
Stage 3 ELS excavation and strut installing works
Stage 3 Construction of box culvert Bay 2 (base slab) and S5A and 5B
salt water-main connection
Stage 3 Construction of box culvert Bay 3 to 6
Trench excavation works at A3-5B for sewage pipeline at Fenwick Pier
Street
Cooling Main Installation (BI/BG/BF) at Expo Drive East Outfall and BF
at Fleming Road
Installation works for Cooling Main (BF)/ Salt Watermain (S3) / Fresh
Watermain (F3)
Work zone X1-1 to X1-3
Construction of C3-1 Outfall
Reinstatement of cable draw pits at Lung King Street was in progress |
Stage 1 Construction of roadside barrier and defect rectification
Stage 2 Backfilling of retaining wall RW1 at slip road 2
Stage 2 ELS and demolition works of bulkhead wall at Bay 10
Stage 2 Steel fixing and formwork erection at Bay 7, 8 and 9 OHVD
Stage 2 Construction of exhaust duct at slip road 3
Stage 3 ELS excavation and strut installing works
Stage 3 Base slab construction of box culvert Bay 2 and Bay 7
Stage 3 Construction of box culvert Bay 1
Stage 3 Construction of Outfall at Expo Drive East and backfilling
work
Sewerage pipeline at Fenwick Pier Street
Pipe laying works for Cooling Main (BI/BG/BF)
Work zone X1-1 to X1-4 at Fleming Road
Pipe laying works of C3-1B and backfilling works of C3-1A |
Stage 1 Construction of roadside barrier was completed and defect
rectification
Stage 2 Construction of exhaust duct
Stage 2 Construction of base slab Bay 10
Stage 3 ELS excavation and strut installing work
Stage 3 Box culvert diversion
Stage 3 Base slab construction of box culvert
Stage 3 Construction works of Outfall at Expo Drive East
Cooling Main Installation (BI/BG) at Expo Drive East
Removal of abandoned cooling main (P7/P8) at Convention Avenue
Sewerage Pipeline A3-4B at Fenwick Pier Street
Installation works for Cooling Main (BI/BG) / Salt Watermain (S3)/
Fresh Watermain (F3)
Reinstatement of Expo Drive East |
2.5.3. Major
construction activities for Contract no. HK/2009/02 have been commenced on 26
Table 2.6 Principal Work Activities
for Contract no. HK/2009/02
March
2015 |
April
2015 |
May
2015 |
Core hole at -19mPD for bulk head wall demolition and wire cut
Blinding layer application for base slab
Waterproofing application for base slab
Concreting for base slab
Struts dismantling
Construction of capping beam at the west side
Excavation at the west side
Installation of observation well, dewatering well, piezometer at the east
side
Grouting and shear pin installation for all D-wall panels at the east
side
Packer tests |
Bulkhead wall breakthrough by Robot at the north side
Bulkhead wall breakthrough by saw cut and wire cut
Waterproofing application for north and south walls
Rebar fixing at the north wall from Bay 1 to Bay 4
Rebar fixing at the south wall of Bay 3 and Bay 4
Formworks erection was now in progress at central wall of Bay 4, at
south wall and north wall of Bay 1
Concrete cast for central wall at Bay 1, Bay 2 and Bay 3
Excavation at the west side and struts installation.
Packer tests at the east side
Excavation at the east side and welding for struts installation
Installation of observation well, dewatering well, piezometer at the east
side
Pump test set up and schedule for pump test |
Removal of scaffolding and clearance works
Bulkhead wall breakthrough by Robot at -12.9mPD upper part
Dismantling of temporary working platform
Preparation for breakthrough the lower part by Robot
Concrete cast for central wall at Bay 4
Concrete cast for south side wall at Bay 1, Bay 2, Bay 3 and Bay 4
Concrete cast for north side wall at Bay 1, Bay 2, Bay 3 and Bay 4
Concrete cast for OHVD base slab at Bay 1
Rebar fixing and formworks erection for OHVD side wall at Bay 1
Pump test
Excavation at Strut Layer S2 of the west side
Excavation at Strut Layer S2 of the east side |
2.5.4. Major
construction activities for Contract no. HY/2009/15 have been commenced on 13
July 2011. During this reporting period, the principal work activities are
summarized in Table 2.7:
Table 2.7 Principal Work Activities
for Contract no. HY/2009/15
March
2015 |
April
2015 |
May
2015 |
Mined Tunnel drill-and-break works at East and West Portal
Permanent lining structure at Mined Tunnel
Construction of diaphragm wall at TPCWAW |
Mined Tunnel drill-and-break works at East and West Portal
Permanent lining structure at Mined Tunnel
Construction of diaphragm wall at TPCWAW
Fabrication of first layer of ELS for TPCWAW |
Construction of OHVD and base slab at Mined Tunnel
Inner bench excavation
Permanent lining structure at Mined Tunnel
Construction of diaphragm wall at TPCWAW
Installation of king post
Fabrication of first layer of ELS for TPCWAW
Excavation of ELS at TPCWAW |
2.5.5. Major
construction activities for Contract no. HY/2009/19 have been commenced on
March 2011. During this reporting period, the principal work activities are
summarized in Table 2.8:
Table 2.8 Principal Work Activities
for Contract no. HY/2009/19
March
2015 |
April
2015 |
May
2015 |
Bored piling (Land)
Demolition of ELS for Cut &Cover Tunnel and EVB
Laying of 1350f pipe
Pre-bored H-pile for Admin. Building continue
Construction of Bridge E
Installation of Noise Barrier/enclosure
IECL Road modification and removal of Median Barrier
Construction of TB Bridge
Abutment D12 construction
Saw cut of parapet at IEC East bound
Construction for TA2 bridge
Construction of temporary steel tower for IEC demolition
JBI Gantry Installation |
Demolition of ELS for Cut &Cover Tunnel and EVB
Pre-bored H-pile for Approach Ramp
IECL Road modification and removal of Median Barrier
Abutment D12 construction
Saw cut of parapet at IEC East bound
Construction of TA2 bridge
Construction of temporary steel tower for IEC demolition
Saw cut of existing west fast lane of IEC bridge
Demolition of bulk head wall between C15 to C19
Column modification at F1 to F8 |
Demolition of ELS for EVB
Pre-bored H-pile for Pier 23
Construction of TA2 bridge
Construction of temporary steel tower for IEC demolition
Saw cut of existing west fast lane of IEC bridge
Demolition of bulk head wall between C15 to C19
Column modification at F1 to F8
|
2.5.6.
Major construction activities for
Contract no. HK/2012/08 have been commenced on March 2013. During the reporting
period, the principal work activities are summarized in Table 2.10
Table 2.9 Principal Work Activities for Contract no. HK/2012/08
March
2015 |
April
2015 |
May
2015 |
Diaphragm wall construction
Installation of dewatering wells
Grouting
Construction of ELS at MVB
Construction of ELS at Zone A1 |
Diaphragm wall construction
Installation of dewatering wells
Grouting
Construction of ELS at MVB
Excavation and installation of lateral support at top-down area
Pre-bored H-pile construction |
Diaphragm wall construction
Installation of dewatering wells
Grouting
Construction of ELS at MVB
Construction of top-down slab
Pre-bored H-pile construction |
2.5.7.
Major construction activities for Contract no.HY/2010/08 have been commenced
on March 2013. During the reporting period, the principal work activities are
summarized in Table 2.11
Table 2.10 Principal Work Activities for Contract no. HY/2010/08
March
2015 |
April
2015 |
May
2015 |
Tree transplanting works next to W1,
Drainage improvement works,
Sheet piling works,
Excavation and Lateral Support for U-structure works,
Erection of noise absorption sheetings,
Pipe piling & grouting works,
Utility diversion works,
Waterproofing works,
Construction of Bowling Green Office &
Construction of ramp for TTA stage II – eastbound |
Drainage improvement works,
Sheet piling works,
Excavation and Lateral Support for U-structure works,
Erection of noise absorption sheetings,
Pipe piling & grouting works,
Utility diversion works,
Waterproofing works,
Provisional of Bowling Green,
Milling & paving works for TTA stage II – westbound &.
Construction of ramp for TTA stage II – eastbound |
Tree protection works next to existing BGO
Drainage improvement works,
Sheet piling works,
Excavation and Lateral Support for U-structure works,
Erection of noise absorption sheetings,
Pipe piling & grouting works,
Utility diversion works,
Waterproofing works,
Renovation works for Bowling Green Office,
Reprovisional of Bowling Green &
Demolition of an existing bowling green office |
2.5.8.
Contract no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning
under FEP-11/364/2009B
Table 2.11 Principal Work Activities for Contract no. HY/2011/08
March
2015 |
April
2015 |
May
2015 |
West Ventilation Building structure construction
Install VE panels bracket and thermal barrier for Tunnel
Site preparation for East Vent Shaft |
West Ventilation Building structure construction
Install VE panels bracket and thermal barrier for Tunnel
Construct reinforcement concrete structure for EVS |
West Ventilation Building structure construction
Install VE panels bracket and thermal barrier for Tunnel
Construct reinforcement concrete structure for EVS |
2.5.9.
Implementation status of the recommended mitigation measures
during this reporting period is presented in Appendix 2.1.
3.1.1.
The
noise monitoring stations for the Project are listed and shown in Table
3.1 and Figure 3.1. Appendix 3.1 shows
the established Action/Limit Levels for the monitoring works.
Table
3.1 Noise Monitoring Station
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun
Area |
M3a |
Tung Lo Wan
Fire Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
*M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
M8 |
City Hall |
* Remark 1: Location
ID has been updated from M7 to M8 for City Hall
* Remark 2: M7e has
become a reference station starting from 7 Aug 2012
Real time Noise Monitoring Stations
3.1.2.
The
noise monitoring stations for the Project are listed and shown in Table 3.2 and Figure 3.1.. Appendix 3.1
shows the established Action/Limit Levels for the monitoring works.
Table 3.2 Real Time Noise
Monitoring Station
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section Whitefield Depot |
North Point |
RTN2a |
Electric Centre |
North Point |
RTN3 |
Pok Leung Kuk Yu |
Tin Hau |
RTN4 |
|
* RTN2 was relocated from
Oil Street Community Liaison Centre to Electric Centre on
05 Oct 2012 and re-designated
as RTN2a.
Noise Monitoring
Parameters, Frequency and Duration
3.1.3.
The construction noise level shall be measured in terms of
the A-weighted equivalent continuous sound pressure level (Leq). Leq (30
minutes) shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For
all other time periods, Leq (5 minutes) shall be employed for
comparison with the Noise Control Ordinance (NCO) criteria.
Supplementary information for data auditing, statistical results such as L10
and L90 shall also be obtained for reference.
3.1.4.
Noise
monitoring shall be carried out at all the designated monitoring stations. The
monitoring frequency shall depend on the scale of the construction activities.
The following is an initial guide on the regular monitoring frequency for each
station on a weekly basis when noise generating activities are underway:
·
One
set of measurements between 0700 and 1900 hours on normal weekdays.
3.1.5.
Real
time noise shall be carried out at the designated monitoring stations. The
following is an initial guide on the regular monitoring frequency for each
station on a 24 hours daily basis when noise generating activities are
underway:
·
One
set of measurements between 0700 and 1900 hours on normal weekdays.
·
One
set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and
2300 hours on public holidays.
·
One
set of measurements between 2300 and 0700 hours on next day on everyday.
3.1.6.
If
construction works are extended to include works during the hours of 1900 –
0700 as well as public holidays and Sundays, additional weekly impact
monitoring shall be carried out during respective restricted hours periods.
Applicable permits under NCO shall be obtained by the Contractor.
Monitoring Equipment
3.1.7.
As
referred to in the Technical Memorandum ™ issued under the NCO, sound level
meters in compliance with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be
used for carrying out the noise monitoring. Immediately prior to and following
each noise measurement the accuracy of the sound level meter shall be checked
using an acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agree to within 1.0 dB.
3.1.8.
Noise
measurements shall not be made in fog, rain, wind with a steady speed exceeding
5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with
a portable wind speed meter capable of measuring the wind speed in m/s.
3.1.9.
The
sound level meter shall be checked using an acoustic calibrator generating a
known sound pressure level at a known frequency before deployment to the site
and during each site visit. Measurements may be accepted as valid only if the
calibration level from before and after the noise measurement agree to within
1.0 dB.
Air Quality Monitoring
Stations
3.2.1. The air monitoring stations for the Project are
listed and shown in Table 3.3 and Figure 3.1. Appendix 3.1 shows the established
Action/Limit Levels for the monitoring works.
Table
3.3 Air Monitoring Stations
Station ID |
Monitoring
Location |
Description |
CMA1b |
Oil Street Site Office* |
North Point |
CMA2a |
|
|
CMA3a |
CWB PRE Site Office |
|
CMA4a |
Society for the Prevention
of Cruelty to Animals |
Wan Chai |
CMA5b |
Pedestrian Plaza** |
Wan Chai |
MA1e |
International Finance Centre (Eastern End of Podium) |
Central |
MA1w |
International Finance Centre (Western End of Podium) |
Central |
Remarks*: The
location ID of monitoring station CMA1b was updated as “Oil Street Site Office”
in
Remarks**: With respect to the area handover, the air
quality monitoring station CMA5a at Children Playgrounds opposite to the
Pedestrian Plaza was relocated to the Pedestrian Plaza on 3 December 2014. The
station reference and location ID of the air quality monitoring station CMA5a
was updated as CMA5b and Pedestrian Plaza respectively.
Air Monitoring Parameters,
Frequency and Duration
3.2.2. One-hour and 24-hour TSP levels should be measured
to indicate the impacts of construction dust on air quality. The 24-hour TSP
levels shall be measured by following the standard high volume sampling method
as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part
50), Appendix B.
3.2.3. All relevant data including temperature, pressure,
weather conditions, elapsed-time meter reading for the start and stop of the
sampler, identification and weight of the filter paper, and any other local
atmospheric factors affecting or affected by site conditions, etc., shall be
recorded down in detail.
3.2.4. For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
Sampling Procedure and
Monitoring Equipment
3.2.5. High volume samplers (HVSs) in compliance with the
following specifications shall be used for carrying out the 1-hour and 24-hour
TSP monitoring:
·
0.6
– 1.7 m3 per minute adjustable flow range;
·
Equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours
operation;
·
Installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
·
Capable
of providing a minimum exposed area of 406 cm2;
·
Flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
·
Equipped
with a shelter to protect the filter and sampler;
·
Incorporated
with an electronic mass flow rate controller or other equivalent devices;
·
Equipped
with a flow recorder for continuous monitoring;
·
Provided
with a peaked roof inlet;
·
Incorporated
with a manometer;
·
Able
to hold and seal the filter paper to the sampler housing at horizontal
position;
·
Easily
changeable filter; and
·
Capable
of operating continuously for a 24-hour period.
3.2.6. Initial calibration of dust monitoring equipment
shall be conducted upon installation and thereafter at bi-monthly intervals.
The transfer standard shall be traceable to the internationally recognized
primary standard and be calibrated annually. The concern parties such as IEC
shall properly document the calibration data for future reference. All the data
should be converted into standard temperature and pressure condition.
3.2.7. Laboratory Measurement / Analysis
3.2.8. A clean laboratory with constant temperature and
humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
3.2.9. Filter paper of size 8” x 10” shall be labelled
before sampling. It shall be a clean filter paper with no pinholes, and shall
be conditioned in a humidity-controlled chamber for over 24-hours and be
pre-weighed before use for the sampling.
3.2.10. After sampling, the filter paper loaded with dust
shall be kept in a clean and tightly sealed plastic bag. The filter paper shall
then be returned to the laboratory for reconditioning in the humidity controlled
chamber followed by accurate weighing by an electronic balance with readout
down to 0.1 mg. The balance shall be regularly calibrated against a traceable
standard.
3.2.11. All the collected samples shall be kept in a good
condition for 6 months before disposal.
4.0.1. Per EPD’s letter
dated 3 Aug 2012 (received by ET on 6 Aug 2012 through HyD), noise monitoring
at M8 – City Hall commenced on 7 Aug 2012, and the monitoring station M7e –
International Finance Centre (Eastern Podium) has become a reference station
starting from 7 Aug 2012.
4.0.2. Due to safety
concerns, the monitoring location for M4b – Victoria Centre has been finely
adjusted from 7 June 2012.
4.0.3. Monitoring for report of review baseline noise
level was performed from 11
4.0.4. The environmental monitoring will be implemented
based on the division of works areas of each designed project managed under
different contracts with separate FEP applied by individual contractors. Overall layout showing work areas of various
contracts, latest status of work commencement and monitoring stations is shown
in Figure
2.1 and Figure 3.1. The monitoring results
are presented in according to the Individual Contract(s).
4.0.5. In the reporting period, the concurrent contracts are
as follows:
Contract
no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (
Contract
no. HY/2009/18 – Central –Wanchai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
Contract
no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009
Contract
no. HK/2009/01 –Wanchai Development Phase II – Central –Wanchai Bypass at Hong
Kong Convention and Exhibition Centre under FEP-02/364/2009
Contract
no. HK/2009/02 Wanchai Development Phase II – Central- Wanchai Bypass at Wanchai
East under FEP-01/364/2009
Contract
no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at
Wan Chai West under FEP-09/364/200/B
Contract
no. HY/2010/08 – Central and WanChai Bypass – Slip road 8 Section under FEP-10/364/2009/B
Contract no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning
under FEP-11/364/2009/B
Contract no.
HY/2009/18 – Central – Wanchai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
4.1.1.
Noise
monitoring for the Central Interchange works under contract no. HY/2009/18 was
commenced on 22
Table
4.1
Noise Monitoring Station for Contract no. HY/2009/18
Station |
Description |
*M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
M8 |
City Hall |
* Remark : M7e has become a reference station starting from 7 Aug 2012
4.1.2. No exceedance was recorded in this
reporting quarter.
4.1.3. Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 4.1.
Contract no. HK/2009/01 - Wanchai Development Phase
II - Central - Wanchai Bypass at Hong Kong Convention and Exhibition Centre -
Tunnel Works under FEP-02/364/2009 and Contract no. HK/2009/02 - Wanchai
Development Phase II - Central - Wanchai Bypass at Wanchai East (CWB Tunnel)
under FEP-01/364/2009
4.1.4.
The
commencement of construction works for Contract no. HK/2009/01 under
FEP-02/364/2009 is on 25 August 2011
and HK/2009/02 under FEP-01/364/2009 is on 26
Table
4.2
Noise
Monitoring Stations
for Contract nos. HK/2009/01 and HK/2009/02
Station |
Description |
M1a |
Harbour Road Sports Centre |
4.1.5. No exceedance was recorded in this
reporting quarter.
4.1.6. Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 4.1.
Contract no.
HY/2009/15 - Central-Wanchai Bypass – Tunnel (
4.1.7.
The
commencement of construction works for Contract no. HY/2009/15 under
FEP-06/364/2009/A was on 13 July 2011. Noise
monitoring was commenced on 13 July 2011. The proposed
division of noise monitoring stations are summarized in Table 4.3 below.
Table
4.3
Noise Monitoring
Station for Contract nos. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
4.1.8.
No action or limit level exceedance was recorded in this reporting quarter.
4.1.9. Details of
noise monitoring results and graphical presentation can be referred in Appendix 4.1.
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
4.1.10. Noise monitoring for the tunnel works under
contract no. HY/2009/19 was commenced on 24
Table 4.4
Noise Monitoring
Stations for Contract no. HY/2009/19
Station |
Description |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
4.1.11.
Three limit level exceedances at M6 – HK Baptist Church Henrietta
Secondary School were recorded on 21 April
2015, 5 and 27 May 2015 in this reporting quarter.
4.1.12.
Traffic noise was observed during monitoring on 21 April 2015 and it was considered as the major
noise contribution. As such, the limit level exceedances were concluded as
non-project related.
4.1.13.
IEC bridge deck saw cutting works under HY/2009/19 was observed during
monitoring on 5 May 2015 and no noise mitigation measures was provided
for the concerned works. The saw cutting works was considered as the major
noise contribution and the limit level exceedance was concluded as Project
related. Mitigation measures including the use of movable noise barrier for the
saw cutting machine was committed by the Contractor as the CWB RSS confirmed
the concerned construction works at the concerned section was temporarily
completed on 5 May 2015 and tentatively to be resumed in June 2015. Additional
noise monitoring was conducted and no further exceedance was identified.
4.1.14.
IEC bridge deck saw cutting works under HY/2009/19 was observed during
monitoring on 27 May 2015 and single noise barrier was provided to the
saw cut machine. The mitigation measures was considered inadequate based on the
Contractor submitted rectification proposal and the noise level measured. The
saw cutting works was considered as the major noise contribution and the limit
level exceedance was concluded as Project related. Mitigation measures
including provision of additional movable noise barriers for the saw cutting
machine was implemented by the Contractor and additional noise monitoring was
conducted and no further exceedance was identified.
4.1.15.
No action or limit level exceedance was
recorded in March 2015.
4.1.16. Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 4.1 and the
Notification of Exceedance can be referred in Appendix 6.2.
Contract no. HY/2010/08 – Central-Wanchai Bypass –Wanchai Bypass Tunnel
(Slip Raod 8 Section) under FEP-09/364/2009/B
4.1.17. The commencement of construction works
for Contract no. HY/2010/08 under FEP-10/364/2009/B was on 02 September 2013.
Noise monitoring was commenced on 02 September 2013. The proposed divisions of
noise monitoring stations are summarized in Table 4.5 below.
Table 4.5 Noise
Monitoring Stations for Contract
no. HY/2010/08
Station |
Description |
M3a |
Tung
Lo Wan Fire Station |
4.1.18.
No action or limit level exceedance was recorded in this reporting quarter.
4.1.19.
Noise monitoring results measured in this reporting period are reviewed
and summarized. Details of noise
monitoring results and graphical presentation can be referred in Appendix 4.1.
Contract no. HY/2011/08 – Central - Wan Chai
Bypass (CWB) – Tunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning
4.1.20. Noise monitoring for the Central
Interchange works under contract no. HY/2009/18 was commenced on 22 April
2011.The proposed division of noise monitoring stations for Contract no.
HY/2009/18 are summarized in Table 4.6 below:
Table
4.6 Noise Monitoring Stations for Contract no. HY/2011/08
Station |
Description |
*M7e |
International
Finance Centre (Eastern End of Podium) |
M7w |
International
Finance Centre (Western End of Podium) |
M8 |
City
Hall |
* Remark: M7e has become a reference station
starting from 7 Aug 2012
4.1.21.
No action or limit level exceedance was recorded in this reporting quarter.
4.1.22.
Noise monitoring results measured in this reporting period are reviewed
and summarized. Details of noise
monitoring results and graphical presentation can be referred in Appendix 4.1.
Contract no.
HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under FEP-07/364/2009/A
4.2.1.
Real
time noise monitoring results measured in this reporting period are reviewed
and summarized. Details
of real time noise monitoring results and graphical presentation can be
referred to Appendix
4.2
4.2.2.
The
proposed division of noise monitoring stations are summarized in Table 4.5
below. Real time noise monitoring for major construction works under contract
no. HY/2009/19 was commenced on 24
Table 4.7 Real Time Noise
Monitoring Stations
for Contract no. HY/2009/19
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD Hong Kong Transport Section Whitefield Depot |
RTN2a |
North Point |
Electric Centre
(Replacement of RTN2) |
RTN3 |
North Point |
Pok Leung Kuk Yu |
RTN4 |
Tin Hau |
|
* Real time noise monitoring results and graphical presentation during
night time period are for information only.
*Real-time noise monitoring results and graphical presentation for RTN3
during restricted hours are for information only as no night classes were
conducted at the educational institute.
Reporting month of March 2015
4.2.3.
Limit level exceedances were recorded at RTN1-FEHD Hong Kong Transport
Section Whitfield Depot on 27 March 2015 during daytime in the reporting month.
After checking with Contractor of HY/2009/19, concreting and bitumen laying
works was conducted at the concerned location during the recorded period while
breaking works at pavement adjacent to the monitoring station for utilities
works by non-CWB project Contractor was observed on the same date. As such, the
exceedances were considered to be non-Project related and contributed by nearby
non-CWB construction works.
4.2.4.
Limit level exceedances were recorded at
RTN2a-Electric Centre during daytime on 28 February 2015 and 3, 4, 5, 6, 7, 9
and 26 March 2015 during day time in the reporting month. After checking with
Contractor of HY/2009/19, trench excavation and sheet piling works were
undertaken by the Contractor and noise mitigation measures including erection
of noise blanket was implemented by the Contractor while breaking works and
excavation works was observed across March 2015 at the construction site
located next to the concerned monitoring station. In view of the above, the
exceedances were considered to be non-Project related and contributed by nearby
non-CWB construction site works.
4.2.5.
No limit level exceedance was recorded at
RTN3-Yue Lee Mo Fan Memorial School during daytime in the reporting month.
4.2.6.
No Limit level exceedance was recorded at
RTN4-Causeway Bay Community Centre in the reporting month.
Reporting month of April
2015
4.2.7.
No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport Section
Whitfield Depot in the reporting month.
4.2.8.
Limit level exceedances were recorded at
RTN2a-Electric Centre during daytime on 31 March, 2, 8, 9, 10 and 11 April 2015
during day time in the reporting month. After checking with Contractor of
HY/2009/19, sheet-pile driving works were conducted on 31 March 2015 and 2
April 2015 while sheet-pile extraction works were conducted on 8, 9, 10 and 11
April 2015. Noise mitigation measures including erection of noise blanket was
implemented by the Contractor while breaking works and excavation works were
observed across the concerned period at the construction site located next to the
monitoring station. In view of the above, the exceedances were considered to be
non-Project related and contributed by nearby non-CWB construction site works.
4.2.9.
Limit level exceedances were recorded at
RTN3-Yue Lee Mo Fan Memorial School during daytime on 31 March, 1, 8 and 24
April 2015 in the reporting month. After checking with Contractor of HY/2009/19,
median barrier cutting works was conducted at Pier F13 on 31 March 2015 and on 1
April 2015. In view of the exceedances was non-continuous and the concerned construction works was continued on
26 March 2015 and 27 March 2015 at location opposite to the monitoring location
while no exceedance was identified, the exceedances were considered to be not
related to the Project and contributed by nearby traffic. On 8 April 2015, manual
cleaning works was conducted and the exceedances were considered to be not
related to the Project and contributed by nearby traffic. On 24 April 2015,
coring was conducted at Pier F6 to F7, in view of the exceedances was non-continuous
and the concerned construction works was continued on the same monitoring date opposite
to the monitoring location at Pier F7 to F9 progressively towards the
monitoring station while no exceedance was identified, the exceedances were
considered to be not related to the Project and contributed by nearby traffic.
4.2.10.
No limit level exceedance was recorded at
RTN4-Causeway Bay Community Centre in the reporting month.
Reporting month
of May 2015
4.2.11.
No limit level exceedance
was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the
reporting month.
4.2.12.
Limit level exceedances were recorded at
RTN2a-Electric Centre during daytime on19 May 2015 during day time in the
reporting month. After checking with Contractor of HY/2009/19, U beam lifting works
with trailers and crawler cranes was conducted while breaking works and
excavation works was noted on-going at the construction site located next to
the monitoring station. In view of the above, the exceedances were considered
to be non-Project related and contributed by nearby non-CWB construction site
works.
4.2.13.
Limit level exceedances were recorded at
RTN3-Yue Lee Mo Fan Memorial School during daytime on 30 April, 8 and 12 May
2015 in the reporting month. After checking with Contractor of HY/2009/19, railing
installation and manual fixing was conducted on 30 April 2015 with no major
noise emanating works and the exceedances was non-continuous and considered to
be contributed by nearby IEC traffic and not related to Project.
On 8 May 2015, parapet
cutting works with saw cut was conducted across the exceedance period with
significant noise level elevation while ad hoc inspection on the same date
observed that no mitigation measures was provided for the saw cutting
works. As such, the exceedances was considered
to be related to the Project works while the concerned work was completed on
the same date. In view of the exceedances, the Contractor of HY/2009/19 has
committed the implementation of the noise barrier at sides and front for
parapet cutting works around the concerned location and no further exceedance
was recorded on the next monitoring day.
On 12 May 2015,
after checking with Contractor of HY/2009/19, IEC bridge deck longitudinal
works cutting was conducted during the monitoring period and temporary noise
barrier was provided for the concerned works.
In view of the exceedances was non-continuous and while the concerned
construction works was in continuous operation with implementation of the noise
mitigation measures while , the exceedances were considered to be not related
to the Project and contributed by nearby traffic.
4.2.14.
No limit level exceedance was recorded at
RTN4-Causeway Bay Community Centre in the reporting month.
4.2.15.
Real
time noise monitoring results measured in this reporting quarter are reviewed
and summarized. Details of real time noise monitoring results and graphical
presentation can be referred to Appendix
4.2
4.3.1 Due to extension of site boundary by
contractor of HY/2009/19, location of air monitoring station CMA1b – Oil Street
Community Liaison Centre has been finely adjusted on 21
Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
4.3.2
Air monitoring for the Central Interchange
works under contract no. HY/2009/18 was commenced on 21 April 2011. The
proposed division of air monitoring stations are summarized in Table 4.6
below.
Table 4.8
Air
Monitoring Stations for Contract no. HY/2009/18
Station |
Description |
MA1e |
International Finance Centre (Eastern End of Podium) |
MA1w |
International Finance Centre (Western End of Podium) |
4.3.3
No action or limit level exceedance was
recorded in the reporting period.
4.3.4
Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 4.3.
Contract no. HK/2009/01 - Wan Chai Development Phase
II - Central - Wan Chai Bypass at
4.3.5
The
commencement of construction works for Contract no. HK/2009/01 under
FEP-02/364/2009 is on 25 August 2011. The
proposed division of air monitoring stations are summarized in Table
4.7 below.
Table 4.9
Air
Monitoring Station for Contract no. HK/2009/01
Station |
Description |
CMA5b |
Pedestrian Plaza |
4.3.6
No action or limit level exceedance was
recorded in the reporting period.
4.3.7 Air quality monitoring results measured in this
reporting period are reviewed and summarized.
Details of air monitoring results and graphical presentation can be
referred in Appendix 4.3.
Contract no. HK/2009/02 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
4.3.8 The commencement of construction works for
HK/2009/02 under FEP-01/364/2009 is on 26
Table
4.10
Air
Monitoring Station for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
4.3.9
No action or limit level exceedance was
recorded in the reporting period.
4.3.10 Air quality monitoring results measured in this
reporting period are reviewed and summarized.
Details of air monitoring results and graphical presentation can be
referred in Appendix 4.3.
Contract no.
HY/2009/15 - Central-Wanchai Bypass – Tunnel (
4.3.11
The
commencement of construction works for Contract no. HY/2009/15 under
FEP-06/364/2009/A was on 13 July 2011. The proposed division of air
monitoring stations are summarized in Table 4.9
below.
Table 4.11 Air Monitoring Station
for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB site office at Wanchai
Waterfront Promenade |
4.3.12
No action or limit level exceedance was
recorded in the reporting period.
4.3.13 Air quality monitoring results measured
in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 4.3.
Contract no.
HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under FEP-07/364/2009/A
4.3.14 Air monitoring for the tunnel works was commenced
on 26
Table
4.12
Air Monitoring
Stations
for Contract no. HY/2009/19
Station |
Description |
CMA1b |
Oil Street Site Office |
CMA2a |
|
4.3.15
No action or limit level exceedance was recorded in the reporting
period.
4.3.16
No action or limit level exceedance was
recorded in the reporting period.
4.3.17
Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of air monitoring results and graphical presentation can be
referred in Appendix 4.3.
Contract no. HK/2012/08- Wan Chai Development Phase
II – Central-Wan Chai Bypass at Wan Chai West
4.3.18
The commencement of construction works for
Contract no. HK/2012/08 under FEP-09/364/2009/C was on May 2014. Air quality
monitoring was commenced on 14 July 2011. The proposed division of air monitoring stations are summarized in Table
5.13 below.
Table
4.13 Air Monitoring Station for Contract
no. HK/2012/08
Station |
Description |
CMA5b |
Pedestrian Plaza |
4.3.19
No action or limit level exceedance was
recorded in the reporting period.
4.3.20
Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of air monitoring results
and graphical presentation can be referred in Appendix 4.3.
Contract no. HY/2010/08 –
Central-Wanchai Bypass –Wanchai Bypass Tunnel (Slip Raod 8 Section) under FEP-09/364/2009/B
4.3.21
The commencement of construction works for
Contract no. HY/2010/08 under FEP-09/364/2009/B was on July 2014. Air quality
monitoring was commenced on 14 July 2011. The proposed division of air monitoring stations are summarized in Table
5.14 below.
Table
4.14 Air Monitoring Station for Contract
no. HY/2010/08
Station |
Description |
CMA3a |
CWB PRE Site Office |
4.3.22
No action or limit level exceedance was
recorded in the reporting period.
4.3.23 Air quality monitoring results measured
in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 4.3.
Contract no.
HY/2011/08 – Central - Wan Chai Bypass (CWB) – Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning
4.3.24
Air monitoring for the Central Interchange
works under contract no. HY/2011/08 was commenced on 21 April 2011. The
proposed division of air monitoring stations are summarized in Table 5.15
below.
Table
4.15
Air Monitoring Stations for Contract
no. HY/2011/08
Station |
Description |
MA1e |
International Finance Centre (Eastern End of
Podium) |
MA1w |
International Finance Centre (Western End of
Podium) |
4.3.25
No action or limit level exceedance was
recorded in the reporting period.
4.3.26 Air quality monitoring results measured
in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 4.3.
Contract no. HK/2009/01 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at
4.4.1.
Inert
and non-inert C&D waste was disposed of in this reporting period. Details
of the waste flow table are summarized in Table 4.11.
Table
4.16 Details of Waste Disposal for Contract no. HK/2009/01
Inert C&D materials
disposed |
8632.21 |
131853.43 |
TKO137, TM38 |
Inert C&D materials
recycled |
17940.41 |
69222.03 |
N/A |
Non-inert C&D
materials disposed |
272.28 |
2371.37 |
SENT Landfill |
Non-inert C&D
materials recycled |
74000 |
546179 |
N/A |
Chemical waste disposed |
30 |
10380 |
Kwun Kee (Chemical Waste Collector) |
Marine Sediment (Type 1 – Open Sea Disposal
(Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3 |
6344 |
9194 |
East
of Cha Chau South
Brothers |
Contract no. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
4.4.2.
Inert and non-inert C&D waste were disposed of in this reporting
period. Details of the waste flow table are summarized in Table 4.12.
Table 4.17 Details of Waste Disposal for Contract no.
HK/2009/02
Inert C&D materials
disposed |
52968.29 |
343568.412 |
TKO137, TM 38 |
Inert C&D materials
recycled |
Nil |
18161 |
WCR2 |
Non-inert C&D
materials disposed |
87.33 |
1967.757 |
SENT Landfill |
Non-inert C&D
materials recycled |
Nil |
N/A |
N/A |
Chemical waste disposed |
1224 |
18253 |
N/A |
Remarks:
The cumulative amount Non-inert C&D material recycled has been updated in
the reporting
quarter.
Contract no. HY/2009/18 - Central - Wan Chai Bypass
(CWB) – Central Interchange under FEP-05/364/2009/A
4.4.3.
Inert and non-inert C&D waste was disposed of in this reporting
period. Details of the waste flow table are summarized in Table 4.13.
Table 4.18 Details of Waste Disposal for
Contract no. HY/2009/18
Inert C&D materials
disposed |
2849.051 |
122860.441 |
T.K.O. 137 |
Inert C&D materials
recycled |
50 |
58784.05 |
N/A |
Non-inert C&D
materials disposed |
119.164 |
3073.067 |
SENT Landfill |
Non-inert C&D materials recycled (tonnes) |
30.54 |
837.07 |
N/A |
Chemical waste disposed |
Nil |
4440 |
N/A |
Contract no. HY/2009/15 - Central-Wanchai Bypass –
Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
4.4.4.
Inert and non-inert C&D waste was disposed of in this reporting
period. Details of the waste flow table are summarized in Table 4.14.
Table 4.19 Details of Waste Disposal for
Contract no. HY/2009/15
Inert C&D materials
disposed |
16455.5 Nil |
552162.97 243352.01 |
Tuen Mun Area 38 TKO137 FB |
Inert C&D materials
recycled |
Nil |
304860.3 |
HY/2009/11 ex-PCWA TS4 |
Non-inert C&D
materials disposed |
117.27 |
2777.93 |
SENT Landfill |
Non-inert C&D
materials recycled |
Nil |
5496446.2 |
Xun Xiang Metal ware Skylight Recycle (paper) |
Chemical waste disposed |
Nil |
22755 |
Dunwell Group |
Marine Sediment (Type1-Open Sea Disposal (Dedicate
Sites) &Type 2 – Confined Marine Disposal), m3 |
Nil |
5684 |
South of the Brothers |
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/A
4.4.5.
Inert C&D materials was recycled non-inert C&D waste was disposed of in this reporting period. Details
of the waste flow table are summarized in Table 4.15.
Table 4.20 Details of Waste Disposal for
Contract no. HY/2009/19
Inert C&D materials
disposed |
3675.68 |
604556.83 |
N/A |
Nil |
81822.39 |
N/A |
|
Non-inert C&D
materials disposed |
651.88 |
2988.31 |
SENT Landfill |
Non-inert C&D materials
recycled |
28.3 |
439.73 |
N/A |
Chemical waste disposed |
0.52 |
9.36 |
N/A |
Marine Sediment (Tunnel) (Type 1- Open Sea
Disposal), m3 |
Nil |
20556 |
South of Cheung Chau |
Marine Sediment (Tunnel) (Type 1- Open Sea
Disposal (Dedicated Sites) & Type 2 – Confined Marine Disposal), m3 |
Nil |
30751 |
East
of Sha Chau |
Contract no. HK/2012/08 Wan Chai Development
Phase II - Central-Wan Chai Bypass at Wan Chai West under FEP-09/364/2009/B
4.4.6.
No inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 4.16.
Table 4.21 Details of Waste Disposal for Contract no. HK/2012/08
Waste
Type* |
Quantity
this quarter, m3 |
Cumulative-to-Date,
m3 |
Disposal
/ Dumping Grounds |
Inert C&D materials disposed |
29498 |
63497 |
N/A |
Inert C&D materials recycled |
25079 |
27438 |
N/A |
Non-inert C&D materials disposed |
115 |
515 |
N/A |
Non-inert C&D materials recycled |
NIL |
NIL |
N/A |
Chemical waste disposed |
NIL |
NIL |
N/A |
Contract no. HY/2010/08
Central – Wan Chai Bypass (CWB) –
Tunnel (Slip Road 8) under FEP-10/364/2009/B
4.4.7.
No inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 4.18.
Table 4.22 Details
of Waste Disposal for Contract no. HY/2010/08
Waste Type* |
Quantity this quarter, m3 |
Cumulative-to-Date, m3 |
Disposal / Dumping Grounds |
Inert
C&D materials disposed |
3526 Nil |
21607.4 363 |
TM 38 TKO area 137 |
Inert C&D materials recycled |
Nil |
Nil |
Nil |
Non-inert C&D materials disposed |
80 |
784 |
SENT |
Non-inert C&D materials recycled |
Nil |
Nil |
Nil |
Chemical waste disposed |
300 |
835 |
Nil |
Contract no. HY/2011/08
Central –Central - Wan Chai Bypass
(CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning under FEP-11/364/2009B
4.4.8.
No inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.23.
Table
4.23 Details
of Waste Disposal for Contract no. HY/2011/08
Waste Type* |
Quantity this quarter, m3 |
Cumulative-to-Date, m3 |
Disposal / Dumping Grounds |
Inert
C&D materials disposed |
Nil |
14.4 |
Nil |
Inert
C&D materials recycled |
Nil |
Nil |
Nil |
Non-inert
C&D materials disposed |
64.878 |
95.455 |
Nil |
Non-inert
C&D materials recycled |
2.04 |
5.69 |
Nil |
Chemical
waste disposed(kg) |
3800 |
3800 |
Nil |
Remarks: The cumulative amount of non-inert C&D material recycled
has been updated in the
reporting quarter.
5.0.1. The Event Action Plan for construction noise and air
quality are presented in Appendix 5.1.
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central
Interchange under FEP-05/364/2009/A
5.1.1.
No limit or action level exceedance was
recorded in this reporting quarter.
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at
5.1.2.
No limit or action level exceedance was
recorded in this reporting quarter.
Contract no. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel)
5.1.3.
No limit or action level exceedance was
recorded in this reporting quarter.
Contract no. HY/2009/15 - Central-Wanchai Bypass –
Tunnel (
5.1.4. No limit
or action level exceedance was recorded in this reporting quarter.
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/A
4.1.23.
Three limit level exceedances at M6 – HK Baptist Church Henrietta
Secondary School were recorded on 21 April
2015, 5 and 27 May 2015 in this reporting quarter.
4.1.24.
Traffic noise was observed during monitoring on 21 April 2015 and it was considered as the major
noise contribution. As such, the limit level exceedances were concluded as
non-project related.
4.1.25.
IEC bridge deck saw cutting works under HY/2009/19 was observed during
monitoring on 5 May 2015 and no noise mitigation measures was provided
for the concerned works. The saw cutting works was considered as the major
noise contribution and the limit level exceedance was concluded as Project
related. Mitigation measures including the use of movable noise barrier for the
saw cutting machine was committed by the Contractor as the CWB RSS confirmed
the concerned construction works at the concerned section was temporarily
completed on 5 May 2015 and tentatively to be resumed in June 2015. Additional
noise monitoring was conducted and no further exceedance was identified.
4.1.26.
IEC bridge deck saw cutting works under HY/2009/19 was observed during
monitoring on 27 May 2015 and single noise barrier was provided to the
saw cut machine. The mitigation measures was considered inadequate based on the
Contractor submitted rectification proposal and the noise level measured. The
saw cutting works was considered as the major noise contribution and the limit
level exceedance was concluded as Project related. Mitigation measures
including provision of additional movable noise barriers for the saw cutting
machine was implemented by the Contractor and additional noise monitoring was
conducted and no further exceedance was identified.
4.1.27.
No action or limit level exceedance was
recorded in March 2015.
Contract no. HY/2010/08 – Central-Wanchai Bypass –
Tunnel (Slip Road 8 Section) under FEP-10/364/2009/B
4.1.28.
No limit or action level exceedance was recorded in the reporting
quarter
Contract no. HY/2011/08 Central –Central - Wan Chai
Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with
Tunnel Commissioning under FEP-11/364/2009B
4.1.29.
No limit or action level exceedance was recorded in the reporting
quarter.
5.2.1.
No
exceedance was recorded in the reporting quarter.
Contract no.
HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
5.2.2.
No
exceedance was recorded in the reporting quarter.
Contract nos.
HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan
Chai East (CWB Tunnel)
5.2.3.
No
exceedance was recorded in the reporting quarter.
Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (
5.2.4.
No
exceedance was recorded in the reporting quarter.
Contract no.
HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under FEP-07/364/2009/A
5.2.5. No exceedance was recorded in the reporting quarter.
Contract
no. HK/2012/08 Wan Chai Development Phase II - Central-Wan Chai Bypass at Wan
Chai West under FEP-09/364/2009/B
5.2.6.
No
exceedance was recorded in the reporting quarter.
Contract
no. HY/2010/08 – Central-Wanchai Bypass – Tunnel (Slip Raod 8 Section) under
FEP-10/364/2009/B
5.2.1
No exceedance was recorded in the reporting
quarter
Contract no. HY/2011/08
Central –Central - Wan Chai Bypass
(CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning under FEP-11/364/2009B
5.2.2
No exceedance was recorded in the reporting
quarter.
Contract no. HY/2009/19 - Central - Wanchai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/A
Reporting month of March 2015
5.3.1.
Limit level exceedances
were recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot on 27 March
2015 during daytime in the reporting month. After checking with Contractor of
HY/2009/19, concreting and bitumen laying works was conducted at the concerned
location during the recorded period while breaking works at pavement adjacent
to the monitoring station for utilities works by non-CWB project Contractor was
observed on the same date. As such, the exceedances were considered to be
non-Project related and contributed by nearby non-CWB construction works.
5.3.2.
Limit level exceedances were recorded at
RTN2a-Electric Centre during daytime on 28 February 2015 and 3, 4, 5, 6, 7, 9
and 26 March 2015 during day time in the reporting month. After checking with
Contractor of HY/2009/19, trench excavation and sheet piling works were
undertaken by the Contractor and noise mitigation measures including erection
of noise blanket was implemented by the Contractor while breaking works and
excavation works was observed across March 2015 at the construction site
located next to the concerned monitoring station. In view of the above, the
exceedances were considered to be non-Project related and contributed by nearby
non-CWB construction site works.
5.3.3.
No limit level exceedance was recorded at
RTN3-Yue Lee Mo Fan Memorial School during daytime in the reporting month.
5.3.4.
No Limit level exceedance was recorded at
RTN4-Causeway Bay Community Centre in the reporting month.
Reporting month of April
2015
5.3.5.
No limit level exceedance
was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the
reporting month.
5.3.6.
Limit level exceedances were recorded at
RTN2a-Electric Centre during daytime on 31 March, 2, 8, 9, 10 and 11 April 2015
during day time in the reporting month. After checking with Contractor of
HY/2009/19, sheet-pile driving works were conducted on 31 March 2015 and 2
April 2015 while sheet-pile extraction works were conducted on 8, 9, 10 and 11
April 2015. Noise mitigation measures including erection of noise blanket was
implemented by the Contractor while breaking works and excavation works were
observed across the concerned period at the construction site located next to
the monitoring station. In view of the above, the exceedances were considered
to be non-Project related and contributed by nearby non-CWB construction site
works.
5.3.7.
Limit level exceedances were recorded at
RTN3-Yue Lee Mo Fan Memorial School during daytime on 31 March, 1, 8 and 24
April 2015 in the reporting month. After checking with Contractor of HY/2009/19,
median barrier cutting works was conducted at Pier F13 on 31 March 2015 and on 1
April 2015. In view of the exceedances was non-continuous and the concerned construction works was continued on
26 March 2015 and 27 March 2015 at location opposite to the monitoring location
while no exceedance was identified, the exceedances were considered to be not
related to the Project and contributed by nearby traffic. On 8 April 2015, manual
cleaning works was conducted and the exceedances were considered to be not
related to the Project and contributed by nearby traffic. On 24 April 2015,
coring was conducted at Pier F6 to F7, in view of the exceedances was
non-continuous and the concerned construction works was continued on the same
monitoring date opposite to the monitoring location at Pier F7 to F9
progressively towards the monitoring station while no exceedance was
identified, the exceedances were considered to be not related to the Project
and contributed by nearby traffic.
5.3.8.
No limit level exceedance was recorded at
RTN4-Causeway Bay Community Centre in the reporting month.
Reporting month of May 2015
5.3.9.
No limit level exceedance
was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the
reporting month.
5.3.10.
Limit level exceedances were recorded at
RTN2a-Electric Centre during daytime on19 May 2015 during day time in the
reporting month. After checking with Contractor of HY/2009/19, U beam lifting
works with trailers and crawler cranes was conducted while breaking works and
excavation works was noted on-going at the construction site located next to
the monitoring station. In view of the above, the exceedances were considered
to be non-Project related and contributed by nearby non-CWB construction site
works.
5.3.11.
Limit level exceedances were recorded at
RTN3-Yue Lee Mo Fan Memorial School during daytime on 30 April, 8 and 12 May
2015 in the reporting month. After checking with Contractor of HY/2009/19, railing
installation and manual fixing was conducted on 30 April 2015 with no major
noise emanating works and the exceedances was non-continuous and considered to
be contributed by nearby IEC traffic and not related to Project.
On 8 May 2015, parapet cutting works with saw
cut was conducted across the exceedance period with significant noise level
elevation while ad hoc inspection on the same date observed that no mitigation
measures was provided for the saw cutting works. As such, the exceedances was considered to be
related to the Project works while the concerned work was completed on the same
date. In view of the exceedances, the Contractor of HY/2009/19 has committed
the implementation of the noise barrier at sides and front for parapet cutting
works around the concerned location and no further exceedance was recorded on
the next monitoring day.
On 12 May 2015, after checking with
Contractor of HY/2009/19, IEC bridge deck longitudinal works cutting was
conducted during the monitoring period and temporary noise barrier was provided
for the concerned works. In view of the
exceedances was non-continuous and while the concerned construction works was
in continuous operation with implementation of the noise mitigation measures
while , the exceedances were considered to be not related to the Project and
contributed by nearby traffic.
5.3.12.
No limit level exceedance was recorded at
RTN4-Causeway Bay Community Centre in the reporting month.
5.4.1. There was no non-compliance from the site audits in
the reporting period. During environmental site inspections conducted during
the reporting quarter, minor deficiencies were noted. However, the Contractor rectified all
deficiencies after receipt of notification.
5.5.1 There was no particular action taken
since no project-related non-compliance was recorded from the site audits in
the reporting period.
5.5.2
Three project-related non-compliances from
noise monitoring were recorded in the reporting month.
5.6.1
There was no particular action taken since no
non-compliance was recorded from the site audits in the reporting period.
5.6.2
One limit level exceedance was recorded on 5
May 2015 at noise monitoring station M6- HK Baptist Church Henrietta Secondary
School and was considered in relation to IEC bridge deck saw cutting works
under HY/2009/19.Following the Event and Action Plan, additional noise
monitoring was conducted and a proposal for remediation measures was submitted
by the Contractor. Rectification measures including provision of noise barrier
for saw cutting works was committed by the Contractor at the concerned
construction works was completed on the same date as confirmed by RSS and no
further exceedances was recorded during additional monitoring.
5.6.3
One limit level exceedance was recorded on 27
May 2015 at noise monitoring station M6- HK Baptist Church Henrietta Secondary
School and was considered in relation to IEC bridge deck saw cutting works
under HY/2009/19. Following the Event and Action Plan, additional noise
monitoring was conducted and a proposal for remediation measures was submitted
by the Contractor. Rectification measures including provision of additional noise
barrier for saw cutting works was implemented by the Contractor and no further
exceedance was recorded during additional monitoring.
5.6.4
One limit level exceedance was recorded on 08
May 2015 at real-time noise monitoring station RTN3- YLMF memorial School and
was considered in relation to IEC bridge deck parapet cutting saw cutting works
under HY/2009/19. Following the Event and Action Plan, a proposal for
remediation measures was submitted by the Contractor. Rectification measures
including provision of noise barrier at the sides and front for parapet cutting
works was implemented by the Contractor as the concerned construction works was
completed on the same date and no further exceedance was recorded during
subsequent monitoring.
6.0.1.
Four environmental complaints were received in the reporting quarter.
6.0.2.
First public complaint regarding construction dust impact referred by
EPD was received by ET on 09 April 2015 (EPD Ref.:H05/RS/00008074-15 dated 9
April 2015). The complainant reported that:
6.0.3.
Construction dust was generated from lorries transporting out of the
construction via site exit near Expo Drive Central without wheel washing at the
morning of 7 April 2015. Lorries were also found transporting out of the
construction site via gates V2 and V8 without wheel washing and causing dust
nuisance at about 10:30 hours on 9 April 2015.
6.0.4.
ET confirmed with the Resident Site Staff that on 7 April 2015, major
vehicle movements included oil tanker passing at Gate V2 at Expo Drive East and
dump truck passing at Gate V8 at Expo Drive Central under Contract HK/2009/01. On
9 April 2015. major vehicle movements include oil tanker, crane lorry and dump
truck passing at Gate V2 at Expo Drive East and dump truck at Gate V8 at Expo
Drive Central under Contract HK/2009/01.
6.0.5.
Mitigation measures adopted by the Contractor of HK/2009/01 at the above
locations include water hose was provided for wheel washing at Gate V2 and Gate
V8, concrete paving at site exit, dump truck fitted with mechanic cover and
cleaned before leaving construction site and regular street washing at Expo
Drive Central.
6.0.6.
According to the relevant site records under Contract HK/2009/01, on 7
April 2015, major vehicle movements included oil tanker passing at Gate V2 at
Expo Drive East and dump truck passing at Gate V8 at Expo Drive Central under
Contract HK/2009/01 while on 9 April 2015 major vehicle movements include oil
tanker, crane lorry and dump truck passing at Gate V2 at Expo Drive East and
dump truck at Gate V8 at Expo Drive Central under Contract HK/2009/01.
6.0.7.
At the above locations, mitigation measures including water hose for
wheel washing at Gate V2 and Gate V8; concrete paving at site exit; dump truck
fitted with mechanic cover and cleaned before leaving construction site and
regular street washing at Expo Drive Central were generally adopted by the
Contractor of HK/2009/01.
6.0.8.
In view of the public concern on the complaint date, the Contractor of
HK/2009/01 was advised to conduct cleaning at the concerned site exit point and
the section of public road adjoining the site exit to clear any residue grit
and silt deposit to avoid further dust impact.
6.0.9.
Follow up inspection was conducted on 16 April 2015 during weekly
environmental inspection and mitigation measures including water spraying for
dusty haul road and provision of wheel washing were in place. The construction
site exit was observed clear from residue silt / grit at the concerned
location.
6.0.10.
In view of the public concern, the contractor was advised to conduct
training to the construction site workers to enhance the effectiveness of wheel
washing and to ensure proper wheel washing is provided for dump truck and other
vehicle prior to leaving the construction site to avoid generating any dust
nuisance.
6.0.11.
Second public complaint regarding construction noise impact referred by
EPD was received by ET on 09 April 2015 (EPD Ref.:H05/RS/00007861-15 dated 9
April 2015). The complainant reported that construction noise was emanated from
the construction site at Convention Avenue near Renaissance Harbor View Hotel
during the period of Easter Holiday, including April 3 at about 13:00 hours.
6.0.12.
ET confirmed with the Resident Site Staff that from 3 April 2015 to 7
April 2015, from 08:00 hours to 18:00 hours, and at about 13:00 hours on 3
April 2015 at area CWB Tunnel Stage 3, backfilling works was conducted under
HK/2009/01. Either 1 no. of dump truck or 1. no. of excavator was operated on
site at each given time during the concerned period.
6.0.13.
According to the relevant site records under Contract HK/2009/01, from
across 08:00hrs to 18:00hrs during the period from 3 April 2015 to 7 April
2015, backfilling works was conducted under Contract HK/2009/01 at CWB Tunnel
Stage 3. Either 1 no. of dump truck and 1 no. of excavator was operated on site
at each given time during the concerned period and the relevant Construction
Noise Permit GW-RS0104-15 for the works was in place and the same construction
activity was undertaken at around 13:00hrs on 3 April 2015.
6.0.14.
No other concurrent construction activity was undertaken at the
concerned location during the concerned period under Contract HK/2009/01. The
construction activity conducted under Contract HK/2009/01 during the concerned
period was in compliance with the statutory requirement.
6.0.15.
Nevertheless, in view of the concern regarding the noise nuisance raised
by the public at the concerned location, it is considered desirable for the
Contractor of HK/2009/01 to review the truck unloading procedures of the
specific construction task to minimize potential noise emanated during the
course for work.
6.0.16.
Third public complaint regarding visual impact received by the RSS was
referred to the ET on 15 April 2015 (ICC Case Ref.: 2-885677297 dated 13 April
2015). The complainant reported that:
“I live in a building next to Gloucester
Road in Causeway Bay. Recently, I am suffering from unnecessary light source
from the construction site. The banners of the construction companies are
always illuminated with very bright lights.”
6.0.17.
ET confirmed with the Resident Site Staff that the concerned lighting
for the banners was maintained under Contract HY/2010/08.
6.0.18.
The concerned lighting for the banners was maintained under Contract
HY/2010/08 and the concerned lighting was subsequently switched off at all
times since 13 April 2015 to alleviate the lighting nuisance caused to the
surroundings.
6.0.19.
Fourth public complaint regarding construction noise impact referred by
EPD was received by ET on 23 April 2015 (EPD Ref.:H05/RS/00009456-15 dated 23
April 2015). The complainant reported that construction noise emanated from the
road work at Fleming Road and Convention Avenue near Renaissance Harbour View
Hotel almost every night recently causing nuisance.
6.0.20.
ET confirmed with the Resident Site Staff that from 21:00hrs on 20 April
2015 to 06:00hrs on 21 April 2015 and from 21:00hrs on 21 April 2015 to
06:00hrs on 22 April 2015, cooling main connection works was undertaken by the
Contractor of Contract HK/2009/01 at the concerned location. Total 1 no. of
crane lorry and 1 no. of excavator were in operation.
6.0.21.
According to the relevant site records under Contract HK/2009/01, from
21:00hrs on 20 April 2015 to 06:00hrs on 21 April 2015 and from 21:00hrs on 21
April 2015 to 06:00hrs on 22 April 2015, cooling main connection works was
undertaken by the Contractor of Contract HK/2009/01 at the concerned location.
Total 1 no. of crane lorry and 1 no. of excavator were in operation during the
concerned period and the relevant Construction Noise Permit GW-RS0269-15 was
confirmed in place. The construction activity conducted under Contract
HK/2009/01 during the concerned period was in compliance with the statutory
requirement.
6.0.22.
In view of the potential noise nuisance, a notice to affected parties
was issued by the Contractor of Contract HK/2009/01 to the nearby residents
including Renaissance Harbour View Hotel on 17 April 2015. Besides,
construction works undertaken by other parties at the concerned location was
observed at the concerned period.
6.0.23.
The details of
cumulative complaint log and summary of complaints are presented in Appendix
6.1.
6.0.24.
No notification of summons or
prosecution was received in the reporting period. Cumulative statistic on complaints and successful
prosecutions are summarized in Table 6.1 and Table 6.2 respectively.
Table
6.1 Cumulative Statistics on Complaints
Reporting Period |
No. of Complaints |
Commencement of Works up to last
reporting quarter |
38 |
March 2015 – May 2015 |
4 |
Project-to-Date |
42 |
Table 6.2 Cumulative Statistics on Successful
Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this quarter (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
7.0.1.
According to Condition 3.4 of the
EP-364/2009/B, this section addresses the relevant cumulative construction
impact due to the concurrent activities of the current projects including the
Central Reclamation Phase III (CRIII), Wan Chai Development Phase II (WDII),
Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) and
Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB
Tunnel).
7.0.2.
According to the Final
EM&A Report of Central Reclamation Phase III (CRIII) for Contract HK 12/02,
the major construction activities were completed by end of January 2014 and no
construction activities were undertaken thereafter and the water
quality monitoring was completed in October 2011. As such, it is considered that there were no
cumulative construction impact due to the concurrent activities of the current
projects with the Central Reclamation Phase III (CRIII) undertaken by
contractor HK12/02 in the reporting period.
7.0.3.
According to the construction programme of
Central-Wanchai Bypass at Wanchai West at the Central Reclamation Phase III
area, removal of L-shape wall and installation of caisson seawall were
performed in May 2015 reporting month. As no project
related exceedance were recorded during the reporting period, cumulative
construction impact due to the concurrent activities of the current projects
with the Central Reclamation Phase III (CRIII) was considered as insignificant.
7.0.4.
According to the construction programme of
Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern
Corridor Link projects, the major construction activities under Wan Chai
Development Phase II were marine works at HKCEC area, tunnel works
and foundation works at Wan Chai East and temporary reclamation at Wan Chai
West. The major construction activities under Central-Wan Chai
Bypass and Island Eastern Corridor Link Projects were bridge construction and
road works at Central Interchange, land based bored pilling works and ELS works
at Victoria Park, D- wall construction and ELS at TS3, IEC demolition and
tunnel works at North Point area in the reporting month.
7.0.5.
No significant air impact from construction
activities was anticipated in the reporting month. Besides, no project related
exceedance was recorded during the air and noise environmental monitoring
events in the reporting month. Thus, it is evaluated that the cumulative
construction impact from the concurrent projects including Central Reclamation
Phase III (CRIII), Wan Chai Development Phase II (WDII), Central-WanChai Bypass
(CWB), Island Eastern Corridor Link projects (IECL) was insignificant.
8.0.1.
The
EM&A programme was carried out in accordance with the EM&A Manual
requirements, minor alterations to the programme proposed were made in response
to changing circumstances.
Air quality
monitoring
8.0.2.
No action or limit exceedance was recorded in the
reporting quarter.
Noise
monitoring
8.0.3.
No action or limit exceedance was recorded in the
reporting quarter.
Real
time noise monitoring
Reporting month of March 2015
8.0.4.
Limit level exceedances were recorded at RTN1-FEHD Hong Kong Transport
Section Whitfield Depot on 27 March 2015 during daytime in the reporting month.
After checking with Contractor of HY/2009/19, concreting and bitumen laying
works was conducted at the concerned location during the recorded period while
breaking works at pavement adjacent to the monitoring station for utilities
works by non-CWB project Contractor was observed on the same date. As such, the
exceedances were considered to be non-Project related and contributed by nearby
non-CWB construction works.
8.0.5.
Limit level exceedances were recorded at RTN2a-Electric Centre during
daytime on 28 February 2015 and 3, 4, 5, 6, 7, 9 and 26 March 2015 during day
time in the reporting month. After checking with Contractor of HY/2009/19, trench
excavation and sheet piling works were undertaken by the Contractor and noise
mitigation measures including erection of noise blanket was implemented by the
Contractor while breaking works and excavation works was observed across March
2015 at the construction site located next to the concerned monitoring station.
In view of the above, the exceedances were considered to be non-Project related
and contributed by nearby non-CWB construction site works.
8.0.6.
No limit level exceedance was recorded at RTN3-Yue Lee Mo Fan Memorial
School during daytime in the reporting month.
8.0.7.
No Limit level exceedance was recorded at RTN4-Causeway Bay Community
Centre in the reporting month.
Reporting month of April
2015
8.0.8.
No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport Section
Whitfield Depot in the reporting month.
8.0.9.
Limit level exceedances were recorded at
RTN2a-Electric Centre during daytime on 31 March, 2, 8, 9, 10 and 11 April 2015
during day time in the reporting month. After checking with Contractor of
HY/2009/19, sheet-pile driving works were conducted on 31 March 2015 and 2
April 2015 while sheet-pile extraction works were conducted on 8, 9, 10 and 11
April 2015. Noise mitigation measures including erection of noise blanket was
implemented by the Contractor while breaking works and excavation works were
observed across the concerned period at the construction site located next to
the monitoring station. In view of the above, the exceedances were considered
to be non-Project related and contributed by nearby non-CWB construction site
works.
8.0.10.
Limit level exceedances were recorded at
RTN3-Yue Lee Mo Fan Memorial School during daytime on 31 March, 1, 8 and 24
April 2015 in the reporting month. After checking with Contractor of HY/2009/19,
median barrier cutting works was conducted at Pier F13 on 31 March 2015 and on 1
April 2015. In view of the exceedances was non-continuous and the concerned construction works was continued on
26 March 2015 and 27 March 2015 at location opposite to the monitoring location
while no exceedance was identified, the exceedances were considered to be not
related to the Project and contributed by nearby traffic. On 8 April 2015, manual
cleaning works was conducted and the exceedances were considered to be not
related to the Project and contributed by nearby traffic. On 24 April 2015,
coring was conducted at Pier F6 to F7, in view of the exceedances was
non-continuous and the concerned construction works was continued on the same
monitoring date opposite to the monitoring location at Pier F7 to F9
progressively towards the monitoring station while no exceedance was
identified, the exceedances were considered to be not related to the Project
and contributed by nearby traffic.
8.0.11.
No limit level exceedance was recorded at
RTN4-Causeway Bay Community Centre in the reporting month.
Reporting month of May 2014
8.0.12.
No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport Section
Whitfield Depot in the reporting month.
8.0.13.
Limit level exceedances were recorded at
RTN2a-Electric Centre during daytime on19 May 2015 during day time in the
reporting month. After checking with Contractor of HY/2009/19, U beam lifting
works with trailers and crawler cranes was conducted while breaking works and
excavation works was noted on-going at the construction site located next to
the monitoring station. In view of the above, the exceedances were considered
to be non-Project related and contributed by nearby non-CWB construction site
works.
8.0.14.
Limit level exceedances were recorded at
RTN3-Yue Lee Mo Fan Memorial School during daytime on 30 April, 8 and 12 May
2015 in the reporting month. After checking with Contractor of HY/2009/19, railing
installation and manual fixing was conducted on 30 April 2015 with no major
noise emanating works and the exceedances was non-continuous and considered to
be contributed by nearby IEC traffic and not related to Project.
On 8 May 2015, parapet cutting works with saw cut was conducted across
the exceedance period with significant noise level elevation while ad hoc
inspection on the same date observed that no mitigation measures was provided
for the saw cutting works. As such, the
exceedances was considered to be related to the Project works while the
concerned work was completed on the same date. In view of the exceedances, the
Contractor of HY/2009/19 has committed the implementation of the noise barrier
at sides and front for parapet cutting works around the concerned location and
no further exceedance was recorded on the next monitoring day.
On 12 May 2015,
after checking with Contractor of HY/2009/19, IEC bridge deck longitudinal
works cutting was conducted during the monitoring period and temporary noise
barrier was provided for the concerned works.
In view of the exceedances was non-continuous and while the concerned
construction works was in continuous operation with implementation of the noise
mitigation measures while , the exceedances were considered to be not related
to the Project and contributed by nearby traffic.
8.0.15.
No limit level exceedance was recorded at
RTN4-Causeway Bay Community Centre in the reporting month.
Environmental Complaints
8.0.16.
Four environmental complaints were received in the reporting quarter.
8.0.17.
First public complaint regarding construction dust impact referred by
EPD was received by ET on 09 April 2015 (EPD Ref.:H05/RS/00008074-15 dated 9
April 2015). The complainant reported that:
8.0.18.
Construction dust was generated from lorries transporting out of the
construction via site exit near Expo Drive Central without wheel washing at the
morning of 7 April 2015. Lorries were also found transporting out of the
construction site via gates V2 and V8 without wheel washing and causing dust
nuisance at about 10:30 hours on 9 April 2015.
8.0.19.
ET confirmed with the Resident Site Staff that on 7 April 2015, major
vehicle movements included oil tanker passing at Gate V2 at Expo Drive East and
dump truck passing at Gate V8 at Expo Drive Central under Contract HK/2009/01. On
9 April 2015, major vehicle movements include oil tanker, crane lorry and dump
truck passing at Gate V2 at Expo Drive East and dump truck at Gate V8 at Expo
Drive Central under Contract HK/2009/01.
8.0.20.
Mitigation measures adopted by the Contractor of HK/2009/01 at the above
locations include water hose was provided for wheel washing at Gate V2 and Gate
V8, concrete paving at site exit, dump truck fitted with mechanic cover and
cleaned before leaving construction site and regular street washing at Expo
Drive Central.
8.0.21.
According to the relevant site records under Contract HK/2009/01, on 7
April 2015, major vehicle movements included oil tanker passing at Gate V2 at
Expo Drive East and dump truck passing at Gate V8 at Expo Drive Central under
Contract HK/2009/01 while on 9 April 2015 major vehicle movements include oil
tanker, crane lorry and dump truck passing at Gate V2 at Expo Drive East and
dump truck at Gate V8 at Expo Drive Central under Contract HK/2009/01.
8.0.22.
At the above locations, mitigation measures including water hose for
wheel washing at Gate V2 and Gate V8; concrete paving at site exit; dump truck
fitted with mechanic cover and cleaned before leaving construction site and
regular street washing at Expo Drive Central were generally adopted by the
Contractor of HK/2009/01.
8.0.23.
In view of the public concern on the complaint date, the Contractor of
HK/2009/01 was advised to conduct cleaning at the concerned site exit point and
the section of public road adjoining the site exit to clear any residue grit
and silt deposit to avoid further dust impact.
8.0.24.
Follow up inspection was conducted on 16 April 2015 during weekly
environmental inspection and mitigation measures including water spraying for
dusty haul road and provision of wheel washing were in place. The construction
site exit was observed clear from residue silt / grit at the concerned
location.
8.0.25.
In view of the public concern, the contractor was advised to conduct
training to the construction site workers to enhance the effectiveness of wheel
washing and to ensure proper wheel washing is provided for dump truck and other
vehicle prior to leaving the construction site to avoid generating any dust
nuisance.
8.0.26.
Second public complaint regarding construction noise impact referred by
EPD was received by ET on 09 April 2015 (EPD Ref.:H05/RS/00007861-15 dated 9
April 2015). The complainant reported that construction noise was emanated from
the construction site at Convention Avenue near Renaissance Harbor View Hotel
during the period of Easter Holiday, including April 3 at about 13:00 hours.
8.0.27.
ET confirmed with the Resident Site Staff that from 3 April 2015 to 7
April 2015, from 08:00 hours to 18:00 hours, and at about 13:00 hours on 3
April 2015 at area CWB Tunnel Stage 3, backfilling works was conducted under
HK/2009/01. Either 1 no. of dump truck or 1. no. of excavator was operated on
site at each given time during the concerned period.
8.0.28.
According to the relevant site records under Contract HK/2009/01, from
across 08:00hrs to 18:00hrs during the period from 3 April 2015 to 7 April
2015, backfilling works was conducted under Contract HK/2009/01 at CWB Tunnel
Stage 3. Either 1 no. of dump truck and 1 no. of excavator was operated on site
at each given time during the concerned period and the relevant Construction
Noise Permit GW-RS0104-15 for the works was in place and the same construction
activity was undertaken at around 13:00hrs on 3 April 2015.
8.0.29.
No other concurrent construction activity was undertaken at the
concerned location during the concerned period under Contract HK/2009/01. The
construction activity conducted under Contract HK/2009/01 during the concerned
period was in compliance with the statutory requirement.
8.0.30.
Nevertheless, in view of the concern regarding the noise nuisance raised
by the public at the concerned location, it is considered desirable for the
Contractor of HK/2009/01 to review the truck unloading procedures of the
specific construction task to minimize potential noise emanated during the
course for work.
8.0.31.
Third public complaint regarding visual impact received by the RSS was
referred to the ET on 15 April 2015 (ICC Case Ref.: 2-885677297 dated 13 April
2015). The complainant reported that:
“I live in a building next to Gloucester
Road in Causeway Bay. Recently, I am suffering from unnecessary light source
from the construction site. The banners of the construction companies are
always illuminated with very bright lights.”
8.0.32.
ET confirmed with the Resident Site Staff that the concerned lighting
for the banners was maintained under Contract HY/2010/08.
8.0.33.
The concerned lighting for the banners was maintained under Contract
HY/2010/08 and the concerned lighting was subsequently switched off at all
times since 13 April 2015 to alleviate the lighting nuisance caused to the
surroundings.
8.0.34.
Fourth public complaint regarding construction noise impact referred by
EPD was received by ET on 23 April 2015 (EPD Ref.:H05/RS/00009456-15 dated 23
April 2015). The complainant reported that construction noise emanated from the
road work at Fleming Road and Convention Avenue near Renaissance Harbour View
Hotel almost every night recently causing nuisance.
8.0.35.
ET confirmed with the Resident Site Staff that from 21:00hrs on 20 April
2015 to 06:00hrs on 21 April 2015 and from 21:00hrs on 21 April 2015 to
06:00hrs on 22 April 2015, cooling main connection works was undertaken by the
Contractor of Contract HK/2009/01 at the concerned location. Total 1 no. of
crane lorry and 1 no. of excavator were in operation.
8.0.36.
According to the relevant site records under Contract HK/2009/01, from
21:00hrs on 20 April 2015 to 06:00hrs on 21 April 2015 and from 21:00hrs on 21
April 2015 to 06:00hrs on 22 April 2015, cooling main connection works was
undertaken by the Contractor of Contract HK/2009/01 at the concerned location.
Total 1 no. of crane lorry and 1 no. of excavator were in operation during the
concerned period and the relevant Construction Noise Permit GW-RS0269-15 was
confirmed in place. The construction activity conducted under Contract
HK/2009/01 during the concerned period was in compliance with the statutory
requirement.
8.0.37.
In view of the potential noise nuisance, a notice to affected parties
was issued by the Contractor of Contract HK/2009/01 to the nearby residents
including Renaissance Harbour View Hotel on 17 April 2015. Besides,
construction works undertaken by other parties at the concerned location was
observed at the concerned period. The construction programmes of individual contracts
are provided in Appendix 8.1.