Contract No: HK/2015/01 Wanchai Development Phase II and Sampling,
Field Measurement and Testing Work (Stage 3) Environmental Permit no. EP-364/2009/D, Further Evironmental
permit nos. fep-01/364/2009, fep-02/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEp-07/364/2009/D,
FEP-09/364/2009/B, fep-10/364/2009/B and fep-11/364/2009/B Quarterly
Environmental Monitoring
and
Audit Report
- June 2016 to August 2016 -
|
CLIENTS: |
|
Civil
Engineering and Development Department and Highways
Department |
Lam Geotechnics
Limited 11/F Centre
Point Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
September 2016 |
2.2 Scope of the Project and Site
Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact
Personnel
2.5 Principal Work and Activities
4.2. Real Time Noise Monitoring Results
4.3. Air quality
monitoring Results
5.3. Real Time Noise Monitoring
5.5. Review of the Reasons for and the
Implications of Non-compliance.
5.6. Summary of action taken in the event of
and follow-up on non-compliance.
6. Complaints, Notification
of Summons and Prosecution
7. Cumulative Construction
Impact due to the Concurrent Projects
lIST
OF TABLES
Table I Principal Work
Activities for Contract no. HY/2009/18
Table II Principal
Work Activities for Contract no. HK/2009/01
Table III Principal Work Activities for
Contract no. HK/2009/02
Table IV Principal Work Activities for Contract
no. HY/2009/15
Table V Principal
Work Activities for Contract no. HY/2009/19
Table VI Principal Work Activities for Contract
no. HK/2012/08
Table VII Principal Work Activities for Contract
no. HY/2010/08
Table VIII Principal Work Activities for Contract no.
HY/2011/08
Table 2.1 Schedule
2 Designated Projects under this Project
Table 2.2 Details
of Individual Contracts under the Project
Table 2.3 Contact
Details of Key Personnel
Table 2.4 Principal Work Activities for
Contract no. HY/2009/18
Table 2.5 Principal Work Activities for
Contract no. HK/2009/01
Table 2.6 Principal
Work Activities for Contract no. HK/2009/02
Table 2.7 Principal
Work Activities for Contract no. HY/2009/15
Table 2.8 Principal
Work Activities for Contract no. HY/2009/19
Table 2.9 Principal
Work Activities for Contract no. HK/2012/08
Table 2.10 Principal Work
Activities for Contract no. HY/2010/08
Table 2.11 Principal Work
Activities for Contract no. HY/2011/08
Table 3.1 Noise
Monitoring Stations
Table 3.2 Real
Time Noise Monitoring Stations
Table 3.3 Air
quality monitoring Stations
Table 4.1 Noise Monitoring Station
for Contract no. HY/2009/18
Table 4.2 Noise Monitoring
Stations for Contract nos. HK/2009/01 and HK/2009/02
Table 4.3 Noise Monitoring Station
for Contract nos. HY/2009/15
Table 4.4 Noise
Monitoring Stations for Contract no. HY/2009/19
Table 4.5 Noise Monitoring Stations for Contract
no. HY/2010/08
Table 4.6 Noise Monitoring Stations for Contract no.
HY/2011/08
Table 4.7 Real
Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 4.8 Real Time
Noise Monitoring Stations for Contract
no. HY/2011/08
Table 4.9 Air
quality monitoring Stations for Contract no. HY/2009/18
Table 4.10 Air
quality monitoring Stations for Contract no. HK/2009/01
Table 4.11 Air
quality monitoring Station for Contract no. HK/2009/02
Table 4.12 Air
quality monitoring Station for Contract no. HY/2009/15
Table 4.13 Air
quality monitoring Stations for Contract no. HY/2009/19
Table 4.14 Air quality
monitoring Stations for Contract no. HK/2012/08
Table 4.15 Air
quality monitoring Stations for Contract no. HY/2010/08
Table 4.16 Air quality monitoring Stations for
Contract no. HY/2011/08
Table 4.17 Details
of Waste Disposal for Contract no. HK/2009/01
Table 4.18 Details
of Waste Disposal for Contract no. HK/2009/02
Table 4.19 Details
of Waste Disposal for Contract no. HY/2009/18
Table 4.20 Details
of Waste Disposal for Contract no. HY/2009/15
Table 4.21 Details
of Waste Disposal for Contract no. HY/2009/19
Table 4.22 Details
of Waste Disposal for Contract no. HK/2012/08
Table 4.23 Details of Waste Disposal for Contract no.
HY/2010/08
Table 4.24 Details of
Waste Disposal for Contract no. HY/2011/08
Table 6.1 Cumulative
Statistics on Complaints
Table 6.2 Cumulative
Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure
2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure
3.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 2.1 Environmental Mitigation
Implementation Schedule
Appendix 3.1 Action and Limit Level
Appendix 4.1 Noise Monitoring Results and
Graphical Presentations
Appendix
4.2 Real-time Noise Monitoring Results and
Graphical Presentations
Appendix 4.3 Air Quality Monitoring Results
and Graphical Presentations
Appendix 5.1 Event Action Plans
Appendix 6.1 Complaint Log
Appendix 6.2 Notification of Exceedance
Appendix 8.1 Construction Programme of
Individual Contracts
EXECUTIVE
SUMMARY
Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB)
- Central Interchange under FEP-05/364/2009/
Major construction activities for Contract no. HY/2009/18 have been
commenced on 21
Table I Principal Work Activities for Contract
no. HY/2009/18
June 2016 |
July 2016 |
August 2016 |
Drainage works Road works Landscaping works Modification and Construction of Sign
Gantries / Traffic Signs Maintenance works |
Drainage works Road works Landscaping works Modification and Construction of Sign
Gantries / Traffic Signs Maintenance works |
Drainage works Road works Landscaping works Modification and Construction of Sign
Gantries / Traffic Signs Maintenance works |
Contract no.
HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009
Major construction activities
for Contract no. HK/2009/01 have been commenced on 25 August 2011. During this
reporting period, the principal work activities are summarized as below:
Table II Principal Work
Activities for Contract no. HK/2009/01
June 2016 |
July 2016 |
August 2016 |
Stage 4 backfilling works was in
progress. Stage 4 tunnel structure construction
was completed. Reinstatement of outfall was in
progress. |
Stage 4 backfilling works Reinstatement of outfall Road and Drain works |
Stage 4 backfilling works Reinstatement of outfall Road and Drain works |
Contract no.
HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
Major construction activities
for Contract no. HK/2009/02 have been commenced on 26
Table III Principal Work Activities for Contract no.
HK/2009/02
June 2016 |
July 2016 |
August 2016 |
Site clearance works was on going at
OHVD at Tunnel Portion 1. Site clearance works was on going at
OHVD at Tunnel Portion 2. Waterproofing works for side wall Side wall construction Tunnel top slab construction Cutting of Eastern Bulkhead Wall Removal of scaffolds underneath tunnel
soffit Waterproofing layer at tunnel top slab Diaphragm wall panel All toe grouting works were Instrumentation work Excavation work Erection of hoarding for the
demolition of ex-WSD Salt Water Pumping Station Fabrication of steel
hoardings |
Remedial works against water leakage
and concrete defects. Middle and side wall construction Tunnel top slab construction Removal of Eastern Bulkhead Wall Removal of scaffolds underneath tunnel
soffit Waterproofing layer at tunnel top slab Removal of ELS S4 Instrumentation work
Excavation work ELS S1 layer installation Pumping test Erection of hoarding for the
demolition of ex-WSD Salt Water Pumping Fabrication of steel hoardings |
Remedial works against water leakage
and concrete defects Installation of precast concrete
covers Middle and side wall construction Tunnel top slab construction Removal of Eastern Bulkhead Wall Waterproofing layer at tunnel top slab Removal of ELS S4 Excavation work ELS S1 layer installation Pumping test Removal of remaining sheet piles and
temporary seawall blocks Erection of hoarding for the
demolition of ex-WSD Salt Water Pumping Station Demolition of ex-WSD salt
water pumping station Backfilling works of HKE Cable
connection works |
Contract no. HY/2009/15 - Central-Wanchai
Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
Major construction activities
for Contract no. HY/2009/15 has been commenced on 13 July 2011. During this
reporting period, the principal work activities are summarized as below:
Table IV Principal Work Activities for Contract no.
HY/2009/15
July
2016 |
August
2016 |
|
Dismantle steel work at TPCWAW Remedial works at Mined Tunnel Remedial works at TS4, TPCWAE Reinstatement of Shaft B between
TPCWAW and TPCWAE |
Remedial
works inside tunnel structure at Mined Tunnel, TS4, TPCWAE and TPCWAW |
Remedial
works inside tunnel structure at Mined Tunnel, TS4, TPCWAE and TPCWAW |
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/D
Major construction activities
for Contract no. HY/2009/19 have been commenced on March 2011. During this
reporting period, the principal work activities are summarized as below:
Table V Principal Work
Activities for Contract no. HY/2009/19
June 2016 |
July 2016 |
August 2016 |
Pier construction for IEC Construction of EVB Column modification at F1 to F8 Oil Street drainage works Approach ramp sheet piling and
pre-bored piling works Bridge construction and segment erection Hing Fat Street modification works EVA structure construction Hing Fat Street Slip Road Bridge E L3
railing construction EVB waterproofing works |
Pier construction for IEC Construction of EVB Column modification at F1 to F8 Approach ramp sheet piling and pre-bored
piling works Bridge construction and segment
erection Hing Fat Street modification works Hing Fat Street Slip Road Bridge E L3
railing construction EVB back filling & waterproofing
works Pier 26 to 28 Tie Beam construction |
Construction of EVB Approach ramp sheet piling, pre-bored
piling and top soil removal works Bridge construction and segment
erection Hing Fat Street modification works Hing Fat Street Slip Road Bridge E L3
railing construction EVB waterproofing & back filling
works Pier 22 to 28 Tie Beam construction |
Contract
no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at
Wan Chai West under FEP-09/364/2009B
Table VI Principal
Work Activities for Contract no. HK/2012/08
June 2016 |
July 2016 |
August 2016 |
Grouting Construction of MVB and CWB Tunnel Construction of concrete plug Excavation and lateral support
installation for CWB tunnel |
Grouting Construction of MVB and CWB Tunnel Construction of concrete plug Excavation and lateral support
installation for CWB tunnel |
Grouting Construction of MVB and CWB Tunnel Construction of concrete plug Excavation and lateral support
installation for CWB tunnel |
Contract
no. HY/2010/08 – Central and WanChai Bypass – Slip road 8 section under
FEP-10/364/2009B
Table VII Principal Work
Activities for Contract no. HY/2010/08
June 2016 |
July 2016 |
August 2016 |
Tree protection works next to existing
BGO, Drainage improvement works, Excavation and Lateral Support for
U-structure, Pipe piling & grouting works, Utility diversion works, Retaining wall works ELS works, D-wall drill cutting works Construction works for subway
extension |
Tree protection works next to existing
BGO, Drainage improvement works, Excavation and Lateral Support for
U-structure, Grouting works, Utility diversion works, Retaining wall works ELS works, Construction works for subway
extension |
Tree protection works next to existing
BGO, Drainage improvement works, Excavation and Lateral Support for
U-structure, Grouting works, Utility diversion works, Retaining wall works ELS works, Construction works for subway
extension |
Contract
no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B
Table VIII Principal Work
Activities for Contract no. HY/2011/08
June 2016 |
July 2016 |
August 2016 |
Construction of Ventilation Buildings,
inclusive of Administration Building, East Ventilation Shaft, West
Ventilation Building Construction of Tunnel Thermal Barrier Installation of Electricals and
Mechanicals Installation of Tunnel Features |
Construction of Ventilation Buildings,
inclusive of Administration Building, East Ventilation Shaft, West
Ventilation Building Construction of Tunnel Thermal Barrier Installation of Electricals and
Mechanicals Installation of Tunnel Features |
Construction of Ventilation Buildings,
inclusive of Administration Building, East Ventilation Shaft, West
Ventilation Building Construction of Tunnel Thermal Barrier Installation of Electricals and Mechanicals Installation of Tunnel Features |
Noise
Monitoring
Real time Noise Monitoring
Air Quality Monitoring
Complaints,
Notifications of Summons and Successful Prosecutions
ET confirmed with the Resident Site
Staff that rebar fixing was carried out on 13 and 14 June 2016 under the
Contractor of HY/2009/19 while formwork cleaning and laying concrete for
stitching and curing work for concrete were carried out under the Contractor of
HY/2009/19 on 15 June 2016 and 16 June 2016 respectively.
Mitigation measures including provision
of metal cover underneath the bridge deck in slanting position at Watson Road
to prevent spilling of water onto public road and provision of tarpaulin sheet
along the guard rails of the bridge deck at Pier 19-20 (opposite to Sea View
Estate) to prevent splashing of water to outside area were implemented by the
Contractor of HY/2009/19.
Based on the site records confirmed by
RSS, rebar fixing was carried out on 13
and 14 June 2016 under the Contractor of
HY/2009/19 while formwork cleaning and laying concrete for stitching and
curing work for concrete were carried out under the Contractor of HY/2009/19 on
15 June 2016 and 16 June 2016 respectively.
Mitigation measures including provision
of metal cover underneath the bridge deck in slanting position at Watson Road
to prevent spilling of water onto public road and provision of tarpaulin sheet
along the guard rails of the bridge deck at Pier 19-20 (opposite to Sea View
Estate) to prevent splashing of water to outside area were implemented by the
Contractor of HY/2009/19.
Follow up inspection was conducted on 22
June 2016, mitigation measures including the use of metal cover underneath the
bridge deck at Watson Road and provision of tarpaulin sheet along the guard
rails of the section of bridge deck opposite to Sea View Estate were
implemented by the Contractor of HY/2009/19. No particular spilling or
splashing of construction water was observed during inspection around the
concerned location.
Nevertheless, in view of the public
concern, the Contractor of HY/2009/19 was suggested that the direction of the
water hose shall be pointed away from the public area as far as practicable
during water use or watering for dust suppression to avoid potential splashing
nuisance caused to the surroundings. The Contractor of HY/2009/19 was also
reminded to maintain proper site drainage to direct surface runoff generated
from construction works or cleaning to the proper collection point within site
area to avoid potential nuisance to the surroundings.
ET confirmed with the Resident Site
Staff that excavation at TS3 and loading of material onto derrick barge (Shun
Tat 28) by crawler crane was undertaken by the Contractor of HY/2010/08 from
19:00hrs to around 02:00hrs on 30 June 2016. Total one crawler crane was in
operation. Noise mitigation measures including equipping the crawler crane with
noise barrier was implemented by the Contractor of HY/2010/08. Dust mitigation
measures including manual spraying of water and mist nozzles are deployed on
the ground level and at the cofferdam.
Based on the site records confirmed by
RSS, excavation at TS3 and loading of material onto derrick barge (Shun Tat 28)
by crawler crane was undertaken by the Contractor of HY/2010/08 from 19:00hrs
on 29 June 2016 to around 02:00hrs on 30 June 2016. No construction works was
conducted at the concerned location after around 02:00hrs on 30 June 2016.
Total one crawler crane was in operation and noise mitigation measures
including equipping the crawler crane with noise barrier was implemented by the
Contractor of HY/2010/08.
Based on review on relevant record,
Construction Noise Permit GW-RS0434-16 for the operation of crawler crane at
the concerned location was in place. However, based on relevant site record, it
was noted that the crawler crane deployed during the concerned period could not
match with the specific PME requirement under condition 3a (Crane, crawler,
mounted with noise barrier (Kobelco 7250S)) of the Construction Noise Permit
GW-RS0434-16 between 23:00hrs to 07:00hrs on the following day. Dust mitigation
measures including manual spraying of water and mist nozzles were deployed on
the ground level and at the cofferdam.
Follow up inspection was conducted on 20
July 2016, the potential concerned excavation works at the concerned location
was not observed and no particular dust impact was observed around the
concerned location.
In view of the above, the Contractor of
HY/2010/08 was advised to review the site control system for construction works
carried out during restricted hours to check and ensure the model/ specific
PMEs deployed are in compliance with relevant Construction Noise Permit. The
Contractor of HY/2010/08 was also reminded to maintain regular maintenance of
the plant and equipment deployed to avoid potential nuisance to the nearby
public. Also, the Contractor of HY/2010/08 was reminded to maintain sufficient
watering for excavated material handling to avoid potential dust nuisance to
the surroundings.
1.1.1.
Lam
Geotechnics Limited (LGL) has been appointed to work as the Environmental Team
(ET) under Environmental Permit no. EP-364/2009/D and Further Environmental permit nos. FEP-01/364/2009, FEP-02/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/D, FEP-09/364/2009/B, FEP-10/364/2009/B and
FEP-11/364/2009/B to implement the Environmental Monitoring and
Audit (EM&A) programme as stipulated in the EM&A Manual of the approved
Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A
Manual of the approved EIA Report for Central-Wan Chai Bypass and Island
Eastern Corridor Link (Register No. AEIAR-041/2001).
1.1.2.
This
report presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.3 of
EM&A Manual and “Environmental Monitoring and Audit Requirements”
under Particular Specification Section 27.
1.1.3. This report documents the finding of EM&A
works during the period from 27 May
2016 to 26 August 2016.
Section 1 Introduction – details the scope and structure of the
report.
Section 2 Project Background – summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section 3 Monitoring Requirements – summarizes all monitoring parameters,
monitoring locations, monitoring frequency, duration and action plan.
Section 4 Monitoring Results – summarizes the monitoring results
obtained in the reporting period.
Section 5 Compliance Audit – summarizes the auditing of monitoring results, all
exceedances environmental parameters.
Section 6 Complaints,
Notification of summons and Prosecution – summarizes the cumulative
statistics on complaints, notification of summons and prosecution
Section 7 Cumulative
Construction Impact due to the Concurrent Projects – summarizes the
relevant cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section 8 Conclusion
2.1.1.
“Wan
Chai Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai
Bypass and Island Eastern Corridor Link” (hereafter called “the Project”) are
Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap.
499) (EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The
key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan
Chai North and North Point for construction of the Central-Wan Chai Bypass and
Island Eastern Corridor Link (CWB). Land formed under the project will be
developed as a world-class waterfront promenade joining that at the new Central
waterfront for public enjoyment.
2.1.3.
There
is a compelling and present need for the CWB to provide relief to the very
congested
2.2.1.
Design and Construction of Central – Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The
study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB)
and Island Eastern Corridor Link (IECL) includes:
·
A dual three-lane trunk road, approximately 4.5 km
in length, and tunnel approximately 3.7 km in length defined from the
connection with the existing Rumsey Street Flyover in Central, through to a
connection with the existing Island Eastern Corridor to the east of the
Causeway Bay Typhoon Shelter (CBTS);
·
The Central Interchange near the Rumsey Street
Flyover to provide road connections to the Central area;
·
Tunnel control buildings and ventilation buildings;
·
Slip roads to connect the CWB to the local road
system in the Wan Chai North and
·
Associated road lighting, road signing, traffic
control and surveillance system; and
·
Other associated works.
2.2.3.
The
project also contains various Schedule 2 DPs that, under the EIAO, require
Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five
individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table 2.1 Schedule 2 Designated Projects under this
Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due
to the multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be
commenced. Contractors of individual
contracts will be required by the EP holder to apply Further Environmental
Permits such
that the impact monitoring stations are sub-divided accordingly to facilitate
the implementation of EM&A programme and to streamline the EM&A
reporting for individual FEP holders correspondingly.
2.3.2.
In
the reporting period, all the contracts were commenced and contract no.
04/HY/2006 had been completed. The details of individual contracts are
summarized in Table2.2.
Table 2.2 Details of Individual Contracts under the
Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HY/2009/17 |
Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced
piling works. |
DP1 |
5 October 2010 (Completed) |
HY/2009/18 |
Central – Wan Chai Bypass (CWB) – Central Interchange |
DP1 |
21 |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II – Central – Wan Chai Bypass at |
DP1, DP2 |
25 August 2011 |
HK/2009/02 |
Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai
East(CWB Tunnel) |
DP1 |
26 |
HY/2009/15 |
Central-Wanchai Bypass – Tunnel ( |
DP1 |
13 July 2011 |
HY/2009/19 |
Central – Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 (Completed) |
HK/2012/08 |
Wan Chai Development Phase II- Central-Wan Chai
Bypass at Wan Chai West |
DP1,DP2, DP3 |
10 March 2014 |
HY/2010/08 |
Central- Wanchai Bypass Tunnel – Tunnel (Slip
Road 8) |
DP1, DP2, DP3 |
21 March 2013 |
HY/2011/08 |
Central - Wan Chai Bypass (CWB) –Tunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning |
DP1 |
8 October 2014 |
2.3.3.
The construction works of Contract no.
04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street under FEP-04/364/2009/A was completed, and the FEP was surrendered by
the Contractor on 11 February 2011.
2.3.4.
Construction of bored pile E3B under HY/2009/17 was confirmed
completed and the respective work area under FEP-03/364/2009 was handover and inspected
under HY/2009/19 from 19 Dec 2012 onwards. Subsequently, the FEP-03/364/2009
was surrendered by the Contractor on 28 March 2013.
2.3.5.
Construction works under HK/2010/06 was confirmed completed and
the respective work area under FEP-08/364/2009/A was handover and inspected
under HK/2012/08 from 22 Sep 2014 onwards. Subsequently, the FEP-08/364/2009/A
was surrendered by the Contractor on 3 October 2014.
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively.
For the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure 2.2. Key
personnel and contact particulars are summarized in Table 2.3.
Table
2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer’s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer’s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3916 1818 |
3529 2829 |
|
Chun
Wo – Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Project Manager |
Mr. Simon Liu |
2162 9909 |
2634 1626 |
Site Agent |
Mr. Andy Yu |
9648 4896 |
|||
Construction Manager |
Mr. Terry Wong |
9757 9846 |
|||
Construction
Manager |
Mr. Wyman
Wong |
9627 2467 |
|||
Construction
Manager |
Mr.
Kenneth Chan |
9160
3850 |
|||
Environmental
Officer |
Ms. Wendy
Ng |
9103
2370 |
|||
Assistant
Environmental Engineer |
Ms. Connie Chan |
9047 6148 |
|||
Chun Wo – CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. K.K. Yuen |
3658-3002 |
2827 9996 |
Project Manager |
Mr. Paul Yu |
3658 3085 |
|||
Environmental Officer |
Mr. C.P. Ho |
9191 8856 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. David Lau |
3758 8879 |
2570 8013 |
Deputy Project Manager |
Mr. William Luk |
9456 9819 |
|||
Deputy Site Agent |
Eric Fong |
6191 9337 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Environmental Engineer |
Mr. Calvin Leung |
9286 9208 |
|||
Leighton Contractors (Asia) Limited |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Jimmy Chu |
2214
7700 |
2140 6799 |
Deputy Site Agent |
Mr. Bob Yeung |
2214
7703 |
|||
Environmental Officer |
Mr. Chris Chan |
2823
1161 |
|||
Assistant Environmental Engineer |
Mr. Christy So |
3937
1065 |
|||
China |
Contractor under Contract no. HY/2009/15 |
Project Director |
Mr. Chris Leung |
3557 6393 |
2566 2192 |
Site Manager |
Mr. Y. Huo |
3557 6368 |
|||
Contractor’s
Representative |
Mr. Rex Chan |
3557
6371 |
|||
Environmental Officer |
Mr. Andy Mak |
3557 6215 |
|||
Environmental Supervisor |
Mr. Harry Wong |
3557 6348 |
|||
China State- Leader JV |
Contractor under Contract no. HK/2012/08 |
Project
Director |
Mr. C.N.
Lai |
9137
1811 |
2877
1522 |
Project
Manager |
Mr. Eddie
Chung |
9193
8871 |
|||
Site
Agent |
Mr. Keith
Tse |
9095
7922 |
|||
Environmental
Officer |
Mr. James
MA |
9130
9549 |
|||
Environmental
Supervisor |
Mr. Y.L.
Ho |
6050
4919 |
|||
China |
Contractor under Contract no.HY/2010/08 |
Project
Director |
Cheung
Kit Cheung |
3557
6399 |
3465 2899 |
Project
Manager |
Chan
Ying Lun |
9812
0592 |
|||
Deputy
Project Manager |
Chris
Leung |
3467
4299 |
|||
Site
Agent |
Mr. Andrew Wong |
3467
4277 |
|||
Environmental
Officer |
Mr. Gabriel
Wong |
3557
6464 |
|||
Environmental
Supervisor |
Mr. Louis
Lam Tsz Kwan |
3557
6470 |
|||
Leighton Joint Venture |
Contractor under Contract no. HY/2011/08 |
Project
Manager |
Paul
Evans |
2823 1111 |
21406799 |
Site
Agent |
Colman Wong |
9730 0806 |
|||
Environmental
Officer |
Malcom
Leung |
3973 0850 |
|||
Environmental
Supervisor |
Christy So |
3973 1065 |
|||
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
RAMBOLL ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
2.5.1.
Major construction activities for Contract no.
HY/2009/18 have been commenced on 21
Table 2.4 Principal Work Activities
for Contract no. HY/2009/18
June
2016 |
July
2016 |
August
2016 |
Drainage works
Road works
Landscaping works
Modification and Construction of Sign Gantries / Traffic Signs
Maintenance works |
Drainage works
Road works
Landscaping works
Modification and Construction of Sign Gantries / Traffic Signs
Maintenance works |
Drainage works
Road works
Landscaping works
Modification and Construction of Sign Gantries / Traffic Signs
Maintenance works |
2.5.2. Major
construction activities for Contract no. HK/2009/01 have been commenced on 25
August 2011. During this reporting period, the principal work activities are
summarized in Table2.5:
Table 2.5 Principal Work Activities
for Contract no. HK/2009/01
June
2016 |
July
2016 |
August
2016 |
Stage 4 backfilling works was in progress.
Stage 4 tunnel structure construction was completed.
Reinstatement of outfall was in progress. |
Stage 4 backfilling works
Reinstatement of outfall
Road and Drain works |
Stage 4 backfilling works
Reinstatement of outfall
Road and Drain works |
2.5.3. Major
construction activities for Contract no. HK/2009/02 have been commenced on 26
Table 2.6 Principal Work Activities
for Contract no. HK/2009/02
June
2016 |
July
2016 |
August
2016 |
Site clearance works was on going at OHVD at Tunnel Portion 1.
Site clearance works was on going at OHVD at Tunnel Portion 2.
Waterproofing works for side wall
Side wall construction
Tunnel top slab construction
Cutting of Eastern Bulkhead Wall
Removal of scaffolds underneath tunnel soffit
Waterproofing layer at tunnel top slab
Diaphragm wall panel
All toe grouting works were
Instrumentation work
Excavation work
Erection of hoarding for the demolition of ex-WSD Salt Water Pumping
Station Fabrication of steel hoardings |
Remedial works against water leakage and concrete defects.
Middle and side wall construction
Tunnel top slab construction
Removal of Eastern Bulkhead Wall
Removal of scaffolds underneath tunnel soffit
Waterproofing layer at tunnel top slab
Removal of ELS S4 Instrumentation work
Excavation work
ELS S1 layer installation
Pumping test
Erection of hoarding for the demolition of ex-WSD Salt Water Pumping
Fabrication of steel hoardings |
Remedial works against water leakage and concrete defects
Installation of precast concrete covers
Middle and side wall construction
Tunnel top slab construction
Removal of Eastern Bulkhead Wall
Waterproofing layer at tunnel top slab
Removal of ELS S4
Excavation work
ELS S1 layer installation
Pumping test
Removal of remaining sheet piles and temporary seawall blocks
Erection of hoarding for the demolition of ex-WSD Salt Water Pumping
Station Demolition of ex-WSD salt water pumping station
Backfilling works of HKE Cable connection works |
2.5.4. Major
construction activities for Contract no. HY/2009/15 have been commenced on 13
July 2011. During this reporting period, the principal work activities are
summarized in Table 2.7:
Table 2.7 Principal Work Activities
for Contract no. HY/2009/15
June
2016 |
July
2016 |
August
2016 |
Dismantle steel work at TPCWAW
Remedial works at Mined Tunnel
Remedial works at TS4, TPCWAE
Reinstatement of Shaft B between TPCWAW and TPCWAE |
Remedial
works inside tunnel structure at Mined Tunnel, TS4, TPCWAE and TPCWAW |
Remedial works inside tunnel structure at Mined
Tunnel, TS4, TPCWAE and TPCWAW |
2.5.5. Major
construction activities for Contract no. HY/2009/19 have been commenced on
March 2011. During this reporting period, the principal work activities are
summarized in Table 2.8:
Table 2.8 Principal Work Activities
for Contract no. HY/2009/19
June
2016 |
July
2016 |
August
2016 |
Pier construction for IEC
Construction of EVB
Column modification at F1 to F8
Oil Street drainage works
Approach ramp sheet piling and pre-bored piling works
Bridge construction and segment
erection
Hing Fat Street modification works
EVA structure construction
Hing Fat Street Slip Road Bridge E L3 railing construction
EVB waterproofing works |
Pier construction for IEC
Construction of EVB
Column modification at F1 to F8
Approach ramp sheet piling and pre-bored piling works
Bridge construction and segment erection
Hing Fat Street modification works
Hing Fat Street Slip Road Bridge E L3 railing construction
EVB back filling & waterproofing works
Pier 26 to 28 Tie Beam construction |
Construction of EVB
Approach ramp sheet piling, pre-bored piling and top soil removal
works
Bridge construction and segment erection
Hing Fat Street modification works
Hing Fat Street Slip Road Bridge E L3 railing construction
EVB waterproofing & back filling works
Pier 22 to 28 Tie Beam construction |
2.5.6.
Major construction activities for
Contract no. HK/2012/08 have been commenced on March 2013. During the reporting
period, the principal work activities are summarized in Table 2.9
Table 2.9 Principal Work Activities for Contract no. HK/2012/08
June
2016 |
July
2016 |
August
2016 |
Grouting
Construction of MVB and CWB Tunnel
Construction of concrete plug
Excavation and lateral support installation for CWB tunnel |
Grouting
Construction of MVB and CWB Tunnel
Construction of concrete plug
Excavation and lateral support installation for CWB tunnel |
Grouting
Construction of MVB and CWB Tunnel
Construction of concrete plug
Excavation and lateral support installation for CWB tunnel |
2.5.7.
Major construction activities for Contract no. HY/2010/08 have been commenced
on March 2013. During the reporting period, the principal work activities are
summarized in Table 2.10
Table 2.10 Principal Work Activities for Contract no. HY/2010/08
June
2016 |
July
2016 |
August
2016 |
Tree protection works next to existing BGO,
Drainage improvement works,
Excavation and Lateral Support for U-structure,
Pipe piling & grouting works,
Utility diversion works,
Retaining wall works
ELS works,
D-wall drill cutting works
Construction works for subway extension |
Tree protection works next to existing BGO,
Drainage improvement works,
Excavation and Lateral Support for U-structure,
Grouting works,
Utility diversion works,
Retaining wall works
ELS works,
Construction works for subway extension |
Tree protection works next to existing BGO,
Drainage improvement works,
Excavation and Lateral Support for U-structure,
Grouting works,
Utility diversion works,
Retaining wall works
ELS works,
Construction works for subway extension |
2.5.8.
Contract no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning
under FEP-11/364/2009B. During the reporting period, the principal work
activities are summarized in Table 2.11
Table 2.11 Principal
Work Activities for Contract no. HY/2011/08
June
2016 |
July
2016 |
August
2016 |
Construction of Ventilation Buildings, inclusive of Administration
Building, East Ventilation Shaft, West Ventilation Building
Construction of Tunnel Thermal Barrier
Installation of Electricals and Mechanicals
Installation of Tunnel Features |
Construction of Ventilation Buildings, inclusive of Administration
Building, East Ventilation Shaft, West Ventilation Building
Construction of Tunnel Thermal Barrier
Installation of Electricals and Mechanicals
Installation of Tunnel Features |
Construction of Ventilation Buildings, inclusive of Administration
Building, East Ventilation Shaft, West Ventilation Building
Construction of Tunnel Thermal Barrier
Installation of Electricals and Mechanicals
Installation of Tunnel Features |
2.5.9.
Implementation status of the recommended mitigation measures
during this reporting period is presented in Appendix 2.1.
3.1.1.
The
noise monitoring stations for the Project are listed and shown in Table
3.1 and Figure 3.1. Appendix 3.1 shows
the established Action/Limit Levels for the monitoring works.
Table
3.1 Noise Monitoring Station
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun
Area |
M3a |
Tung Lo Wan
Fire Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
*M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
M8 |
City Hall |
* Remark 1: Location
ID has been updated from M7 to M8 for City Hall
* Remark 2: M7e has
become a reference station starting from 7 Aug 2012
Real time Noise Monitoring Stations
3.1.2.
The
noise monitoring stations for the Project are listed and shown in Table 3.2 and Figure 3.1.. Appendix 3.1 shows the established Action/Limit Levels for
the monitoring works.
Table 3.2 Real Time Noise
Monitoring Station
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section Whitefield Depot |
North Point |
RTN2a |
Electric Centre |
North Point |
RTN3 |
Po Leung Kuk Yu Lee Mo Fan
Memorial School |
Tin Hau |
RTN4 |
|
* RTN2 was relocated from
Oil Street Community Liaison Centre to Electric Centre on
05 Oct 2012 and re-designated
as RTN2a.
Noise Monitoring
Parameters, Frequency and Duration
3.1.3.
The construction noise level shall be measured in terms of
the A-weighted equivalent continuous sound pressure level (Leq). Leq (30
minutes) shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For
all other time periods, Leq (5 minutes) shall be employed for
comparison with the Noise Control Ordinance (NCO) criteria.
Supplementary information for data auditing, statistical results such as L10
and L90 shall also be obtained for reference.
3.1.4.
Noise
monitoring shall be carried out at all the designated monitoring stations. The
monitoring frequency shall depend on the scale of the construction activities.
The following is an initial guide on the regular monitoring frequency for each
station on a weekly basis when noise generating activities are underway:
·
One
set of measurements between 0700 and 1900 hours on normal weekdays.
3.1.5.
Real
time noise shall be carried out at the designated monitoring stations. The
following is an initial guide on the regular monitoring frequency for each
station on a 24 hours daily basis when noise generating activities are
underway:
·
One
set of measurements between 0700 and 1900 hours on normal weekdays.
·
One
set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and
2300 hours on public holidays.
·
One
set of measurements between 2300 and 0700 hours on next day on everyday.
3.1.6.
If
construction works are extended to include works during the hours of 1900 –
0700 as well as public holidays and Sundays, additional weekly impact
monitoring shall be carried out during respective restricted hours periods.
Applicable permits under NCO shall be obtained by the Contractor.
Monitoring Equipment
3.1.7.
As
referred to in the Technical Memorandum ™ issued under the NCO, sound level
meters in compliance with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be
used for carrying out the noise monitoring. Immediately prior to and following
each noise measurement the accuracy of the sound level meter shall be checked
using an acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agree to within 1.0 dB.
3.1.8.
Noise
measurements shall not be made in fog, rain, wind with a steady speed exceeding
5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with
a portable wind speed meter capable of measuring the wind speed in m/s.
3.1.9.
The
sound level meter shall be checked using an acoustic calibrator generating a
known sound pressure level at a known frequency before deployment to the site
and during each site visit. Measurements may be accepted as valid only if the
calibration level from before and after the noise measurement agree to within
1.0 dB.
Air Quality Monitoring
Stations
3.2.1. The air quality monitoring stations for the Project
are listed and shown in Table 3.3 and Figure 3.1. Appendix 3.1 shows the established
Action/Limit Levels for the monitoring works.
Table
3.3 Air quality monitoring
Stations
Station ID |
Monitoring
Location |
Description |
CMA1b |
Oil Street Site Office* |
North Point |
CMA2a |
|
|
CMA3a |
CWB PRE Site Office |
|
CMA4a |
Society for the
Prevention of Cruelty to Animals |
Wan Chai |
CMA5b |
Pedestrian Plaza** |
Wan Chai |
MA1e |
International Finance Centre (Eastern End of Podium) |
Central |
MA1w |
International Finance Centre (Western End of Podium) |
Central |
Remarks*: The location ID of monitoring
station CMA1b was updated as “Oil Street Site Office” in
Remarks**: With respect to the area handover, the air
quality monitoring station CMA5a at Children Playgrounds opposite to the
Pedestrian Plaza was relocated to the Pedestrian Plaza on 3 December 2014. The
station reference and location ID of the air quality monitoring station CMA5a
was updated as CMA5b and Pedestrian Plaza respectively.
Air quality monitoring
Parameters, Frequency and Duration
3.2.2. One-hour and 24-hour TSP levels should be measured
to indicate the impacts of construction dust on air quality. The 24-hour TSP
levels shall be measured by following the standard high volume sampling method
as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part
50), Appendix B.
3.2.3. All relevant data including temperature, pressure,
weather conditions, elapsed-time meter reading for the start and stop of the
sampler, identification and weight of the filter paper, and any other local
atmospheric factors affecting or affected by site conditions, etc., shall be
recorded down in detail.
3.2.4. For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
Sampling Procedure and
Monitoring Equipment
3.2.5. High volume samplers (HVSs) in compliance with the
following specifications shall be used for carrying out the 1-hour and 24-hour
TSP monitoring:
·
0.6
– 1.7 m3 per minute adjustable flow range;
·
Equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours
operation;
·
Installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
·
Capable
of providing a minimum exposed area of 406 cm2;
·
Flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
·
Equipped
with a shelter to protect the filter and sampler;
·
Incorporated
with an electronic mass flow rate controller or other equivalent devices;
·
Equipped
with a flow recorder for continuous monitoring;
·
Provided
with a peaked roof inlet;
·
Incorporated
with a manometer;
·
Able
to hold and seal the filter paper to the sampler housing at horizontal position;
·
Easily
changeable filter; and
·
Capable
of operating continuously for a 24-hour period.
3.2.6. Initial calibration of dust monitoring equipment
shall be conducted upon installation and thereafter at bi-monthly intervals.
The transfer standard shall be traceable to the internationally recognized
primary standard and be calibrated annually. The concern parties such as IEC
shall properly document the calibration data for future reference. All the data
should be converted into standard temperature and pressure condition.
3.2.7. Laboratory Measurement / Analysis
3.2.8. A clean laboratory with constant temperature and
humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
3.2.9. Filter paper of size 8” x 10” shall be labelled
before sampling. It shall be a clean filter paper with no pinholes, and shall
be conditioned in a humidity-controlled chamber for over 24-hours and be
pre-weighed before use for the sampling.
3.2.10. After sampling, the filter paper loaded with dust
shall be kept in a clean and tightly sealed plastic bag. The filter paper shall
then be returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
readout down to 0.1 mg. The balance shall be regularly calibrated against a
traceable standard.
3.2.11. All the collected samples shall be kept in a good
condition for 6 months before disposal.
4.0.1. Per EPD’s letter
dated 3 Aug 2012 (received by ET on 6 Aug 2012 through HyD), noise monitoring
at M8 – City Hall commenced on 7 Aug 2012, and the monitoring station M7e –
International Finance Centre (Eastern Podium) has become a reference station
starting from 7 Aug 2012.
4.0.2. Due to safety
concerns, the monitoring location for M4b – Victoria Centre has been finely
adjusted from 7 June 2012.
4.0.3. Monitoring for report of review baseline noise
level was performed from 11
4.0.4. The environmental monitoring will be implemented
based on the division of works areas of each designed project managed under
different contracts with separate FEP applied by individual contractors. Overall layout showing work areas of various
contracts, latest status of work commencement and monitoring stations is shown
in Figure
2.1 and Figure 3.1. The monitoring results
are presented in according to the Individual Contract(s).
4.0.5. In the reporting period, the concurrent contracts are
as follows:
Contract
no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (
Contract
no. HY/2009/18 – Central –Wanchai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
Contract
no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009
Contract
no. HK/2009/01 –Wanchai Development Phase II – Central –Wanchai Bypass at Hong
Kong Convention and Exhibition Centre under FEP-02/364/2009
Contract
no. HK/2009/02 Wanchai Development Phase II – Central- Wanchai Bypass at Wanchai
East under FEP-01/364/2009
Contract
no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at
Wan Chai West under FEP-09/364/200/B
Contract
no. HY/2010/08 – Central and WanChai Bypass – Slip road 8 Section under
FEP-10/364/2009/B
Contract no. HY/2011/08 –Central - Wan
Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009/B
Contract no.
HY/2009/18 – Central – Wanchai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
4.1.1.
Noise
monitoring for the Central Interchange works under contract no. HY/2009/18 was
commenced on 22
Table
4.1
Noise Monitoring Station for Contract no. HY/2009/18
Station |
Description |
*M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
M8 |
City Hall |
* Remark: M7e has become a reference station starting from 7 Aug 2012
4.1.2. No exceedance was recorded in this
reporting quarter.
4.1.3. Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 4.1.
Contract no. HK/2009/01 - Wanchai Development Phase
II - Central - Wanchai Bypass at Hong Kong Convention and Exhibition Centre -
Tunnel Works under FEP-02/364/2009 and Contract no. HK/2009/02 - Wanchai
Development Phase II - Central - Wanchai Bypass at Wanchai East (CWB Tunnel)
under FEP-01/364/2009
4.1.4.
The
commencement of construction works for Contract no. HK/2009/01 under
FEP-02/364/2009 is on 25 August 2011
and HK/2009/02 under FEP-01/364/2009 is on 26
Table
4.2
Noise
Monitoring Stations
for Contract nos. HK/2009/01 and HK/2009/02
Station |
Description |
M1a |
Harbour Road Sports Centre |
Reporting Month
of June 2016
4.1.1
Three limit level
exceedances were recorded at M1a- Harbour Road Sports Centre on 07, 13 and 21 June 2016 in this
reporting month.
4.1.2
Operation of hydromill trench cutter at Ex-
Wan Chai Swimming Pool (adjacent to Harbour Road Sports Centre directly
opposite to the monitoring station) under non WDII-CWB Contractor was observed
as the major noise contribution during monitoring on 07 and 13 June 2016 while breaking
opposite to the monitoring station under non WDII-CWB Contractor as major noise
contribution during monitoring on 21 June 2016.
As such, the exceedances were considered as non-Project related.
Reporting Month
of July 2016
4.1.5.
One limit level exceedances was recorded at M1a- Harbour Road Sports
Centre on 28 June 2016 in this reporting month.
4.1.6.
Operation of drill rig at opposite to the monitoring station under non
WDII-CWB Contractor was observed as the major noise contribution during
monitoring on 28 June 2016. As such, the exceedances were considered as
non-Project related.
Reporting Month
of August 2016
4.1.7.
No action or limit level exceedance was recorded in this reporting month.
4.1.8. Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 4.1.
Contract no. HY/2009/15 - Central-Wanchai Bypass –
Tunnel (
4.1.9.
The
commencement of construction works for Contract no. HY/2009/15 under
FEP-06/364/2009/A was on 13 July 2011. Noise
monitoring was commenced on 13 July 2011. The proposed
division of noise monitoring stations are summarized in Table 4.3 below.
Table
4.3
Noise Monitoring
Station for Contract nos. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
4.1.10.
No action or limit level exceedance was recorded in this reporting quarter.
4.1.11. Details of
noise monitoring results and graphical presentation can be referred in Appendix 4.1.
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/D
4.1.12. Noise monitoring for the tunnel works under
contract no. HY/2009/19 was commenced on 24
Table 4.4
Noise Monitoring
Stations for Contract no. HY/2009/19
Station |
Description |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
Reporting Month
of June 2016
4.1.13.
Three limit level exceedances were recorded at
M6- Hk Baptist Church Henrietta Secondary School on 07, 13 and 21 June 2016 in
this reporting month.
4.1.14.
Traffic noise was observed during monitoring on
07, 13 and 21 June 2016 and it was considered as the major noise contribution.
As such, the limit level exceedances were concluded as non-project related.
Reporting Month
of July 2016
4.1.15.
One limit level exceedance was recorded at M6-
HK Baptist Church Henrietta Secondary School on 12 July 2016 in this reporting
month.
4.1.16.
Traffic noise was observed during monitoring on
12 July 2016 and it was considered as the major noise contribution. As such,
the limit level exceedance was concluded as non-project related.
Reporting Month
of August 2016
4.1.17.
No action or limit level exceedance was
recorded in this reporting month.
4.1.18. Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 4.1 and the Notification of Exceedance can be
referred in Appendix 6.2.
Contract no. HY/2010/08 –
Central-Wanchai Bypass –Wanchai Bypass Tunnel (Slip Raod 8 Section) under FEP-09/364/2009/B
4.1.19. The commencement of construction works
for Contract no. HY/2010/08 under FEP-10/364/2009/B was on 02 September 2013.
Noise monitoring was commenced on 02 September 2013. The proposed divisions of
noise monitoring stations are summarized in Table 4.5 below.
Table 4.5
Noise Monitoring Stations
for Contract
no. HY/2010/08
Station |
Description |
M3a |
Tung Lo Wan Fire Station |
4.1.20.
No action or limit level exceedance was recorded in this reporting quarter.
4.1.21.
Noise monitoring results measured in this reporting period are reviewed
and summarized. Details of noise
monitoring results and graphical presentation can be referred in Appendix 4.1.
Contract no.
HY/2011/08 – Central - Wan Chai Bypass (CWB) – Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning
4.1.22. Noise monitoring for the Central
Interchange works under contract no. HY/2009/18 was commenced on 22 April
2011.The proposed division of noise monitoring stations for Contract no.
HY/2009/18 are summarized in Table 4.6 below:
Table 4.6 Noise
Monitoring Stations for
Contract no. HY/2011/08
Station |
Description |
M4b |
Victoria Centre |
*M7e |
International Finance Centre (Eastern End of
Podium) |
M7w |
International Finance Centre (Western End of
Podium) |
M8 |
City Hall |
*
Remark: M7e has become a reference station starting from 7 Aug 2012
4.1.23.
No action or limit level exceedance was recorded in this reporting quarter.
4.1.24.
Noise monitoring results measured in this reporting period are reviewed
and summarized. Details of noise
monitoring results and graphical presentation can be referred in Appendix 4.1.
Contract no.
HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under FEP-07/364/2009/D
4.2.1.
Real
time noise monitoring results measured in this reporting period are reviewed
and summarized. Details
of real time noise monitoring results and graphical presentation can be
referred to Appendix 4.2
4.2.2.
The
proposed division of noise monitoring stations are summarized in Table 4.7
below. Real time noise monitoring for major construction works under contract
no. HY/2009/19 was commenced on 24
Table 4.7 Real Time Noise
Monitoring Stations
for Contract no. HY/2009/19
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD Hong Kong Transport Section Whitefield Depot |
RTN2a |
North Point |
Electric Centre
(Replacement of RTN2) |
RTN3 |
North Point |
Pok Leung Kuk Yu |
RTN4 |
Tin Hau |
|
* Real time noise monitoring results and graphical presentation during
night time period are for information only.
*Real-time noise monitoring results and graphical presentation for RTN3
during restricted hours are for information only as no night classes were
conducted at the educational institute.
Reporting month of June
2016
4.2.3.
No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport Section
Whitfield Depot in the reporting month.
4.2.4.
Limit level exceedances were recorded at RTN2a-Electric Centre on 07, 08, 10,
11, 14, 15, 16, 18, 20, 21 and 22 June 2016 during daytime in the reporting
month. After checking, pre bore and sheet piling works were carried out on 07,
08, 10, 11, 14, 15, 16, 18, 20, 21 and 22 June 2016 and mitigation measures
including erection of noise barrier was implemented by the Contractor of
HY/2009/19 while it was observed that building demolition at non-CWB Project
development site opposite to the monitoring station was conducted across the
monitoring month and was considered as the major noise contribution. As such,
the exceedances were considered as non-Project related.
4.2.5.
No limit level exceedances were recorded at
RTN3-Yue Lee Mo Fan Memorial School in the reporting month.
4.2.6.
No limit level exceedances were recorded at
RTN4-Causeway Bay Community Centre in the reporting month.
Reporting month of July
2016
4.2.7.
No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport Section
Whitfield Depot in the reporting month.
4.2.8.
Limit level exceedances were recorded at RTN2a-Electric Centre on 11 July
2016 during daytime in the reporting month. After checking, pre bore piling and
sheet piling works were carried out on 11 July 2016 during the monitoring
period and mitigation measures including erection of noise barrier was
implemented by the Contractor of HY/2009/19 while adverse weather with frequent
thunderstorm was recorded at the monitoring period across monitoring station at
Eastern District and is considered as the major noise contribution. As such,
the exceedance was considered as non-Project related.
4.2.9.
Limit level exceedance was recorded at
RTN3-Yue Lee Mo Fan Memorial School on 11 July 2016 during daytime in the
reporting month. After checking, no construction works was conducted by
Contract HY/2009/19 on 11 July 2016 during the monitoring period while adverse
weather with frequent thunderstorm was recorded at the monitoring period across
monitoring stations at Eastern District and is considered as the major noise
contribution. As such, the exceedance was considered as non-Project related.
4.2.10.
Limit level exceedances were recorded at
RTN4-Causeway Bay Community Centre on 11, 16, 18 and 20 July 2016 during
daytime in the reporting month. After checking, no construction works was
conducted by Contract HY/2009/19 on 11 July 2016 during monitoring period while
adverse weather with frequent thunderstorm was recorded at the monitoring
period across monitoring station at Eastern District and is considered as the
major noise contribution. As such, the exceedances were considered as
non-Project related.
No construction
works was conducted by Contract of HY/2009/19 on 16 July 2016 and only erection
of scaffolding with no major noise emanation was conducted under Contract
HY/2009/19 on 18 July 2016. As such, the exceedances were considered to be
contributed by nearby traffic and not related to Project works.
On 20 July 2016,
breaking works for concrete base slab for tie beam construction was observed at
Pier 22- 23 directly opposite to the monitoring station was conducted during
the monitoring period and direct noise impact was observed despite the erection
of noise barrier. As such, the exceedances were considered to be related to the
Project works. The concerned construction was completed on the same date and no
further exceedance related to the breaking works was observed. In view of the
project related exceedances and the completion of the concerned breaking works,
the Contractor will improve the mitigation against noise by orientation of
noise barrier to better obstruct the line of sight between the breaking works
and the NSR shall there be any breaking works to be carried out at the
concerned location.
Reporting month
of August 2016
4.2.11.
Limit level exceedance
was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot was
recorded on 09 August 2016 during daytime in the reporting month. After
checking with Contractor of HY/2009/19, no construction activities was
conducted during the recorded period while adverse weather with frequent
thunderstorm was observed and recorded across other monitoring stations at Tin
Hau and North Point District and is considered as the major noise contribution.
As such, the exceedance was considered not related to Project.
4.2.12.
Limit level exceedances
were recorded at RTN2a-Electric Centre on 09 and 10 August 2016 during daytime in
the reporting month. After checking with Contractor of HY/2009/19, no
construction activity was conducted on 09 August 2016 during the recorded
period and unloading of soil at temporary jetty was conducted on 10 August 2016
during the recorded period. Adverse weather with frequent thunderstorm were
recorded at the monitoring period on 09 and 10 August 2016 across monitoring
stations at North Point District and is considered as the major noise
contribution. As such, the exceedance was considered as non-Project related.
4.2.13.
Limit level exceedance was recorded at
RTN3-Yue Lee Mo Fan Memorial School on 09, 10 and 17 August 2016 during daytime
in the reporting month. After checking, no construction works was conducted by
Contract HY/2009/19 on 09, 10 and 17 August 2016 around the concerned location
during the monitoring period while adverse weather with frequent thunderstorm
was recorded at the monitoring period on 09 and 10 August 2016 across
monitoring stations at Eastern District and is considered as the major noise
contribution. As such, the exceedance was considered as non-Project related. On 17 August 2016, erection of U-beam with
launching girder and crane was conducted by HY/2009/19 on 17 August 2016 and no
major noise is considered. As such, the exceedance was considered as
non-Project related.
4.2.14.
Limit level exceedances were recorded at
RTN4-Causeway Bay Community Centre on 04, 09, 11, 12, 13 and 17 August 2016
during daytime in the reporting month. After checking with the Contractor of
HY/2009/19, excavation works and rebar fixing were conducted by Contract
HY/2009/19 on 04 August 2016 around the monitoring location during the recorded
period and no major noise is considered. In addition, construction activities
and intermittent operation of PMEs including excavator, hydraulic breaker and
sheet piling rig were observed at non-CWB Project adjacent to monitoring
station was observed in August 2016. As such, the exceedances were considered
as non-Project related.
On 09 August
2016, excavation and concreting works was conducted under Contract HY/2009/19
around the monitoring location during the recorded periods and no major noise
is considered for the works. In addition, construction activities and
intermittent operation of PMEs including excavator, hydraulic breaker and sheet
piling machine were observed at non-CWB Project adjacent to monitoring station
over August 2016. As such, the exceedances were considered as non-Project
related.
On 11 August
2016 and 12 August 2016 morning, hand held drilling works at IEC bridge deck
(Pier 24) were conducted under HY/2009/19 and hand held breaking works beneath
IEC Bridge deck was conducted during the recorded period. No noise mitigation
measure was provided for the drilling works at IEC bridge deck on 12 August
2016 morning and was observed as the direct noise contribution. Hence, the
exceedances on 11 and 12 August 2016 were considered as related to the Project
works.
On 12 August
2016 afternoon, breaking works beneath the IEC bridge deck and concurrent
excavator mounted breaking works at Pier 23 were observed. Despite the
provision of temporary noise barrier for the ground breaking works by excavator
mounted hydraulic breaker and the hand held breaking works was observed
conducted behind physical barrier, exceedances were recorded and direct noise
contribution was observed in relation to the concurrent operation of hand held
breaker and excavator mounted hydraulic breakers opposite to the monitoring
station and considered as related to the Project works.
The ET informed
the findings to Contractor of HY/2009/19 and advised the Contractor of
HY/2009/19 to review the construction sequence to propose and implement
appropriate remedial actions. Rectification measure including provision of
acoustic noise screen for bridge deck drilling works was provided by the
Contractor of HY/2009/19 on 12 August 2016 and the Contractor of HY/2009/19
reviewed the construction sequence and committed to isolate concurrent bridge
deck drilling or hand held breaking for construction joint underneath IEC
bridge deck or excavator mounted breaking works to avoid cumulative impact due
to concurrent operations. Further checking by the ET was conducted on 14 August
2016, drilling works with acoustic noise screen was observed on IEC bridge deck
while no concurrent breaking works and drilling works was further observed on
14 August 2016 and no further project related exceedance was recorded.
On 13 August
2016, only excavation works was conducted by Contract HY/2009/19 around the
monitoring location during the recorded period and no major noise is
considered. In addition, construction activities and intermittent operation of
PMEs including excavator, hydraulic breaker and sheet piling rig were observed
at non-CWB Project adjacent to monitoring station was observed in August 2016.
As such, the exceedances were considered as non-Project related.
On 17 August
2016, drilling works for tie beam beneath IEC was conducted by Contract
HY/2009/19 immediately behind physical barrier erected around the works
location. In addition, construction activities and intermittent operation of
PMEs including excavator, hydraulic breaker and sheet piling rig were observed
at non-CWB Project adjacent to monitoring station was observed in August 2016.
As such, the exceedances were considered as non-Project related.
4.2.15.
Real
time noise monitoring results measured in this reporting quarter are reviewed
and summarized. Details of real time noise monitoring results and graphical
presentation can be referred to Appendix
4.2
Contract no.
HY/2011/08 – Central - Wan Chai Bypass (CWB) – Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning
4.2.16.
The proposed division of noise monitoring
stations are summarized in Table 4.8 below. Real time noise
monitoring for major construction works under contract no. HY/2011/08 was
commenced on 19 March 2015.
Table 4.8 Real
Time Noise
Monitoring Stations for Contract
no. HY/2011/08
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD
Hong Kong Transport Section Whitfield Depot |
RTN2a1 |
North Point |
Hong
Kong Electric Centre |
RTN4 |
Tin
Hau |
Causeway Bay Community Centre |
* Real time noise monitoring results and graphical presentation during
restrict hours and night time period are for information only and noise during
CNP period shall be controlled under NCO.
Remarks 1: With
respect to the possession of site area Portion Xa and Portion Xb since 7 March
2016 as confirmed by CWB RSS, real time
noise monitoring station RTN2a was associated with Contract no. HY/2011/08 from
07 March 2016 onwards
Reporting month of June 2016
4.2.17.
No limit level exceedance
was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the
reporting month.
4.2.18.
Limit level exceedances
were recorded at RTN2a-Electric Centre on 07, 08, 10, 11, 14, 15, 16, 18, 20,
21 and 22 June 2016 during daytime in the reporting month. After checking, bars
threading with couplers under HY/2011/08 were carried out on 07, 08 June 2016
and steel bar fixing were conducted under Contract HY/2011/08 on 10, 15, 16, 18
and 22 June 2016 and no construction works was undertaken by Contract
HY/2011/08 on 11,14, 20 and 21 June 2016. In addition, it was observed that
building demolition at non-CWB Project development site opposite to the
monitoring station was conducted across the monitoring month and was considered
as the major noise contribution. As such, the exceedances were considered as
non-Project related.
Reporting month of July 2016
4.2.19.
No limit level exceedance
was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the
reporting month.
4.2.20.
Limit level exceedances
were recorded at RTN2a-Electric Centre on 11 July 2016 during daytime in the
reporting month. After checking, no construction works was carried out under
Contract HY/2011/08 on 11 July 2016 during the monitoring period while adverse
weather with frequent thunderstorm was recorded at the monitoring period across
monitoring station at Eastern District and is considered as the major noise
contribution. As such, the exceedance was considered as non-Project related.
Reporting month of August 2016
4.2.21.
Limit level exceedance
was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot was
recorded on 09 August 2016 during daytime in the reporting month. After
checking with Contractor of HY/2011/08, no construction activities was
conducted during the recorded period while adverse weather with frequent
thunderstorm was observed and recorded across other monitoring stations at Tin
Hau and North Point District and is considered as the major noise contribution.
As such, the exceedance was considered not related to Project.
4.2.22.
Limit level exceedances
were recorded at RTN2a-Electric Centre on 09 and 10 August 2016 during daytime in
the reporting month. After checking with Contractor of HY/2011/08, no
construction activity was conducted on 09 August 2016 and 10 August 2016 during
the recorded period. Adverse weather with frequent thunderstorm were recorded
at the monitoring period on 09 and 10 August 2016 across monitoring stations at
North Point District and is considered as the major noise contribution. As such,
the exceedance was considered as non-Project related.
4.2.23.
Limit level exceedances were recorded at
RTN4-Causeway Bay Community Centre on 04, 09, 11, 12, 13 and 17 August 2016
during daytime in the reporting month. After checking with the Contractor of
HY/2011/08, no construction activities was conducted around the monitoring
location during the recorded period on 04, 09, 11, 12, 13 and 17 August 2016.
In addition, construction activities and intermittent operation of PMEs
including excavator, hydraulic breaker and sheet piling rig were observed at
non-CWB Project adjacent to monitoring station was observed in August 2016. As
such, the exceedances were considered as non-Project related.
4.2.24.
Real
time noise monitoring results measured in this reporting quarter are reviewed
and summarized. Details of real time noise monitoring results and graphical
presentation can be referred to Appendix
4.2
4.3.1 Due to extension of site boundary by
contractor of HY/2009/19, location of air quality monitoring station CMA1b –
Oil Street Community Liaison Centre has been finely adjusted on 21
Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central Interchange under FEP-05/364/2009/A
4.3.2
Air quality monitoring for the Central
Interchange works under contract no. HY/2009/18 was commenced on 21 April 2011.
The proposed division of air quality monitoring stations are summarized in Table
4.9 below.
Table 4.9
Air quality monitoring
Stations for Contract no. HY/2009/18
Station |
Description |
MA1e |
International Finance Centre (Eastern End of Podium) |
MA1w |
International Finance Centre (Western End of Podium) |
4.3.3
No action or limit level exceedance was
recorded in the reporting period.
4.3.4
Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 4.3.
Contract no. HK/2009/01 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at
4.3.5
The
commencement of construction works for Contract no. HK/2009/01 under
FEP-02/364/2009 is on 25 August 2011. The
proposed division of air quality monitoring stations are summarized in Table
4.10 below.
Table 4.10
Air quality monitoring
Station for Contract no. HK/2009/01
Station |
Description |
CMA5b |
Pedestrian Plaza |
4.3.6
No action or limit level exceedance was
recorded in the reporting period.
4.3.7 Air quality monitoring results measured in this
reporting period are reviewed and summarized.
Details of air quality monitoring results and graphical presentation can
be referred in Appendix 4.3.
Contract no. HK/2009/02 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
4.3.8 The commencement of construction works for
HK/2009/02 under FEP-01/364/2009 is on 26
Table
4.11
Air quality monitoring
Station for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
4.3.9
No action or limit level exceedance was
recorded in the reporting period.
4.3.10 Air quality monitoring results measured in this
reporting period are reviewed and summarized.
Details of air quality monitoring results and graphical presentation can
be referred in Appendix
4.3.
Contract no.
HY/2009/15 - Central-Wanchai Bypass – Tunnel (
4.3.11
The
commencement of construction works for Contract no. HY/2009/15 under FEP-06/364/2009/A
was on 13 July 2011. The proposed division of air quality monitoring
stations are summarized in Table 4.12
below.
Table 4.12 Air quality monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB site office at Wanchai Waterfront
Promenade |
4.3.12
No action or limit level exceedance was
recorded in the reporting period.
4.3.13 Air quality monitoring results measured
in this reporting period are reviewed and summarized. Details of air quality monitoring results and
graphical presentation can be referred in Appendix 4.3.
Contract no.
HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under FEP-07/364/2009/D
4.3.14 Air quality monitoring for the tunnel works was
commenced on 26
Table
4.13
Air quality monitoring
Stations
for Contract no. HY/2009/19
Station |
Description |
CMA1b |
Oil Street Site Office |
CMA2a |
|
Reporting month
of June 2016
4.3.15
No action or limit level exceedance was
recorded in the reporting period.
Reporting month
of July 2016
4.3.16
No action or limit level exceedance was
recorded in the reporting period.
Reporting month
of August 2016
4.3.17
One 1hr TSP action limit level exceedance was
recorded on 27 August 2016 in the reporting month.
4.3.18
No construction activities was undertaken by
Contractor of HY/2009/19 around the Oil Street Site Office during the
monitoring period and no particular observation regarding air quality impact
was observed during sampling. Mitigation measures including watering for haul
road was generally implemented by the Contractor. In view of the above, the
action level exceedance was considered to be non-project related.
4.3.19
Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of air quality monitoring results and graphical presentation can
be referred in Appendix 4.3.
Contract
no. HK/2012/08- Wan Chai Development Phase II – Central-Wan Chai Bypass at Wan
Chai West
4.3.20
The commencement of construction works for
Contract no. HK/2012/08 under FEP-09/364/2009/C was on May 2014. Air quality
monitoring was commenced on 14 July 2011. The proposed division of air quality
monitoring stations are summarized in Table 4.14 below.
Table 4.14
Air quality monitoring
Station for Contract
no. HK/2012/08
Station |
Description |
CMA5b |
Pedestrian
Plaza |
4.3.21
No action or limit level exceedance was
recorded in the reporting period.
4.3.22
Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of air quality monitoring results and
graphical presentation can be referred in Appendix
4.3.
Contract no. HY/2010/08 – Central-Wanchai Bypass –Wanchai Bypass Tunnel
(Slip Road 8 Section) under FEP-09/364/2009/B
4.3.23
The commencement of construction works for
Contract no. HY/2010/08 under FEP-09/364/2009/B was on July 2014. Air quality
monitoring was commenced on 14 July 2011. The proposed division of air quality
monitoring stations are summarized in Table 4.15 below.
Table 4.15
Air quality monitoring
Station for Contract
no. HY/2010/08
Station |
Description |
CMA3a |
CWB
PRE Site Office |
4.3.24
No action or limit level exceedance was
recorded in the reporting period.
4.3.25
Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of air quality monitoring results and
graphical presentation can be referred in Appendix
4.3.
Contract no. HY/2011/08 – Central - Wan Chai
Bypass (CWB) – Tunnel Buildings, Systems and Fittings, and Works Associated with
Tunnel Commissioning
4.3.26
Air quality monitoring for the Central
Interchange works under contract no. HY/2011/08 was commenced on 21 April 2011.
The proposed division of air quality monitoring stations are summarized in Table
4.16 below.
Table 4.16 Air quality monitoring
Stations for Contract
no. HY/2011/08
Station |
Description |
MA1e |
International
Finance Centre (Eastern End of Podium) |
MA1w |
International
Finance Centre (Western End of Podium) |
CMA1b |
Oil
Street Site Office |
CMA2a |
Causeway
Bay Community Centre |
Reporting month of June 2016
4.3.27
No action or limit level exceedance was
recorded in the reporting period.
Reporting month of July 2016
4.3.28
No action or limit level exceedance was
recorded in the reporting period.
Reporting month of August 2016
4.3.29
One 1hr TSP action limit level exceedance was
recorded on 27 August 2016 in the reporting month.
4.3.30
Only rebar fixing and formboard erection was
undertaken under Contract HK/2011/08 around the Oil Street Site Office during
the monitoring period and no particular observation regarding air quality
impact was observed during sample. In view of the above, the action level
exceedance was considered to be non-project related and contributed by local
ambient condition.
4.3.31
Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of air quality monitoring results and
graphical presentation can be referred in Appendix
4.3.
Contract no. HK/2009/01 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at
4.4.1.
Inert
and non-inert C&D waste was disposed of in this reporting period. Details
of the waste flow table are summarized in Table 4.17.
Table
4.17 Details of Waste Disposal for Contract no. HK/2009/01
Inert C&D materials
disposed |
57.86 |
107849.59 |
TKO137, TM38 |
Inert C&D materials
recycled |
Nil |
98512.03 |
N/A |
Non-inert C&D
materials disposed |
313.56 |
4903.76 |
SENT Landfill |
Non-inert C&D
materials recycled |
75875 |
1284946 |
N/A |
Chemical waste disposed |
Nil |
10400 |
Kwun Kee (Chemical Waste Collector) |
Marine Sediment (Type 1- Open Seas
Disposal), m3 |
Nil |
11527 |
South of Cheung Chau |
Marine Sediment (Type 1 – Open Sea Disposal
(Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3 |
Nil |
16261 |
East
of Cha Chau South
Brothers |
Contract no. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
4.4.2.
Inert and non-inert C&D waste were disposed of in this reporting
period. Details of the waste flow table are summarized in Table 4.18.
Table 4.18 Details of Waste Disposal for Contract no.
HK/2009/02
Inert C&D materials
disposed |
18433 |
501570.412 |
TKO137, TM 38 |
Inert C&D materials
recycled |
Nil |
46520 |
WCR2 |
Non-inert C&D
materials disposed |
821 |
3613.317 |
SENT Landfill |
Non-inert C&D
materials recycled |
Nil |
N/A |
N/A |
Chemical waste disposed |
Nil |
17718 |
N/A |
Marine Sediment (Type 1
– Open Sea Disposal) , m3 |
3197 |
31086 |
South Cheung Chau |
Contract no. HY/2009/18 - Central - Wan Chai Bypass
(CWB) – Central Interchange under FEP-05/364/2009/A
4.4.3.
Inert and non-inert C&D waste was disposed of in this reporting
period. Details of the waste flow table are summarized in Table 4.19.
Table 4.19 Details of Waste Disposal for
Contract no. HY/2009/18
Inert C&D materials
disposed |
450 |
140683.94 |
T.K.O. 137 |
Inert C&D materials
recycled |
Nil |
58787.05 |
N/A |
Non-inert C&D
materials disposed |
84.17 |
4174.86 |
SENT Landfill |
Non-inert C&D materials recycled (tonnes) |
Nil |
878.37 |
N/A |
Chemical waste disposed |
2332 |
6772 |
N/A |
Contract no. HY/2009/15 - Central-Wanchai Bypass –
Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
4.4.4.
Inert and non-inert C&D waste was disposed of in this reporting
period. Details of the waste flow table are summarized in Table 4.20.
Table 4.20 Details of Waste Disposal for
Contract no. HY/2009/15
Inert C&D materials
disposed |
1947.4 Nil |
621670.77 245453.3 |
Tuen Mun Area 38 TKO137 FB |
Inert C&D materials
recycled |
Nil |
358660.77 |
HY/2009/11, ex-PCWA TS4 |
Non-inert C&D
materials disposed |
155.23 |
4465.04 |
SENT Landfill |
Non-inert C&D
materials recycled |
Nil |
5496446.2 |
Xun Xiang Metal ware Skylight Recycle (paper) |
Chemical waste disposed |
Nil |
22755 |
Dunwell Group |
Marine Sediment
(Type1-Open Sea Disposal (Dedicate Sites) &Type 2 – Confined Marine
Disposal), m3 |
Nil |
5684 |
South of the Brothers |
Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009/D
4.4.5.
Inert C&D materials was recycled non-inert C&D waste was disposed of in this reporting period. Details
of the waste flow table are summarized in Table 4.21.
Table 4.21 Details of Waste Disposal for
Contract no. HY/2009/19
Inert C&D materials
disposed |
8348.42 |
657494.74 |
N/A |
Nil |
82349.7 |
N/A |
|
Non-inert C&D
materials disposed |
232.39 |
5048.28 |
SENT Landfill |
Non-inert C&D
materials recycled |
12.16 |
560.56 |
N/A |
Chemical waste disposed |
Nil |
9.92 |
N/A |
Marine Sediment (Tunnel) (Type 1- Open Sea
Disposal), m3 |
Nil |
20556 |
South of Cheung Chau |
Marine Sediment (Tunnel) (Type 1- Open Sea
Disposal (Dedicated Sites) & Type 2 – Confined Marine Disposal), m3 |
Nil |
30751 |
East
of Sha Chau |
Contract no.
HK/2012/08 Wan Chai Development Phase II - Central-Wan Chai Bypass at Wan Chai
West under FEP-09/364/2009/B
4.4.6.
No inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 4.22.
Table
4.22 Details of Waste Disposal for Contract no. HK/2012/08
Waste
Type* |
Quantity
this quarter, m3 |
Cumulative-to-Date,
m3 |
Disposal
/ Dumping Grounds |
Inert C&D materials disposed |
11000 |
172438 |
N/A |
Inert C&D materials recycled |
14848 |
84466 |
N/A |
Non-inert C&D materials disposed |
775 |
2277 |
N/A |
Non-inert C&D materials recycled |
NIL |
Nil |
N/A |
Chemical waste disposed |
NIL |
Nil |
N/A |
Marine Sediment (Type 1) Disposal, m3 |
Nil |
3145 |
South of Cheung Chau/ South of Brothers |
Contract no. HY/2010/08
Central – Wan Chai Bypass (CWB) –
Tunnel (Slip Road 8) under FEP-10/364/2009/B
4.4.7.
No inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 4.23.
Table 4.23 Details of Waste Disposal for Contract no. HY/2010/08
Waste Type* |
Quantity this quarter, m3 |
Cumulative-to-Date, m3 |
Disposal / Dumping Grounds |
Inert C&D materials disposed |
26473.5 57782 11530.1 33168.1 |
567597.7 262656.6 82911.8 71198.7 |
TM 38 WENT SENT TKO area 137 |
Inert C&D
materials recycled |
Nil |
Nil |
Nil |
Non-inert C&D
materials disposed |
395.4 |
2301.06 |
SENT |
Non-inert C&D
materials recycled |
Nil |
Nil |
Nil |
Chemical waste
disposed |
Nil |
979 |
Nil |
Type 1 – Open Sea
Disposal |
5468 |
16368.4 |
East Sha Chau/ South Brothers Island |
Type 2 – Confined
Marine disposal |
Nil |
549.2 |
East Sha Chau |
Contract no. HY/2011/08
Central –Central - Wan Chai Bypass
(CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning under FEP-11/364/2009B
4.4.8.
No inert and Non-inert C&D wastes were
disposed of in this reporting month. Details of the waste flow table are
summarized in Table 4.24.
Table
4.24 Details
of Waste Disposal for Contract no. HY/2011/08
Waste Type* |
Quantity this quarter, m3 |
Cumulative-to-Date, m3 |
Disposal / Dumping Grounds |
Inert
C&D materials disposed |
Nil |
367.68 |
Nil |
Inert
C&D materials recycled |
Nil |
Nil |
Nil |
Non-inert
C&D materials disposed |
118 |
847.57 |
Nil |
Non-inert
C&D materials recycled |
Nil |
31.72 |
Nil |
Chemical
waste disposed(kg) |
Nil |
3800 |
Nil |
5.0.1. The Event Action Plan for construction noise and air
quality are presented in Appendix 5.1.
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central
Interchange under FEP-05/364/2009/A
5.1.1.
No action of limit level exceedance was
recorded in this reporting quarter.
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at
Reporting
month of June 2016
5.1.2.
Three limit level exceedances were recorded
at M1a- Harbour Road Sports Centre on 07, 13 and 21 June 2016 in this reporting
month.
5.1.3.
Operation of hydromill trench cutter at Ex-
Wan Chai Swimming Pool (adjacent to Harbour Road Sports Centre directly
opposite to the monitoring station) under non WDII-CWB Contractor was observed
as the major noise contribution during monitoring on 07 and 13 June 2016 while
breaking opposite to the monitoring station under non WDII-CWB Contractor as
major noise contribution during monitoring on 21 June 2016. As such, the exceedances were considered as
non-Project related.
Reporting month of July 2016
5.1.4. One limit
level exceedances was recorded at M1a- Harbour Road Sports Centre on 28 June
2016 in this reporting month.
5.1.5. Operation
of drill rig at opposite to the monitoring station under non WDII-CWB
Contractor was observed as the major noise contribution during monitoring on 28
July 2016. As such, the exceedances were considered as non-Project related.
Reporting month of August 2016
5.1.6. No action
or limit level exceedance was recorded in the reporting month.
Contract no. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel)
Reporting
month of June 2016
5.1.7.
Three limit level exceedances were recorded
at M1a- Harbour Road Sports Centre on 07, 13 and 21 June 2016 in this reporting
month.
5.1.8.
Operation of hydromill trench cutter at Ex-
Wan Chai Swimming Pool (adjacent to Harbour Road Sports Centre directly
opposite to the monitoring station) under non WDII-CWB Contractor was observed
as the major noise contribution during monitoring on 07 and 13 June 2016 while
breaking opposite to the monitoring station under non WDII-CWB Contractor as
major noise contribution during monitoring on 21 June 2016. As such, the exceedances were considered as
non-Project related.
Reporting month
of July 2016
5.1.9.
One limit level exceedances was recorded at
M1a- Harbour Road Sports Centre on 28 June 2016 in this reporting month.
5.1.10.
Operation of drill rig at opposite to the
monitoring station under non WDII-CWB Contractor was observed as the major
noise contribution during monitoring on 28 June 2016. As such, the exceedances
were considered as non-Project related.
Reporting
month of August 2016
5.1.11.
No action or limit level exceedance was
recorded in the reporting month.
Contract no. HY/2009/15 - Central-Wanchai Bypass –
Tunnel (
5.1.12.
No action or limit level exceedance was
recorded in this reporting quarter.
Contract
no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/A
Reporting month
of June 2016
5.1.13. No action
or limit level exceedance was recorded in the reporting month.
Reporting month
of July 2016
5.1.14.
One limit level exceedance was recorded at
M6- HK Baptist Church Henrietta Secondary School on 12 July 2016 in this
reporting month.
5.1.15.
Traffic noise was observed during monitoring
on 12 July 2016 and it was considered as the major noise contribution. As such,
the limit level exceedance was concluded as non-project related.
Reporting month of August 2016
5.1.16. No action
of limit level exceedance was recorded in the reporting month.
Contract
no. HY/2010/08 – Central-Wanchai Bypass – Tunnel (Slip Road 8 Section) under
FEP-10/364/2009/B
5.1.17.
No action of limit level exceedance was recorded in the reporting
quarter
Contract
no. HY/2011/08 Central –Central - Wan Chai Bypass (CWB) –Tunnel Buildings,
Systems and Fittings, and Works Associated with Tunnel Commissioning under
FEP-11/364/2009B
5.1.18.
No action of limit level exceedance was recorded in the reporting
quarter.
5.2.1.
No action
or limit level exceedance was recorded in the reporting quarter.
Contract no.
HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
5.2.2.
No action
or limit level exceedance was recorded in the reporting quarter.
Contract nos.
HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan
Chai East (CWB Tunnel)
5.2.3.
No action
or limit level exceedance was recorded in the reporting quarter.
Contract no. HY/2009/15 - Central-Wanchai Bypass – Tunnel (
5.2.4.
No action
or limit level exceedance was recorded in the reporting quarter.
Contract no.
HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under FEP-07/364/2009/A
5.2.5.
No action or limit level exceedance was recorded in the reporting month.
Reporting month of July 2016
5.2.6.
No action or limit level exceedance was recorded in the reporting month.
Reporting month of August 2016
5.2.7.
One 1hr TSP action limit level exceedance was recorded on 27 August 2016
in the reporting month.
5.2.8.
No construction activities was undertaken by Contractor of HY/2009/19
around the Oil Street Site Office during the monitoring period and no
particular observation regarding air quality impact was observed during
sampling. Mitigation measures including watering for haul road was generally
implemented by the Contractor. In view of the above, the action level
exceedance was considered to be non-project related.
Contract no. HK/2012/08 Wan Chai Development Phase
II - Central-Wan Chai Bypass at Wan Chai West under FEP-09/364/2009/B
5.2.9.
No
exceedance was recorded in the reporting quarter.
Contract no. HY/2010/08 – Central-Wanchai Bypass –
Tunnel (Slip Raod 8 Section) under FEP-10/364/2009/B
5.2.10.
No exceedance was recorded in the reporting quarter
Contract no. HY/2011/08 Central –Central - Wan Chai Bypass
(CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning under FEP-11/364/2009B
5.2.11.
No action
or limit level exceedance was recorded in the reporting month.
Reporting month of July 2016
5.2.12.
No action
or limit level exceedance was recorded in the reporting month.
Reporting month of August 2016
5.2.13.
One 1hr TSP action limit level exceedance was recorded on 27 August 2016
in the reporting month.
5.2.14.
Only rebar fixing and formboard erection was
undertaken under Contract HK/2011/08 around the Oil Street Site Office during
the monitoring period and no particular observation regarding air quality
impact was observed during sample. In view of the above, the action level
exceedance was considered to be non-project related and contributed by local
ambient condition.
Contract no.
HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under FEP-07/364/2009/D
Reporting month of
June 2016
5.3.1.
No limit level exceedance was recorded at RTN1-FEHD
Hong Kong Transport Section Whitfield Depot in the reporting month.
5.3.2.
Limit level exceedances
were recorded at RTN2a-Electric Centre on 07, 08, 10, 11, 14, 15, 16, 18, 20,
21 and 22 June 2016 during daytime in the reporting month. After checking, pre
bore and sheet piling works were carried out on 07, 08, 10, 11, 14, 15, 16, 18,
20, 21 and 22 June 2016 and mitigation measures including erection of noise
barrier was implemented by the Contractor of HY/2009/19 while it was observed
that building demolition at non-CWB Project development site opposite to the
monitoring station was conducted across the monitoring month and was considered
as the major noise contribution. As such, the exceedances were considered as
non-Project related.
5.3.3.
No limit level exceedances were recorded at
RTN3-Yue Lee Mo Fan Memorial School in the reporting month.
5.3.4.
No limit level exceedances were recorded at
RTN4-Causeway Bay Community Centre in the reporting month.
Reporting month of July
2016
5.3.5.
No limit level exceedance was recorded at RTN1-FEHD
Hong Kong Transport Section Whitfield Depot in the reporting month.
5.3.6.
Limit level exceedances
were recorded at RTN2a-Electric Centre on 11 July 2016 during daytime in the
reporting month. After checking, pre bore piling and sheet piling works were
carried out on 11 July 2016 during the monitoring period and mitigation
measures including erection of noise barrier was implemented by the Contractor of
HY/2009/19 while adverse weather with frequent thunderstorm was recorded at the
monitoring period across monitoring station at Eastern District and is
considered as the major noise contribution. As such, the exceedance was
considered as non-Project related.
5.3.7.
Limit level exceedance was recorded at
RTN3-Yue Lee Mo Fan Memorial School on 11 July 2016 during daytime in the
reporting month. After checking, no construction works was conducted by
Contract HY/2009/19 on 11 July 2016 during the monitoring period while adverse
weather with frequent thunderstorm was recorded at the monitoring period across
monitoring stations at Eastern District and is considered as the major noise
contribution. As such, the exceedance was considered as non-Project related.
5.3.8.
Limit level exceedances were recorded at
RTN4-Causeway Bay Community Centre on 11, 16, 18 and 20 July 2016 during
daytime in the reporting month. After checking, no construction works was
conducted by Contract HY/2009/19 on 11 July 2016 during monitoring period while
adverse weather with frequent thunderstorm was recorded at the monitoring
period across monitoring station at Eastern District and is considered as the
major noise contribution. As such, the exceedances were considered as
non-Project related.
No construction
works was conducted by Contract of HY/2009/19 on 16 July 2016 and only erection
of scaffolding with no major noise emanation was conducted under Contract
HY/2009/19 on 18 July 2016. As such, the exceedances were considered to be
contributed by nearby traffic and not related to Project works.
On 20 July 2016,
breaking works for concrete base slab for tie beam construction was observed at
Pier 22- 23 directly opposite to the monitoring station was conducted during
the monitoring period and direct noise impact was observed despite the erection
of noise barrier. As such, the exceedances were considered to be related to the
Project works. The concerned construction was completed on the same date and no
further exceedance related to the breaking works was observed. In view of the
project related exceedances and the completion of the concerned breaking works,
the Contractor will improve the mitigation against noise by orientation of
noise barrier to better obstruct the line of sight between the breaking works and
the NSR shall there be any breaking works to be carried out at the concerned
location.
Reporting month
of August 2016
5.3.9.
Limit level exceedance was recorded at RTN1-FEHD
Hong Kong Transport Section Whitfield Depot was recorded on 09 August 2016 during
daytime in the reporting month. After checking with Contractor of HY/2009/19,
no construction activities was conducted during the recorded period while
adverse weather with frequent thunderstorm was observed and recorded across
other monitoring stations at Tin Hau and North Point District and is considered
as the major noise contribution. As such, the exceedance was considered not
related to Project.
5.3.10.
Limit level exceedances
were recorded at RTN2a-Electric Centre on 09 and 10 August 2016 during daytime in
the reporting month. After checking with Contractor of HY/2009/19, no
construction activity was conducted on 09 August 2016 during the recorded
period and unloading of soil at temporary jetty was conducted on 10 August 2016
during the recorded period. Adverse weather with frequent thunderstorm were
recorded at the monitoring period on 09 and 10 August 2016 across monitoring
stations at North Point District and is considered as the major noise
contribution. As such, the exceedance was considered as non-Project related.
5.3.11.
Limit level exceedance was recorded at
RTN3-Yue Lee Mo Fan Memorial School on 09, 10 and 17 August 2016 during daytime
in the reporting month. After checking, no construction works was conducted by
Contract HY/2009/19 on 09, 10 and 17 August 2016 around the concerned location
during the monitoring period while adverse weather with frequent thunderstorm
was recorded at the monitoring period on 09 and 10 August 2016 across
monitoring stations at Eastern District and is considered as the major noise contribution.
As such, the exceedance was considered as non-Project related. On 17 August 2016, erection of U-beam with
launching girder and crane was conducted by HY/2009/19 on 17 August 2016 and no
major noise is considered. As such, the exceedance was considered as
non-Project related.
5.3.12.
Limit level exceedances were recorded at
RTN4-Causeway Bay Community Centre on 04, 09, 11, 12, 13 and 17 August 2016
during daytime in the reporting month. After checking with the Contractor of
HY/2009/19, excavation works and rebar fixing were conducted by Contract
HY/2009/19 on 04 August 2016 around the monitoring location during the recorded
period and no major noise is considered. In addition, construction activities
and intermittent operation of PMEs including excavator, hydraulic breaker and
sheet piling rig were observed at non-CWB Project adjacent to monitoring
station was observed in August 2016. As such, the exceedances were considered
as non-Project related.
On 09 August
2016, excavation and concreting works was conducted under Contract HY/2009/19
around the monitoring location during the recorded periods and no major noise
is considered for the works. In addition, construction activities and
intermittent operation of PMEs including excavator, hydraulic breaker and sheet
piling machine were observed at non-CWB Project adjacent to monitoring station
over August 2016. As such, the exceedances were considered as non-Project
related.
On 11 August
2016 and 12 August 2016 morning, hand held drilling works at IEC bridge deck
(Pier 24) were conducted under HY/2009/19 and hand held breaking works beneath
IEC Bridge deck was conducted during the recorded period. No noise mitigation
measure was provided for the drilling works at IEC bridge deck on 12 August
2016 morning and was observed as the direct noise contribution. Hence, the
exceedances on 11 and 12 August 2016 were considered as related to the Project
works.
On 12 August
2016 afternoon, breaking works beneath the IEC bridge deck and concurrent
excavator mounted breaking works at Pier 23 were observed. Despite the
provision of temporary noise barrier for the ground breaking works by excavator
mounted hydraulic breaker and the hand held breaking works was observed
conducted behind physical barrier, exceedances were recorded and direct noise
contribution was observed in relation to the concurrent operation of hand held
breaker and excavator mounted hydraulic breakers opposite to the monitoring
station and considered as related to the Project works.
The ET informed
the findings to Contractor of HY/2009/19 and advised the Contractor of
HY/2009/19 to review the construction sequence to propose and implement
appropriate remedial actions. Rectification measure including provision of
acoustic noise screen for bridge deck drilling works was provided by the
Contractor of HY/2009/19 on 12 August 2016 and the Contractor of HY/2009/19
reviewed the construction sequence and committed to isolate concurrent bridge
deck drilling or hand held breaking for construction joint underneath IEC bridge
deck or excavator mounted breaking works to avoid cumulative impact due to
concurrent operations. Further checking by the ET was conducted on 14 August
2016, drilling works with acoustic noise screen was observed on IEC bridge deck
while no concurrent breaking works and drilling works was further observed on
14 August 2016 and no further project related exceedance was recorded.
On 13 August
2016, only excavation works was conducted by Contract HY/2009/19 around the
monitoring location during the recorded period and no major noise is
considered. In addition, construction activities and intermittent operation of
PMEs including excavator, hydraulic breaker and sheet piling rig were observed
at non-CWB Project adjacent to monitoring station was observed in August 2016.
As such, the exceedances were considered as non-Project related.
On 17 August 2016, drilling works for tie beam beneath IEC was conducted
by Contract HY/2009/19 immediately behind physical barrier erected around the
works location. In addition, construction activities and intermittent operation
of PMEs including excavator, hydraulic breaker and sheet piling rig were
observed at non-CWB Project adjacent to monitoring station was observed in
August 2016. As such, the exceedances were considered as non-Project related.
Contract no. HY/2011/08 Central –Central - Wan Chai Bypass (CWB) –Tunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning
under FEP-11/364/2009B
5.3.13.
No limit level exceedance
was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the
reporting month.
5.3.14.
Limit level exceedances were recorded at
RTN2a-Electric Centre on 07, 08, 10, 11, 14, 15, 16, 18, 20, 21 and 22 June
2016 during daytime in the reporting month. After checking, bars threading with
couplers under HY/2011/08 were carried out on 07, 08 June 2016 and steel bar
fixing were conducted under Contract HY/2011/08 on 10, 15, 16, 18 and 22 June
2016 and no construction works was undertaken by Contract HY/2011/08 on 11,14,
20 and 21 June 2016. In addition, it was observed that building demolition at
non-CWB Project development site opposite to the monitoring station was
conducted across the monitoring month and was considered as the major noise
contribution. As such, the exceedances were considered as non-Project related.
Reporting month of July 2016
5.3.15.
No limit level exceedance
was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot in the
reporting month.
5.3.16.
Limit level exceedances were recorded at RTN2a-Electric
Centre on 11 July 2016 during daytime in the reporting month. After checking,
no construction works was carried out under Contract HY/2011/08 on 11 July 2016
during the monitoring period while adverse weather with frequent thunderstorm
was recorded at the monitoring period across monitoring station at Eastern
District and is considered as the major noise contribution. As such, the
exceedance was considered as non-Project related.
Reporting month
of August 2016
5.3.17.
Limit level exceedance
was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot was
recorded on 09 August 2016 during daytime in the reporting month. After
checking with Contractor of HY/2011/08, no construction activities was
conducted during the recorded period while adverse weather with frequent
thunderstorm was observed and recorded across other monitoring stations at Tin
Hau and North Point District and is considered as the major noise contribution.
As such, the exceedance was considered not related to Project.
5.3.18.
Limit level exceedances were recorded at
RTN2a-Electric Centre on 09 and 10 August 2016 during daytime in the reporting
month. After checking with Contractor of HY/2011/08, no construction activity
was conducted on 09 August 2016 and 10 August 2016 during the recorded period.
Adverse weather with frequent thunderstorm were recorded at the monitoring
period on 09 and 10 August 2016 across monitoring stations at North Point
District and is considered as the major noise contribution. As such, the
exceedance was considered as non-Project related.
5.3.19.
Limit level exceedances were recorded at
RTN4-Causeway Bay Community Centre on 04, 09, 11, 12, 13 and 17 August 2016
during daytime in the reporting month. After checking with the Contractor of
HY/2011/08, no construction activities was conducted around the monitoring
location during the recorded period on 04, 09, 11, 12, 13 and 17 August 2016.
In addition, construction activities and intermittent operation of PMEs
including excavator, hydraulic breaker and sheet piling rig were observed at
non-CWB Project adjacent to monitoring station was observed in August 2016. As
such, the exceedances were considered as non-Project related.
5.4.1.
There was no non-compliance from the site
audits in the reporting period. During environmental site inspections conducted
during the reporting quarter, minor deficiencies were noted. However, the Contractor rectified all
deficiencies after receipt of notification.
5.6.1
There was no particular action taken since no
non-compliance was recorded from site audits in the reporting period.
6.0.1 Two environmental complaints were received in the reporting quarter.
6.0.2
First EPD complaint was referred by EPD was received by ET on 16 June
2016 (Case Ref.: H08/RS/00014627-16). The complainant reported that his or her
properties were covered by many water stains which were splashing from the
working area of Island Eastern Corridor near Sea View Estate.
ET confirmed with the Resident Site
Staff that rebar fixing was carried out on 13 and 14 June 2016 under the
Contractor of HY/2009/19 while formwork cleaning and laying concrete for
stitching and curing work for concrete were carried out under the Contractor of
HY/2009/19 on 15 June 2016 and 16 June 2016 respectively.
Mitigation measures including provision
of metal cover underneath the bridge deck in slanting position at Watson Road
to prevent spilling of water onto public road and provision of tarpaulin sheet
along the guard rails of the bridge deck at Pier 19-20 (opposite to Sea View
Estate) to prevent splashing of water to outside area were implemented by the
Contractor of HY/2009/19.
Based on the site records confirmed by
RSS, rebar fixing was carried out on 13
and 14 June 2016 under the Contractor of
HY/2009/19 while formwork cleaning and laying concrete for stitching and
curing work for concrete were carried out under the Contractor of HY/2009/19 on
15 June 2016 and 16 June 2016 respectively.
Mitigation measures including provision
of metal cover underneath the bridge deck in slanting position at Watson Road
to prevent spilling of water onto public road and provision of tarpaulin sheet
along the guard rails of the bridge deck at Pier 19-20 (opposite to Sea View
Estate) to prevent splashing of water to outside area were implemented by the
Contractor of HY/2009/19.
Follow up inspection was conducted on 22
June 2016, mitigation measures including the use of metal cover underneath the
bridge deck at Watson Road and provision of tarpaulin sheet along the guard
rails of the section of bridge deck opposite to Sea View Estate were
implemented by the Contractor of HY/2009/19. No particular spilling or
splashing of construction water was observed during inspection around the concerned
location.
Nevertheless, in view of the public
concern, the Contractor of HY/2009/19 was suggested that the direction of the
water hose shall be pointed away from the public area as far as practicable
during water use or watering for dust suppression to avoid potential splashing
nuisance caused to the surroundings. The Contractor of HY/2009/19 was also
reminded to maintain proper site drainage to direct surface runoff generated
from construction works or cleaning to the proper collection point within site
area to avoid potential nuisance to the surroundings.
6.0.3
Second public complaint referred by EPD was received by ET on 14 July
2016 (Case Ref.: H08/RS/00016213-16). The complainant reported the concern
about night time construction noise from construction works between 0200hrs to
0300hrs and construction dust emission from construction site of TS3 near Slip
Road 8 section.
ET confirmed with the Resident Site
Staff that excavation at TS3 and loading of material onto derrick barge (Shun
Tat 28) by crawler crane was undertaken by the Contractor of HY/2010/08 from
19:00hrs to around 02:00hrs on 30 June 2016. Total one crawler crane was in
operation. Noise mitigation measures including equipping the crawler crane with
noise barrier was implemented by the Contractor of HY/2010/08. Dust mitigation
measures including manual spraying of water and mist nozzles are deployed on
the ground level and at the cofferdam.
Based on the site records confirmed by
RSS, excavation at TS3 and loading of material onto derrick barge (Shun Tat 28)
by crawler crane was undertaken by the Contractor of HY/2010/08 from 19:00hrs
on 29 June 2016 to around 02:00hrs on 30 June 2016. No construction works was
conducted at the concerned location after around 02:00hrs on 30 June 2016.
Total one crawler crane was in operation and noise mitigation measures
including equipping the crawler crane with noise barrier was implemented by the
Contractor of HY/2010/08.
Based on review on relevant record,
Construction Noise Permit GW-RS0434-16 for the operation of crawler crane at
the concerned location was in place. However, based on relevant site record, it
was noted that the crawler crane deployed during the concerned period could not
match with the specific PME requirement under condition 3a (Crane, crawler,
mounted with noise barrier (Kobelco 7250S)) of the Construction Noise Permit
GW-RS0434-16 between 23:00hrs to 07:00hrs on the following day. Dust mitigation
measures including manual spraying of water and mist nozzles were deployed on
the ground level and at the cofferdam.
Follow up inspection was conducted on 20
July 2016, the potential concerned excavation works at the concerned location
was not observed and no particular dust impact was observed around the
concerned location.
In view of the above, the Contractor of
HY/2010/08 was advised to review the site control system for construction works
carried out during restricted hours to check and ensure the model/ specific
PMEs deployed are in compliance with relevant Construction Noise Permit. The
Contractor of HY/2010/08 was also reminded to maintain regular maintenance of
the plant and equipment deployed to avoid potential nuisance to the nearby
public. Also, the Contractor of HY/2010/08 was reminded to maintain sufficient
watering for excavated material handling to avoid potential dust nuisance to
the surroundings.
6.0.1.
The details of cumulative complaint log and summary of
complaints are presented in Appendix 6.1.
6.0.2.
No notification of summons or
prosecution was received in the reporting period. Cumulative statistic on complaints and successful
prosecutions are summarized in Table 6.1 and Table 6.2 respectively.
Table
6.1 Cumulative Statistics on Complaints
Reporting Period |
No.
of Complaints |
Commencement
of Works up to last reporting quarter |
65 |
June 2016 – August 2016 |
2 |
Project-to-Date |
67 |
Table 6.2 Cumulative Statistics on Successful
Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this quarter (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
7.0.2.
According to the Final EM&A Report of Central
Reclamation Phase III (CRIII) for Contract HK 12/02, the major construction
activities were completed by end of January 2014 and no construction activities
were undertaken thereafter and the water
quality monitoring was completed in October 2011. As such, it is considered that there were no
cumulative construction impact due to the concurrent activities of the current
projects with the Central Reclamation Phase III (CRIII) undertaken by
contractor HK12/02 in the reporting period.
7.0.3.
According to the construction programme of
Central-Wanchai Bypass at Wanchai West at the Central Reclamation Phase III area
include structural works for tunnel construction, road works and drainage
works, and seawall modification were performed in August 2016 reporting month. As no project
related exceedance were recorded during the reporting period, cumulative
construction impact due to the concurrent activities of the current projects
with the Central Reclamation Phase III (CRIII) was considered as insignificant.
7.0.4.
According
to the construction programme of Wan Chai Development Phase II, Central-Wan
Chai Bypass and Island Eastern Corridor Link projects, the major construction
activities under Wan Chai Development Phase II were tunnel works at Wan Chai
East and back filling works, culvert reinstatement and road and drain works at
Wan Chai West. The major construction activities under Central-Wan Chai Bypass
and Island Eastern Corridor Link Projects were road works and ventilation
building construction at Central Interchange, temporary reclamation removal
works at Ex-PCWAW, ELS works and retaining wall construction at Victoria Park,
ELS works and tunnel works at TS3; bridge construction, piling and tunnel works
at North Point area in the reporting month. In addition, other non-Wan Chai
Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link
projects was observed
undertaken at Wan Chai North and North Point area.
7.0.5.
No significant air impact from construction
activities was anticipated in the reporting month. Besides, no project related
exceedance was recorded during the air and noise environmental monitoring
events in the reporting month. Thus, it is evaluated that the cumulative
construction impact from the concurrent projects including Central Reclamation
Phase III (CRIII), Wan Chai Development Phase II (WDII), Central-WanChai Bypass
(CWB), Island Eastern Corridor Link projects (IECL) was insignificant.
8.0.1.
The
EM&A programme was carried out in accordance with the EM&A Manual
requirements, minor alterations to the programme proposed were made in response
to changing circumstances.
Air quality monitoring
8.0.2.
One 1hr TSP action level exceedance was recorded at CMA1b- Oil Street
Site Office on 27 August 2016 in the reporting month. The exceedance was
concluded as non-project related.
Noise
monitoring
8.0.3.
Three limit level exceedances were recorded at noise monitoring station
M1a – Habour Road Sports Center on 07, 13 and 21 June 2016. The exceedances
were concluded as non-project related.
8.0.4.
One limit level exceedance was recorded at noise monitoring station M1a
– Habour Road Sports Center on 28 June 2016. The exceedance was concluded as
non-project related.
8.0.5.
One limit level exceedance was recorded at noise monitoring station M6 –
HK Baptist Church Henrietta Secondary School on 12 July 2016. The exceedance
was concluded as non-project related.
Real
time noise monitoring
Reporting month of June 2016
8.0.6.
No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport
Section Whitfield Depot in the reporting month.
8.0.7.
Limit level exceedances were recorded at RTN2a-Electric Centre on 07,
08, 10, 11, 14, 15, 16, 18, 20, 21 and 22
June 2016 during daytime in the reporting month. After checking, pre bore
and sheet piling works were carried out on 07, 08, 10, 11, 14, 15, 16, 18, 20,
21 and 22 June 2016 and mitigation measures including erection of noise barrier
was implemented by the Contractor of HY/2009/19 while it was observed that
building demolition at non-CWB Project development site opposite to the
monitoring station was conducted across the monitoring month and was considered
as the major noise contribution. As such, the exceedances were considered as
non-Project related.
8.0.8.
Limit level exceedances were recorded at RTN2a-Electric Centre on 07,
08, 10, 11, 14, 15, 16, 18, 20, 21 and 22 June 2016 during daytime in the
reporting month. After checking, bars threading with couplers under HY/2011/08
were carried out on 07, 08 June 2016 and steel bar fixing were conducted under
Contract HY/2011/08 on 10, 15, 16, 18 and 22 June 2016 and no construction
works was undertaken by Contract HY/2011/08 on 11,14, 20 and 21 June 2016. In
addition, it was observed that building demolition at non-CWB Project
development site opposite to the monitoring station was conducted across the
monitoring month and was considered as the major noise contribution. As such,
the exceedances were considered as non-Project related.
8.0.9.
No limit level exceedances were recorded at RTN3-Yue Lee Mo Fan Memorial
School in the reporting month.
8.0.10.
No limit level exceedances were recorded at RTN4-Causeway Bay Community
Centre in the reporting month.
Reporting month of July
2016
8.0.11.
No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport
Section Whitfield Depot in the reporting month.
8.0.12.
Limit level exceedances were recorded at RTN2a-Electric Centre on 11
July 2016 during daytime in the reporting month. After checking, pre bore
piling and sheet piling works were carried out on 11 July 2016 during the
monitoring period and mitigation measures including erection of noise barrier
was implemented by the Contractor of HY/2009/19 while adverse weather with
frequent thunderstorm was recorded at the monitoring period across monitoring
station at Eastern District and is considered as the major noise contribution.
As such, the exceedance was considered as non-Project related.
8.0.13.
Limit level exceedances were recorded at RTN2a-Electric Centre on 11 July
2016 during daytime in the reporting month. After checking, no construction
works was carried out under Contract HY/2011/08 on 11 July 2016 during the
monitoring period while adverse weather with frequent thunderstorm was recorded
at the monitoring period across monitoring station at Eastern District and is
considered as the major noise contribution. As such, the exceedance was
considered as non-Project related.
8.0.14.
Limit level exceedance was recorded at RTN3-Yue Lee Mo Fan Memorial School
on 11 July 2016 during daytime in the reporting month. After checking, no
construction works was conducted by Contract HY/2009/19 on 11 July 2016 during
the monitoring period while adverse weather with frequent thunderstorm was
recorded at the monitoring period across monitoring stations at Eastern
District and is considered as the major noise contribution. As such, the
exceedance was considered as non-Project related.
8.0.15.
Limit level exceedances were recorded at RTN4-Causeway Bay Community
Centre on 11, 16, 18 and 20 July 2016 during daytime in the reporting month. After
checking, no construction works was conducted by Contract HY/2009/19 on 11 July
2016 during monitoring period while adverse weather with frequent thunderstorm
was recorded at the monitoring period across monitoring station at Eastern
District and is considered as the major noise contribution. As such, the
exceedances were considered as non-Project related.
No construction works was conducted by Contract of HY/2009/19 on 16 July
2016 and only erection of scaffolding with no major noise emanation was
conducted under Contract HY/2009/19 on 18 July 2016. As such, the exceedances
were considered to be contributed by nearby traffic and not related to Project
works.
On 20 July 2016, breaking works for concrete base slab for tie beam
construction was observed at Pier 22- 23 directly opposite to the monitoring
station was conducted during the monitoring period and direct noise impact was
observed despite the erection of noise barrier. As such, the exceedances were
considered to be related to the Project works. The concerned construction was
completed on the same date and no further exceedance related to the breaking
works was observed. In view of the project related exceedances and the
completion of the concerned breaking works, the Contractor will improve the
mitigation against noise by orientation of noise barrier to better obstruct the
line of sight between the breaking works and the NSR shall there be any
breaking works to be carried out at the concerned location.
Reporting month of August 2016
8.0.16.
Limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport
Section Whitfield Depot was recorded on 09 August 2016 during daytime in the
reporting month. After checking with Contractor of HY/2009/19, no construction
activities was conducted during the recorded period while adverse weather with
frequent thunderstorm was observed and recorded across other monitoring
stations at Tin Hau and North Point District and is considered as the major
noise contribution. As such, the exceedance was considered not related to
Project.
8.0.17.
Limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport Section
Whitfield Depot was recorded on 09 August 2016 during daytime in the reporting
month. After checking with Contractor of HY/2011/08, no construction activities
was conducted during the recorded period while adverse weather with frequent
thunderstorm was observed and recorded across other monitoring stations at Tin
Hau and North Point District and is considered as the major noise contribution.
As such, the exceedance was considered not related to Project.
8.0.18.
Limit level exceedances were recorded at RTN2a-Electric Centre on 09 and
10 August 2016 during daytime in the reporting month. After checking with
Contractor of HY/2009/19, no construction activity was conducted on 09 August
2016 during the recorded period and unloading of soil at temporary jetty was
conducted on 10 August 2016 during the recorded period. Adverse weather with
frequent thunderstorm were recorded at the monitoring period on 09 and 10
August 2016 across monitoring stations at North Point District and is
considered as the major noise contribution. As such, the exceedance was
considered as non-Project related.
8.0.19.
Limit level exceedances were recorded at RTN2a-Electric Centre on 09 and 10
August 2016 during daytime in the reporting month. After checking with
Contractor of HY/2011/08, no construction activity was conducted on 09 August
2016 and 10 August 2016 during the recorded period. Adverse weather with frequent
thunderstorm were recorded at the monitoring period on 09 and 10 August 2016
across monitoring stations at North Point District and is considered as the
major noise contribution. As such, the exceedance was considered as non-Project
related.
8.0.20.
Limit level exceedance was recorded at RTN3-Yue Lee Mo Fan Memorial
School on 09, 10 and 17 August 2016 during daytime in the reporting month.
After checking, no construction works was conducted by Contract HY/2009/19 on
09, 10 and 17 August 2016 around the concerned location during the monitoring
period while adverse weather with frequent thunderstorm was recorded at the
monitoring period on 09 and 10 August 2016 across monitoring stations at
Eastern District and is considered as the major noise contribution. As such,
the exceedance was considered as non-Project related. On 17 August 2016, erection of U-beam with
launching girder and crane was conducted by HY/2009/19 on 17 August 2016 and no
major noise is considered. As such, the exceedance was considered as non-Project
related.
8.0.21.
Limit level exceedances were recorded at RTN4-Causeway Bay Community
Centre on 04, 09, 11, 12, 13 and 17 August 2016 during daytime in the reporting
month. After checking with the Contractor of HY/2009/19, excavation works and
rebar fixing were conducted by Contract HY/2009/19 on 04 August 2016 around the
monitoring location during the recorded period and no major noise is
considered. In addition, construction activities and intermittent operation of
PMEs including excavator, hydraulic breaker and sheet piling rig were observed
at non-CWB Project adjacent to monitoring station was observed in August 2016.
As such, the exceedances were considered as non-Project related.
On 09 August 2016, excavation and concreting works was conducted under
Contract HY/2009/19 around the monitoring location during the recorded periods
and no major noise is considered for the works. In addition, construction
activities and intermittent operation of PMEs including excavator, hydraulic
breaker and sheet piling machine were observed at non-CWB Project adjacent to
monitoring station over August 2016. As such, the exceedances were considered
as non-Project related.
On 11 August 2016 and 12 August 2016 morning, hand held drilling works
at IEC bridge deck (Pier 24) were conducted under HY/2009/19 and hand held
breaking works beneath IEC Bridge deck was conducted during the recorded
period. No noise mitigation measure was provided for the drilling works at IEC
bridge deck on 12 August 2016 morning and was observed as the direct noise
contribution. Hence, the exceedances on 11 and 12 August 2016 were considered
as related to the Project works.
On 12 August 2016 afternoon, breaking works beneath the IEC bridge deck
and concurrent excavator mounted breaking works at Pier 23 were observed.
Despite the provision of temporary noise barrier for the ground breaking works
by excavator mounted hydraulic breaker and the hand held breaking works was
observed conducted behind physical barrier, exceedances were recorded and
direct noise contribution was observed in relation to the concurrent operation
of hand held breaker and excavator mounted hydraulic breakers opposite to the
monitoring station and considered as related to the Project works.
The ET informed the findings to Contractor of HY/2009/19 and advised the
Contractor of HY/2009/19 to review the construction sequence to propose and
implement appropriate remedial actions. Rectification measure including
provision of acoustic noise screen for bridge deck drilling works was provided by
the Contractor of HY/2009/19 on 12 August 2016 and the Contractor of HY/2009/19
reviewed the construction sequence and committed to isolate concurrent bridge
deck drilling or hand held breaking for construction joint underneath IEC
bridge deck or excavator mounted breaking works to avoid cumulative impact due
to concurrent operations. Further checking by the ET was conducted on 14 August
2016, drilling works with acoustic noise screen was observed on IEC bridge deck
while no concurrent breaking works and drilling works was further observed on
14 August 2016 and no further project related exceedance was recorded.
On 13 August 2016, only excavation works was conducted by Contract
HY/2009/19 around the monitoring location during the recorded period and no major
noise is considered. In addition, construction activities and intermittent
operation of PMEs including excavator, hydraulic breaker and sheet piling rig
were observed at non-CWB Project adjacent to monitoring station was observed in
August 2016. As such, the exceedances were considered as non-Project related.
On 17 August 2016, drilling works for
tie beam beneath IEC was conducted by Contract HY/2009/19 immediately behind
physical barrier erected around the works location. In addition, construction
activities and intermittent operation of PMEs including excavator, hydraulic
breaker and sheet piling rig were observed at non-CWB Project adjacent to
monitoring station was observed in August 2016. As such, the exceedances were
considered as non-Project related.
8.0.22.
Limit level exceedances were recorded at RTN4-Causeway Bay Community
Centre on 04, 09, 11, 12, 13 and 17 August 2016 during daytime in the reporting
month. After checking with the Contractor of HY/2011/08, no construction
activities was conducted around the monitoring location during the recorded
period on 04, 09, 11, 12, 13 and 17 August 2016. In addition, construction
activities and intermittent operation of PMEs including excavator, hydraulic
breaker and sheet piling rig were observed at non-CWB Project adjacent to
monitoring station was observed in August 2016. As such, the exceedances were
considered as non-Project related.
Environmental Complaints
8.0.23.
Two environmental complaints were received in the reporting quarter.
8.0.24.
First EPD complaint was referred by EPD was received by ET on 16 June
2016 (Case Ref.: H08/RS/00014627-16). The complainant reported that his or her
properties were covered by many water stains which were splashing from the
working area of Island Eastern Corridor near Sea View Estate.
ET confirmed with the Resident Site
Staff that rebar fixing was carried out on 13 and 14 June 2016 under the
Contractor of HY/2009/19 while formwork cleaning and laying concrete for
stitching and curing work for concrete were carried out under the Contractor of
HY/2009/19 on 15 June 2016 and 16 June 2016 respectively.
Mitigation measures including provision
of metal cover underneath the bridge deck in slanting position at Watson Road
to prevent spilling of water onto public road and provision of tarpaulin sheet
along the guard rails of the bridge deck at Pier 19-20 (opposite to Sea View
Estate) to prevent splashing of water to outside area were implemented by the
Contractor of HY/2009/19.
Based on the site records confirmed by
RSS, rebar fixing was carried out on 13
and 14 June 2016 under the Contractor of
HY/2009/19 while formwork cleaning and laying concrete for stitching and
curing work for concrete were carried out under the Contractor of HY/2009/19 on
15 June 2016 and 16 June 2016 respectively.
Mitigation measures including provision
of metal cover underneath the bridge deck in slanting position at Watson Road
to prevent spilling of water onto public road and provision of tarpaulin sheet
along the guard rails of the bridge deck at Pier 19-20 (opposite to Sea View
Estate) to prevent splashing of water to outside area were implemented by the
Contractor of HY/2009/19.
Follow up inspection was conducted on 22
June 2016, mitigation measures including the use of metal cover underneath the
bridge deck at Watson Road and provision of tarpaulin sheet along the guard
rails of the section of bridge deck opposite to Sea View Estate were
implemented by the Contractor of HY/2009/19. No particular spilling or
splashing of construction water was observed during inspection around the
concerned location.
Nevertheless, in view of the public
concern, the Contractor of HY/2009/19 was suggested that the direction of the
water hose shall be pointed away from the public area as far as practicable
during water use or watering for dust suppression to avoid potential splashing
nuisance caused to the surroundings. The Contractor of HY/2009/19 was also
reminded to maintain proper site drainage to direct surface runoff generated
from construction works or cleaning to the proper collection point within site
area to avoid potential nuisance to the surroundings.
8.0.25.
Second public complaint referred by EPD was received by ET on 14 July
2016 (Case Ref.: H08/RS/00016213-16). The complainant reported the concern
about night time construction noise from construction works between 0200hrs to
0300hrs and construction dust emission from construction site of TS3 near Slip
Road 8 section.
ET confirmed with the Resident Site
Staff that excavation at TS3 and loading of material onto derrick barge (Shun
Tat 28) by crawler crane was undertaken by the Contractor of HY/2010/08 from
19:00hrs to around 02:00hrs on 30 June 2016. Total one crawler crane was in
operation. Noise mitigation measures including equipping the crawler crane with
noise barrier was implemented by the Contractor of HY/2010/08. Dust mitigation
measures including manual spraying of water and mist nozzles are deployed on
the ground level and at the cofferdam.
Based on the site records confirmed by
RSS, excavation at TS3 and loading of material onto derrick barge (Shun Tat 28)
by crawler crane was undertaken by the Contractor of HY/2010/08 from 19:00hrs
on 29 June 2016 to around 02:00hrs on 30 June 2016. No construction works was
conducted at the concerned location after around 02:00hrs on 30 June 2016.
Total one crawler crane was in operation and noise mitigation measures
including equipping the crawler crane with noise barrier was implemented by the
Contractor of HY/2010/08.
Based on review on relevant record,
Construction Noise Permit GW-RS0434-16 for the operation of crawler crane at
the concerned location was in place. However, based on relevant site record, it
was noted that the crawler crane deployed during the concerned period could not
match with the specific PME requirement under condition 3a (Crane, crawler,
mounted with noise barrier (Kobelco 7250S)) of the Construction Noise Permit
GW-RS0434-16 between 23:00hrs to 07:00hrs on the following day. Dust mitigation
measures including manual spraying of water and mist nozzles were deployed on
the ground level and at the cofferdam.
Follow up inspection was conducted on 20
July 2016, the potential concerned excavation works at the concerned location
was not observed and no particular dust impact was observed around the concerned
location.
In view of the above, the Contractor of
HY/2010/08 was advised to review the site control system for construction works
carried out during restricted hours to check and ensure the model/ specific
PMEs deployed are in compliance with relevant Construction Noise Permit. The
Contractor of HY/2010/08 was also reminded to maintain regular maintenance of
the plant and equipment deployed to avoid potential nuisance to the nearby
public. Also, the Contractor of HY/2010/08 was reminded to maintain sufficient
watering for excavated material handling to avoid potential dust nuisance to
the surroundings.
8.0.26.
The construction programmes of individual contracts are provided in Appendix 8.1.