Contract No: HK/2015/01

 

Wanchai Development Phase II and Central Wanchai Bypass

Sampling, Field Measurement and Testing Work (Stage 3)

 

Environmental Permit no. EP-364/2009/D,

Further Evironmental permit nos. fep-01/364/2009, fep-02/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEp-07/364/2009/D, FEP-09/364/2009/B, fep-10/364/2009/B and fep-11/364/2009/B

 

Quarterly Environmental Monitoring
and Audit Report

 

- MARCH 2016 to MAY 2016 -

 

CLIENTS:

PREPARED BY:

 

 

Civil Engineering and Development

Department

 

and

 

Highways Department

 

Lam Geotechnics Limited

 

11/F Centre Point

181-185 Gloucester Road,

Wanchai, H.K.

 

Telephone: (852) 2882-3939

Facsimile: (852) 2882-3331

E-mail: info@lamenviro.com

Website: http://www.lamenviro.com

 

 

 

 

 

CHECKED by:



 

 

 

 

 

                                               

Raymond Dai

Environmental Team Leader

 

 

 

DATE:

 

 

 

 29 June 2016


Table of contents

 

1.     Introduction.. 19

1.1       Scope of the Report 19

1.2       Structure of the Report 19

2.     Project Background.. 20

2.1       Background. 20

2.2       Scope of the Project and Site Description.. 20

2.3       Division of the Project Responsibility. 21

2.4       Project Organization and Contact Personnel 23

2.5       Principal Work and Activities. 25

3.     Monitoring Requirements. 30

3.1.      Noise Monitoring. 30

3.2.      Air quality monitoring. 32

4.     Monitoring Results. 34

4.1.      Noise Monitoring Results. 35

4.2.      Real Time Noise Monitoring Results. 39

4.3.      Air quality monitoring Results. 43

4.4.      Waste Monitoring Results. 48

5.     Compliance Audit.. 52

5.1.      Noise Monitoring. 52

5.2.      Air quality monitoring. 54

5.3.      Real Time Noise Monitoring. 55

5.4.      Site Audit 57

5.5.      Review of the Reasons for and the Implications of Non-compliance. 57

5.6.      Summary of action taken in the event of and follow-up on non-compliance. 58

6.     Complaints, Notification of Summons and Prosecution.. 59

7.     Cumulative Construction Impact due to the Concurrent Projects  67

8.     Conclusion.. 68


lIST OF TABLES

 

Table I          Principal Work Activities for Contract no. HY/2009/18

Table II         Principal Work Activities for Contract no. HK/2009/01

Table III        Principal Work Activities for Contract no. HK/2009/02

Table IV       Principal Work Activities for Contract no. HY/2009/15

Table V        Principal Work Activities for Contract no. HY/2009/19

Table VI       Principal Work Activities for Contract no. HK/2012/08

Table VII      Principal Work Activities for Contract no. HY/2010/08

Table VIII     Principal Work Activities for Contract no. HY/2011/08

Table 2.1      Schedule 2 Designated Projects under this Project

Table 2.2      Details of Individual Contracts under the Project

Table 2.3      Contact Details of Key Personnel

Table 2.4      Principal Work Activities for Contract no. HY/2009/18

Table 2.5      Principal Work Activities for Contract no. HK/2009/01

Table 2.6      Principal Work Activities for Contract no. HK/2009/02

Table 2.7      Principal Work Activities for Contract no. HY/2009/15

Table 2.8      Principal Work Activities for Contract no. HY/2009/19

Table 2.9      Principal Work Activities for Contract no. HK/2012/08

Table 2.10    Principal Work Activities for Contract no. HY/2010/08

Table 2.11    Principal Work Activities for Contract no. HY/2011/08

Table 3.1      Noise Monitoring Stations

Table 3.2      Real Time Noise Monitoring Stations

Table 3.3      Air quality monitoring Stations

Table 4.1      Noise Monitoring Station for Contract no. HY/2009/18

Table 4.2      Noise Monitoring Stations for Contract nos. HK/2009/01 and HK/2009/02

Table 4.3      Noise Monitoring Station for Contract nos. HY/2009/15

Table 4.4      Noise Monitoring Stations for Contract no. HY/2009/19

Table 4.5      Noise Monitoring Stations for Contract no. HY/2010/08

Table 4.6     Noise Monitoring Stations for Contract no. HY/2011/08

Table 4.7      Real Time Noise Monitoring Stations for Contract no. HY/2009/19

Table 4.8      Real Time Noise Monitoring Stations  for Contract no. HY/2011/08

Table 4.9      Air quality monitoring Stations for Contract no. HY/2009/18

Table 4.10    Air quality monitoring Stations for Contract no. HK/2009/01

Table 4.11    Air quality monitoring Station for Contract no. HK/2009/02

Table 4.12    Air quality monitoring Station for Contract no. HY/2009/15

Table 4.13    Air quality monitoring Stations for Contract no. HY/2009/19

Table 4.14    Air quality monitoring Stations for Contract no. HK/2012/08

Table 4.15    Air quality monitoring Stations for Contract no. HY/2010/08

Table 4.16    Air quality monitoring Stations for Contract no. HY/2011/08

Table 4.17    Details of Waste Disposal for Contract no. HK/2009/01

Table 4.18    Details of Waste Disposal for Contract no. HK/2009/02

Table 4.19    Details of Waste Disposal for Contract no. HY/2009/18

Table 4.20    Details of Waste Disposal for Contract no. HY/2009/15

Table 4.21    Details of Waste Disposal for Contract no. HY/2009/19

Table 4.22    Details of Waste Disposal for Contract no. HK/2012/08

Table 4.23    Details of Waste Disposal for Contract no. HY/2010/08

Table 4.24   Details of Waste Disposal for Contract no. HY/2011/08

Table 6.1      Cumulative Statistics on Complaints

Table 6.2      Cumulative Statistics on Successful Prosecutions

 

 

 

 

 

 

 

 

 

 

 

 

lIST OF FIGUREs

 

Figure 2.1         Project Layout

Figure 2.2         Project Organization Chart

Figure 3.1         Locations of Environmental Monitoring Stations

 

lIST OF APPENDIces

 

Appendix 2.1    Environmental Mitigation Implementation Schedule

Appendix 3.1    Action and Limit Level

Appendix 4.1    Noise Monitoring Results and Graphical Presentations

Appendix 4.2    Real-time Noise Monitoring Results and Graphical Presentations

Appendix 4.3    Air Quality Monitoring Results and Graphical Presentations

Appendix 5.1    Event Action Plans

Appendix 6.1    Complaint Log

Appendix 6.2     Notification of Exceedance

Appendix 8.1    Construction Programme of Individual Contracts


 

EXECUTIVE SUMMARY

 

  1. This is the Environmental Monitoring and Audit (EM&A) Quarterly Report – March 2016 to May 2016 specific for Environmental Permit no. EP-364/2009/D, Further Environmental Permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/D, FEP-09/364/2009/B, FEP-10/364/2009/B AND FEP-11/364/2009/B. The EM&A report is prepared by the Environmental Team (ET) employed under Contract No. HK/2011/07 Wan Chai Development Phase II and Central Wanchai Bypass – Sampling, Field Measurement and Testing Works (Stage 2). This report presents the environmental monitoring findings and information recorded during the period from 27 February 2016 to 26 May 2016. The cut-off date of reporting is at 26th of each reporting quarter.

 

 

  1. In the reporting quarter, the principal work activities of individual contracts are included as follows:

Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB)  - Central Interchange under FEP-05/364/2009/

Major construction activities for Contract no. HY/2009/18 have been commenced on 21 April 2011. During this reporting period, the principal work activities for Contract no. HY/2009/18 are summarized as below:

Table I        Principal Work Activities for Contract no. HY/2009/18

March 2016

April 2016

May 2016

Ÿ   Drainage works

Ÿ   Road works

Ÿ   Landscaping works

Ÿ   Maintenance works

Ÿ   Drainage works

Ÿ   Road works

Ÿ   Landscaping works

Ÿ   Modification and Construction of Sign Gantries / Traffic Signs

Ÿ   Maintenance works

 

Ÿ   Drainage works

Ÿ   Road works

Ÿ   Landscaping works

Ÿ   Modification and Construction of Sign Gantries / Traffic Signs

Ÿ   Maintenance works

 

 

 

 

 

 

 

 

 

 

 

Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009

Major construction activities for Contract no. HK/2009/01 have been commenced on 25 August 2011. During this reporting period, the principal work activities are summarized as below:

Table II       Principal Work Activities for Contract no. HK/2009/01

March 2016

April 2016

May 2016

Ÿ   Stage 3a backfilling works

Ÿ   Stage 3b backfilling works

Ÿ   Stage 4 demolition of the bulkhead wall

Ÿ   Stage 4 construction tunnel structure

Ÿ   Reinstatement of outfall

Ÿ   Reinstatement of triangular planter at Fenwick Pier Street

 

Ÿ   Stage 3a backfilling works

Ÿ   Stage 3b backfilling works

Ÿ   Stage 4 construction tunnel structure

Ÿ   Reinstatement of outfall

Ÿ   Reinstatement of triangular planter at Fenwick Pier Street

 

Ÿ   Stage 3b backfilling works

Ÿ   Stage 4 construction tunnel structure

Ÿ   Reinstatement of outfall

Ÿ   Reinstatement of triangular planter at Fenwick Pier Street

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

Major construction activities for Contract no. HK/2009/02 have been commenced on 26 April 2011. During this reporting period, the principal work activities are summarized as below:

Table III      Principal Work Activities for Contract no. HK/2009/02

March 2016

April 2016

May 2016

Ÿ   Installation of steel angles for trough cover

Ÿ   Site clearance works was on going at OHVD at Tunnel Portion 1.

Ÿ   Construction of road side barriers

Ÿ   Construction of manhole frame & cover, gully frame and grating

Ÿ   Installation of steel angles for trough cover

Ÿ   Site clearance works was on going at OHVD at Tunnel Portion 1.

Ÿ   Construction of road side barriers

Ÿ   Construction of manhole frame & cover, gully frame and grating

Ÿ   100% excavation for formation level

Ÿ   100% blinding layer

Ÿ   95% Waterproofing works and base slab construction

Ÿ   Approximately 10% middle wall

Ÿ   Casting of Bored pile

Ÿ   Diaphragm wall panel construction

Ÿ   King post works

Ÿ   Demolition of existing Sun Hung Kai cooling water pumping station

Ÿ   Demolition of the existing structure

 

Ÿ   Site clearance works was on going at OHVD at Tunnel Portion 1.

Ÿ   Waterproofing works and base slab construction were completed

Ÿ   Middle wall and side wall construction

Ÿ   Diaphragm wall panel construction

Ÿ   King post work was completed

Ÿ   Instrumentation work was on going

 

 

Ÿ   Site clearance works was on going at OHVD at Tunnel Portion 1.

Ÿ   Site clearance works was on going at OHVD at Tunnel Portion 2.

Ÿ   Waterproofing work for side wall

Ÿ   Middle wall and side wall construction

Ÿ   Tunnel top slab construction

Ÿ   Diaphragm wall panel construction

Ÿ   Instrumentation work was on going

Ÿ   Excavation work

 

Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

Major construction activities for Contract no. HY/2009/15 has been commenced on 13 July 2011. During this reporting period, the principal work activities are summarized as below:

Table IV     Principal Work Activities for Contract no. HY/2009/15

March 2016

April 2016

May 2016

Ÿ   Construction RC structure at TPCWAW

Ÿ   Dismantle steel work at TPCWAW

Ÿ   Remaining works inside tunnel at TS4 and TPCWAE

Ÿ   Remedial works at Mined Tunnel

 

Ÿ   Backfilling works at TPCWAW

Ÿ   Dismantle steel work at TPCWAW

Ÿ   Remaining works inside tunnel at TS4 and TPCWAE

Ÿ   Remedial works at Mined Tunnel

Ÿ   Reinstatement of Shaft B between TPCWAW and TPCWAE

 

Ÿ   Dismantle steel work at TPCWAW

Ÿ   Remedial works at Mined Tunnel

Ÿ   Remedial works at TS4, TPCWAE

Ÿ   Reinstatement of Shaft B between TPCWAW and TPCWAE

 

 

Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D

Major construction activities for Contract no. HY/2009/19 have been commenced on March 2011. During this reporting period, the principal work activities are summarized as below:

Table V      Principal Work Activities for Contract no. HY/2009/19

March 2016

April 2016

May 2016

Ÿ   Pier construction for IEC

Ÿ   Construction of EVB

Ÿ   Column modification at F1 to F8

Ÿ   Watson Road laying of new water pipe

Ÿ   Oil Street drainage works

Ÿ   Excavation / Construction of retaining wall

Ÿ   Bridge segment erections

Ÿ   Pre-bored H-pile for Approach Ramp

Ÿ   Hing Fat Street modification works

Ÿ   EVA Temporary works

Ÿ   Hing Fat Street Slip Road Bridge E parapet construction

Ÿ   Pier construction for IEC

Ÿ   Construction of EVB

Ÿ   Column modification at F1 to F8

Ÿ   Watson Road laying of new water pipe

Ÿ   Oil Street drainage works

Ÿ   Excavation / Construction of retaining wall/Piling works/Approach Ramp

Ÿ   Bridge segment erections

Ÿ   Hing Fat Street modification works

Ÿ   EVA bulkhead removal

Ÿ   Hing Fat Street Slip Road Bridge E parapet construction

 

Ÿ   Pier construction for IEC

Ÿ   Construction of EVB

Ÿ   Column modification at F1 to F8

Ÿ   Oil Street drainage works

Ÿ   Bridge construction  and segment erection

Ÿ   Hing Fat Street modification works

Ÿ   EVA structure construction

Ÿ   Hing Fat Street Slip Road Bridge E L3 railing construction

Ÿ   Approach ramp sheet piling works

Ÿ   EVB waterproofing works

 

Contract no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan Chai West under FEP-09/364/2009B

Table VI                       Principal Work Activities for Contract no. HK/2012/08

March 2016

April 2016

May 2016

Ÿ   Grouting

Ÿ   Construction of MVB

Ÿ   Pre-bored H-pile construction

Ÿ   Construction of concrete plug

Ÿ   Excavation and lateral support installation for CWB tunnel

 

Ÿ   Grouting

Ÿ   Construction of MVB

Ÿ   Pre-bored H-pile construction

Ÿ   Construction of concrete plug

Ÿ   Excavation and lateral support installation for CWB tunnel

 

 

Ÿ   Grouting

Ÿ   Construction of MVB

Ÿ   Construction of concrete plug

Ÿ   Excavation and lateral support installation for CWB tunnel

Ÿ   Structural works for CWB tunnel construction

 

 

 

Contract no. HY/2010/08 – Central and WanChai Bypass – Slip road 8 section under FEP-10/364/2009B

Table VII      Principal Work Activities for Contract no. HY/2010/08

March 2016

April 2016

May 2016

Ÿ   Tree protection works next to existing BGO,

Ÿ   Drainage improvement works,

Ÿ   Excavation and Lateral Support for U-structure,

Ÿ   Grouting works,

Ÿ   Utility diversion works,

Ÿ   Retaining wall works

Ÿ   ELS works,

Ÿ   D-wall drill cutting works

Ÿ   Construction works for subway extension

Ÿ    

Ÿ   Tree protection works next to existing BGO,

Ÿ   Drainage improvement works,

Ÿ   Excavation and Lateral Support for U-structure,

Ÿ   Pipe piling & grouting works,

Ÿ   Utility diversion works,

Ÿ   Retaining wall works

Ÿ   ELS works,

Ÿ   D-wall drill cutting works

Ÿ   Construction works for subway extension

 

Ÿ   Tree protection works next to existing BGO,

Ÿ   Drainage improvement works,

Ÿ   Excavation and Lateral Support for U-structure,

Ÿ   Pipe piling & grouting works,

Ÿ   Utility diversion works,

Ÿ   Retaining wall works

Ÿ   ELS works,

Ÿ   Construction works for subway extension

 

 

 

 

 

 

 

 

 

Contract no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B

 

Table VIII       Principal Work Activities for Contract no. HY/2011/08

March 2016

April 2016

May 2016

Ÿ   Construction of Ventilation Buildings, inclusive of Administrative Building, East Ventilation Shaft/Building, West Ventilation Building

Ÿ   Construction of Tunnel Thermal Barrier

Ÿ   Installation of Electricals and Mechanicals

 

Ÿ   Construction of Ventilation Buildings, inclusive of Administrative Building, East Ventilation Shaft, West Ventilation Building

Ÿ   Construction of Tunnel Thermal Barrier

Ÿ   Installation of Electricals and Mechanicals

Ÿ   Installation of Tunnel Features

 

Ÿ   Construction of Ventilation Buildings, inclusive of Administration Building, East Ventilation Shaft West Ventilation Building

Ÿ   Construction of Tunnel Thermal Barrier

Ÿ   Installation of Electricals and Mechanicals

Ÿ   Installation of Tunnel Features

 

 

Noise Monitoring

  1. Noise monitoring was conducted at M1a - Harbour Road Sports Center; M2b - Noon-day gun area; M3a - Tung Lo Wan Fire Station; M4b - Victoria Center; M5b - City Garden, M6 - HK Baptist Church Henrietta Secondary School, M7e and M7w – International Finance Centre eastern and western wing, and M8 – City Hall on a weekly basis.
  2. Three limit level exceedances were recorded at noise monitoring station M1a – Habour Road Sports Center on 02, 08 and 15 March 2016. The exceedances were concluded as non-project related.
  3. Two limit level exceedances were recorded at noise monitoring station M1a – Habour Road Sports Center on 29 March 2016 and 12 April 2016. The exceedances were concluded as non-project related.
  4. Two limit level exceedances were recorded at noise monitoring station M6 – HK Baptist Church Henrietta Secondary School on 11 and 19 April 2016. The exceedances were concluded as non-project related.
  5. Two limit level exceedances were recorded at noise monitoring station M1a – Habour Road Sports Center on 04 and 24 May 2016. The exceedances were concluded as non-project related.

 

       Real time Noise Monitoring

  1. 24-hour real time noise monitoring was conducted at RTN1 - FEHD Hong Kong Transport Section Whitefield Depot for the pilling works in FEHD Whitfield Depot and RTN2 – Tunnel (North Point Section) and Island Eastern Corridor Link during the period from 28 September 2012 til 10am on 5 October 2012 in the reporting period.
  2. Real time noise monitoring station at Oil Street Community Liaison Centre (RTN2- Oil Street Community Centre) was relocated from Oil Street Community Liaison Centre to Hong Kong Electric (RTN2a- Electric Centre) on 5 Oct which is a representative of the noise sensitive receiver City Garden. The baseline noise level of RTN2a will adopt the results derived from the baseline noise monitoring conducted in Electric Centre from 4 December 2009 to 17 December 2009.
  3. As confirmed by CWB RSS, the IECL parapet removal operations will commence in March 2013.  Liaison was conducted with HK Baptist Church Henrietta Secondary School and Po Leung Kuk Yu Lee Mo Fan Memorial School regarding the set up of RTN3 real time noise monitoring station.  Po Leung Kuk Yu Lee Mo Fan Memorial School grant permission for set up on 4 Sep 2012 and station set up was performed on 14 Sep 2012.
  4. Real Time Noise Monitoring at RTN3- Po Leung Kuk Yu Lee Mo Fan Memorial School was commenced since 06 Oct 2012.
  5. Causeway Bay Community Centre has granted permission for set up of real time noise monitoring station on 21 Dec 2012 and station set up was performed on 27 Dec 2012.  The Baseline noise level of RTN4- Causeway Bay Community Centre will adopt the results from the baseline noise monitoring report for EP/364/2009 in 22 April 2010 in which approved by EPD.
  6. According to clause 3.1 stated in EP-364/2009B, “the real-time monitoring system shall be in place no later than two weeks before the commencement date of demolition works of the existing Island Eastern Corridor”. IEC demolition associated construction works was commenced on 3 Feb 2013 and Real time noise monitoring at RTN4-Causeway Bay Community Centre was commenced on 13 Jan 2013.
  7. Real-time noise monitoring station RTN1-FEHD Whitfield Depot was finely adjusted from 2/F to roof-top at FEHD Whitfield Depot on 24 June 2013 with respect to the commencement of advance works for IEC parapet demolition.
  8. No limit level exceedance was recorded in March, April and May reporting month at RTN1- FEHD Hong Kong Transport Section Whitfield Depot during this reporting quarter.
  9. No project related exceedance was recorded in March and April reporting month and no limit level exceedance was recorded in May reporting month at RTN2a-Hong Kong Electric Centre during this reporting quarter.
  10. No limit level exceedance was recorded in March reporting month and no project related exceedance was recorded in April and May reporting month at RTN3-Yu Lee Mo Fan Memorial School during this reporting quarter.
  11. No project related exceedance was recorded in April and May reporting month and no limit level exceedance was recorded in March reporting month at RTN4- Causeway Bay Community Centre in the reporting quarter.

 

Air Quality Monitoring

  1. Due to extension of site boundary by contractor of HY/2009/19, location of air quality monitoring station CMA1b – Oil Street Community Liaison Centre has been finely adjusted on 21 April 2012.
  2. 1-hour and 24-hour Total Suspended Particulates (TSP) monitoring were conducted at CMA1b - Oil Street Community Liaison Centre; CMA2a - Causeway Bay Community Center; CMA3a - CWB PRE Site Office Area; CMA4a – Society for the Prevention of Cruelty to Animals; CMA5a - Children Garden opposite to Pedestrian Plaza; MA1e and MA1w – International Finance Centre eastern and western wing on every six days basis.
  3. One action level exceedance for TSP monitoring was recorded at CMA5b – Pedestrian Plaza on 14 April 2016 in the reporting month. The exceedance was concluded as non-project related.

 

Complaints, Notifications of Summons and Successful Prosecutions

  1. Eight environmental complaints were received in the reporting quarter.

 

  1. First public complaint regarding construction noise referred by ICC was received by ET on 03 March 2016 (ICC Ref.: CASE#2-1938637403 dated 01 March 2016). The complainant reported that construction noise was emanated from road works located between Lung Wo Road and Lung Wui Road Interface.

 

Further information was referred by RSS on 15 March 2016, the complainant clarified on 15 March 2016 that construction noise was emanated from road works located between Lung Wo Road and Lung Wui Road Interface during midnight and has lasted for one and half month resulting in nuisance to nearby residence.

 

Further information was referred by RSS on 18 March 2016, the complainant further clarified on 18 March 2016 that the concerned location shall be Lung King Street near the parking spaces for motorcycles and the Contract no. as stated on the publicity board is HK/2012/08. Furthermore, the complainant identified the noise was from power generators.

ET confirmed with the Resident Site Staff that there was neither construction works nor operation of power generators under Contract HK/2012/08 at the concerned location from 1900hrs to 0700hrs during the period from 23 February 2016 to 14 March 2016.

Based on the complaint information referred by ICC on 3 March 2016, according to the relevant site records provided by RSS, from 0800hrs to 1800hrs on both 29 February 2016 and 01 March 2016, drainage works was undertaken by Contract HK/2012/08 at Lung Wo Road and one excavator was in operation for soil excavation. Follow up inspection was conducted during the weekly environmental site inspection on 08 March 2016 and no particular noise emanating works was observed.

 

Based on the further information provided by the complainant on 15 March 2016, the complainant clarified on 15 March 2016 that Construction noise was emanated from road works located between Lung Wo Road and Lung Wui Road Interface during midnight and has lasted for one and half month resulting in nuisance to nearby residence. On 18 March 2016, the complainant further clarified on 18 March 2016 that the concerned location shall be Lung King Street near the parking spaces for motorcycles and the Contract no. as stated on the publicity board is HK/2012/08. Furthermore, the complainant identified the noise was from power generators. According to the relevant site records provided by RSS, there was neither construction works nor operation of power generators under Contract HK/2012/08 at the concerned location from 1900hrs to 0700hrs during the period from 23 February 2016 to 14 March 2016.

 

Nevertheless, in view of the public concern, the Contractor is recommended to maintain regular maintenance of the plant and equipment deployed to avoid potential nuisance to the nearby public.

 

  1. Second public complaint regarding construction dust, plant exhaust, construction noise and water quality referred by EPD was received by ET on 10 March 2016 (EPD Ref.: H05/RS/00005206-16 dated 10 March 2016). The complainant reported that construction dust, plant exhaust and construction noise generated from the construction work of Contract HK/2012/08 at waterfront of Lung King Street caused nuisance, and the water quality at the waterfront of Lung King Street was becoming worse that accumulation of the floating refuse and foam was found.

 

ET confirmed with the Resident Site Staff that soil excavation at ELS area, Zone A2(2), was carried out, where at approx. 100m from the waterfront of Lung King Street from 08:00 hrs to 18:00 hrs on 07 March 2016 under Contract HK/2012/08.  Two excavators were involved at that location. Erection of falsework for culvert L was carried out near the waterfront of Lung King Street from 08:00 hrs to 18:00 hrs on 07 March 2016 under Contract HK/2012/08.  One lorry crane was involved for lifting falsework elements. Dust suppression measures including the water sprinklers were installed along site haul road.

Regularly removed the floating refuse at the waterfront of Lung King Street was conducted by the Contractor of HK/2012/08. The concerned observed floating foam at the waterfront of Lung King Street was found originating from the diverted cooling mains discharge.

 

According to the relevant site records provided by RSS, soil excavation at ELS area, Zone A2(2) was carried out, where at approx.100m from the waterfront of Lung King Street under Contract HK/2012/08 from 08:00hrs to 18:00hrs on 07 March 2016 and two excavators were in operation at that location while erection of falsework for culvert L was carried out near the waterfront of Lung King Street from 08:00hrs and 18:00hrs on 07 March 2016 under Contract HK/2012/08 and one lorry crane was involved for lifting falsework elements. Dust suppression measures including the use of water sprinklers along the site haul road was implemented by the Contractor of HK/2012/08 and removal of floating refuse was regularly conducted at the waterfront of Lung King Street by the Contractor of HK/2012/08. Upon investigation, the concerned observed floating foam at the waterfront of Lung King Street was found originating from the diverted cooling mains discharge.

 

Follow up inspection was conducted during the weekly environmental site inspection on 15 March 2016 and dust suppression measures including watering for haul road, tarpaulin sheet covering for cement bags stored on site and three side and top covering for grouting station were implemented while and no dark smoke emission from the plant and machinery deployed on site was observed. Noise mitigation measures including acoustic covering was implementing for excavator mounted breaker. In addition, removal of floating refuse on site was observed implemented by the Contractor of HK/2012/08 and no accumulation of floating refuse was found. The concerned foam originating from diverted cooling mains discharge was observed during inspection and the dispersion of the concerned foam of unknown chemical nature was observed isolated from the nearby public area.

 

Nevertheless, in view of the public concern, the Contractor was recommended to maintain regular checking of the plants and equipment deployed on site to avoid potential air quality impact to the nearby public and to maintain adequate dust suppression measures on site to avoid potential dust impact to the surroundings. The Contractor was reminded to maintain regular cleaning of floating refuse within the construction site area to avoid potential nuisance to the surroundings. The Contractor was also reminded to maintain the noise mitigation measure if breaking works would be required. The Contractor was also suggested to reflect the observed foam to relevant Cooling Mains owners.

 

  1. Third public complaint regarding direct discharge of muddy effluent referred by EPD was received by ET on 31 March 2016 (Case Ref.: H08/RS/00006732-16). The complainant reported that muddy water was observed discharged from the construction site of Central – Wan Chai Bypass – Tunnel (North Point Section) and Island Eastern Corridor Link (Contract No. HY/2009/19) into Victoria Habour via a drain hole.

 

ET confirmed with the Resident Site Staff that pipe Laying works between Pier 32 and Pier 33 and excavation and blinding works for Manhole at Pier 34 were in progress on 22 March 2016.

The observed drain hole was identified to be the outlet point of a manhole and a section of an abandoned U-channel (extending from the concerned manhole to the Hong Kong Electric Substation in length along the site boundary) was adjoining the concerned manhole and sandbag was previously placed at the U-channel at the location near the inlet point to the concerned manhole.

 

Based on the site records confirmed by RSS, pipe laying works between Pier 32 and Pier 33 and excavation and blinding works for Manhole at Pier 34 were in progress on 22 March 2016. The observed drain hole was identified to be the outlet point of a manhole and a section of an abandoned U-channel (extending from the concerned manhole to the Hong Kong Electric Substation in length along the site boundary) was adjoining the concerned manhole and sandbag was previously placed at the U-channel at the location near the inlet point to the concerned manhole. In addition, no site discharge point was connected to the aforesaid U-channel and the concerned manhole. In view of the environmental concern, the following remedial and precautionary actions were taken by the Contractor of HY/2009/19 on 29 March 2016.

 

i)              Plugging the inlet point of the concerned manhole (connecting to the abandoned U-channel) with concrete;

ii)             Plugging the outlet of the concerned manhole (connecting to the observed drain hole) with concrete;

iii)            Filling the concerned manhole with rubbles;

iv)            Shifting the unused wastewater treatment plant around the concerned location to other site location for use.

 

Follow-up inspection was conducted by the Environmental Team on 06 April 2016. No further contaminated runoff discharge was observed from the concerned drain hole and precautionary measures including provision of concrete bunding was implemented along the site boundary at the concerned location to avoid potential surface overflow. The pipe laying works and the excavation works was found at distant location away from the concerned drain hole with no surface drain connection and no particular effluent was generated from the work. As such, no information indicate the discharge was related to the above construction activities.

However, it was noted that another section of surface drainage channel within the construction site (perpendicular in direction to the initial identified abandoned U-channel) was also in connection to concerned manhole and minor residue mud deposition was observed within the surface drainage channel. Despite the above additional surface drainage channel identified, the outlet point of concerned final manhole (in connection with the observed drain hole) was observed plugged with concrete and filled with rubbles as rectification measure to avoid any further contaminated runoff discharge via the observed drain hole.

 

Nevertheless, the Contractor of HY/2009/19 was reminded to conduct regular cleaning works for site surface drainage channel to avoid accumulation of silt and soil and avoid potential overflow by directing the surface runoff within the surface drainage channel to proper collection point for necessary treatment prior to discharge. The Contractor of HY/2009/19 was also reminded to check and review other surface drainage channel within the construction site to avoid potential runoff related impact via surface drainage channel to the nearby waters.

In addition, it was noticed that water was discharged from a piping extending from City Garden and the discharged water would result in seepage across the site hoarding into the abandoned U-channel. The Contractor of HY/2009/19 was suggested to liaise with the City Garden Management Office for proper connection of the observed pipping with discharge to prevent further seepage water into the construction site.                

              

  1. Forth public complaint regarding construction dust emission was referred by EPD was received by ET on 05 April 2016 (Case Ref.: H08/RS/00007662-16). The complainant reported that construction dust emission arising from drilling activity from the construction site of Central – Wan Chai Bypass – Tunnel (North Point Section) and Island Eastern Corridor Link (Contract No. HY/2009/19).

 

ET confirmed with the Resident Site Staff that drilling holes for installation of starter bars was carried out under Contract HY/2009/19 at the vertical cut face of the existing IEC road slab on 05 April 2016

 

Based on the site records confirmed by RSS, drilling holes for installation of starter bars was carried out under Contract HY/2009/19 at the vertical cut face of the existing IEC road slab on 05 April 2016 and according to the photo information provided by the EPD, no dust suppression measures was implemented during the observed drilling works on 05 April 2016.

 

According to Air Pollution Control Ordinance, for pneumatic or power-driven drilling, cutting and polishing, water or a dust suppression chemical shall be continuously sprayed on the surface where any pneumatic or power-driven drilling, cutting, polishing or other mechanical breaking operation that causes dust emission is carried out, unless the process is accompanied by the operation of an effective dust extraction and filtering device.

 

Follow-up inspection was conducted on 06 April 2016, rectification actions including the use of vacuum suction to extract dust generated during the concerned drilling works was observed implemented by the Contractor of HY/2009/19 for starter bars drilling works. 

 

  1. Fifth public complaint regarding landscape aspect was referred by RSS was received by ET on 11 April 2016 (Case Ref.:2-2036525055). The complainant reported that a tree (6 meters in height and 1.5 meters in diameter) was found toppled at 111 Victoria Park Road, near Lamp post 38632 and blocking the Pedestrian pathway on 27 March 2016.

 

ET confirmed with the Resident Site Staff that the concerned tree was identified as T710 and no construction activity in the vicinity of tree T710 on 27 March 2016 and no construction works are required in or near its vicinity. 

 

Based on the site records confirmed by RSS, the concerned tree was identified as the retained tree T710 maintained under the Contract of HY/2010/08 and the concerned tree T710 was located outside the assessment area in the relevant Project EIA Report. No construction works are required in the vicinity of concerned tree T710 and no construction activity was conducted in the vicinity of tree T710 on 27 March 2016. Nevertheless, based on RSS information, recent tree monitoring report indicates an existing cavity at trunk and the concerned tree T710 has been recommended to be felled in the tree risk assessment Form 2.

 

With respect to the observed incident of the toppling of the concerned tree T710, the Contractor of HY/2010/08 was instructed by RSS to remove the broken trunk/ remains to avoid impact to the surroundings. The concerned tree T710 shall be compensated by the Contractor of HY/2010/08 in accordance with the Development Bureau Technical Circular (Works) No. 7/2015 and the detail on compensation would be further agreed with Victoria Park Management Office. Follow-up inspection was conducted on 13 April 2016, and the remaining parts of the concerned tree T710 was observed felled to avoid further impact to nearby public road.

 

  1. Sixth public complaint regarding muddy dispersion referred by RSS was received by ET on 13 April 2016. The complainant reported that muddy water was observed to disperse from Contract HK/2009/02 site area to Victoria Harbour occasionally as there was no silt curtain installed under the buoyancy floats. The location concerned was the East of Star Ferry Piers (Contract No. HK/2009/02).

 

ET confirmed with the Resident Site Staff that no marine construction activities or land construction activities under Contract HK/2009/02 at the concerned location on 12 April 2016.

Surface runoff control measures including provision of concrete bund at the concerned location was implemented by Contract HK/2009/02.

No soil & silt deposition along the seawall at the concerned location on 12 April 2016.

No discharge point located in the vicinity of the concerned location under Contract HK/2009/02.

Silt curtain with buoyancy floats acting as anchor points was installed at Monitoring Station RW21-P789 for Water intakes.

 

Based on the site records confirmed by RSS, no marine construction activities or land construction activities was carried out under Contract HK/2009/02 at the concerned location on 12 April 2016 and no soil and silt deposition was found along the seawall at the concerned location and precautionary measures for site runoff control including provision of concrete bund along boundary of site area near the waterfront around the concerned location was implemented by the Contractor HK/2009/02. In addition, no discharge point under Contract HK/2009/02 was located in the vicinity of the concerned location. Based on information confirmed by RSS, the buoyancy floats deployed at the concerned location are acting as the anchor points for the silt curtain deployed around the WQM Station RW21-P789 for the WSD and Cooling Water Intakes group.

 

Follow-up inspection was conducted on 14 April 2016, no surface runoff from the construction site nor discharge of contaminated effluent was observed around the concerned location and precautionary measures including the provision of concrete bund at the concerned location was observed maintained by the Contractor of HK/2009/02 and the silt curtain deployed around the WQM station RW21-P789 was generally in order.

In view of the public concern on the water quality, the Contractor of HK/2009/02 was reminded to maintain effective surface runoff protection and provide proper collection point of construction effluent around the concerned location to avoid potential surface runoff related impact.

 

  1. Seventh public complaint regarding muddy water discharge referred by EPD was received by ET on 13 April 2016 (EPD Ref.: H05/RS/00008367-16 dated 13 April 2016). The complainant reported that muddy water was discharged from the construction work of Contract HK/2012/08 to the sea outside the Hong Kong Academy for Performing Arts on 13 April 2016 morning.

 

ET confirmed with the Resident Site Staff that internal transport of soil to the hopper barge for storage via landing barge was conducted by Contractor of HK/2012/08 during 0800 hours to 1000 hours on 13 April 2016 at the sea outside the concerned location and 3 nos. of dump trucks were deployed for the operation.

Protection measure including provision of sandbag bunding along the side of the landing barge was implemented by the Contractor of HK/2012/08.

 

According to the relevant site records provided by RSS, internal transport of soil to the hopper barge for storage via landing barge was conducted by Contractor of HK/2012/08 during 0800 hours to 1000 hours on 13 April 2016 at the sea outside the concerned location and 3 nos. of dump trucks were deployed for the operation. Protection measure including provision of sandbag bunding along the side of the landing barge was implemented by the Contractor of HK/2012/08. In addition, amber rainstorm warning signal was hoisted from 0630 hours to 1200 hours on 13 April 2016 and during the above time period, muddy water was observed from the upstream of culvert L outside the HK/2012/08 site.

 

Follow up inspection was conducted on 19 April 2016, protection measures including provision of sandbag bunding along the side of the landing barge was implemented and no mud or soil deposition was observed along the seawall and no discharge point was located within the temporary water channel connecting the Culvert L outfall location to the Victoria Harbour. In addition, piling works was observed at the north side of Zone A1 on 19 April 2016 and construction effluent collection from piling work via sedimentation tank to wastewater treatment facility was implemented and steel barrier was installed around the piling works area to mitigate against potential surface runoff related impact.

 

Nevertheless, in view of the public concern, the Contractor was reminded to maintain adequate perimeter embankment protection along the seawall boundary and maintain proper construction effluent collection system to avoid potential runoff related impact to nearby waters.

 

 

  1. Eighth EPD complaint regarding noise nuisance referred by RSS was received by ET on 27 May 2016 (EPD Ref: H05/RS/00012646-16 dated 27 May 2016). The complainant reported that a generator was operated round-the-clock in the Chun Wo- CRGL JV construction site near Wanchai Ferry Pier that cause noise nuisance. (Contract No. HK/2009/02).

 

ET confirmed with the Resident Site Staff that a generator deployed under Contract HK/2009/02 near the covered walkway for Wanchai Ferry Pier at Portion 2 area and was operated from 1900hrs on 24 May 2016 to 0700hrs on 25 May 2016 and from 1900hrs on 25 May 2016 to 0700hrs on 26 May 2016. The generator was used for the power supply of lighting inside Tunnel Portions 1 and 2.

 

According to the relevant site records provided by RSS, a generator deployed under Contract HK/2009/02 near the covered walkway for Wanchai Ferry Pier at Portion 2 area and was operated from 1900hrs on 24 May 2016 to 0700hrs on 25 May 2016 and from 1900hrs on 25 May 2016 to 0700hrs on 26 May 2016. The generator was used for the power supply of lighting inside Tunnel Portions 1 and 2. Based on review on site information, relevant Construction Noise Permits GW-RS0516-16 and GW-RS0390-16 for the operation of the concerned generator were confirmed in place while no sufficient site information was considered available to demonstrate the use of acoustic enclosure for the operation of the generator following the special condition 3d item 4. Despite the above, the Contractor of HK/2009/02 has suspended the use of the generator at the concerned location after 2300hours to minimize potential noise concern to the surroundings from 28 May 2016.

 

Nevertheless, the Contractor of HK/2009/02 was reminded to upkeep the site control system for construction works carried out during restricted hours and night time for Construction Noise Permit compliance and maintain regular maintenance of the plant and equipment deployed to avoid potential nuisance to the nearby public.

 

1.         Introduction

1.1          Scope of the Report

1.1.1.     Lam Geotechnics Limited (LGL) has been appointed to work as the Environmental Team (ET) under Environmental Permit no. EP-364/2009/D and Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/D, FEP-09/364/2009/B, FEP-10/364/2009/B and FEP-11/364/2009/B to implement the Environmental Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual of the approved Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001).

1.1.2.     This report presents the environmental monitoring and auditing work carried out in accordance to the Section 10.3 of EM&A Manual and “Environmental Monitoring and Audit Requirements” under Particular Specification Section 27.

1.1.3.     This report documents the finding of EM&A works during the period from 27 February 2016 to 26 May 2016.

1.2          Structure of the Report

 

Section 1          Introduction – details the scope and structure of the report.

 

Section 2          Project Background – summarizes background and scope of the project, site description, project organization and contact details of key personnel during the reporting period.

 

Section 3          Monitoring Requirements – summarizes all monitoring parameters, monitoring locations, monitoring frequency, duration and action plan.

 

Section 4          Monitoring Results – summarizes the monitoring results obtained in the reporting period.

 

Section 5          Compliance Audit – summarizes the auditing of monitoring results, all exceedances environmental parameters.

 

Section 6          Complaints, Notification of summons and Prosecution – summarizes the cumulative statistics on complaints, notification of summons and prosecution

 

Section 7          Cumulative Construction Impact due to the Concurrent Projects summarizes the relevant cumulative construction impact due to the concurrent activities of the concurrent Projects.

 

Section 8          Conclusion

2.         Project Background

2.1          Background

2.1.1.     “Wan Chai Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai Bypass and Island Eastern Corridor Link” (hereafter called “the Project”) are Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO).  The Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and 11 December 2008 respectively.

2.1.2.     The key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai North and North Point for construction of the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed under the project will be developed as a world-class waterfront promenade joining that at the new Central waterfront for public enjoyment.

2.1.3.     There is a compelling and present need for the CWB to provide relief to the very congested east-west Connaught Road Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is currently operating beyond its capacity. The CWB will provide relief to the existing congestion along the Corridor and cater for the anticipated growth of traffic on Hong Kong Island. Without the CWB and its access roads, there will not be sufficient capacity to serve the heavy traffic demands at both strategic and local levels.

 

2.2          Scope of the Project and Site Description

2.2.1.     Design and Construction of Central – Wan Chai Bypass and Island Eastern Corridor Link under the Project involves the construction and operation of a trunk road and its road tunnel more than 800m in length between portals that is shown at Figure 2.1.

2.2.2.     The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:

·          A dual three-lane trunk road, approximately 4.5 km in length, and tunnel approximately 3.7 km in length defined from the connection with the existing Rumsey Street Flyover in Central, through to a connection with the existing Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);

·          The Central Interchange near the Rumsey Street Flyover to provide road connections to the Central area;

·          Tunnel control buildings and ventilation buildings;

·          Slip roads to connect the CWB to the local road system in the Wan Chai North and Causeway Bay area;

·          Associated road lighting, road signing, traffic control and surveillance system; and

·          Other associated works.

 

2.2.3.     The project also contains various Schedule 2 DPs that, under the EIAO, require Environmental Permits (EPs) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.

Table 2.1    Schedule 2 Designated Projects under this Project

Item

Designated Project

EIAO Reference

Reason for inclusion

DP1

Central-Wanchai Bypass (CWB) including its road tunnel and slip roads

Schedule 2, Part I, A.1 and A.7

Trunk road and road tunnel more than 800 m in length

DP2

Road P2 and other roads which are classified as primary/district distributor roads

Schedule 2, Part I, A.1

Primary / district distributor roads

DP3

Reclamation works including associated dredging works

Schedule 2, Part I, C.1 and C.12

Reclamation more than 5 ha in size and a dredging operation less than 100 m from a seawater intake point

DP5

Wan Chai East Sewage Outfall

Schedule 2, Part I, F.5 and F.6

Submarine sewage pipelines with a total diameter more than 1,200 mm and include a submarine sewage outfall

DP6

Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui

Schedule 2, Part I, C.12

A dredging operation less than 100 m from a seawater intake point

 

2.3          Division of the Project Responsibility

2.3.1.     Due to the multi-contract nature of the Project, there are a number of contracts sub-dividing the whole works area into different work areas to be commenced.  Contractors of individual contracts will be required by the EP holder to apply Further Environmental Permits such that the impact monitoring stations are sub-divided accordingly to facilitate the implementation of EM&A programme and to streamline the EM&A reporting for individual FEP holders correspondingly.

2.3.2.     In the reporting period, all the contracts were commenced and contract no. 04/HY/2006 had been completed. The details of individual contracts are summarized in Table2.2.

Table 2.2    Details of Individual Contracts under the Project

Contract No.

Contract Title

Associated DP(s)

Construction Commencement Date

HY/2009/17

Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works.

DP1

5 October 2010

(Completed)

HY/2009/18

Central – Wan Chai Bypass (CWB) – Central Interchange

DP1

21 April 2011

04/HY/2006

Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street

DP1

September 2010

(Completed)

HK/2009/01

Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works

DP1, DP2

25 August 2011

HK/2009/02

Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East(CWB Tunnel)

DP1

26 April 2011

HY/2009/15

Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)

DP1

13 July 2011

HY/2009/19

Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

DP1

24 March 2011

HK/2010/06

Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen Wan Line

DP3

22 March 2011

(Completed)

HK/2012/08

Wan Chai Development Phase II- Central-Wan Chai Bypass at Wan Chai West

DP1,DP2, DP3

10 March 2014

HY/2010/08

Central- Wanchai Bypass Tunnel – Tunnel (Slip Road 8)

DP1, DP2, DP3

21 March 2013

HY/2011/08

Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning

DP1

8 October 2014

 

2.3.3.     The construction works of Contract no. 04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A was completed, and the FEP was surrendered by the Contractor on 11 February 2011.

2.3.4.     Construction of bored pile E3B under HY/2009/17 was confirmed completed and the respective work area under FEP-03/364/2009 was handover and inspected under HY/2009/19 from 19 Dec 2012 onwards. Subsequently, the FEP-03/364/2009 was surrendered by the Contractor on 28 March 2013.

2.3.5.     Construction works under HK/2010/06 was confirmed completed and the respective work area under FEP-08/364/2009/A was handover and inspected under HK/2012/08 from 22 Sep 2014 onwards. Subsequently, the FEP-08/364/2009/A was surrendered by the Contractor on 3 October 2014.

 

 

 

 

 

2.4          Project Organization and Contact Personnel

2.4.1.     Civil Engineering and Development Department and Highways Department are the overall project controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer, Contractor(s), Environmental Team and Independent Environmental Checker are appointed to manage and control environmental issues.

2.4.2.     The proposed project organization and lines of communication with respect to environmental protection works are shown in Figure 2.2.  Key personnel and contact particulars are summarized in Table 2.3.

Table 2.3    Contact Details of Key Personnel

Party

Role

Post

Name

Contact No.

Contact Fax

AECOM

Engineer’s Representative for WDII

Principal Resident Engineer

Mr. Frankie Fan

2587 1778

2587 1877

Engineer’s Representative for CWB

Principal Resident Engineer

Mr. Peter Poon

3916 1818

3529 2829

Chun Wo – Leader Joint Venture

Contractor under Contract no. HK/2009/01

Project Manager

Mr. Simon Liu

2162 9909

2634 1626

Site Agent

Mr. Andy Yu

9648 4896

Construction Manager

Mr. Terry Wong

9757 9846

Construction Manager

Mr. Wyman Wong

9627 2467

Construction Manager

Mr. Kenneth Chan

9160 3850

Environmental Officer

Ms. Wendy Ng

9103 2370

Assistant Environmental Engineer

Ms. Connie Chan

9047 6148

Chun Wo – CRGL Joint Venture

Contractor under Contract no. HK/2009/02

Site Agent

Mr. K.K. Yuen

3658-3002

2827 9996

Project Manager

Mr. Paul Yu

3658 3085

Environmental Officer

Mr. C.P. Ho

9191 8856

Chun Wo - CRGL - MBEC Joint Venture

Contractor under Contract no. HY/2009/19

Project Manager

Mr. David Lau

3758 8879

2570 8013

Deputy Project Manager

Mr. William Luk

9456 9819

Deputy Site Agent

Eric Fong

6191 9337

Environmental Manager /

Environmental Officer

Mr. M.H. Isa

9884 0810

Environmental Engineer

Mr. Calvin Leung

9286 9208

Leighton Contractors (Asia) Limited

Contractor under Contract no. HY/2009/18

Site Agent

Mr. Jimmy Chu

2214 7700

2140 6799

Deputy Site Agent

Mr. Bob Yeung

2214 7703

Environmental Officer

Mr. Chris Chan

2823 1161

Assistant Environmental Engineer

Mr. Christy So

3937 1065

China State Construction Engineering (HK) Ltd.

Contractor under Contract no. HY/2009/15

Project Director

Mr. Chris Leung

3557 6393

2566 2192

Site Manager

Mr. Y. Huo

3557 6368

Contractor’s Representative

Mr. Rex Chan

3557 6371

Environmental Officer

Mr. Andy Mak

3557 6215

Environmental Supervisor

Mr. Harry Wong

3557 6348

China State- Leader JV

Contractor under Contract no. HK/2012/08

Project Director

Mr. C.N. Lai

9137 1811

2877 1522

Project Manager

Mr. Eddie Chung

9193 8871

Site Agent

Mr. Keith Tse

9095 7922

Environmental Officer

Mr. James MA

9130 9549

Environmental Supervisor

Mr. Y.L. Ho

6050 4919

China State

Contractor under Contract no.HY/2010/08

Project Director

Cheung Kit Cheung

3557 6399

3465 2899

Project Manager

Chan Ying Lun

9812 0592

Deputy Project Manager

Chris Leung

3467 4299

Site Agent

Mr. Andrew Wong

3467 4277

Environmental Officer

Mr. Gabriel Wong

3557 6464

Environmental Supervisor

Mr. Louis Lam Tsz Kwan

3557 6470

Leighton Joint Venture

Contractor under Contract no. HY/2011/08

Project Manager

Paul Evans

2823 1111

21406799

Site Agent

Colman Wong

9730 0806

Environmental Officer

Malcom Leung

3973 0850

Environmental Supervisor

Christy So

3973 1065

Lam Geotechnics Limited

Environmental Team (ET)

Environmental Team Leader (ETL)

Mr. Raymond Dai

2882 3939

2882 3331

RAMBOLL ENVIRON Hong Kong Limited

Independent Environmental Checker (IEC)

Independent Environmental Checker (IEC)

Mr. David Yeung

3465 2888

3465 2899

 

2.5          Principal Work and Activities

2.5.1.     Major construction activities for Contract no. HY/2009/18 have been commenced on 21 April 2011. During this reporting period, the principal work activities for Contract no. HY/2009/18 are summarized in Table2.4:

Table 2.4    Principal Work Activities for Contract no. HY/2009/18

March 2016

April 2016

May 2016

Ÿ   Drainage works

Ÿ   Road works

Ÿ   Landscaping works

Ÿ   Maintenance works

Ÿ   Drainage works

Ÿ   Road works

Ÿ   Landscaping works

Ÿ   Modification and Construction of Sign Gantries / Traffic Signs

Ÿ   Maintenance works

 

Ÿ   Drainage works

Ÿ   Road works

Ÿ   Landscaping works

Ÿ   Modification and Construction of Sign Gantries / Traffic Signs

Ÿ   Maintenance works

 

2.5.2.     Major construction activities for Contract no. HK/2009/01 have been commenced on 25 August 2011. During this reporting period, the principal work activities are summarized in Table2.5:

Table 2.5    Principal Work Activities for Contract no. HK/2009/01

March 2016

April 2016

May 2016

Ÿ   Stage 3a backfilling works

Ÿ   Stage 3b backfilling works

Ÿ   Stage 4 demolition of the bulkhead wall

Ÿ   Stage 4 construction tunnel structure

Ÿ   Reinstatement of outfall

Ÿ   Reinstatement of triangular planter at Fenwick Pier Street

 

Ÿ   Stage 3a backfilling works

Ÿ   Stage 3b backfilling works

Ÿ   Stage 4 construction tunnel structure

Ÿ   Reinstatement of outfall

Ÿ   Reinstatement of triangular planter at Fenwick Pier Street

 

Ÿ   Stage 3b backfilling works

Ÿ   Stage 4 construction tunnel structure

Ÿ   Reinstatement of outfall

Ÿ   Reinstatement of triangular planter at Fenwick Pier Street

 

 

2.5.3.     Major construction activities for Contract no. HK/2009/02 have been commenced on 26 April 2011. During this reporting period, the principal work activities are summarized in Table2.6:

 

 

Table 2.6    Principal Work Activities for Contract no. HK/2009/02

March 2016

April 2016

May 2016

Ÿ   Installation of steel angles for trough cover

Ÿ   Site clearance works was on going at OHVD at Tunnel Portion 1.

Ÿ   Construction of road side barriers

Ÿ   Construction of manhole frame & cover, gully frame and grating

Ÿ   Installation of steel angles for trough cover

Ÿ   Site clearance works was on going at OHVD at Tunnel Portion 1.

Ÿ   Construction of road side barriers

Ÿ   Construction of manhole frame & cover, gully frame and grating

Ÿ   100% excavation for formation level

Ÿ   100% blinding layer

Ÿ   95% Waterproofing works and base slab construction

Ÿ   Approximately 10% middle wall

Ÿ   Casting of Bored pile

Ÿ   Diaphragm wall panel construction

Ÿ   King post works

Ÿ   Demolition of existing Sun Hung Kai cooling water pumping station

Ÿ   Demolition of the existing structure

Ÿ   Site clearance works was on going at OHVD at Tunnel Portion 1.

Ÿ   Waterproofing works and base slab construction were completed

Ÿ   Middle wall and side wall construction

Ÿ   Diaphragm wall panel construction

Ÿ   King post work was completed

Ÿ   Instrumentation work was on going

 

 

Ÿ   Site clearance works was on going at OHVD at Tunnel Portion 1.

Ÿ   Site clearance works was on going at OHVD at Tunnel Portion 2.

Ÿ   Waterproofing work for side wall

Ÿ   Middle wall and side wall construction

Ÿ   Tunnel top slab construction

Ÿ   Diaphragm wall panel construction

Ÿ   Instrumentation work was on going

Ÿ   Excavation work

 

 

 

2.5.4.     Major construction activities for Contract no. HY/2009/15 have been commenced on 13 July 2011. During this reporting period, the principal work activities are summarized in Table 2.7:

Table 2.7    Principal Work Activities for Contract no. HY/2009/15

March 2016

April 2016

May 2016

Ÿ   Construction RC structure at TPCWAW

Ÿ   Dismantle steel work at TPCWAW

Ÿ   Remaining works inside tunnel at TS4 and TPCWAE

Ÿ   Remedial works at Mined Tunnel

 

Ÿ   Backfilling works at TPCWAW

Ÿ   Dismantle steel work at TPCWAW

Ÿ   Remaining works inside tunnel at TS4 and TPCWAE

Ÿ   Remedial works at Mined Tunnel

Ÿ   Reinstatement of Shaft B between TPCWAW and TPCWAE

 

Ÿ   Dismantle steel work at TPCWAW

Ÿ   Remedial works at Mined Tunnel

Ÿ   Remedial works at TS4, TPCWAE

Ÿ   Reinstatement of Shaft B between TPCWAW and TPCWAE

 

2.5.5.     Major construction activities for Contract no. HY/2009/19 have been commenced on March 2011. During this reporting period, the principal work activities are summarized in Table 2.8:

Table 2.8    Principal Work Activities for Contract no. HY/2009/19

March 2016

April 2016

May 2016

Ÿ   Pier construction for IEC

Ÿ   Construction of EVB

Ÿ   Column modification at F1 to F8

Ÿ   Watson Road laying of new water pipe

Ÿ   Oil Street drainage works

Ÿ   Excavation / Construction of retaining wall

Ÿ   Bridge segment erections

Ÿ   Pre-bored H-pile for Approach Ramp

Ÿ   Hing Fat Street modification works

Ÿ   EVA Temporary works

Ÿ   Hing Fat Street Slip Road Bridge E parapet construction

Ÿ   Pier construction for IEC

Ÿ   Construction of EVB

Ÿ   Column modification at F1 to F8

Ÿ   Watson Road laying of new water pipe

Ÿ   Oil Street drainage works

Ÿ   Excavation / Construction of retaining wall/Piling works/Approach Ramp

Ÿ   Bridge segment erections

Ÿ   Hing Fat Street modification works

Ÿ   EVA bulkhead removal

Ÿ   Hing Fat Street Slip Road Bridge E parapet construction

 

Ÿ   Pier construction for IEC

Ÿ   Construction of EVB

Ÿ   Column modification at F1 to F8

Ÿ   Oil Street drainage works

Ÿ   Bridge construction  and segment erection

Ÿ   Hing Fat Street modification works

Ÿ   EVA structure construction

Ÿ   Hing Fat Street Slip Road Bridge E L3 railing construction

Ÿ   Approach ramp sheet piling works

Ÿ   EVB waterproofing works

 

 

 

2.5.6.     Major construction activities for Contract no. HK/2012/08 have been commenced on March 2013. During the reporting period, the principal work activities are summarized in Table 2.9

Table 2.9      Principal Work Activities for Contract no. HK/2012/08

March 2016

April 2016

May 2016

Ÿ   Grouting

Ÿ   Construction of MVB

Ÿ   Pre-bored H-pile construction

Ÿ   Construction of concrete plug

Ÿ   Excavation and lateral support installation for CWB tunnel

Ÿ   Grouting

Ÿ   Construction of MVB

Ÿ   Pre-bored H-pile construction

Ÿ   Construction of concrete plug

Ÿ   Excavation and lateral support installation for CWB tunnel

Ÿ   Grouting

Ÿ   Construction of MVB

Ÿ   Construction of concrete plug

Ÿ   Excavation and lateral support installation for CWB tunnel

Ÿ   Structural works for CWB tunnel construction

2.5.7.     Major construction activities for Contract no. HY/2010/08 have been commenced on March 2013. During the reporting period, the principal work activities are summarized in Table 2.10

             Table 2.10          Principal Work Activities for Contract no. HY/2010/08

March 2016

April 2016

May 2016

Ÿ   Tree protection works next to existing BGO,

Ÿ   Drainage improvement works,

Ÿ   Excavation and Lateral Support for U-structure,

Ÿ   Grouting works,

Ÿ   Utility diversion works,

Ÿ   Retaining wall works

Ÿ   ELS works,

Ÿ   D-wall drill cutting works

Ÿ   Construction works for subway extension

Ÿ    

Ÿ   Tree protection works next to existing BGO,

Ÿ   Drainage improvement works,

Ÿ   Excavation and Lateral Support for U-structure,

Ÿ   Pipe piling & grouting works,

Ÿ   Utility diversion works,

Ÿ   Retaining wall works

Ÿ   ELS works,

Ÿ   D-wall drill cutting works

Ÿ   Construction works for subway extension

 

Ÿ   Tree protection works next to existing BGO,

Ÿ   Drainage improvement works,

Ÿ   Excavation and Lateral Support for U-structure,

Ÿ   Pipe piling & grouting works,

Ÿ   Utility diversion works,

Ÿ   Retaining wall works

Ÿ   ELS works,

Ÿ   Construction works for subway extension

 

 

 

 

 

 

2.5.8.     Contract no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B. During the reporting period, the principal work activities are summarized in Table 2.11

            Table 2.11                    Principal Work Activities for Contract no. HY/2011/08

March 2016

April 2016

May 2016

Ÿ   Construction of Ventilation Buildings, inclusive of Administrative Building, East Ventilation Shaft/Building, West Ventilation Building

Ÿ   Construction of Tunnel Thermal Barrier

Ÿ   Installation of Electricals and Mechanicals

 

Ÿ   Construction of Ventilation Buildings, inclusive of Administrative Building, East Ventilation Shaft, West Ventilation Building

Ÿ   Construction of Tunnel Thermal Barrier

Ÿ   Installation of Electricals and Mechanicals

Ÿ   Installation of Tunnel Features

 

Ÿ   Construction of Ventilation Buildings, inclusive of Administration Building, East Ventilation Shaft West Ventilation Building

Ÿ   Construction of Tunnel Thermal Barrier

Ÿ   Installation of Electricals and Mechanicals

Ÿ   Installation of Tunnel Features

 

2.5.9.     Implementation status of the recommended mitigation measures during this reporting period is presented in Appendix 2.1.

3.         Monitoring Requirements

3.1.          Noise Monitoring

Noise Monitoring Stations

3.1.1.     The noise monitoring stations for the Project are listed and shown in Table 3.1 and Figure 3.1.  Appendix 3.1 shows the established Action/Limit Levels for the monitoring works.

Table 3.1    Noise Monitoring Station

Station

Description

M1a

Harbour Road Sports Centre

M2b

Noon Gun Area

M3a

Tung Lo Wan Fire Station

M4b

Victoria Centre

M5b

City Garden

M6

HK Baptist Church Henrietta Secondary School

*M7e

International Finance Centre (Eastern End of Podium)

M7w

International Finance Centre (Western End of Podium)

M8

City Hall

* Remark 1: Location ID has been updated from M7 to M8 for City Hall

* Remark 2: M7e has become a reference station starting from 7 Aug 2012

Real time Noise Monitoring Stations

3.1.2.     The noise monitoring stations for the Project are listed and shown in Table 3.2 and Figure 3.1.. Appendix 3.1 shows the established Action/Limit Levels for the monitoring works.

Table 3.2    Real Time Noise Monitoring Station

District

Station

Description

Tin Hau

RTN1

FEHD Hong Kong Transport Section Whitefield Depot

North Point

RTN2a

Electric Centre

North Point

RTN3

Po Leung Kuk Yu Lee Mo Fan Memorial School

Tin Hau

RTN4

Causeway Bay Community Centre

* RTN2 was relocated from Oil Street Community Liaison Centre to Electric Centre on

   05 Oct 2012 and re-designated as RTN2a.

 

 

 

 

Noise Monitoring Parameters, Frequency and Duration

3.1.3.     The construction noise level shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq (30 minutes) shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For all other time periods, Leq (5 minutes) shall be employed for comparison with the Noise Control Ordinance (NCO) criteria. Supplementary information for data auditing, statistical results such as L10 and L90 shall also be obtained for reference.

3.1.4.     Noise monitoring shall be carried out at all the designated monitoring stations. The monitoring frequency shall depend on the scale of the construction activities. The following is an initial guide on the regular monitoring frequency for each station on a weekly basis when noise generating activities are underway:

·          One set of measurements between 0700 and 1900 hours on normal weekdays.

3.1.5.     Real time noise shall be carried out at the designated monitoring stations. The following is an initial guide on the regular monitoring frequency for each station on a 24 hours daily basis when noise generating activities are underway:

·          One set of measurements between 0700 and 1900 hours on normal weekdays.

·          One set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and 2300 hours on public holidays.

·          One set of measurements between 2300 and 0700 hours on next day on everyday.

3.1.6.     If construction works are extended to include works during the hours of 1900 – 0700 as well as public holidays and Sundays, additional weekly impact monitoring shall be carried out during respective restricted hours periods. Applicable permits under NCO shall be obtained by the Contractor.

Monitoring Equipment

3.1.7.     As referred to in the Technical Memorandum ™ issued under the NCO, sound level meters in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying out the noise monitoring. Immediately prior to and following each noise measurement the accuracy of the sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency. Measurements may be accepted as valid only if the calibration level from before and after the noise measurement agree to within 1.0 dB.

3.1.8.     Noise measurements shall not be made in fog, rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with a portable wind speed meter capable of measuring the wind speed in m/s.

3.1.9.     The sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency before deployment to the site and during each site visit. Measurements may be accepted as valid only if the calibration level from before and after the noise measurement agree to within 1.0 dB.

3.2.          Air quality monitoring

Air Quality Monitoring Stations

3.2.1.     The air quality monitoring stations for the Project are listed and shown in Table 3.3 and Figure 3.1. Appendix 3.1 shows the established Action/Limit Levels for the monitoring works.

Table 3.3  Air quality monitoring Stations

Station ID

Monitoring Location

Description

CMA1b

Oil Street Site Office*

North Point

CMA2a

Causeway Bay Community Centre

Causeway Bay

CMA3a

CWB PRE Site Office

Causeway Bay

CMA4a

Society for the Prevention of Cruelty to Animals

Wan Chai

CMA5b

Pedestrian Plaza**

Wan Chai

MA1e

International Finance Centre (Eastern End of Podium)

Central

MA1w

International Finance Centre (Western End of Podium)

Central

Remarks*: The location ID of monitoring station CMA1b was updated as “Oil Street Site Office” in April 2013. With respect to the removal of Oil Street Site Office, the respective air quality monitoring station CMA1b was finely adjusted on 11 September 2015.

Remarks**:  With respect to the area handover, the air quality monitoring station CMA5a at Children Playgrounds opposite to the Pedestrian Plaza was relocated to the Pedestrian Plaza on 3 December 2014. The station reference and location ID of the air quality monitoring station CMA5a was updated as CMA5b and Pedestrian Plaza respectively.

 

Air quality monitoring Parameters, Frequency and Duration

3.2.2.     One-hour and 24-hour TSP levels should be measured to indicate the impacts of construction dust on air quality. The 24-hour TSP levels shall be measured by following the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.

3.2.3.     All relevant data including temperature, pressure, weather conditions, elapsed-time meter reading for the start and stop of the sampler, identification and weight of the filter paper, and any other local atmospheric factors affecting or affected by site conditions, etc., shall be recorded down in detail.

3.2.4.     For regular impact monitoring, the sampling frequency of at least once in every six-days, shall be strictly observed at all the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least three times in every six-days should be undertaken when the highest dust impact occurs.

 

Sampling Procedure and Monitoring Equipment

3.2.5.     High volume samplers (HVSs) in compliance with the following specifications shall be used for carrying out the 1-hour and 24-hour TSP monitoring:

·          0.6 – 1.7 m3 per minute adjustable flow range;

·          Equipped with a timing / control device with +/- 5 minutes accuracy for 24 hours operation;

·          Installed with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;

·          Capable of providing a minimum exposed area of 406 cm2;

·          Flow control accuracy: +/- 2.5% deviation over 24-hour sampling period;

·          Equipped with a shelter to protect the filter and sampler;

·          Incorporated with an electronic mass flow rate controller or other equivalent devices;

·          Equipped with a flow recorder for continuous monitoring;

·          Provided with a peaked roof inlet;

·          Incorporated with a manometer;

·          Able to hold and seal the filter paper to the sampler housing at horizontal position;

·          Easily changeable filter; and

·          Capable of operating continuously for a 24-hour period.

 

3.2.6.     Initial calibration of dust monitoring equipment shall be conducted upon installation and thereafter at bi-monthly intervals. The transfer standard shall be traceable to the internationally recognized primary standard and be calibrated annually. The concern parties such as IEC shall properly document the calibration data for future reference. All the data should be converted into standard temperature and pressure condition.

3.2.7.     Laboratory Measurement / Analysis

3.2.8.     A clean laboratory with constant temperature and humidity control, and equipped with necessary measuring and conditioning instruments to handle the dust samples collected, shall be available for sample analysis, and equipment calibration and maintenance. The laboratory should be HOKLAS accredited.

3.2.9.     Filter paper of size 8” x 10” shall be labelled before sampling. It shall be a clean filter paper with no pinholes, and shall be conditioned in a humidity-controlled chamber for over 24-hours and be pre-weighed before use for the sampling.

3.2.10.   After sampling, the filter paper loaded with dust shall be kept in a clean and tightly sealed plastic bag. The filter paper shall then be returned to the laboratory for reconditioning in the humidity controlled chamber followed by accurate weighing by an electronic balance with readout down to 0.1 mg. The balance shall be regularly calibrated against a traceable standard.

3.2.11.   All the collected samples shall be kept in a good condition for 6 months before disposal.

 

 

4.       Monitoring Results

4.0.1.     Per EPD’s letter dated 3 Aug 2012 (received by ET on 6 Aug 2012 through HyD), noise monitoring at M8 – City Hall commenced on 7 Aug 2012, and the monitoring station M7e – International Finance Centre (Eastern Podium) has become a reference station starting from 7 Aug 2012.

4.0.2.     Due to safety concerns, the monitoring location for M4b – Victoria Centre has been finely adjusted from 7 June 2012.

4.0.3.     Monitoring for report of review baseline noise level was performed from 11 April 2011 to 8 June 2011.  Then the report was submitted on the 20 June 2011, verified by IEC on 18 July 2011 and was approved by ER by January 2012.  The new baseline is used for the noise calculation starting from the January 2012 reporting month.

4.0.4.     The environmental monitoring will be implemented based on the division of works areas of each designed project managed under different contracts with separate FEP applied by individual contractors.  Overall layout showing work areas of various contracts, latest status of work commencement and monitoring stations is shown in Figure 2.1 and Figure 3.1. The monitoring results are presented in according to the Individual Contract(s).

4.0.5.     In the reporting period, the concurrent contracts are as follows:

Ÿ   Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

Ÿ   Contract no. HY/2009/18 – Central –Wanchai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A

Ÿ   Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009

Ÿ   Contract no. HK/2009/01 –Wanchai Development Phase II – Central –Wanchai Bypass at Hong Kong Convention and Exhibition Centre under FEP-02/364/2009

Ÿ   Contract no. HK/2009/02 Wanchai Development Phase II – Central- Wanchai Bypass at Wanchai East under FEP-01/364/2009

Ÿ   Contract no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at Wan Chai West under FEP-09/364/200/B

Ÿ   Contract no. HY/2010/08 – Central and WanChai Bypass – Slip road 8 Section under FEP-10/364/2009/B

Ÿ   Contract no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009/B

 

 

 

 

 

 

  4.1.       Noise Monitoring Results

 

Contract no. HY/2009/18 – Central – Wanchai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A

4.1.1.     Noise monitoring for the Central Interchange works under contract no. HY/2009/18 was commenced on 22 April 2011.The proposed division of noise monitoring stations for Contract no. HY/2009/18 are summarized in Table 4.1 below.

Table 4.1    Noise Monitoring Station for Contract no. HY/2009/18

Station

Description

*M7e

International Finance Centre (Eastern End of Podium)

M7w

International Finance Centre (Western End of Podium)

M8

City Hall

* Remark: M7e has become a reference station starting from 7 Aug 2012

 

4.1.2.     No exceedance was recorded in this reporting quarter.

4.1.3.     Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 4.1.

 

Contract no. HK/2009/01 - Wanchai Development Phase II - Central - Wanchai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009 and Contract no. HK/2009/02 - Wanchai Development Phase II - Central - Wanchai Bypass at Wanchai East (CWB Tunnel) under FEP-01/364/2009

4.1.4.     The commencement of construction works for Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011 and HK/2009/02 under FEP-01/364/2009 is on 26 April 2011.The proposed division of air quality monitoring stations are summarized in Table 4.2 below.

Table 4.2    Noise Monitoring Stations for Contract nos. HK/2009/01 and HK/2009/02

Station

Description

M1a

Harbour Road Sports Centre

Reporting Month of March 2016

4.1.1       Three limit level exceedances were recorded at M1a- Harbour Road Sports Centre on 02, 08 and 15 March 2016 in this reporting month.

4.1.2       Operation of multiple air compressor at Ex- Wan Chai Swimming Pool (adjacent to Habour Road Sports Centre directly opposite to the monitoring station) under non WDII-CWB Contractor was observed as the major noise contribution during monitoring on 02 and 08 March 2016 while operation of multiple air compressor and piling works at Ex- Wan Chai Swimming Pool (adjacent to Habour Road Sports Centre directly opposite to the monitoring station) under non WDII-CWB Contractor as major noise contribution during monitoring on 15 March 2016.  As such, the exceedances were considered as non-Project related.

Reporting Month of April 2016

4.1.5.     Two limit level exceedances were recorded at M1a- Harbour Road Sports Centre on 29 March 2016 and 12 April 2016 in this reporting month.

4.1.6.     Operation of multiple air compressor at Ex- Wan Chai Swimming Pool (adjacent to Habour Road Sports Centre directly opposite to the monitoring station) under non WDII-CWB Contractor was observed as the major noise contribution during monitoring on 29 March 2016 while breaking works at Ex- Wan Chai Swimming Pool (adjacent to Habour Road Sports Centre directly opposite to the monitoring station) under non WDII-CWB Contractor as major noise contribution during monitoring on 12 April 2016.  As such, the exceedances were considered as non-Project related.

Reporting Month of May 2016

4.1.7.     Two limit level exceedances were recorded at M1a- Harbour Road Sports Centre on 04 and 24 May 2016 in this reporting month.

4.1.8.     Breaking works at Ex- Wan Chai Swimming Pool (adjacent to Harbour Road Sports Centre directly opposite to the monitoring station) under non WDII-CWB Contractor was observed as the major noise contribution during monitoring on 04 May 2016 while operation of Hydromil Trench Cutter at Ex- Wan Chai Swimming Pool (adjacent to Harbour Road Sports Centre directly opposite to the monitoring station) under non WDII-CWB Contractor as major noise contribution during monitoring on 24 May 2016.  As such, the exceedances were considered as non-Project related.

4.1.9.     Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 4.1.

Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

4.1.10.   The commencement of construction works for Contract no. HY/2009/15 under FEP-06/364/2009/A was on 13 July 2011. Noise monitoring was commenced on 13 July 2011. The proposed division of noise monitoring stations are summarized in Table 4.3 below.

Table 4.3    Noise Monitoring Station for Contract nos. HY/2009/15

Station

Description

M2b

Noon Gun Area

M3a

Tung Lo Wan Fire Station

 

4.1.11.   No action or limit level exceedance was recorded in this reporting quarter.

4.1.12.   Details of noise monitoring results and graphical presentation can be referred in Appendix 4.1. 

Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D

4.1.13.   Noise monitoring for the tunnel works under contract no. HY/2009/19 was commenced on 24 April 2011. The proposed division of noise monitoring stations are summarized in Table 4.4 below.

Table 4.4    Noise Monitoring Stations for Contract no. HY/2009/19

Station

Description

M4b

Victoria Centre

M5b

City Garden

M6

HK Baptist Church Henrietta Secondary School

 

        

 

 

Reporting Month of March 2016

4.1.14.   No action or limit level exceedance was recorded in this reporting month.

Reporting Month of April 2016

4.1.15.   Two limit level exceedances were recorded at M6 – HK Baptist Church Henrietta Secondary School on 11 and 19 April 2016 in the reporting month.

4.1.16.   Traffic noise was observed during monitoring on 11 and 19 April 2016 and it was considered as the major noise contribution. As such, the limit level exceedances were concluded as non-project related.

Reporting Month of May 2016

4.1.17.   No action or limit level exceedance was recorded in this reporting month.

4.1.18.   Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 4.1 and the Notification of Exceedance can be referred in Appendix 6.2.

 

 

 

 

 

Contract no. HY/2010/08 – Central-Wanchai Bypass –Wanchai Bypass Tunnel (Slip Raod 8 Section) under FEP-09/364/2009/B

4.1.19.   The commencement of construction works for Contract no. HY/2010/08 under FEP-10/364/2009/B was on 02 September 2013. Noise monitoring was commenced on 02 September 2013. The proposed divisions of noise monitoring stations are summarized in Table 4.5 below.

 

Table 4.5    Noise Monitoring Stations for Contract no. HY/2010/08

Station

Description

M3a

Tung Lo Wan Fire Station

4.1.20.   No action or limit level exceedance was recorded in this reporting quarter.

4.1.21.   Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 4.1.

Contract no. HY/2011/08 – Central - Wan Chai Bypass (CWB) – Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning

4.1.22.   Noise monitoring for the Central Interchange works under contract no. HY/2009/18 was commenced on 22 April 2011.The proposed division of noise monitoring stations for Contract no. HY/2009/18 are summarized in Table 4.6 below:

Table 4.6      Noise Monitoring Stations for Contract no. HY/2011/08

Station

Description

M4b

Victoria Centre

*M7e

International Finance Centre (Eastern End of Podium)

M7w

International Finance Centre (Western End of Podium)

M8

City Hall

* Remark: M7e has become a reference station starting from 7 Aug 2012

4.1.23.   No action or limit level exceedance was recorded in this reporting quarter.

4.1.24.   Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 4.1.

 

 

 

 

 

 

  4.2.       Real Time Noise Monitoring Results

Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D

4.2.1.     Real time noise monitoring results measured in this reporting period are reviewed and summarized. Details of real time noise monitoring results and graphical presentation can be referred to Appendix 4.2

4.2.2.     The proposed division of noise monitoring stations are summarized in Table 4.7 below. Real time noise monitoring for major construction works under contract no. HY/2009/19 was commenced on 24 April 2011.

Table 4.7    Real Time Noise Monitoring Stations for Contract no. HY/2009/19

Location ID

District

Description

RTN1

Tin Hau

FEHD Hong Kong Transport Section Whitefield Depot

RTN2a

North Point

Electric Centre  (Replacement of RTN2)

RTN3

North Point

Pok Leung Kuk Yu Lee Mo Fun Memorial School

RTN4

Tin Hau

Causeway Bay Community Centre

* Real time noise monitoring results and graphical presentation during night time period are for information only.

*Real-time noise monitoring results and graphical presentation for RTN3 during restricted hours are for information only as no night classes were conducted at the educational institute.

             Reporting month of March 2016

4.2.3.     No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the reporting month.

4.2.4.     Limit level exceedances were recorded at RTN2a-Electric Centre on 01 and 02 March 2016 during daytime in the reporting month. On 01 March 2016, sheet piling and excavation works were undertaken by Contract HY/2009/19 and mitigation measures including erection of temporary noise barrier was implemented while roof top cleaning works by non-CWB Contractor was undertaken immediately next to the noise monitoring station and was considered as major noise contribution. On 02 March 2016, sheet piling, excavation and concreting works were undertaken by Contract HY/2009/19 and noise mitigation measures including the erection of noise barrier was implemented while roof top floor cleaning works at the roof top by non-CWB Contractor was undertaken immediately next to the noise monitoring station and was considered as major noise contribution. As such, the exceedances were considered as non-Project related.

4.2.5.     No limit level exceedances were recorded at RTN3-Yue Lee Mo Fan Memorial School in the reporting month.

4.2.6.     No limit level exceedances were recorded at RTN4-Causeway Bay Community Centre in the reporting month.

Reporting month of April 2016

4.2.7.     No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the reporting month.

4.2.8.     Limit level exceedances were recorded at RTN2a-Electric Centre on 02, 05, 06, 08, 21, 23, 25 and 26 April 2016 during daytime in the reporting month. On 02, 05 and 06 April 2016, only installation of pre-cast parapet, pipe laying works and concreting of blinding layer for pipe laying were undertaken by Contract HY/2009/19, no major noise concern of the works was considered. On 08 April 2016, excavation and backfilling works and erection of concrete surround were conducted and no major noise concern was considered for the works. On 23 April 2016, backfilling works and concreting for manhole cover were conducted and no major noise concern was considered for the works. On 21, 25 and 26 April 2016, concreting and excavation for drain pipe were conducted and no major noise concern was considered for the works.  Nevertheless, roof top water proofing works by non-CWB Contractor was undertaken immediately next to the noise monitoring station across the monitoring period across April 2016 and was considered as major noise contribution As such, the exceedances were considered as non-Project related.

4.2.9.     Limit level exceedances were recorded at RTN3-Yue Lee Mo Fan Memorial School on 13, 18 and 25 April 2016 in the reporting month. On 13, 18 and 25 April 2016 during the monitoring period, no construction works was undertaken under Contract HY/2009/19. Nevertheless, based on relevant data from Hong Kong observatory, adverse weather condition with significant rainfall was recorded on 13, 18 and 25 April 2016 and thunderstorm warning signal was hoisted on 13 and 25 April 2016 and considered as the major noise contribution. As such, the exceedances were considered as non-project related.

4.2.10.   Limit level exceedances were recorded at RTN4-Causeway Bay Community Centre on 08 and 09 April 2016 in the reporting month. On 8 April 2016, minor vertical face drilling works was conducted and on 09 April 2016 crosshead concreting was conducted under HY/2009/19. In view of the same construction sequence of vertical face drilling was extended to other time period with no noise emanation recorded and drilling works immediately next to the monitoring station by non-CWB Contractor for external panel installation at Causeway Bay Community Centre was conducted on the monitoring date, the exceedances were considered as non- Project related.

Reporting month of May 2016

4.2.11.   No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the reporting month.

4.2.12.   No limit level exceedances were recorded at RTN2a-Electric Centre in the reporting month.

4.2.13.   Limit level exceedances were recorded at RTN3-Yue Lee Mo Fan Memorial School on 27 April 2016, 3 and 10 May2016 in the reporting month. On 27 April 2016 during the monitoring period, no construction works was undertaken under Contract HY/2009/19 and cast-in-item installation and erection of formwork was conducted under Contract HY/2009/19 on 03 and 10 May 2016 respectively. Based on relevant data from Hong Kong observatory, adverse weather condition with significant rainfall was recorded on 27 April 2016 amber rainstorm warning signal and red rainstorm warning signal was hoisted on 03 and 10 May 2016 respectively and considered as the major noise contribution. As such, the exceedances were considered as non-project related.

4.2.14.   Limit level exceedances were recorded at RTN4-Causeway Bay Community Centre on 04 May 2016 in the reporting month. On 04 May 2016, segment installation was conducted under HY/2009/19 while external panel installation works was observed undertaken by non-CWB Contractor at Causeway Bay Community Centre near the monitoring station and considered as the major noise contribution. As such, the exceedance was considered as non- Project related.

4.2.15.   Real time noise monitoring results measured in this reporting quarter are reviewed and summarized. Details of real time noise monitoring results and graphical presentation can be referred to Appendix 4.2

Contract no. HY/2011/08 – Central - Wan Chai Bypass (CWB) – Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning

4.2.16.   The proposed division of noise monitoring stations are summarized in Table 4.8 below. Real time noise monitoring for major construction works under contract no. HY/2011/08 was commenced on 19 March 2015.

Table 4.8    Real Time Noise Monitoring Stations for Contract no. HY/2011/08

Location ID

District

Description

RTN1

Tin Hau

FEHD Hong Kong Transport Section Whitfield Depot

RTN2a1

North Point

Hong Kong Electric Centre

* Real time noise monitoring results and graphical presentation during restrict hours and night time period are for information only and noise during CNP period shall be controlled under NCO.

    Remarks 1: With respect to the possession of site area Portion Xa and Portion Xb since 7 March 2016 as confirmed by CWB RSS,  real time noise monitoring station RTN2a was associated with Contract no. HY/2011/08 from 07 March 2016 onwards

     Reporting month of March 2016

4.2.17.   No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the reporting month.

4.2.18.   Limit level exceedances were recorded at RTN2a- Electric Centre on 01 and 02 March 2016 during daytime in the reporting month. No construction works was undertaken under Contract HY/2011/08 while roof top floor cleaning works at the roof top by non-CWB Contractor was undertaken immediately next to the noise monitoring station and was considered as major noise contribution. As such, the exceedances were considered as non-Project related.

 

Reporting month of April 2016

4.2.19.   No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the reporting month.

4.2.20.   Limit level exceedances were recorded at RTN2a-Electric Centre on 02, 05, 06, 08, 21, 23, 25 and 26 April 2016 during daytime in the reporting month. No construction works was undertaken under Contract HY/2011/08 on 02, 05, 06, 08, 21, 23 April 2016. On 25 April 2016, site formation with one excavator in operation and on 26 April 2016, manual rebar installation with coupler was conducted and no major noise concern was considered for the above works Nevertheless, roof top water proofing works by non-CWB Contractor was undertaken immediately next to the noise monitoring station across the monitoring period across April 2016 and was considered as major noise contribution As such, the exceedances were considered as non-Project related.

Reporting month of May 2016

4.2.21.   No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the reporting month.

4.2.22.   No limit level exceedances were recorded at RTN2a-Electric Centre in the reporting month.

4.2.23.   Real time noise monitoring results measured in this reporting quarter are reviewed and summarized. Details of real time noise monitoring results and graphical presentation can be referred to Appendix 4.2

 

 

 

 

 

  4.3.       Air quality monitoring Results

4.3.1       Due to extension of site boundary by contractor of HY/2009/19, location of air quality monitoring station CMA1b – Oil Street Community Liaison Centre has been finely adjusted on 21 April 2012.

Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A

4.3.2       Air quality monitoring for the Central Interchange works under contract no. HY/2009/18 was commenced on 21 April 2011. The proposed division of air quality monitoring stations are summarized in Table 4.9 below.

Table 4.9    Air quality monitoring Stations for Contract no. HY/2009/18

Station

Description

MA1e

International Finance Centre (Eastern End of Podium)

MA1w

International Finance Centre (Western End of Podium)

 

4.3.3       No action or limit level exceedance was recorded in the reporting period.

4.3.4       Air quality monitoring results measured in this reporting period are reviewed and summarized. Details of air quality monitoring results and graphical presentation can be referred in Appendix 4.3. 

 

Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009

4.3.5       The commencement of construction works for Contract no. HK/2009/01 under FEP-02/364/2009 is on 25 August 2011. The proposed division of air quality monitoring stations are summarized in Table 4.10 below.

Table 4.10 Air quality monitoring Station for Contract no. HK/2009/01

Station

Description

CMA5b

Pedestrian Plaza

Reporting month of March 2016

4.3.6       No action or limit level exceedance was recorded in this reporting month.

Reporting month of April 2016

4.3.7       One action level exceedance was recorded at monitoring station CMA5b on 14 April 2016 during 1hr TSP monitoring in the reporting month.

4.3.8       Only work activities within tunnel section and no construction activities at ground was undertaken on the monitoring date around Pedestrian Plaza under Contract HK/2009/01 and no particular observation regarding air quality impact was observed during sampling. In view of the above, the action level exceedance was considered to be non-project related and contributed by local ambient condition.

Reporting month of May 2016

4.3.9       No action or limit level exceedance was recorded in this reporting month.

4.3.10    Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air quality monitoring results and graphical presentation can be referred in Appendix 4.3. 

 

Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

4.3.11    The commencement of construction works for HK/2009/02 under FEP-01/364/2009 is on 26 April 2011. The proposed division of air quality monitoring stations are summarized in Table 4.11 below.

Table 4.11 Air quality monitoring Station for Contract no. HK/2009/02

Station

Description

CMA4a

Society for the Prevention of Cruelty to Animals

4.3.12    No action or limit level exceedance was recorded in the reporting period.

4.3.13    Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air quality monitoring results and graphical presentation can be referred in Appendix 4.3. 

 

Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

4.3.14    The commencement of construction works for Contract no. HY/2009/15 under FEP-06/364/2009/A was on 13 July 2011. The proposed division of air quality monitoring stations are summarized in Table 4.12 below.

Table 4.12 Air quality monitoring Station for Contract no. HY/2009/15

Station

Description

CMA3a

CWB site office at  Wanchai Waterfront Promenade

4.3.15    No action or limit level exceedance was recorded in the reporting period.

4.3.16    Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air quality monitoring results and graphical presentation can be referred in Appendix 4.13. 

Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D

4.3.17    Air quality monitoring for the tunnel works was commenced on 26 April 2011 for Contract no. HY/2009/19 under FEP-07/364/2009/A. The proposed division of air quality monitoring stations are summarized in Table 4.13 below.

Table 4.13 Air quality monitoring Stations for Contract no. HY/2009/19

Station

Description

CMA1b

Oil Street Site Office

CMA2a

Causeway Bay Community Centre

4.3.18    No action or limit level exceedance was recorded in the reporting period.

4.3.19    Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air quality monitoring results and graphical presentation can be referred in Appendix 4.3. 

 

Contract no. HK/2012/08- Wan Chai Development Phase II – Central-Wan Chai Bypass at Wan Chai West

4.3.20    The commencement of construction works for Contract no. HK/2012/08 under FEP-09/364/2009/C was on May 2014. Air quality monitoring was commenced on 14 July 2011. The proposed division of air quality monitoring stations are summarized in Table 4.14 below.

Table 4.14 Air quality monitoring Station for Contract no. HK/2012/08

Station

Description

CMA5b

Pedestrian Plaza

Reporting month of March 2016

4.3.21    No action or limit level exceedance was recorded in this reporting month.

Reporting month of April 2016

4.3.22    One action level exceedance was recorded at monitoring station CMA5b on 14 April 2016 during 1hr TSP monitoring in the reporting month.

4.3.23    After investigation, formwork erection and internal transfer of excavated material were undertaken on the monitoring date at around Pedestrian Plaza under Contractor of HK/2012/08, dust suppression measure including haul road and excavated soil maintained in dampened condition were implemented and no particular observation regarding air quality impact was observed during sampling. In view of the above, the action level exceedance was considered to be non-project related and contributed by local ambient condition.

Reporting month of May 2016

4.3.24    No action or limit level exceedance was recorded in this reporting month.

4.3.25    Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air quality monitoring results and graphical presentation can be referred in Appendix 4.3.

 

Contract no. HY/2010/08 – Central-Wanchai Bypass –Wanchai Bypass Tunnel (Slip Raod 8 Section) under FEP-09/364/2009/B

4.3.26    The commencement of construction works for Contract no. HY/2010/08 under FEP-09/364/2009/B was on July 2014. Air quality monitoring was commenced on 14 July 2011. The proposed division of air quality monitoring stations are summarized in Table 4.15 below.

Table 4.15 Air quality monitoring Station for Contract no. HY/2010/08

Station

Description

CMA3a

CWB PRE Site Office

4.3.27    No action or limit level exceedance was recorded in the reporting period.

4.3.28    Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air quality monitoring results and graphical presentation can be referred in Appendix 4.3. 

 

Contract no. HY/2011/08 – Central - Wan Chai Bypass (CWB) – Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning

4.3.29    Air quality monitoring for the Central Interchange works under contract no. HY/2011/08 was commenced on 21 April 2011. The proposed division of air quality monitoring stations are summarized in Table 4.16 below.

Table 4.16   Air quality monitoring Stations for Contract no. HY/2011/08

Station

Description

MA1e

International Finance Centre (Eastern End of Podium)

MA1w

International Finance Centre (Western End of Podium)

CMA1b

Oil Street Site Office

CMA2a

Causeway Bay Community Centre

4.3.30    No action or limit level exceedance was recorded in the reporting period.

4.3.31    Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air quality monitoring results and graphical presentation can be referred in Appendix 4.3. 

 

  4.4.       Waste Monitoring Results

Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009

4.4.1.     Inert and non-inert C&D waste was disposed of in this reporting period. Details of the waste flow table are summarized in Table 4.17.

Table 4.17  Details of Waste Disposal for Contract no. HK/2009/01

Waste Type*

Quantity this quarter, m3

Cumulative-to-Date. m3

Disposal / Dumping Grounds

Inert C&D materials disposed

            1661.15

107791.73

TKO137, TM38

Inert C&D materials recycled

439.5

98512.03

N/A

Non-inert C&D materials disposed

333.14

4590.2

SENT Landfill

Non-inert C&D materials recycled

91905

1209071

N/A

Chemical waste disposed

Nil

10400

Kwun Kee (Chemical Waste Collector)

Marine Sediment

(Type 1- Open Seas Disposal), m3

Nil

11527

 

South of Cheung Chau

Marine Sediment (Type 1 – Open Sea Disposal (Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3

Nil

16261

East of Cha Chau

South Brothers

 Remarks: The cumulative amount of inert C&D materials recycled was clarified in the reporting quarterly

Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

4.4.2.     Inert and non-inert C&D waste were disposed of in this reporting period. Details of the waste flow table are summarized in Table 4.18.

Table 4.18  Details of Waste Disposal for Contract no. HK/2009/02

Waste Type*

Quantity this quarter,  m3

Cumulative-to-Date.  m3

Disposal / Dumping Grounds

Inert C&D materials disposed

15844

483137.412

TKO137, TM 38

Inert C&D materials recycled

Nil

46520

WCR2

Non-inert C&D materials disposed

436

2792.317

SENT Landfill

Non-inert C&D materials recycled

Nil

N/A

N/A

Chemical waste disposed

Nil

17718

N/A

 

Marine Sediment (Type 1 – Open Sea Disposal) , m3

Nil

27889

South Cheung Chau

 

Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A

4.4.3.     Inert and non-inert C&D waste was disposed of in this reporting period. Details of the waste flow table are summarized in Table 4.19.

Table 4.19  Details of Waste Disposal for Contract no. HY/2009/18

Waste Type*

Quantity this quarter,  m3

Cumulative-to-Date.  m3

Disposal / Dumping Grounds

Inert C&D materials disposed

1752.96

140233.94

T.K.O. 137

Inert C&D materials recycled

Nil

58787.05

N/A

Non-inert C&D materials disposed

122.27

4090.69

SENT Landfill

Non-inert C&D materials recycled

(tonnes)

2.16

878.37

N/A

Chemical waste disposed

Nil

4440

N/A

       

Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

4.4.4.     Inert and non-inert C&D waste was disposed of in this reporting period. Details of the waste flow table are summarized in Table 4.20.

Table 4.20  Details of Waste Disposal for Contract no. HY/2009/15

Waste Type*

Quantity this quarter,  m3

Cumulative-to-Date.  m3

Disposal / Dumping Grounds

Inert C&D materials disposed

Nil

Nil

619723.37

245453.3

Tuen Mun Area 38

TKO137 FB

Inert C&D materials recycled

Nil

358660.77

HY/2009/11, ex-PCWA

TS4

Non-inert C&D materials disposed

442.81

4309.81

SENT Landfill

Non-inert C&D materials recycled

Nil

5496446.2

Xun Xiang Metal ware

Skylight Recycle (paper)

Chemical waste disposed

Nil

22755

Dunwell Group

Marine Sediment (Type1-Open Sea Disposal (Dedicate Sites) &Type 2 – Confined Marine Disposal), m3

Nil

5684

South of the Brothers

 Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D

4.4.5.     Inert C&D materials was recycled non-inert C&D waste was disposed of in this reporting period. Details of the waste flow table are summarized in Table 4.21.

Table 4.21  Details of Waste Disposal for Contract no. HY/2009/19

Waste Type*

Quantity this quarter,  m3

Cumulative-to-Date.  m3

Disposal / Dumping Grounds

Inert C&D materials disposed

4498.39

649146.32

N/A

Inert C&D materials recycled

Nil

82349.7

N/A

Non-inert C&D materials disposed

486.96

4815.89

SENT Landfill

Non-inert C&D materials recycled

18.79

548.4

N/A

Chemical waste disposed

              0.49

9.92

N/A

Marine Sediment (Tunnel) (Type 1- Open Sea Disposal), m3

Nil

20556

South of Cheung Chau

Marine Sediment (Tunnel) (Type 1- Open Sea Disposal (Dedicated Sites) & Type 2 – Confined Marine Disposal), m3

Nil

30751

East of Sha Chau

             

Contract no. HK/2012/08 Wan Chai Development Phase II - Central-Wan Chai Bypass at Wan Chai West under FEP-09/364/2009/B

4.4.6.     No inert and Non-inert C&D wastes were disposed of in this reporting month. Details of the waste flow table are summarized in Table 4.22.

Table 4.22  Details of Waste Disposal for Contract no. HK/2012/08

Waste Type*

Quantity this quarter,  m3

Cumulative-to-Date,  m3

Disposal / Dumping Grounds

Inert C&D materials disposed

23097

161438

N/A

Inert C&D materials recycled

32664

69618

N/A

Non-inert C&D materials disposed

387

1502

N/A

Non-inert C&D materials recycled

NIL

NIL

N/A

Chemical waste disposed

NIL

NIL

N/A

Marine Sediment

(Type 1) Disposal, m3

Nil

3145

South of Cheung Chau/ South of Brothers

Contract no. HY/2010/08 Central – Wan Chai Bypass (CWB) – Tunnel (Slip Road 8) under FEP-10/364/2009/B

4.4.7.     No inert and Non-inert C&D wastes were disposed of in this reporting month. Details of the waste flow table are summarized in Table 4.23.

Table 4.23  Details of Waste Disposal for Contract no. HY/2010/08

Waste Type*

Quantity this quarter,  m3

Cumulative-to-Date,  m3

Disposal / Dumping Grounds

Inert C&D materials disposed

 

84793.3

120521.1

60929.7

37641.6

541124.2

204874.6

71381.7

38030.6

TM 38

WENT

SENT

TKO area 137

Inert C&D materials recycled

Nil

Nil

Nil

Non-inert C&D materials disposed

322.66

1905.66

SENT

Non-inert C&D materials recycled

Nil

Nil

Nil

Chemical waste disposed

Nil

979

Nil

Type 1 – Open Sea Disposal

10900.4

10900.4

East Sha Chau/ South Brothers Island

Type 2 – Confined Marine disposal

549.2

549.2

East Sha Chau

 

 

           

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

             Remarks: The cumulative amount of inert C&D material disposed was clarified by the Contractor in the reporting period.

 

 

 

 

 

 

 

 

 

Contract no. HY/2011/08 Central –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B

4.4.8.     No inert and Non-inert C&D wastes were disposed of in this reporting month. Details of the waste flow table are summarized in Table 4.24.

Table 4.24  Details of Waste Disposal for Contract no. HY/2011/08

Waste Type*

Quantity this quarter,  m3

Cumulative-to-Date,  m3

Disposal / Dumping Grounds

Inert C&D materials disposed

9.82

367.68

 Nil

Inert C&D materials recycled

Nil

Nil

 Nil

Non-inert C&D materials disposed

147.39

729.57

                Nil

Non-inert C&D materials recycled

Nil

31.72

Nil

Chemical waste disposed(kg)

Nil

3800

Nil

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

        

5.         Compliance Audit

5.0.1.     The Event Action Plan for construction noise and air quality are presented in Appendix 5.1.

5.1.          Noise Monitoring

Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A

 

5.1.1.     No limit or action level exceedance was recorded in this reporting quarter.

Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works 

5.1.2.     Three limit level exceedances were recorded at M1a- Harbour Road Sports Centre on 02, 08 and 15 March 2016 in this reporting month.

5.1.3.     Operation of multiple air compressor at Ex- Wan Chai Swimming Pool (adjacent to Habour Road Sports Centre directly opposite to the monitoring station) under non WDII-CWB Contractor was observed as the major noise contribution during monitoring on 02 and 08 March 2016 while operation of multiple air compressor and piling works at Ex- Wan Chai Swimming Pool (adjacent to Habour Road Sports Centre directly opposite to the monitoring station) under non WDII-CWB Contractor as major noise contribution during monitoring on 15 March 2016.  As such, the exceedances were considered as non-Project related.

5.1.4.     Two limit level exceedances were recorded at M1a- Harbour Road Sports Centre on 29 March 2016 and 12 April 2016 in this reporting month.

5.1.5.     Operation of multiple air compressor at Ex- Wan Chai Swimming Pool (adjacent to Habour Road Sports Centre directly opposite to the monitoring station) under non WDII-CWB Contractor was observed as the major noise contribution during monitoring on 29 March 2016 while breaking works at Ex- Wan Chai Swimming Pool (adjacent to Habour Road Sports Centre directly opposite to the monitoring station) under non WDII-CWB Contractor as major noise contribution during monitoring on 12 April 2016.  As such, the exceedances were considered as non-Project related.

5.1.6.     Two limit level exceedances were recorded at M1a- Harbour Road Sports Centre on 04 and 24 May 2016 in this reporting month.

5.1.7.     Breaking works at Ex- Wan Chai Swimming Pool (adjacent to Harbour Road Sports Centre directly opposite to the monitoring station) under non WDII-CWB Contractor was observed as the major noise contribution during monitoring on 04 May 2016 while operation of Hydromil Trench Cutter at Ex- Wan Chai Swimming Pool (adjacent to Harbour Road Sports Centre directly opposite to the monitoring station) under non WDII-CWB Contractor as major noise contribution during monitoring on 24 May 2016.  As such, the exceedances were considered as non-Project related.

 

Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel)

5.1.8.     Three limit level exceedances were recorded at M1a- Harbour Road Sports Centre on 02, 08 and 15 March 2016 in this reporting month.

5.1.9.     Operation of multiple air compressor at Ex- Wan Chai Swimming Pool (adjacent to Habour Road Sports Centre directly opposite to the monitoring station) under non WDII-CWB Contractor was observed as the major noise contribution during monitoring on 02 and 08 March 2016 while operation of multiple air compressor and piling works at Ex- Wan Chai Swimming Pool (adjacent to Habour Road Sports Centre directly opposite to the monitoring station) under non WDII-CWB Contractor as major noise contribution during monitoring on 15 March 2016.  As such, the exceedances were considered as non-Project related.

5.1.10.   Two limit level exceedances were recorded at M1a- Harbour Road Sports Centre on 29 March 2016 and 12 April 2016 in this reporting month.

5.1.11.   Operation of multiple air compressor at Ex- Wan Chai Swimming Pool (adjacent to Habour Road Sports Centre directly opposite to the monitoring station) under non WDII-CWB Contractor was observed as the major noise contribution during monitoring on 29 March 2016 while breaking works at Ex- Wan Chai Swimming Pool (adjacent to Habour Road Sports Centre directly opposite to the monitoring station) under non WDII-CWB Contractor as major noise contribution during monitoring on 12 April 2016.  As such, the exceedances were considered as non-Project related.

5.1.12.   Two limit level exceedances were recorded at M1a- Harbour Road Sports Centre on 04 and 24 May 2016 in this reporting month.

5.1.13.   Breaking works at Ex- Wan Chai Swimming Pool (adjacent to Harbour Road Sports Centre directly opposite to the monitoring station) under non WDII-CWB Contractor was observed as the major noise contribution during monitoring on 04 May 2016 while operation of Hydromil Trench Cutter at Ex- Wan Chai Swimming Pool (adjacent to Harbour Road Sports Centre directly opposite to the monitoring station) under non WDII-CWB Contractor as major noise contribution during monitoring on 24 May 2016.  As such, the exceedances were considered as non-Project related.

 

Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) FEP-06/364/2009/A

5.1.14.   No limit or action level exceedance was recorded in this reporting quarter.

 

 

 

 

 

Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

4.1.25.   Two limit level exceedances were recorded at M6 – HK Baptist Church Henrietta Secondary School on 11 and 19 April 2016 in the reporting month.

4.1.26.   Traffic noise was observed during monitoring on 11 and 19 April 2016 and it was considered as the major noise contribution. As such, the limit level exceedances were concluded as non-project related.

Contract no. HY/2010/08 – Central-Wanchai Bypass – Tunnel (Slip Road 8 Section) under FEP-10/364/2009/B

5.1.15.   No limit or action level exceedance was recorded in the reporting quarter

Contract no. HY/2011/08 Central –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B

5.1.16.   No limit or action level exceedance was recorded in the reporting quarter.

5.2.          Air quality monitoring

Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A

5.2.1.     No exceedance was recorded in the reporting quarter.

Contract no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and Exhibition Centre - Tunnel Works

5.2.2.     No exceedance was recorded in the reporting quarter.

 

Contract nos. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel)

5.2.3.     No exceedance was recorded in the reporting quarter.

Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) FEP-06/364/2009/A

 

5.2.4.     No exceedance was recorded in the reporting quarter.

Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/A

5.2.5.     No exceedance was recorded in the reporting quarter.

Contract no. HK/2012/08 Wan Chai Development Phase II - Central-Wan Chai Bypass at Wan Chai West under FEP-09/364/2009/B

5.2.6.     No exceedance was recorded in the reporting quarter.

Contract no. HY/2010/08 – Central-Wanchai Bypass – Tunnel (Slip Raod 8 Section) under FEP-10/364/2009/B

5.2.1       No exceedance was recorded in the reporting quarter

Contract no. HY/2011/08 Central –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B

5.2.2       No exceedance was recorded in the reporting quarter.

5.3.          Real Time Noise Monitoring

Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/D

             Reporting month of March 2016

4.2.24.   No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the reporting month.

4.2.25.   Limit level exceedances were recorded at RTN2a-Electric Centre on 01 and 02 March 2016 during daytime in the reporting month. On 01 March 2016, sheet piling and excavation works were undertaken by Contract HY/2009/19 and mitigation measures including erection of temporary noise barrier was implemented while roof top cleaning works by non-CWB Contractor was undertaken immediately next to the noise monitoring station and was considered as major noise contribution. On 02 March 2016, sheet piling, excavation and concreting works were undertaken by Contract HY/2009/19 and noise mitigation measures including the erection of noise barrier was implemented while roof top floor cleaning works at the roof top by non-CWB Contractor was undertaken immediately next to the noise monitoring station and was considered as major noise contribution. As such, the exceedances were considered as non-Project related.

4.2.26.   No limit level exceedances were recorded at RTN3-Yue Lee Mo Fan Memorial School in the reporting month.

4.2.27.   No limit level exceedances were recorded at RTN4-Causeway Bay Community Centre in the reporting month.

Reporting month of April 2016

4.2.28.   No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the reporting month.

4.2.29.   Limit level exceedances were recorded at RTN2a-Electric Centre on 02, 05, 06, 08, 21, 23, 25 and 26 April 2016 during daytime in the reporting month. On 02, 05 and 06 April 2016, only installation of pre-cast parapet, pipe laying works and concreting of blinding layer for pipe laying were undertaken by Contract HY/2009/19, no major noise concern of the works was considered. On 08 April 2016, excavation and backfilling works and erection of concrete surround were conducted and no major noise concern was considered for the works. On 23 April 2016, backfilling works and concreting for manhole cover were conducted and no major noise concern was considered for the works. On 21, 25 and 26 April 2016, concreting and excavation for drain pipe were conducted and no major noise concern was considered for the works.  Nevertheless, roof top water proofing works by non-CWB Contractor was undertaken immediately next to the noise monitoring station across the monitoring period across April 2016 and was considered as major noise contribution As such, the exceedances were considered as non-Project related.

4.2.30.   Limit level exceedances were recorded at RTN3-Yue Lee Mo Fan Memorial School on 13, 18 and 25 April 2016 in the reporting month. On 13, 18 and 25 April 2016 during the monitoring period, no construction works was undertaken under Contract HY/2009/19. Nevertheless, based on relevant data from Hong Kong observatory, adverse weather condition with significant rainfall was recorded on 13, 18 and 25 April 2016 and thunderstorm warning signal was hoisted on 13 and 25 April 2016 and considered as the major noise contribution. As such, the exceedances were considered as non-project related.

4.2.31.   Limit level exceedances were recorded at RTN4-Causeway Bay Community Centre on 08 and 09 April 2016 in the reporting month. On 8 April 2016, minor vertical face drilling works was conducted and on 09 April 2016 crosshead concreting was conducted under HY/2009/19. In view of the same construction sequence of vertical face drilling was extended to other time period with no noise emanation recorded and drilling works immediately next to the monitoring station by non-CWB Contractor for external panel installation at Causeway Bay Community Centre was conducted on the monitoring date, the exceedances were considered as non- Project related.

Reporting month of May 2016

4.2.32.   No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the reporting month.

4.2.33.   No limit level exceedances were recorded at RTN2a-Electric Centre in the reporting month.

4.2.34.   Limit level exceedances were recorded at RTN3-Yue Lee Mo Fan Memorial School on 27 April 2016, 3 and 10 May2016 in the reporting month. On 27 April 2016 during the monitoring period, no construction works was undertaken under Contract HY/2009/19 and cast-in-item installation and erection of formwork was conducted under Contract HY/2009/19 on 03 and 10 May 2016 respectively. Based on relevant data from Hong Kong observatory, adverse weather condition with significant rainfall was recorded on 27 April 2016 amber rainstorm warning signal and red rainstorm warning signal was hoisted on 03 and 10 May 2016 respectively and considered as the major noise contribution. As such, the exceedances were considered as non-project related.

Limit level exceedances were recorded at RTN4-Causeway Bay Community Centre on 04 May 2016 in the reporting month. On 04 May 2016, segment installation was conducted under HY/2009/19 while external panel installation works was observed undertaken by non-CWB Contractor at Causeway Bay Community Centre near the monitoring station and considered as the major noise contribution. As such, the exceedance was considered as non- Project related.

 

Contract no. HY/2011/08 Central –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B

     Reporting month of March 2016

5.3.1       No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the reporting month.

5.3.2       Limit level exceedances were recorded at RTN2a- Electric Centre on 01 and 02 March 2016 during daytime in the reporting month. No construction works was undertaken under Contract HY/2011/08 while roof top floor cleaning works at the roof top by non-CWB Contractor was undertaken immediately next to the noise monitoring station and was considered as major noise contribution. As such, the exceedances were considered as non-Project related.

Reporting month of April 2016

5.3.3       No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the reporting month.

5.3.4       Limit level exceedances were recorded at RTN2a-Electric Centre on 02, 05, 06, 08, 21, 23, 25 and 26 April 2016 during daytime in the reporting month. No construction works was undertaken under Contract HY/2011/08 on 02, 05, 06, 08, 21, 23 April 2016. On 25 April 2016, site formation with one excavator in operation and on 26 April 2016, manual rebar installation with coupler was conducted and no major noise concern was considered for the above works Nevertheless, roof top water proofing works by non-CWB Contractor was undertaken immediately next to the noise monitoring station across the monitoring period across April 2016 and was considered as major noise contribution As such, the exceedances were considered as non-Project related.

Reporting month of May 2016

5.3.5       No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the reporting month.

5.3.6       No limit level exceedances were recorded at RTN2a-Electric Centre in the reporting month.

5.4.          Site Audit

5.4.1.     There was no non-compliance from the site audits in the reporting period. During environmental site inspections conducted during the reporting quarter, minor deficiencies were noted.  However, the Contractor rectified all deficiencies after receipt of notification.

5.5.          Review of the Reasons for and the Implications of Non-compliance

5.5.1       There was no particular action taken since no project-related non-compliance was recorded from the monitoring and site audits in the reporting period.

5.5.2       With respect to the complaint case referred by EPD received by ET on 05 April 2016 (Case Ref.:H08/RS/00007662-16). The complainant reported that construction dust emission arising from drilling activity from the construction site of Central – Wan Chai Bypass – Tunnel (North Point Section) and Island Eastern Corridor Link (Contract No. HY/2009/19).

5.5.3       Based on the site records confirmed by RSS, drilling holes for installation of starter bars was carried out under Contract HY/2009/19 at the vertical cut face of the existing IEC road slab on 05 April 2016 and according to the photo information provided by the EPD, no dust suppression measures was implemented during the observed drilling works on 05 April 2016. According to Air Pollution Control Ordinance, for pneumatic or power-driven drilling, cutting and polishing, water or a dust suppression chemical shall be continuously sprayed on the surface where any pneumatic or power-driven drilling, cutting, polishing or other mechanical breaking operation that causes dust emission is carried out, unless the process is accompanied by the operation of an effective dust extraction and filtering device.

5.5.4       Based on the information advised by the CWB RSS on 05 May 2016, a case of construction noise permit contravention under Contract HY/2009/19 was identified by the EPD on 24 April 2016.

5.6.          Summary of action taken in the event of and follow-up on non-compliance

5.6.1       There was no particular action taken since no non-compliance was recorded from the monitoring and site audits in the reporting period.

5.6.2       With respect to the identified case on drilling works without dust suppression measures, follow-up inspection was conducted on 06 April 2016, rectification actions including the use of vacuum suction to extract dust generated during the concerned drilling works was observed implemented by the Contractor of HY/2009/19 for starter bars drilling works. 

5.6.3       A Record of Inspection regarding the drilling works conducted on 05 April 2016 was subsequently issued by the EPD to the Contractor of HY/2009/19 on 21 April 2016.

5.6.4       With respect to the identified case on contravention on construction noise permit (Contract HY/2009/19), the construction noise permit no. GW-RS197-16 was cancelled by the Authority on 27 April 2016.Further information to be submitted by the Contractor of HY/2009/19 and CWB RSS team was requested by the Environmental Team for follow up.

 

 

 

 

 

6.         Complaints, Notification of Summons and Prosecution

6.0.1       Eight environmental complaints were received in the reporting quarter.

6.0.2       First public complaint regarding construction noise referred by ICC was received by ET on 03 March 2016 (ICC Ref.: CASE#2-1938637403 dated 01 March 2016). The complainant reported that construction noise was emanated from road works located between Lung Wo Road and Lung Wui Road Interface.

 

Further information was referred by RSS on 15 March 2016, the complainant clarified on 15 March 2016 that construction noise was emanated from road works located between Lung Wo Road and Lung Wui Road Interface during midnight and has lasted for one and half month resulting in nuisance to nearby residence.

 

Further information was referred by RSS on 18 March 2016, the complainant further clarified on 18 March 2016 that the concerned location shall be Lung King Street near the parking spaces for motorcycles and the Contract no. as stated on the publicity board is HK/2012/08. Furthermore, the complainant identified the noise was from power generators.

ET confirmed with the Resident Site Staff that there was neither construction works nor operation of power generators under Contract HK/2012/08 at the concerned location from 1900hrs to 0700hrs during the period from 23 February 2016 to 14 March 2016.

Based on the complaint information referred by ICC on 3 March 2016, according to the relevant site records provided by RSS, from 0800hrs to 1800hrs on both 29 February 2016 and 01 March 2016, drainage works was undertaken by Contract HK/2012/08 at Lung Wo Road and one excavator was in operation for soil excavation. Follow up inspection was conducted during the weekly environmental site inspection on 08 March 2016 and no particular noise emanating works was observed.

 

Based on the further information provided by the complainant on 15 March 2016, the complainant clarified on 15 March 2016 that Construction noise was emanated from road works located between Lung Wo Road and Lung Wui Road Interface during midnight and has lasted for one and half month resulting in nuisance to nearby residence. On 18 March 2016, the complainant further clarified on 18 March 2016 that the concerned location shall be Lung King Street near the parking spaces for motorcycles and the Contract no. as stated on the publicity board is HK/2012/08. Furthermore, the complainant identified the noise was from power generators. According to the relevant site records provided by RSS, there was neither construction works nor operation of power generators under Contract HK/2012/08 at the concerned location from 1900hrs to 0700hrs during the period from 23 February 2016 to 14 March 2016.

 

Nevertheless, in view of the public concern, the Contractor is recommended to maintain regular maintenance of the plant and equipment deployed to avoid potential nuisance to the nearby public.

 

6.0.3       Second public complaint regarding construction dust, plant exhaust, construction noise and water quality referred by EPD was received by ET on 10 March 2016 (EPD Ref.: H05/RS/00005206-16 dated 10 March 2016). The complainant reported that construction dust, plant exhaust and construction noise generated from the construction work of Contract HK/2012/08 at waterfront of Lung King Street caused nuisance, and the water quality at the waterfront of Lung King Street was becoming worse that accumulation of the floating refuse and foam was found.

 

ET confirmed with the Resident Site Staff that soil excavation at ELS area, Zone A2(2), was carried out, where at approx. 100m from the waterfront of Lung King Street from 08:00 hrs to 18:00 hrs on 07 March 2016 under Contract HK/2012/08.  Two excavators were involved at that location. Erection of falsework for culvert L was carried out near the waterfront of Lung King Street from 08:00 hrs to 18:00 hrs on 07 March 2016 under Contract HK/2012/08.  One lorry crane was involved for lifting falsework elements. Dust suppression measures including the water sprinklers were installed along site haul road.

Regularly removed the floating refuse at the waterfront of Lung King Street was conducted by the Contractor of HK/2012/08. The concerned observed floating foam at the waterfront of Lung King Street was found originating from the diverted cooling mains discharge.

 

According to the relevant site records provided by RSS, soil excavation at ELS area, Zone A2(2) was carried out, where at approx.100m from the waterfront of Lung King Street under Contract HK/2012/08 from 08:00hrs to 18:00hrs on 07 March 2016 and two excavators were in operation at that location while erection of falsework for culvert L was carried out near the waterfront of Lung King Street from 08:00hrs and 18:00hrs on 07 March 2016 under Contract HK/2012/08 and one lorry crane was involved for lifting falsework elements. Dust suppression measures including the use of water sprinklers along the site haul road was implemented by the Contractor of HK/2012/08 and removal of floating refuse was regularly conducted at the waterfront of Lung King Street by the Contractor of HK/2012/08. Upon investigation, the concerned observed floating foam at the waterfront of Lung King Street was found originating from the diverted cooling mains discharge.

 

Follow up inspection was conducted during the weekly environmental site inspection on 15 March 2016 and dust suppression measures including watering for haul road, tarpaulin sheet covering for cement bags stored on site and three side and top covering for grouting station were implemented while and no dark smoke emission from the plant and machinery deployed on site was observed. Noise mitigation measures including acoustic covering was implementing for excavator mounted breaker. In addition, removal of floating refuse on site was observed implemented by the Contractor of HK/2012/08 and no accumulation of floating refuse was found. The concerned foam originating from diverted cooling mains discharge was observed during inspection and the dispersion of the concerned foam of unknown chemical nature was observed isolated from the nearby public area.

 

Nevertheless, in view of the public concern, the Contractor was recommended to maintain regular checking of the plants and equipment deployed on site to avoid potential air quality impact to the nearby public and to maintain adequate dust suppression measures on site to avoid potential dust impact to the surroundings. The Contractor was reminded to maintain regular cleaning of floating refuse within the construction site area to avoid potential nuisance to the surroundings. The Contractor was also reminded to maintain the noise mitigation measure if breaking works would be required. The Contractor was also suggested to reflect the observed foam to relevant Cooling Mains owners.

 

6.0.4       Third public complaint regarding direct discharge of muddy effluent referred by EPD was received by ET on 31 March 2016 (Case Ref.: H08/RS/00006732-16). The complainant reported that muddy water was observed discharged from the construction site of Central – Wan Chai Bypass – Tunnel (North Point Section) and Island Eastern Corridor Link (Contract No. HY/2009/19) into Victoria Habour via a drain hole.

 

ET confirmed with the Resident Site Staff that pipe Laying works between Pier 32 and Pier 33 and excavation and blinding works for Manhole at Pier 34 were in progress on 22 March 2016.

The observed drain hole was identified to be the outlet point of a manhole and a section of an abandoned U-channel (extending from the concerned manhole to the Hong Kong Electric Substation in length along the site boundary) was adjoining the concerned manhole and sandbag was previously placed at the U-channel at the location near the inlet point to the concerned manhole.

 

Based on the site records confirmed by RSS, pipe laying works between Pier 32 and Pier 33 and excavation and blinding works for Manhole at Pier 34 were in progress on 22 March 2016. The observed drain hole was identified to be the outlet point of a manhole and a section of an abandoned U-channel (extending from the concerned manhole to the Hong Kong Electric Substation in length along the site boundary) was adjoining the concerned manhole and sandbag was previously placed at the U-channel at the location near the inlet point to the concerned manhole. In addition, no site discharge point was connected to the aforesaid U-channel and the concerned manhole. In view of the environmental concern, the following remedial and precautionary actions were taken by the Contractor of HY/2009/19 on 29 March 2016.

 

v)             Plugging the inlet point of the concerned manhole (connecting to the abandoned U-channel) with concrete;

vi)            Plugging the outlet of the concerned manhole (connecting to the observed drain hole) with concrete;

vii)           Filling the concerned manhole with rubbles;

viii)          Shifting the unused wastewater treatment plant around the concerned location to other site location for use.

 

Follow-up inspection was conducted by the Environmental Team on 06 April 2016. No further contaminated runoff discharge was observed from the concerned drain hole and precautionary measures including provision of concrete bunding was implemented along the site boundary at the concerned location to avoid potential surface overflow. The pipe laying works and the excavation works was found at distant location away from the concerned drain hole with no surface drain connection and no particular effluent was generated from the work. As such, no information indicate the discharge was related to the above construction activities.

However, it was noted that another section of surface drainage channel within the construction site (perpendicular in direction to the initial identified abandoned U-channel) was also in connection to concerned manhole and minor residue mud deposition was observed within the surface drainage channel. Despite the above additional surface drainage channel identified, the outlet point of concerned final manhole (in connection with the observed drain hole) was observed plugged with concrete and filled with rubbles as rectification measure to avoid any further contaminated runoff discharge via the observed drain hole.

 

Nevertheless, the Contractor of HY/2009/19 was reminded to conduct regular cleaning works for site surface drainage channel to avoid accumulation of silt and soil and avoid potential overflow by directing the surface runoff within the surface drainage channel to proper collection point for necessary treatment prior to discharge. The Contractor of HY/2009/19 was also reminded to check and review other surface drainage channel within the construction site to avoid potential runoff related impact via surface drainage channel to the nearby waters.

In addition, it was noticed that water was discharged from a piping extending from City Garden and the discharged water would result in seepage across the site hoarding into the abandoned U-channel. The Contractor of HY/2009/19 was suggested to liaise with the City Garden Management Office for proper connection of the observed pipping with discharge to prevent further seepage water into the construction site.                

              

6.0.5       Forth public complaint regarding construction dust emission was referred by EPD was received by ET on 05 April 2016 (Case Ref.: H08/RS/00007662-16). The complainant reported that construction dust emission arising from drilling activity from the construction site of Central – Wan Chai Bypass – Tunnel (North Point Section) and Island Eastern Corridor Link (Contract No. HY/2009/19).

 

ET confirmed with the Resident Site Staff that drilling holes for installation of starter bars was carried out under Contract HY/2009/19 at the vertical cut face of the existing IEC road slab on 05 April 2016

 

Based on the site records confirmed by RSS, drilling holes for installation of starter bars was carried out under Contract HY/2009/19 at the vertical cut face of the existing IEC road slab on 05 April 2016 and according to the photo information provided by the EPD, no dust suppression measures was implemented during the observed drilling works on 05 April 2016.

 

According to Air Pollution Control Ordinance, for pneumatic or power-driven drilling, cutting and polishing, water or a dust suppression chemical shall be continuously sprayed on the surface where any pneumatic or power-driven drilling, cutting, polishing or other mechanical breaking operation that causes dust emission is carried out, unless the process is accompanied by the operation of an effective dust extraction and filtering device.

 

Follow-up inspection was conducted on 06 April 2016, rectification actions including the use of vacuum suction to extract dust generated during the concerned drilling works was observed implemented by the Contractor of HY/2009/19 for starter bars drilling works. 

 

6.0.6       Fifth public complaint regarding landscape aspect was referred by RSS was received by ET on 11 April 2016 (Case Ref.:2-2036525055). The complainant reported that a tree (6 meters in height and 1.5 meters in diameter) was found toppled at 111 Victoria Park Road, near Lamp post 38632 and blocking the Pedestrian pathway on 27 March 2016.

 

ET confirmed with the Resident Site Staff that the concerned tree was identified as T710 and no construction activity in the vicinity of tree T710 on 27 March 2016 and no construction works are required in or near its vicinity. 

 

Based on the site records confirmed by RSS, the concerned tree was identified as the retained tree T710 maintained under the Contract of HY/2010/08 and the concerned tree T710 was located outside the assessment area in the relevant Project EIA Report. No construction works are required in the vicinity of concerned tree T710 and no construction activity was conducted in the vicinity of tree T710 on 27 March 2016. Nevertheless, based on RSS information, recent tree monitoring report indicates an existing cavity at trunk and the concerned tree T710 has been recommended to be felled in the tree risk assessment Form 2.

 

With respect to the observed incident of the toppling of the concerned tree T710, the Contractor of HY/2010/08 was instructed by RSS to remove the broken trunk/ remains to avoid impact to the surroundings. The concerned tree T710 shall be compensated by the Contractor of HY/2010/08 in accordance with the Development Bureau Technical Circular (Works) No. 7/2015 and the detail on compensation would be further agreed with Victoria Park Management Office. Follow-up inspection was conducted on 13 April 2016, and the remaining parts of the concerned tree T710 was observed felled to avoid further impact to nearby public road.

 

6.0.7       Sixth public complaint regarding muddy dispersion referred by RSS was received by ET on 13 April 2016. The complainant reported that muddy water was observed to disperse from Contract HK/2009/02 site area to Victoria Harbour occasionally as there was no silt curtain installed under the buoyancy floats. The location concerned was the East of Star Ferry Piers (Contract No. HK/2009/02).

 

ET confirmed with the Resident Site Staff that no marine construction activities or land construction activities under Contract HK/2009/02 at the concerned location on 12 April 2016.

Surface runoff control measures including provision of concrete bund at the concerned location was implemented by Contract HK/2009/02.

No soil & silt deposition along the seawall at the concerned location on 12 April 2016.

No discharge point located in the vicinity of the concerned location under Contract HK/2009/02.

Silt curtain with buoyancy floats acting as anchor points was installed at Monitoring Station RW21-P789 for Water intakes.

 

Based on the site records confirmed by RSS, no marine construction activities or land construction activities was carried out under Contract HK/2009/02 at the concerned location on 12 April 2016 and no soil and silt deposition was found along the seawall at the concerned location and precautionary measures for site runoff control including provision of concrete bund along boundary of site area near the waterfront around the concerned location was implemented by the Contractor HK/2009/02. In addition, no discharge point under Contract HK/2009/02 was located in the vicinity of the concerned location. Based on information confirmed by RSS, the buoyancy floats deployed at the concerned location are acting as the anchor points for the silt curtain deployed around the WQM Station RW21-P789 for the WSD and Cooling Water Intakes group.

 

Follow-up inspection was conducted on 14 April 2016, no surface runoff from the construction site nor discharge of contaminated effluent was observed around the concerned location and precautionary measures including the provision of concrete bund at the concerned location was observed maintained by the Contractor of HK/2009/02 and the silt curtain deployed around the WQM station RW21-P789 was generally in order.

In view of the public concern on the water quality, the Contractor of HK/2009/02 was reminded to maintain effective surface runoff protection and provide proper collection point of construction effluent around the concerned location to avoid potential surface runoff related impact.

 

6.0.8       Seventh public complaint regarding muddy water discharge referred by EPD was received by ET on 13 April 2016 (EPD Ref.: H05/RS/00008367-16 dated 13 April 2016). The complainant reported that muddy water was discharged from the construction work of Contract HK/2012/08 to the sea outside the Hong Kong Academy for Performing Arts on 13 April 2016 morning.

 

ET confirmed with the Resident Site Staff that internal transport of soil to the hopper barge for storage via landing barge was conducted by Contractor of HK/2012/08 during 0800 hours to 1000 hours on 13 April 2016 at the sea outside the concerned location and 3 nos. of dump trucks were deployed for the operation.

Protection measure including provision of sandbag bunding along the side of the landing barge was implemented by the Contractor of HK/2012/08.

 

According to the relevant site records provided by RSS, internal transport of soil to the hopper barge for storage via landing barge was conducted by Contractor of HK/2012/08 during 0800 hours to 1000 hours on 13 April 2016 at the sea outside the concerned location and 3 nos. of dump trucks were deployed for the operation. Protection measure including provision of sandbag bunding along the side of the landing barge was implemented by the Contractor of HK/2012/08. In addition, amber rainstorm warning signal was hoisted from 0630 hours to 1200 hours on 13 April 2016 and during the above time period, muddy water was observed from the upstream of culvert L outside the HK/2012/08 site.

 

Follow up inspection was conducted on 19 April 2016, protection measures including provision of sandbag bunding along the side of the landing barge was implemented and no mud or soil deposition was observed along the seawall and no discharge point was located within the temporary water channel connecting the Culvert L outfall location to the Victoria Harbour. In addition, piling works was observed at the north side of Zone A1 on 19 April 2016 and construction effluent collection from piling work via sedimentation tank to wastewater treatment facility was implemented and steel barrier was installed around the piling works area to mitigate against potential surface runoff related impact.

 

Nevertheless, in view of the public concern, the Contractor was reminded to maintain adequate perimeter embankment protection along the seawall boundary and maintain proper construction effluent collection system to avoid potential runoff related impact to nearby waters.

 

6.0.9       Eighth EPD complaint regarding noise nuisance referred by RSS was received by ET on 27 May 2016 (EPD Ref: H05/RS/00012646-16 dated 27 May 2016). The complainant reported that a generator was operated round-the-clock in the Chun Wo- CRGL JV construction site near Wanchai Ferry Pier that cause noise nuisance. (Contract No. HK/2009/02).

 

ET confirmed with the Resident Site Staff that a generator deployed under Contract HK/2009/02 near the covered walkway for Wanchai Ferry Pier at Portion 2 area and was operated from 1900hrs on 24 May 2016 to 0700hrs on 25 May 2016 and from 1900hrs on 25 May 2016 to 0700hrs on 26 May 2016. The generator was used for the power supply of lighting inside Tunnel Portions 1 and 2.

 

According to the relevant site records provided by RSS, a generator deployed under Contract HK/2009/02 near the covered walkway for Wanchai Ferry Pier at Portion 2 area and was operated from 1900hrs on 24 May 2016 to 0700hrs on 25 May 2016 and from 1900hrs on 25 May 2016 to 0700hrs on 26 May 2016. The generator was used for the power supply of lighting inside Tunnel Portions 1 and 2. Based on review on site information, relevant Construction Noise Permits GW-RS0516-16 and GW-RS0390-16 for the operation of the concerned generator were confirmed in place while no sufficient site information was considered available to demonstrate the use of acoustic enclosure for the operation of the generator following the special condition 3d item 4. Despite the above, the Contractor of HK/2009/02 has suspended the use of the generator at the concerned location after 2300hours to minimize potential noise concern to the surroundings from 28 May 2016.

 

Nevertheless, the Contractor of HK/2009/02 was reminded to upkeep the site control system for construction works carried out during restricted hours and night time for Construction Noise Permit compliance and maintain regular maintenance of the plant and equipment deployed to avoid potential nuisance to the nearby public.

6.0.1.     The details of cumulative complaint log and summary of complaints are presented in Appendix 6.1.

 

 

6.0.2.     No notification of summons or prosecution was received in the reporting period. Cumulative statistic on complaints and successful prosecutions are summarized in Table 6.1 and Table 6.2 respectively.

Table 6.1    Cumulative Statistics on Complaints

Reporting Period

     No. of Complaints

Commencement of Works up to last reporting quarter

  57

March 2016 – May 2016

  8

Project-to-Date

   65

 

Table 6.2    Cumulative Statistics on Successful Prosecutions

Environmental Parameters

Cumulative No. Brought Forward

No. of Successful Prosecutions this quarter (Offence Date)

Cumulative No. Project-to-Date

Air

-

0

0

Noise

-

0

0

Waste

-

0

0

Total

-

0

0

 

7.         Cumulative Construction Impact due to the Concurrent Projects

7.0.1.     According to Condition 3.4 of the EP-364/2009/B, this section addresses the relevant cumulative construction impact due to the concurrent activities of the current projects including the Central Reclamation Phase III (CRIII), Wan Chai Development Phase II (WDII), Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) and Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel).

7.0.2.     According to the Final EM&A Report of Central Reclamation Phase III (CRIII) for Contract HK 12/02, the major construction activities were completed by end of January 2014 and no construction activities were undertaken thereafter and the water quality monitoring was completed in October 2011.  As such, it is considered that there were no cumulative construction impact due to the concurrent activities of the current projects with the Central Reclamation Phase III (CRIII) undertaken by contractor HK12/02 in the reporting period.

7.0.3.     According to the construction programme of Central-Wanchai Bypass at Wanchai West at the Central Reclamation Phase III area include structural works for tunnel construction, road works and drainage works, removal of bulkhead wall and seawall modification were performed in May 2016 reporting month. As no project related exceedance were recorded during the reporting period, cumulative construction impact due to the concurrent activities of the current projects with the Central Reclamation Phase III (CRIII) was considered as insignificant. 

7.0.4.     According to the construction programme of Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects, the major construction activities under Wan Chai Development Phase II were tunnel works, D-wall construction at Wan Chai East and culvert construction, tunnel construction and ELS works at Wan Chai West. The major construction activities under Central-Wan Chai Bypass and Island Eastern Corridor Link Projects were road works at Central Interchange, backfilling works at Ex-PCWAW, ELS works and retaining wall construction at Victoria Park, ELS works and tunnel works at TS3; bridge construction, piling and tunnel works at North Point area in the reporting month. In addition, other non-Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects was observed undertaken at Wan Chai North area.

7.0.5.     No significant air impact from construction activities was anticipated in the reporting month. Besides, no project related exceedance was recorded during the air and noise environmental monitoring events in the reporting month. Thus, it is evaluated that the cumulative construction impact from the concurrent projects including Central Reclamation Phase III (CRIII), Wan Chai Development Phase II (WDII), Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) was insignificant.

 

 

 

8.         Conclusion

8.0.1.     The EM&A programme was carried out in accordance with the EM&A Manual requirements, minor alterations to the programme proposed were made in response to changing circumstances.

Air quality monitoring

8.0.2.     One action level exceedance for TSP monitoring was recorded at CMA5b – Pedestrian Plaza on 14 April 2016 in the reporting month. The exceedance was concluded as non-project related.

Noise monitoring

8.0.3.     Three limit level exceedances were recorded at noise monitoring station M1a – Habour Road Sports Center on 02, 08 and 15 March 2016. The exceedances were concluded as non-project related.

8.0.4.     Two limit level exceedances were recorded at noise monitoring station M1a – Habour Road Sports Center on 29 March 2016 and 12 April 2016. The exceedances were concluded as non-project related.

8.0.5.     Two limit level exceedances were recorded at noise monitoring station M6 – HK Baptist Church Henrietta Secondary School on 11 and 19 April 2016. The exceedances were concluded as non-project related.

8.0.6.     Two limit level exceedances were recorded at noise monitoring station M1a – Habour Road Sports Center on 04 and 24 May 2016. The exceedances were concluded as non-project related.

Real time noise monitoring

Reporting month of March 2016

8.0.7.     No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the reporting month.

8.0.8.     Limit level exceedances were recorded at RTN2a-Electric Centre on 01 and 02 March 2016 during daytime in the reporting month. On 01 March 2016, sheet piling and excavation works were undertaken by Contract HY/2009/19 and mitigation measures including erection of temporary noise barrier was implemented while roof top cleaning works by non-CWB Contractor was undertaken immediately next to the noise monitoring station and was considered as major noise contribution. On 02 March 2016, sheet piling, excavation and concreting works were undertaken by Contract HY/2009/19 and noise mitigation measures including the erection of noise barrier was implemented while roof top floor cleaning works at the roof top by non-CWB Contractor was undertaken immediately next to the noise monitoring station and was considered as major noise contribution. As such, the exceedances were considered as non-Project related.

8.0.9.     Limit level exceedances were recorded at RTN2a- Electric Centre on 01 and 02 March 2016 during daytime in the reporting month. No construction works was undertaken under Contract HY/2011/08 while roof top floor cleaning works at the roof top by non-CWB Contractor was undertaken immediately next to the noise monitoring station and was considered as major noise contribution. As such, the exceedances were considered as non-Project related.

8.0.10.   No limit level exceedances were recorded at RTN3-Yue Lee Mo Fan Memorial School in the reporting month.

8.0.11.   No limit level exceedances were recorded at RTN4-Causeway Bay Community Centre in the reporting month.

Reporting month of April 2016

8.0.12.   No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the reporting month.

8.0.13.   Limit level exceedances were recorded at RTN2a-Electric Centre on 02, 05, 06, 08, 21, 23, 25 and 26 April 2016 during daytime in the reporting month. On 02, 05 and 06 April 2016, only installation of pre-cast parapet, pipe laying works and concreting of blinding layer for pipe laying were undertaken by Contract HY/2009/19, no major noise concern of the works was considered. On 08 April 2016, excavation and backfilling works and erection of concrete surround were conducted and no major noise concern was considered for the works. On 23 April 2016, backfilling works and concreting for manhole cover were conducted and no major noise concern was considered for the works. On 21, 25 and 26 April 2016, concreting and excavation for drain pipe were conducted and no major noise concern was considered for the works.  Nevertheless, roof top water proofing works by non-CWB Contractor was undertaken immediately next to the noise monitoring station across the monitoring period across April 2016 and was considered as major noise contribution As such, the exceedances were considered as non-Project related.

8.0.14.   Limit level exceedances were recorded at RTN2a-Electric Centre on 02, 05, 06, 08, 21, 23, 25 and 26 April 2016 during daytime in the reporting month. No construction works was undertaken under Contract HY/2011/08 on 02, 05, 06, 08, 21, 23 April 2016. On 25 April 2016, site formation with one excavator in operation and on 26 April 2016, manual rebar installation with coupler was conducted and no major noise concern was considered for the above works Nevertheless, roof top water proofing works by non-CWB Contractor was undertaken immediately next to the noise monitoring station across the monitoring period across April 2016 and was considered as major noise contribution As such, the exceedances were considered as non-Project related.

 

8.0.15.   Limit level exceedances were recorded at RTN3-Yue Lee Mo Fan Memorial School on 13, 18 and 25 April 2016 in the reporting month. On 13, 18 and 25 April 2016 during the monitoring period, no construction works was undertaken under Contract HY/2009/19. Nevertheless, based on relevant data from Hong Kong observatory, adverse weather condition with significant rainfall was recorded on 13, 18 and 25 April 2016 and thunderstorm warning signal was hoisted on 13 and 25 April 2016 and considered as the major noise contribution. As such, the exceedances were considered as non-project related.

8.0.16.   Limit level exceedances were recorded at RTN4-Causeway Bay Community Centre on 08 and 09 April 2016 in the reporting month. On 8 April 2016, minor vertical face drilling works was conducted and on 09 April 2016 crosshead concreting was conducted under HY/2009/19. In view of the same construction sequence of vertical face drilling was extended to other time period with no noise emanation recorded and drilling works immediately next to the monitoring station by non-CWB Contractor for external panel installation at Causeway Bay Community Centre was conducted on the monitoring date, the exceedances were considered as non- Project related.

Reporting month of May 2016

8.0.17.   No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the reporting month.

8.0.18.   No limit level exceedances were recorded at RTN2a-Electric Centre in the reporting month.

8.0.19.   Limit level exceedances were recorded at RTN3-Yue Lee Mo Fan Memorial School on 27 April 2016, 3 and 10 May2016 in the reporting month. On 27 April 2016 during the monitoring period, no construction works was undertaken under Contract HY/2009/19 and cast-in-item installation and erection of formwork was conducted under Contract HY/2009/19 on 03 and 10 May 2016 respectively. Based on relevant data from Hong Kong observatory, adverse weather condition with significant rainfall was recorded on 27 April 2016 amber rainstorm warning signal and red rainstorm warning signal was hoisted on 03 and 10 May 2016 respectively and considered as the major noise contribution. As such, the exceedances were considered as non-project related.

8.0.20.   Limit level exceedances were recorded at RTN4-Causeway Bay Community Centre on 04 May 2016 in the reporting month. On 04 May 2016, segment installation was conducted under HY/2009/19 while external panel installation works was observed undertaken by non-CWB Contractor at Causeway Bay Community Centre near the monitoring station and considered as the major noise contribution. As such, the exceedance was considered as non- Project related.

Environmental Complaints

8.0.21.   Eight environmental complaints were received in the reporting quarter.

 

8.0.22.   First public complaint regarding construction noise referred by ICC was received by ET on 03 March 2016 (ICC Ref.: CASE#2-1938637403 dated 01 March 2016). The complainant reported that construction noise was emanated from road works located between Lung Wo Road and Lung Wui Road Interface.

 

Further information was referred by RSS on 15 March 2016, the complainant clarified on 15 March 2016 that construction noise was emanated from road works located between Lung Wo Road and Lung Wui Road Interface during midnight and has lasted for one and half month resulting in nuisance to nearby residence.

 

Further information was referred by RSS on 18 March 2016, the complainant further clarified on 18 March 2016 that the concerned location shall be Lung King Street near the parking spaces for motorcycles and the Contract no. as stated on the publicity board is HK/2012/08. Furthermore, the complainant identified the noise was from power generators.

ET confirmed with the Resident Site Staff that there was neither construction works nor operation of power generators under Contract HK/2012/08 at the concerned location from 1900hrs to 0700hrs during the period from 23 February 2016 to 14 March 2016.

Based on the complaint information referred by ICC on 3 March 2016, according to the relevant site records provided by RSS, from 0800hrs to 1800hrs on both 29 February 2016 and 01 March 2016, drainage works was undertaken by Contract HK/2012/08 at Lung Wo Road and one excavator was in operation for soil excavation. Follow up inspection was conducted during the weekly environmental site inspection on 08 March 2016 and no particular noise emanating works was observed.

 

Based on the further information provided by the complainant on 15 March 2016, the complainant clarified on 15 March 2016 that Construction noise was emanated from road works located between Lung Wo Road and Lung Wui Road Interface during midnight and has lasted for one and half month resulting in nuisance to nearby residence. On 18 March 2016, the complainant further clarified on 18 March 2016 that the concerned location shall be Lung King Street near the parking spaces for motorcycles and the Contract no. as stated on the publicity board is HK/2012/08. Furthermore, the complainant identified the noise was from power generators. According to the relevant site records provided by RSS, there was neither construction works nor operation of power generators under Contract HK/2012/08 at the concerned location from 1900hrs to 0700hrs during the period from 23 February 2016 to 14 March 2016.

 

Nevertheless, in view of the public concern, the Contractor is recommended to maintain regular maintenance of the plant and equipment deployed to avoid potential nuisance to the nearby public.

 

8.0.23.   Second public complaint regarding construction dust, plant exhaust, construction noise and water quality referred by EPD was received by ET on 10 March 2016 (EPD Ref.: H05/RS/00005206-16 dated 10 March 2016). The complainant reported that construction dust, plant exhaust and construction noise generated from the construction work of Contract HK/2012/08 at waterfront of Lung King Street caused nuisance, and the water quality at the waterfront of Lung King Street was becoming worse that accumulation of the floating refuse and foam was found.

 

ET confirmed with the Resident Site Staff that soil excavation at ELS area, Zone A2(2), was carried out, where at approx. 100m from the waterfront of Lung King Street from 08:00 hrs to 18:00 hrs on 07 March 2016 under Contract HK/2012/08.  Two excavators were involved at that location. Erection of falsework for culvert L was carried out near the waterfront of Lung King Street from 08:00 hrs to 18:00 hrs on 07 March 2016 under Contract HK/2012/08.  One lorry crane was involved for lifting falsework elements. Dust suppression measures including the water sprinklers were installed along site haul road.

Regularly removed the floating refuse at the waterfront of Lung King Street was conducted by the Contractor of HK/2012/08. The concerned observed floating foam at the waterfront of Lung King Street was found originating from the diverted cooling mains discharge.

 

According to the relevant site records provided by RSS, soil excavation at ELS area, Zone A2(2) was carried out, where at approx.100m from the waterfront of Lung King Street under Contract HK/2012/08 from 08:00hrs to 18:00hrs on 07 March 2016 and two excavators were in operation at that location while erection of falsework for culvert L was carried out near the waterfront of Lung King Street from 08:00hrs and 18:00hrs on 07 March 2016 under Contract HK/2012/08 and one lorry crane was involved for lifting falsework elements. Dust suppression measures including the use of water sprinklers along the site haul road was implemented by the Contractor of HK/2012/08 and removal of floating refuse was regularly conducted at the waterfront of Lung King Street by the Contractor of HK/2012/08. Upon investigation, the concerned observed floating foam at the waterfront of Lung King Street was found originating from the diverted cooling mains discharge.

 

Follow up inspection was conducted during the weekly environmental site inspection on 15 March 2016 and dust suppression measures including watering for haul road, tarpaulin sheet covering for cement bags stored on site and three side and top covering for grouting station were implemented while and no dark smoke emission from the plant and machinery deployed on site was observed. Noise mitigation measures including acoustic covering was implementing for excavator mounted breaker. In addition, removal of floating refuse on site was observed implemented by the Contractor of HK/2012/08 and no accumulation of floating refuse was found. The concerned foam originating from diverted cooling mains discharge was observed during inspection and the dispersion of the concerned foam of unknown chemical nature was observed isolated from the nearby public area.

 

Nevertheless, in view of the public concern, the Contractor was recommended to maintain regular checking of the plants and equipment deployed on site to avoid potential air quality impact to the nearby public and to maintain adequate dust suppression measures on site to avoid potential dust impact to the surroundings. The Contractor was reminded to maintain regular cleaning of floating refuse within the construction site area to avoid potential nuisance to the surroundings. The Contractor was also reminded to maintain the noise mitigation measure if breaking works would be required. The Contractor was also suggested to reflect the observed foam to relevant Cooling Mains owners.

 

8.0.24.   Third public complaint regarding direct discharge of muddy effluent referred by EPD was received by ET on 31 March 2016 (Case Ref.: H08/RS/00006732-16). The complainant reported that muddy water was observed discharged from the construction site of Central – Wan Chai Bypass – Tunnel (North Point Section) and Island Eastern Corridor Link (Contract No. HY/2009/19) into Victoria Habour via a drain hole.

 

ET confirmed with the Resident Site Staff that pipe Laying works between Pier 32 and Pier 33 and excavation and blinding works for Manhole at Pier 34 were in progress on 22 March 2016.

The observed drain hole was identified to be the outlet point of a manhole and a section of an abandoned U-channel (extending from the concerned manhole to the Hong Kong Electric Substation in length along the site boundary) was adjoining the concerned manhole and sandbag was previously placed at the U-channel at the location near the inlet point to the concerned manhole.

 

Based on the site records confirmed by RSS, pipe laying works between Pier 32 and Pier 33 and excavation and blinding works for Manhole at Pier 34 were in progress on 22 March 2016. The observed drain hole was identified to be the outlet point of a manhole and a section of an abandoned U-channel (extending from the concerned manhole to the Hong Kong Electric Substation in length along the site boundary) was adjoining the concerned manhole and sandbag was previously placed at the U-channel at the location near the inlet point to the concerned manhole. In addition, no site discharge point was connected to the aforesaid U-channel and the concerned manhole. In view of the environmental concern, the following remedial and precautionary actions were taken by the Contractor of HY/2009/19 on 29 March 2016.

 

ix)            Plugging the inlet point of the concerned manhole (connecting to the abandoned U-channel) with concrete;

x)             Plugging the outlet of the concerned manhole (connecting to the observed drain hole) with concrete;

xi)            Filling the concerned manhole with rubbles;

xii)           Shifting the unused wastewater treatment plant around the concerned location to other site location for use.

 

Follow-up inspection was conducted by the Environmental Team on 06 April 2016. No further contaminated runoff discharge was observed from the concerned drain hole and precautionary measures including provision of concrete bunding was implemented along the site boundary at the concerned location to avoid potential surface overflow. The pipe laying works and the excavation works was found at distant location away from the concerned drain hole with no surface drain connection and no particular effluent was generated from the work. As such, no information indicate the discharge was related to the above construction activities.

However, it was noted that another section of surface drainage channel within the construction site (perpendicular in direction to the initial identified abandoned U-channel) was also in connection to concerned manhole and minor residue mud deposition was observed within the surface drainage channel. Despite the above additional surface drainage channel identified, the outlet point of concerned final manhole (in connection with the observed drain hole) was observed plugged with concrete and filled with rubbles as rectification measure to avoid any further contaminated runoff discharge via the observed drain hole.

 

Nevertheless, the Contractor of HY/2009/19 was reminded to conduct regular cleaning works for site surface drainage channel to avoid accumulation of silt and soil and avoid potential overflow by directing the surface runoff within the surface drainage channel to proper collection point for necessary treatment prior to discharge. The Contractor of HY/2009/19 was also reminded to check and review other surface drainage channel within the construction site to avoid potential runoff related impact via surface drainage channel to the nearby waters.

In addition, it was noticed that water was discharged from a piping extending from City Garden and the discharged water would result in seepage across the site hoarding into the abandoned U-channel. The Contractor of HY/2009/19 was suggested to liaise with the City Garden Management Office for proper connection of the observed pipping with discharge to prevent further seepage water into the construction site.                

              

8.0.25.   Forth public complaint regarding construction dust emission was referred by EPD was received by ET on 05 April 2016 (Case Ref.: H08/RS/00007662-16). The complainant reported that construction dust emission arising from drilling activity from the construction site of Central – Wan Chai Bypass – Tunnel (North Point Section) and Island Eastern Corridor Link (Contract No. HY/2009/19).

 

ET confirmed with the Resident Site Staff that drilling holes for installation of starter bars was carried out under Contract HY/2009/19 at the vertical cut face of the existing IEC road slab on 05 April 2016

 

Based on the site records confirmed by RSS, drilling holes for installation of starter bars was carried out under Contract HY/2009/19 at the vertical cut face of the existing IEC road slab on 05 April 2016 and according to the photo information provided by the EPD, no dust suppression measures was implemented during the observed drilling works on 05 April 2016.

 

According to Air Pollution Control Ordinance, for pneumatic or power-driven drilling, cutting and polishing, water or a dust suppression chemical shall be continuously sprayed on the surface where any pneumatic or power-driven drilling, cutting, polishing or other mechanical breaking operation that causes dust emission is carried out, unless the process is accompanied by the operation of an effective dust extraction and filtering device.

 

Follow-up inspection was conducted on 06 April 2016, rectification actions including the use of vacuum suction to extract dust generated during the concerned drilling works was observed implemented by the Contractor of HY/2009/19 for starter bars drilling works. 

 

 

8.0.26.   Fifth public complaint regarding landscape aspect was referred by RSS was received by ET on 11 April 2016 (Case Ref.:2-2036525055). The complainant reported that a tree (6 meters in height and 1.5 meters in diameter) was found toppled at 111 Victoria Park Road, near Lamp post 38632 and blocking the Pedestrian pathway on 27 March 2016.

 

ET confirmed with the Resident Site Staff that the concerned tree was identified as T710 and no construction activity in the vicinity of tree T710 on 27 March 2016 and no construction works are required in or near its vicinity. 

 

Based on the site records confirmed by RSS, the concerned tree was identified as the retained tree T710 maintained under the Contract of HY/2010/08 and the concerned tree T710 was located outside the assessment area in the relevant Project EIA Report. No construction works are required in the vicinity of concerned tree T710 and no construction activity was conducted in the vicinity of tree T710 on 27 March 2016. Nevertheless, based on RSS information, recent tree monitoring report indicates an existing cavity at trunk and the concerned tree T710 has been recommended to be felled in the tree risk assessment Form 2.

 

With respect to the observed incident of the toppling of the concerned tree T710, the Contractor of HY/2010/08 was instructed by RSS to remove the broken trunk/ remains to avoid impact to the surroundings. The concerned tree T710 shall be compensated by the Contractor of HY/2010/08 in accordance with the Development Bureau Technical Circular (Works) No. 7/2015 and the detail on compensation would be further agreed with Victoria Park Management Office. Follow-up inspection was conducted on 13 April 2016, and the remaining parts of the concerned tree T710 was observed felled to avoid further impact to nearby public road.

 

8.0.27.   Sixth public complaint regarding muddy dispersion referred by RSS was received by ET on 13 April 2016. The complainant reported that muddy water was observed to disperse from Contract HK/2009/02 site area to Victoria Harbour occasionally as there was no silt curtain installed under the buoyancy floats. The location concerned was the East of Star Ferry Piers (Contract No. HK/2009/02).

 

ET confirmed with the Resident Site Staff that no marine construction activities or land construction activities under Contract HK/2009/02 at the concerned location on 12 April 2016.

Surface runoff control measures including provision of concrete bund at the concerned location was implemented by Contract HK/2009/02.

No soil & silt deposition along the seawall at the concerned location on 12 April 2016.

No discharge point located in the vicinity of the concerned location under Contract HK/2009/02.

Silt curtain with buoyancy floats acting as anchor points was installed at Monitoring Station RW21-P789 for Water intakes.

 

Based on the site records confirmed by RSS, no marine construction activities or land construction activities was carried out under Contract HK/2009/02 at the concerned location on 12 April 2016 and no soil and silt deposition was found along the seawall at the concerned location and precautionary measures for site runoff control including provision of concrete bund along boundary of site area near the waterfront around the concerned location was implemented by the Contractor HK/2009/02. In addition, no discharge point under Contract HK/2009/02 was located in the vicinity of the concerned location. Based on information confirmed by RSS, the buoyancy floats deployed at the concerned location are acting as the anchor points for the silt curtain deployed around the WQM Station RW21-P789 for the WSD and Cooling Water Intakes group.

 

Follow-up inspection was conducted on 14 April 2016, no surface runoff from the construction site nor discharge of contaminated effluent was observed around the concerned location and precautionary measures including the provision of concrete bund at the concerned location was observed maintained by the Contractor of HK/2009/02 and the silt curtain deployed around the WQM station RW21-P789 was generally in order.

In view of the public concern on the water quality, the Contractor of HK/2009/02 was reminded to maintain effective surface runoff protection and provide proper collection point of construction effluent around the concerned location to avoid potential surface runoff related impact.

 

8.0.28.   Seventh public complaint regarding muddy water discharge referred by EPD was received by ET on 13 April 2016 (EPD Ref.: H05/RS/00008367-16 dated 13 April 2016). The complainant reported that muddy water was discharged from the construction work of Contract HK/2012/08 to the sea outside the Hong Kong Academy for Performing Arts on 13 April 2016 morning.

 

ET confirmed with the Resident Site Staff that internal transport of soil to the hopper barge for storage via landing barge was conducted by Contractor of HK/2012/08 during 0800 hours to 1000 hours on 13 April 2016 at the sea outside the concerned location and 3 nos. of dump trucks were deployed for the operation.

Protection measure including provision of sandbag bunding along the side of the landing barge was implemented by the Contractor of HK/2012/08.

 

According to the relevant site records provided by RSS, internal transport of soil to the hopper barge for storage via landing barge was conducted by Contractor of HK/2012/08 during 0800 hours to 1000 hours on 13 April 2016 at the sea outside the concerned location and 3 nos. of dump trucks were deployed for the operation. Protection measure including provision of sandbag bunding along the side of the landing barge was implemented by the Contractor of HK/2012/08. In addition, amber rainstorm warning signal was hoisted from 0630 hours to 1200 hours on 13 April 2016 and during the above time period, muddy water was observed from the upstream of culvert L outside the HK/2012/08 site.

 

Follow up inspection was conducted on 19 April 2016, protection measures including provision of sandbag bunding along the side of the landing barge was implemented and no mud or soil deposition was observed along the seawall and no discharge point was located within the temporary water channel connecting the Culvert L outfall location to the Victoria Harbour. In addition, piling works was observed at the north side of Zone A1 on 19 April 2016 and construction effluent collection from piling work via sedimentation tank to wastewater treatment facility was implemented and steel barrier was installed around the piling works area to mitigate against potential surface runoff related impact.

 

Nevertheless, in view of the public concern, the Contractor was reminded to maintain adequate perimeter embankment protection along the seawall boundary and maintain proper construction effluent collection system to avoid potential runoff related impact to nearby waters.

 

8.0.29.   Eighth EPD complaint regarding noise nuisance referred by RSS was received by ET on 27 May 2016 (EPD Ref: H05/RS/00012646-16 dated 27 May 2016). The complainant reported that a generator was operated round-the-clock in the Chun Wo- CRGL JV construction site near Wanchai Ferry Pier that cause noise nuisance. (Contract No. HK/2009/02).

 

ET confirmed with the Resident Site Staff that a generator deployed under Contract HK/2009/02 near the covered walkway for Wanchai Ferry Pier at Portion 2 area and was operated from 1900hrs on 24 May 2016 to 0700hrs on 25 May 2016 and from 1900hrs on 25 May 2016 to 0700hrs on 26 May 2016. The generator was used for the power supply of lighting inside Tunnel Portions 1 and 2.

 

According to the relevant site records provided by RSS, a generator deployed under Contract HK/2009/02 near the covered walkway for Wanchai Ferry Pier at Portion 2 area and was operated from 1900hrs on 24 May 2016 to 0700hrs on 25 May 2016 and from 1900hrs on 25 May 2016 to 0700hrs on 26 May 2016. The generator was used for the power supply of lighting inside Tunnel Portions 1 and 2. Based on review on site information, relevant Construction Noise Permits GW-RS0516-16 and GW-RS0390-16 for the operation of the concerned generator were confirmed in place while no sufficient site information was considered available to demonstrate the use of acoustic enclosure for the operation of the generator following the special condition 3d item 4. Despite the above, the Contractor of HK/2009/02 has suspended the use of the generator at the concerned location after 2300hours to minimize potential noise concern to the surroundings from 28 May 2016.

 

Nevertheless, the Contractor of HK/2009/02 was reminded to upkeep the site control system for construction works carried out during restricted hours and night time for Construction Noise Permit compliance and maintain regular maintenance of the plant and equipment deployed to avoid potential nuisance to the nearby public.

 

8.0.30.   The construction programmes of individual contracts are provided in Appendix 8.1.