Contract No: HK/2015/01 Wanchai Development Phase II and Sampling,
Field Measurement and Testing Work (Stage 3) Environmental Permit no. EP-364/2009/E, Further Evironmental
permit nos. fep-01/364/2009, fep-02/364/2009, FEP-05/364/2009/A, FEp-06/364/2009/a, FEp-07/364/2009/D,
FEP-09/364/2009/B, fep-10/364/2009/B and fep-11/364/2009/B, FEP-12/364/2009/D Quarterly
Environmental Monitoring
and
Audit Report
- JUNE 2017 to AUGUST 2017 -
|
CLIENTS: |
|
Civil
Engineering and Development Department and Highways
Department |
Lam Geotechnics
Limited 11/F Centre
Point Wanchai, H.K. Telephone: (852) 2882-3939 Facsimile: (852) 2882-3331 E-mail: info@lamenviro.com Website: http://www.lamenviro.com |
|
|
|
|
|
CHECKED by: |
|
Raymond Dai Environmental Team Leader |
|
DATE: |
|
04 October 2017 |
2.2 Scope of the Project and Site
Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact
Personnel
2.5 Principal Work and Activities
4.2. Real Time Noise Monitoring Results
4.3. Air quality
monitoring Results
5.3. Real Time Noise Monitoring
5.5. Review of the Reasons for and the
Implications of Non-compliance.
5.6. Summary of action taken in the event of
and follow-up on non-compliance.
6. Complaints, Notification
of Summons and Prosecution
7. Cumulative Construction
Impact due to the Concurrent Projects
lIST
OF TABLES
Table I Principal Work
Activities for Contract no. HY/2009/18
Table II Principal
Work Activities for Contract no. HK/2009/01
Table III Principal Work Activities for
Contract no. HK/2009/02
Table IV Principal Work Activities for
Contract no. HY/2009/15
Table V Principal
Work Activities for Contract no. HY/2009/19
Table VI Principal Work Activities for Contract
no. HK/2012/08
Table VII Principal Work Activities for Contract
no. HY/2010/08
Table VIII Principal Work Activities for Contract no.
HY/2011/08
Table 2.1 Schedule
2 Designated Projects under this Project
Table 2.2 Details
of Individual Contracts under the Project
Table 2.3 Contact
Details of Key Personnel
Table 2.4 Principal Work Activities for
Contract no. HY/2009/18
Table 2.5 Principal Work Activities for
Contract no. HK/2009/01
Table 2.6 Principal
Work Activities for Contract no. HK/2009/02
Table 2.7 Principal
Work Activities for Contract no. HY/2009/15
Table 2.8 Principal
Work Activities for Contract no. HY/2009/19
Table 2.9 Principal
Work Activities for Contract no. HK/2012/08
Table 2.10 Principal Work
Activities for Contract no. HY/2010/08
Table 2.11 Principal Work
Activities for Contract no. HY/2011/08
Table 3.1 Noise
Monitoring Stations
Table 3.2 Real
Time Noise Monitoring Stations
Table 3.3 Air
quality monitoring Stations
Table 4.1 Noise Monitoring Station
for Contract no. HY/2009/18
Table 4.2 Noise Monitoring
Stations for Contract nos. HK/2009/01 and HK/2009/02
Table 4.3 Noise Monitoring Station
for Contract nos. HY/2009/15
Table 4.4 Noise
Monitoring Stations for Contract no. HY/2009/19
Table 4.5 Noise Monitoring Stations for Contract
no. HY/2010/08
Table 4.6 Noise Monitoring Stations for Contract no.
HY/2011/08
Table 4.7 Real
Time Noise Monitoring Stations for Contract no. HY/2009/19
Table 4.8 Real Time
Noise Monitoring Stations for Contract
no. HY/2011/08
Table 4.9 Air
quality monitoring Stations for Contract no. HY/2009/18
Table 4.10 Air
quality monitoring Stations for Contract no. HK/2009/01
Table 4.11 Air quality
monitoring Station for Contract no. HK/2009/02
Table 4.12 Air
quality monitoring Station for Contract no. HY/2009/15
Table 4.13 Air
quality monitoring Stations for Contract no. HY/2009/19
Table 4.14 Air
quality monitoring Stations for Contract no. HK/2012/08
Table 4.15 Air
quality monitoring Stations for Contract no. HY/2010/08
Table 4.16 Air quality monitoring Stations for
Contract no. HY/2011/08
Table 4.17 Details
of Waste Disposal for Contract no. HK/2009/01
Table 4.18 Details
of Waste Disposal for Contract no. HK/2009/02
Table 4.19 Details
of Waste Disposal for Contract no. HY/2009/18
Table 4.20 Details
of Waste Disposal for Contract no. HY/2009/15
Table 4.21 Details
of Waste Disposal for Contract no. HY/2009/19
Table 4.22 Details
of Waste Disposal for Contract no. HK/2012/08
Table 4.23 Details of Waste Disposal for Contract no.
HY/2010/08
Table 4.24 Details of
Waste Disposal for Contract no. HY/2011/08
Table 6.1 Cumulative
Statistics on Complaints
Table 6.2 Cumulative
Statistics on Successful Prosecutions
lIST OF FIGUREs
Figure
2.1 Project Layout
Figure
2.2 Project Organization Chart
Figure
3.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 2.1 Environmental Mitigation
Implementation Schedule
Appendix 3.1 Action and Limit Level
Appendix 4.1 Noise Monitoring Results and
Graphical Presentations
Appendix
4.2 Real-time Noise Monitoring Results and
Graphical Presentations
Appendix 4.3 Air Quality Monitoring Results
and Graphical Presentations
Appendix 5.1 Event Action Plans
Appendix 6.1 Complaint Log
Appendix 6.2 Notification of Exceedance
Appendix 8.1 Construction Programme of
Individual Contracts
EXECUTIVE
SUMMARY
Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB)
- Central Interchange under FEP-05/364/2009
Major construction activities for Contract no. HY/2009/18 have been
commenced on 21
Table I Principal Work Activities for Contract
no. HY/2009/18
June 2017 |
July 2017 |
August 2017 |
Drainage works Road works Landscaping works Maintenance works |
Drainage works Road works Landscaping works Maintenance works |
Landscaping works Maintenance works |
Contract no.
HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Hong
Kong Convention and Exhibition Centre - Tunnel Works under FEP-02/364/2009
Major construction activities
for Contract no. HK/2009/01 have been commenced on 25 August 2011. During this
reporting period, the principal work activities are summarized as below:
Table II Principal Work
Activities for Contract no. HK/2009/01
June 2017 |
July 2017 |
August 2017 |
Reinstatement of amenity area Road and Drain works |
Reinstatement of amenity area Road and Drain works |
Reinstatement of amenity area Road and Drain works |
Contract no.
HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan
Chai East (CWB Tunnel) under FEP-01/364/2009
Major construction activities
for Contract no. HK/2009/02 have been commenced on 26
Table III Principal Work Activities for Contract no.
HK/2009/02
June 2017 |
July 2017 |
August 2017 |
Rectification works for the defects
recorded in the inspection for the end of maintenance period of Observation
Deck and Staircase ST-01 Rectification works for cracks/joints
with water leakage inside OHVD cells was completed. Rebar fixing and formwork at Hung Hing
Road Flyover approach ramp bay 1 base slab Rebar fixing and formwork at Hung Hing
Road Flyover approach ramp bay 2 base slab Backfilling works Cleaning of cross road duct Rectification works against water
leakage and remedial works against concrete defects of the tunnel structure Outstanding works inside tunnel. Concreting for roadside barrier Erection of scaffolding for
construction of top slab Tunnel top slab Dismantling of scaffolding. Trial pit works for sewage works at
Wan Shing Street Rectification works for uneven road
surface at Hung Hing Road |
Rectification works for the defects
recorded in the inspection for the end of maintenance period of Observation
Deck and Staircase ST-01 Rectification works for cracks/joints
with water leakage inside OHVD cells Concreting of Hung Hing Road Flyover
approach ramp bay 3 base slab Rebar fixing and formwork at Hung Hing
Road Flyover approach ramp bay 1 base slab Rebar fixing and formwork at Hung Hing
Road Flyover approach ramp bay 2 wall Backfilling works up to +4.0mPD inside
cofferdam Remedial work for cross road duct Rectification works against water
leakage and remedial works against concrete defects of the tunnel structure Outstanding works inside tunnel Concreting for roadside barrier Removal of scaffolding and formwork
inside tunnel Removal of silo tank Waterproofing and screeding works on
top of tunnel Removal of strut and removal of waling
Reinstatement of temporary access
opening at Bay 7 Breaking of D-Wall panel Backfilling work for the area to be
handed over to MTR SCL 1123 Sewage works at Wan Shing Street Rectification works for uneven road
surface at Hung Hing Road |
Removal of the existing sheet piles
along the north face of WSD Salt Water Pumping Station Remedial works for the sewer between
manholes FMH2 and CP4 was in progress. 5% construction of the top slab inside
the access shaft of Tunnel Portion 2 100% of rebar fixing and formwork at
Hung Hing Road Flyover approach ramp bay 1 base slab Construction of Hung Hing Road Flyover
approach ramp bay 2 structural wall Approx. 25% remedial work for cross
road duct Approx. 90% rectification works
against water leakage and remedial works against concrete defects of the
tunnel structure Concreting for roadside barrier Removal of scaffolding and formwork
inside tunnel Removal of strut and waling Reinstatement of temporary access
opening at Bay 7 Breaking of all D-Wall panel 100% of backfilling work for the area
to be handed over to MTR SCL 1123 Sewage works at Wan Shing Street Rectification works for faded road
marking at temporary Hung Hing Road Flyover |
Contract no. HY/2009/15 - Central-Wanchai
Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
Major construction activities
for Contract no. HY/2009/15 has been commenced on 13 July 2011. During this reporting
period, the principal work activities are summarized as below:
Table IV Principal Work Activities for Contract no.
HY/2009/15
July
2017 |
August 2017 |
|
Remedial works inside tunnel structure
at Mined Tunnel, TS4, TPCWAE and TPCWAW Reinstatement work at the PRE Office
car park area |
Remedial works inside tunnel structure
at Mined Tunnel, TS4, TPCWAE and TPCWAW Reinstatement work at the PRE Office
car park area |
Remedial works of landing step at
HY/2009/15 office |
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under
FEP-07/364/2009/D
Major construction activities
for Contract no. HY/2009/19 have been commenced on March 2011. During this
reporting period, the principal work activities are summarized as below:
Table V Principal Work
Activities for Contract no. HY/2009/19
June 2017 |
July 2017 |
August 2017 |
Approach ramp sheet piling, pre-bored
piling and top soil removal works Bridge Construction Pier 30-32 Cap Construction IEC noise enclosure/barrier
installation Excavation / Construction of retaining
wall FEHD Metal Roof Construction Pre-bored H-piles for Approach Ramp
Phase 2 Construction Hing Fat Street modification works |
Approach ramp sheet piling, pre-bored
piling and top soil removal works Approach ramp structure Construction. Bridge Construction Pier 30-32 Cap Construction Excavation / Construction of retaining
wall FEHD Metal Roof Construction Pre-bored H-piles for Approach Ramp
Phase 2 Construction Hing Fat Street road and drainage
works |
Approach ramp sheet piling and top soil removal works Approach ramp structure Construction. Bridge Construction Pier 30-32 Cap Construction Excavation / Construction of D12
Abutment &retaining wall FEHD Metal Roof Construction and
drainage works Pre-bored H-piles for Approach Ramp
Phase 2 Construction Hing Fat Street road and drainage
works Oil street drainage works |
Contract
no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at
Wan Chai West under FEP-09/364/2009/B and FEP-12/364/2009/D
Table VI Principal
Work Activities for Contract no. HK/2012/08
June 2017 |
July 2017 |
August
2017 |
Grouting Construction of Slip Road 1 Construction of drainage |
Construction of Slip Road 1 Construction of drainage Asphalt paving of A2 Road |
Construction of Slip Road 1 Construction of drainage Asphalt paving of A2 Road |
Contract
no. HY/2010/08 – Central and WanChai Bypass – Slip road 8 section under
FEP-10/364/2009B
Table VII Principal Work
Activities for Contract no. HY/2010/08
June 2017 |
July 2017 |
August 2017 |
Tree protection works next to existing
BGO, Drainage improvement works, Utility diversion works, Retaining wall works ELS works, Construction works for subway
extension |
Tree protection works next to existing
BGO, Drainage improvement works, Utility diversion works, Retaining wall works ELS works, Construction works for subway
extension |
Tree protection works next to existing
BGO, Drainage improvement works, Utility diversion works, Retaining wall works ELS works, Construction works for subway
extension |
Contract
no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009B
Table VIII Principal Work
Activities for Contract no. HY/2011/08
June 2017 |
July 2017 |
August 2017 |
Construction of Ventilation Buildings,
inclusive of Administration Building, Central Ventilation Building, East
Ventilation Shaft/Building, West Ventilation Building Construction of Tunnel Thermal Barrier Installation of Electricals and
Mechanicals Installation of Tunnel Features |
Construction of Ventilation Buildings,
inclusive of Administration Building, Central Ventilation Building, East
Ventilation Shaft/Building, West Ventilation Building Construction of Tunnel Thermal Barrier Installation of Electricals and
Mechanicals Installation of Tunnel Features |
Construction of Ventilation Buildings,
inclusive of Administration Building, Central Ventilation Building, East
Ventilation Shaft/Building, West Ventilation Building Construction of Tunnel Thermal Barrier Installation of Electricals and
Mechanicals Installation of Tunnel Features |
Noise
Monitoring
Real time Noise Monitoring
Air Quality
Monitoring
Complaints,
Notifications of Summons and Successful Prosecutions
ET confirmed with the Resident Site
Staff that Manual re-bar fixing works was carried out under Contract HK/2009/02
from 2300hrs to 2330hrs on 26 June 2017 at Portion 5 Bay 15 (Non - Designated
Area) top slab area adjacent to the covered walkway of the Wan Chai Ferry Pier.
1 no. of generator was operated at ground level and 2 nos. of generators were
operated below ground level from 2300hrs to 2400hrs on 26 June 2017. In
addition 16 electric water pump were operated below ground level from 2300hrs
to 2400hrs on 26 June 2017.
Notwithstanding the information stated
in above item 1), according to relevant Resident Site Staff site record, it was
recorded that 1 no. of mobile crane and 1 no. of bar bender were deployed and
operated at Portion 5 area (West of Wan Chai Ferry Pier) under Contract
HK/2009/02 after 2300hrs on 26 July 2017. Upon warning given by WDII Resident
Site staff to the Contractor of HK/2009/02, the operation of crawler crane for
lifting rebar and operation of bar bender machine were suspended at around
2315hrs on 26 June 2017.
No construction activity and site
operation was carried out under Contract HK/2009/01 from 2300hrs to 2400hrs on
26 June 2017.
According to the RSS site information,
manual re-bar fixing works was carried out under Contract HK/2009/02 from
2300hrs to 2330hrs on 26 June 2017 at Portion 5 Bay 15 (Non - Designated Area)
top slab area adjacent to the covered walkway of the Wan Chai Ferry Pier. 1 no.
of generator was operated at ground level and 2 nos. of generators were
operated below ground level from 2300hrs to 2400hrs on 26 June 2017 while 16
electric water pump were operated below ground level at Portion 5 Bay from
2300hrs to 2400hrs on 26 June 2017 and the relevant Construction Noise Permit
GW-RS0527-17 for the above operation was in place. However, site record on the
model of generators deployed on the concerned night was not available.
Notwithstanding the above, according to
relevant Resident Site Staff site record, it was recorded that 1 no. of mobile
crane and 1 no. of bar bender machine were deployed and operated at Portion 5
area (West of Wan Chai Ferry Pier) under Contract HK/2009/02 after 2300hrs on
26 July 2017 without a valid Construction Noise Permit. Upon warning given by
WDII Resident Site staff to the Contractor of HK/2009/02, the operation of
crawler crane for lifting rebar and operation of bar bender machine were
suspended at around 2315hrs on 26 June 2017. According to Contractor of HK/2009/02,
the operation bar bender machine was suspended upon warning by RSS team and the
operation of crawler crane was suspended upon moving to a proper location to
avoid obstruction for next day work.
Meanwhile, no construction activity and
site operation was carried out under Contract HK/2009/01 from 2300hrs to
2400hrs on 26 June 2017. In view of the above operation of powered mechanical
equipment under Contract HK/2009/02 beyond 2300hrs, the Contractor of
HK/2009/02 was required and urged to implement the following remedial measures
to ensure the strict construction noise permit compliance including:-
Fully review the site control system for
construction works carried out during restricted hours, in particular to ensure
the frontline supervisors responsible for restricted hours construction
operations are trained with comprehensive understanding on the requirement of
the Construction Noise Permit in force to ensure the PMEs deployed are in
compliance with relevant Construction Noise Permit.
To assign delegated and competent
personnel on-site to conduct checking on the deployment of PMEs on-site prior
and during restricted hours to ensure only PMEs allowed under relevant
Construction Noise Permit would be operated.
In addition, the following preventive measures
are also recommended including the Contractor of HK/2009/02 is recommended to
provide regular briefing and training section to site staffs and frontline
workers to enhance the workers awareness and understanding on relevant
Construction Noise Permit(s) requirement during restricted hours.
The Contractor of HK/2009/02 is
recommended to review the construction operation planning procedures to ensure
relevant PME(s) required for conducting the planned operation to ensure
required PME are adequate considered and covered by relevant Construction Noise
Permit.
In view of the recent concern over
restricted hours construction operations, a meeting was held amongst the CEDD,
the RSS team, the Contractor of HK/2009/02 and the Environmental Team on 21
July 2017 to review the site control measures and enhancement measures to be
adopted for restricted hours construction operations control for Construction
Noise Permit Compliance. A detailed implementation plan would be prepared by
the Contractor of HK/2009/02 and further supplemented.
An ICC complaint case (Ref:
2-4122021589) was Referred to the ET on 25 July 2017. The complainant reported
that the workers are now doing extremely noisy works at the Island Eastern
Corridor near Provident Centre affecting the nearby residents. As the ICC
complaint case refers to the noise concern at the same location at the same
hours on the same date, hence the ICC case is considered as the same complaint
case under the EPD complaint for investigation purpose.
ET confirmed with the Resident Site
Staff that emergency road repairing work including the repairing of movement
joint at Pier 46 and three potholes along IEC Westbound was carried out under
Contract HY/2009/19 around the concerned location from 0000hrs to 0600hrs on 14
July 2017. Total 1 no. of hand held breaker and 1 no. of hand held drill for
grout mixing were operated.
According to the RSS site information,
emergency road repairing work including the repairing of movement joint at Pier
46 and three potholes along IEC Westbound was carried out under Contract
HY/2009/19 around the concerned location from 0000hrs to 0600hrs on 14 July
2017. Total 1 no. of hand held breaker and 1 no. of hand held drill for grout
mixing were operated. A written advance notification was issued to the EPD on
13 July 2017 regarding the aforesaid emergency road repairing works. In view of
the public concern, the Contractor of HY/2009/19 is recommended to adopt
additional noise mitigation measure for future emergency road repairing works,
if any, at night time hours around the concerned location. In response to the
public concern, the Contractor of HY/2009/19 would adopt the following
additional measures for future emergency road repairing works including: i) For
any emergency works requiring, for example, breaking or any other noisy
activities, wherever possible, temporary noise barrier or acoustic mat will be
use to fence of the line of sight between the noise emanating source and the
NSR, ii) Covering breaking head with acoustic mat to minimize noise if breaking
would be conducted and iii) complete noisy work as soon as possible to minimize
disturbance to the nearby residents.
ET confirmed with the Resident Site
Staff that unloading of fill material was conducted under Contract HK/2009/02
at WCR3 area (West of Wan Chai Ferry Pier) from 2300hrs on 19 July 2017 to
0540hrs on 20 July 2017. 1 no. of grab dredger was operated for the above
construction works. No construction activities or site operation was conducted
under Contract HK/2009/01 from 2300hrs on 19 July 2019 to 0700hrs on 20 July
2017.
According to the RSS site information,
unloading of fill material was conducted under Contract HK/2009/02 at WCR3 area
(West of Wan Chai Ferry Pier) from 2300hrs on 19 July 2017 to 0540hrs on 20
July 2017. 1 no. of grab dredger was operated for the above construction works
and relevant Construction Noise Permit GW-RS0348-17 was in place and noise
barrier with surface mass density of not less than 5kg/m2 was provided to the
power generating part of the grab dredger operated from 2300hrs on 19 July 2017
to 0540hrs on 20 July 2017. Meanwhile, no construction activities or site
operation was conducted under Contract HK/2009/01 from 2300hrs on 19 July 2019
to 0700hrs on 20 July 2017.
In view of the public concern, the
Contractor of HK/2009/02 was reminded to upkeep the site control system for
construction works carried out during restricted hours and night time for
Construction Noise Permit compliance and maintain regular maintenance of the
plant and equipment deployed to avoid potential nuisance to the nearby public.
ET confirmed with the Resident Site
Staff that breaking works and backfilling works were conducted under Contract
HK/2009/02 at the concerned location on 25 July 2017 afternoon.
Dust mitigation measures including water
spraying was implemented for the above construction activities on 25 July 2017
at the concerned location.
According to the RSS site information,
breaking works and backfilling works were conducted under Contract HK/2009/02
at the concerned location on 25 July 2017 afternoon while dust mitigation
measures including water spraying was implemented for the above construction
activities on 25 July 2017 at the concerned location. During Environmental Team
ad hoc inspection conducted on 26 July 2017, water spraying was found
insufficient to mitigate the extended area of breaking operation and
construction dust impact to surroundings public area was observed.
Subsequently, Contractor of HK/2009/02 was reminded to enhance the dust
suppression measure for the dust generating works.
In response to the observed
environmental concern, the Contractor of HK/2009/02 has strengthened the water spraying
coverage to all breaking operation area and haul road to minimize the potential
dust impact. Follow up inspection was conducted by Environmental Team on 27
July 2017 and no further dust impact was observed.
1.1.1.
Lam
Geotechnics Limited (LGL) has been appointed to work as the Environmental Team
(ET) under Environmental Permit no. EP-364/2009/E and Further Environmental
permit nos. FEP-01/364/2009,
FEP-02/364/2009, FEP-05/364/2009/A, FEP-06/364/2009/A, FEP-07/364/2009/D, FEP-09/364/2009/B, FEP-10/364/2009/B, FEP-11/364/2009/B
and FEP-12/364/2009/D to
implement the Environmental Monitoring and Audit (EM&A) programme as stipulated
in the EM&A Manual of the approved Environmental Impact Assessment (EIA)
Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register
No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for
Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001).
1.1.2.
This
report presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.3 of
EM&A Manual and “Environmental Monitoring and Audit Requirements”
under Particular Specification Section 27.
1.1.3. This report documents the finding of EM&A
works during the period from 27 May 2017 to 26 August 2017.
Section 1 Introduction – details the scope and structure of the
report.
Section 2 Project Background – summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section 3 Monitoring Requirements – summarizes all monitoring parameters,
monitoring locations, monitoring frequency, duration and action plan.
Section 4 Monitoring Results – summarizes the monitoring results
obtained in the reporting period.
Section 5 Compliance Audit – summarizes the auditing of monitoring results, all
exceedances environmental parameters.
Section 6 Complaints,
Notification of summons and Prosecution – summarizes the cumulative
statistics on complaints, notification of summons and prosecution
Section 7 Cumulative
Construction Impact due to the Concurrent Projects – summarizes the
relevant cumulative construction impact due to the concurrent activities of the
concurrent Projects.
Section 8 Conclusion
2.1.1.
“Wan
Chai Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai
Bypass and Island Eastern Corridor Link” (hereafter called “the Project”) are
Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap.
499) (EIAO). The Environmental Impact
Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The
key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan
Chai North and North Point for construction of the Central-Wan Chai Bypass and
Island Eastern Corridor Link (CWB). Land formed under the project will be
developed as a world-class waterfront promenade joining that at the new Central
waterfront for public enjoyment.
2.1.3.
There
is a compelling and present need for the CWB to provide relief to the very
congested
2.2.1.
Design and Construction of Central – Wan Chai
Bypass and Island Eastern Corridor Link under the Project involves the
construction and operation of a trunk road and its road tunnel more than 800m
in length between portals that is shown at Figure 2.1.
2.2.2.
The
study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB)
and Island Eastern Corridor Link (IECL) includes:
·
A dual three-lane trunk road, approximately 4.5 km
in length, and tunnel approximately 3.7 km in length defined from the
connection with the existing Rumsey Street Flyover in Central, through to a
connection with the existing Island Eastern Corridor to the east of the
Causeway Bay Typhoon Shelter (CBTS);
·
The Central Interchange near the Rumsey Street
Flyover to provide road connections to the Central area;
·
Tunnel control buildings and ventilation buildings;
·
Slip roads to connect the CWB to the local road
system in the Wan Chai North and
·
Associated road lighting, road signing, traffic
control and surveillance system; and
·
Other associated works.
2.2.3.
The
project also contains various Schedule 2 DPs that, under the EIAO, require
Environmental Permits (EPs) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five
individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table 2.1 Schedule 2 Designated Projects under this
Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due
to the multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be
commenced. Contractors of individual
contracts will be required by the EP holder to apply Further Environmental
Permits such
that the impact monitoring stations are sub-divided accordingly to facilitate
the implementation of EM&A programme and to streamline the EM&A
reporting for individual FEP holders correspondingly.
2.3.2.
In
the reporting period, all the contracts were commenced and contract no.
04/HY/2006 had been completed. The details of individual contracts are
summarized in Table2.2.
Table 2.2 Details of Individual Contracts under the
Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction Commencement Date |
HY/2009/17 |
Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced
piling works. |
DP1 |
5 October 2010 (Completed) |
HY/2009/18 |
Central – Wan Chai Bypass (CWB) – Central Interchange |
DP1 |
21 |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 (Completed) |
HK/2009/01 |
Wan Chai Development Phase II – Central – Wan Chai Bypass at |
DP1, DP2 |
25 August 2011 |
HK/2009/02 |
Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai
East(CWB Tunnel) |
DP1 |
26 |
HY/2009/15 |
Central-Wanchai Bypass – Tunnel ( |
DP1 |
13 July 2011 |
HY/2009/19 |
Central – Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 (Completed) |
HK/2012/08 |
Wan Chai Development Phase II- Central-Wan Chai
Bypass at Wan Chai West |
DP1,DP2, DP3 |
10 March 2014 |
HY/2010/08 |
Central- Wanchai Bypass Tunnel – Tunnel (Slip
Road 8) |
DP1, DP2, DP3 |
21 March 2013 |
HY/2011/08 |
Central - Wan Chai Bypass (CWB) –Tunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning |
DP1 |
8 October 2014 |
2.3.3.
The construction works of Contract no.
04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street under FEP-04/364/2009/A was completed, and the FEP was surrendered by
the Contractor on 11 February 2011.
2.3.4.
Construction of bored pile E3B under HY/2009/17 was confirmed
completed and the respective work area under FEP-03/364/2009 was handover and inspected
under HY/2009/19 from 19 Dec 2012 onwards. Subsequently, the FEP-03/364/2009
was surrendered by the Contractor on 28 March 2013.
2.3.5.
Construction works under HK/2010/06 was confirmed completed and
the respective work area under FEP-08/364/2009/A was handover and inspected
under HK/2012/08 from 22 Sep 2014 onwards. Subsequently, the FEP-08/364/2009/A
was surrendered by the Contractor on 3 October 2014.
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively.
For the construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure 2.2. Key
personnel and contact particulars are summarized in Table 2.3.
Table
2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer’s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer’s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3916 1818 |
3529 2829 |
|
Chun
Wo – Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Site Agent |
Mr. Andy Yu |
9648 4896 |
2634 1626 |
Construction Manager |
Mr. Terry Wong |
9757 9846 |
|||
Construction
Manager |
Mr.
Terry Tsang |
6683
9394 |
|||
Chun Wo – CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. Paul Yu |
3658-3002 |
2827 9996 |
Environmental Officer |
Mr. C.P. Ho |
9191 8856 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570 8013 |
Deputy Project Manager |
Mr. William Luk |
9456 9819 |
|||
Site Agent |
Mr. David Lau |
3758 8879 |
|||
Deputy Site Agent |
Mr. Eric Fong |
6191 9337 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
3757 8218 |
|||
Assistant Environmental Officer |
Mr. James Chan |
3757 8217 |
|||
Leighton Contractors (Asia) Limited |
Contractor under Contract no. HY/2009/18 |
Site Agent |
Mr. Jimmy Chu |
2214
7700 |
2140 6799 |
Environmental Officer |
Mr. Chris Chan |
2823
1161 |
|||
Assistant Environmental Engineer |
Mr. Christy So |
3937
1065 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Contractor’s
Representative |
Mr. Rex Chan |
3557
6371 |
2566 2192 |
Environmental Officer |
Mr. Andy Mak |
3557 6215 |
|||
China State- Leader JV |
Contractor under Contract no. HK/2012/08 |
Project
Director |
Mr. C.N.
Lai |
9137
1811 |
2877
1522 |
Project
Manager |
Mr. Eddie
Chung |
9193
8871 |
|||
Site
Agent |
Mr. Keith
Tse |
9095
7922 |
|||
Environmental
Officer |
Mr. James
MA |
9130
9549 |
|||
Environmental
Supervisor |
Mr. Y.L.
Ho |
6050
4919 |
|||
China |
Contractor under Contract no.HY/2010/08 |
Project
Director |
Cheung
Kit Cheung |
3557
6399 |
3465 2899 |
Project
Manager |
Chan
Ying Lun |
9812
0592 |
|||
Deputy
Project Manager |
Chris
Leung |
3467
4299 |
|||
Site
Agent |
Mr. Francis Suen |
3467
4277 |
|||
Environmental
Officer |
Mr. Gabriel
Wong |
3557
6464 |
|||
Assistant
Environmental Officer |
Mr. Desmond
Ho |
3557
6470 |
|||
Leighton Joint Venture |
Contractor under Contract no. HY/2011/08 |
Project
Manager |
Paul
Evans |
2823 1111 |
21406799 |
Site
Agent |
Colman Wong |
9730 0806 |
|||
Environmental
Officer |
Malcom
Leung |
3973 0850 |
|||
Environmental
Supervisor |
Christy So |
3973 1065 |
|||
Lam Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
RAMBOLL ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent
Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
2.5.1.
Major construction activities for Contract no.
HY/2009/18 have been commenced on 21
Table 2.4 Principal Work Activities
for Contract no. HY/2009/18
June
2017 |
July
2017 |
August 2017 |
Drainage works
Road works
Landscaping works
Maintenance works |
Drainage works
Road works
Landscaping works
Maintenance works |
Landscaping works
Maintenance works |
2.5.2. Major
construction activities for Contract no. HK/2009/01 have been commenced on 25
August 2011. During this reporting period, the principal work activities are
summarized in Table2.5:
Table 2.5 Principal Work Activities
for Contract no. HK/2009/01
June
2017 |
July
2017 |
August 2017 |
Reinstatement of amenity area
Road and Drain works |
Reinstatement of amenity area
Road and Drain works |
Reinstatement of amenity area
Road and Drain works |
2.5.3. Major
construction activities for Contract no. HK/2009/02 have been commenced on 26
Table 2.6 Principal Work Activities
for Contract no. HK/2009/02
June
2017 |
July
2017 |
August 2017 |
Rectification works for the defects recorded in the inspection for the
end of maintenance period of Observation Deck and Staircase ST-01
Rectification works for cracks/joints with water leakage inside OHVD
cells was completed.
Rebar fixing and formwork at Hung Hing Road Flyover approach ramp bay
1 base slab
Rebar fixing and formwork at Hung Hing Road Flyover approach ramp bay
2 base slab
Backfilling works
Cleaning of cross road duct
Rectification works against water leakage and remedial works against
concrete defects of the tunnel structure
Outstanding works inside tunnel.
Concreting for roadside barrier
Erection of scaffolding for construction of top slab
Tunnel top slab
Dismantling of scaffolding.
Trial pit works for sewage works at Wan Shing Street
Rectification works for uneven road surface at Hung Hing Road |
Rectification works for the defects recorded in the inspection for the
end of maintenance period of Observation Deck and Staircase ST-01
Rectification works for cracks/joints with water leakage inside OHVD
cells
Concreting of Hung Hing Road Flyover approach ramp bay 3 base slab
Rebar fixing and formwork at Hung Hing Road Flyover approach ramp bay
1 base slab
Rebar fixing and formwork at Hung Hing Road Flyover approach ramp bay
2 wall
Backfilling works up to +4.0mPD inside cofferdam
Remedial work for cross road duct
Rectification works against water leakage and remedial works against
concrete defects of the tunnel structure
Outstanding works inside tunnel
Concreting for roadside barrier
Removal of scaffolding and formwork inside tunnel
Removal of silo tank
Waterproofing and screeding works on top of tunnel
Removal of strut and removal of waling
Reinstatement of temporary access opening at Bay 7
Breaking of D-Wall panel
Backfilling work for the area to be handed over to MTR SCL 1123
Sewage works at Wan Shing Street
Rectification works for uneven road surface at Hung Hing Road |
Removal of the existing sheet piles along the north face of WSD Salt
Water Pumping Station
Remedial works for the sewer between manholes FMH2 and CP4 was in
progress.
5% construction of the top slab inside the access shaft of Tunnel
Portion 2
100% of rebar fixing and formwork at Hung Hing Road Flyover approach
ramp bay 1 base slab
Construction of Hung Hing Road Flyover approach ramp bay 2 structural wall
Approx. 25% remedial work for cross road duct
Approx. 90% rectification works against water leakage and remedial
works against concrete defects of the tunnel structure
Concreting for roadside barrier
Removal of scaffolding and formwork inside tunnel
Removal of strut and waling
Reinstatement of temporary access opening at Bay 7
Breaking of all D-Wall panel
100% of backfilling work for the area to be handed over to MTR SCL
1123
Sewage works at Wan Shing Street
Rectification works for faded road marking at temporary Hung Hing Road
Flyover |
2.5.4. Major
construction activities for Contract no. HY/2009/15 have been commenced on 13
July 2011. During this reporting period, the principal work activities are
summarized in Table 2.7:
Table 2.7 Principal Work Activities
for Contract no. HY/2009/15
June
2017 |
July
2017 |
August 2017 |
Remedial works inside tunnel structure at Mined Tunnel, TS4, TPCWAE
and TPCWAW
Reinstatement work at the PRE Office car park area |
Remedial works inside tunnel structure at Mined Tunnel, TS4, TPCWAE
and TPCWAW
Reinstatement work at the PRE Office car park area |
Remedial works of landing step at HY/2009/15 office |
2.5.5. Major
construction activities for Contract no. HY/2009/19 have been commenced on
March 2011. During this reporting period, the principal work activities are
summarized in Table 2.8:
Table 2.8 Principal Work Activities
for Contract no. HY/2009/19
June
2017 |
July
2017 |
August 2017 |
Approach ramp sheet piling, pre-bored piling and top soil removal works
Bridge Construction
Pier 30-32 Cap Construction
IEC noise enclosure/barrier installation
Excavation / Construction of retaining wall
FEHD Metal Roof Construction
Pre-bored H-piles for Approach Ramp Phase 2 Construction
Hing Fat Street modification works |
Approach ramp sheet piling, pre-bored piling and top soil removal works
Approach ramp structure Construction.
Bridge Construction
Pier 30-32 Cap Construction
Excavation / Construction of retaining wall
FEHD Metal Roof Construction
Pre-bored H-piles for Approach Ramp Phase 2 Construction
Hing Fat Street road and drainage works |
Approach ramp sheet piling and
top soil removal works
Approach ramp structure Construction.
Bridge Construction
Pier 30-32 Cap Construction
Excavation / Construction of D12 Abutment &retaining wall
FEHD Metal Roof Construction and drainage works
Pre-bored H-piles for Approach Ramp Phase 2 Construction
Hing Fat Street road and drainage works
Oil street drainage works |
2.5.6.
Major construction activities for
Contract no. HK/2012/08 have been commenced on March 2013. During the reporting
period, the principal work activities are summarized in Table 2.9
Table 2.9 Principal Work Activities for Contract no. HK/2012/08
June
2017 |
July
2017 |
August 2017 |
Grouting
Construction of Slip Road 1
Construction of drainage |
Construction of Slip Road 1
Construction of drainage
Asphalt paving of A2 Road |
Construction of Slip Road 1
Construction of drainage
Asphalt paving of A2 Road |
2.5.7.
Major construction activities for Contract no. HY/2010/08 have been commenced
on March 2013. During the reporting period, the principal work activities are
summarized in Table 2.10
Table 2.10 Principal Work Activities for Contract no. HY/2010/08
June
2017 |
July
2017 |
August 2017 |
Tree protection works next to existing BGO,
Drainage improvement works,
Utility diversion works,
Retaining wall works
ELS works,
Construction works for subway extension |
Tree protection works next to existing BGO,
Drainage improvement works,
Utility diversion works,
Retaining wall works
ELS works,
Construction works for subway extension |
Tree protection works next to existing BGO,
Drainage improvement works,
Utility diversion works,
Retaining wall works
ELS works,
Construction works for subway extension |
2.5.8.
Contract no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning
under FEP-11/364/2009B. During the reporting period, the principal work
activities are summarized in Table 2.11
Table 2.11 Principal
Work Activities for Contract no. HY/2011/08
June
2017 |
July
2017 |
August 2017 |
Construction of Ventilation Buildings, inclusive of Administration
Building, Central Ventilation Building, East Ventilation Shaft/Building, West
Ventilation Building
Construction of Tunnel Thermal Barrier
Installation of Electricals and Mechanicals
Installation of Tunnel Features |
Construction of Ventilation Buildings, inclusive of Administration
Building, Central Ventilation Building, East Ventilation Shaft/Building, West
Ventilation Building
Construction of Tunnel Thermal Barrier
Installation of Electricals and Mechanicals
Installation of Tunnel Features |
Construction of Ventilation Buildings, inclusive of Administration
Building, Central Ventilation Building, East Ventilation Shaft/Building, West
Ventilation Building
Construction of Tunnel Thermal Barrier
Installation of Electricals and Mechanicals
Installation of Tunnel Features |
2.5.9.
Implementation status of the recommended mitigation measures
during this reporting period is presented in Appendix 2.1.
3.1.1.
The
noise monitoring stations for the Project are listed and shown in Table
3.1 and Figure 3.1. Appendix 3.1 shows
the established Action/Limit Levels for the monitoring works.
Table
3.1 Noise Monitoring Station
Station |
Description |
M1a* |
Footbridge at Ex-Harbour Road Sports Centre |
M2b |
Noon Gun
Area |
M3a |
Tung Lo Wan
Fire Station |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
M7e* |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
M8** |
City Hall |
Remark*: Location ID
has been updated from M7 to M8 for City Hall
Remark**: M7e has
become a reference station starting from 7 Aug 2012
Remarks***: The
location ID of monitoring station M1a was updated as “Footbridge for Ex-Harbour
Road Sports Centre” in May 2017.
Real time Noise Monitoring Stations
3.1.2.
The
noise monitoring stations for the Project are listed and shown in Table 3.2 and Figure 3.1.. Appendix 3.1 shows the established Action/Limit Levels for
the monitoring works.
Table 3.2 Real Time Noise
Monitoring Station
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong Transport Section Whitefield Depot |
North Point |
RTN2a* |
Electric Centre |
North Point |
RTN3 |
Po Leung Kuk Yu Lee Mo Fan
Memorial School |
Tin Hau |
RTN4 |
|
Remarks*: RTN2 was
relocated from Oil Street Community Liaison Centre to Electric Centre on 05 Oct
2012 and re-designated as RTN2a.
Noise Monitoring
Parameters, Frequency and Duration
3.1.3.
The construction noise level shall be measured in terms of
the A-weighted equivalent continuous sound pressure level (Leq). Leq (30
minutes) shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For
all other time periods, Leq (5 minutes) shall be employed for
comparison with the Noise Control Ordinance (NCO) criteria.
Supplementary information for data auditing, statistical results such as L10
and L90 shall also be obtained for reference.
3.1.4.
Noise
monitoring shall be carried out at all the designated monitoring stations. The
monitoring frequency shall depend on the scale of the construction activities.
The following is an initial guide on the regular monitoring frequency for each
station on a weekly basis when noise generating activities are underway:
·
One
set of measurements between 0700 and 1900 hours on normal weekdays.
3.1.5.
Real
time noise shall be carried out at the designated monitoring stations. The
following is an initial guide on the regular monitoring frequency for each
station on a 24 hours daily basis when noise generating activities are
underway:
·
One
set of measurements between 0700 and 1900 hours on normal weekdays.
·
One
set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and
2300 hours on public holidays.
·
One
set of measurements between 2300 and 0700 hours on next day on everyday.
3.1.6.
If
construction works are extended to include works during the hours of 1900 –
0700 as well as public holidays and Sundays, additional weekly impact
monitoring shall be carried out during respective restricted hours periods.
Applicable permits under NCO shall be obtained by the Contractor.
Monitoring Equipment
3.1.7.
As
referred to in the Technical Memorandum ™ issued under the NCO, sound level
meters in compliance with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be
used for carrying out the noise monitoring. Immediately prior to and following
each noise measurement the accuracy of the sound level meter shall be checked
using an acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agree to within 1.0 dB.
3.1.8.
Noise
measurements shall not be made in fog, rain, wind with a steady speed exceeding
5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with
a portable wind speed meter capable of measuring the wind speed in m/s.
3.1.9.
The
sound level meter shall be checked using an acoustic calibrator generating a
known sound pressure level at a known frequency before deployment to the site
and during each site visit. Measurements may be accepted as valid only if the
calibration level from before and after the noise measurement agree to within
1.0 dB.
Air Quality Monitoring
Stations
3.2.1. The air quality monitoring stations for the Project
are listed and shown in Table 3.3 and Figure 3.1. Appendix 3.1 shows the established
Action/Limit Levels for the monitoring works.
Table
3.3 Air quality monitoring
Stations
Station ID |
Monitoring
Location |
Description |
CMA1b |
Harbour Grand Hotel
Boundary Wall |
North Point |
CMA2a |
|
|
CMA3a |
CWB PRE Site Office |
|
CMA4a |
Society for the
Prevention of Cruelty to Animals |
Wan Chai |
CMA5b |
Pedestrian Plaza** |
Wan Chai |
MA1e |
International Finance Centre (Eastern End of Podium) |
Central |
MA1w |
International Finance Centre (Western End of Podium) |
Central |
Remarks*: The location ID of monitoring
station CMA1b was updated as “Oil Street Site Office” in
Remarks**: With respect to the area handover, the air
quality monitoring station CMA5a at Children Playgrounds opposite to the
Pedestrian Plaza was relocated to the Pedestrian Plaza on 3 December 2014. The
station reference and location ID of the air quality monitoring station CMA5a
was updated as CMA5b and Pedestrian Plaza respectively.
Air quality monitoring
Parameters, Frequency and Duration
3.2.2. One-hour and 24-hour TSP levels should be measured
to indicate the impacts of construction dust on air quality. The 24-hour TSP
levels shall be measured by following the standard high volume sampling method
as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part
50), Appendix B.
3.2.3. All relevant data including temperature, pressure,
weather conditions, elapsed-time meter reading for the start and stop of the
sampler, identification and weight of the filter paper, and any other local
atmospheric factors affecting or affected by site conditions, etc., shall be
recorded down in detail.
3.2.4. For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
Sampling Procedure and
Monitoring Equipment
3.2.5. High volume samplers (HVSs) in compliance with the
following specifications shall be used for carrying out the 1-hour and 24-hour
TSP monitoring:
·
0.6
– 1.7 m3 per minute adjustable flow range;
·
Equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours
operation;
·
Installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
·
Capable
of providing a minimum exposed area of 406 cm2;
·
Flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
·
Equipped
with a shelter to protect the filter and sampler;
·
Incorporated
with an electronic mass flow rate controller or other equivalent devices;
·
Equipped
with a flow recorder for continuous monitoring;
·
Provided
with a peaked roof inlet;
·
Incorporated
with a manometer;
·
Able
to hold and seal the filter paper to the sampler housing at horizontal
position;
·
Easily
changeable filter; and
·
Capable
of operating continuously for a 24-hour period.
3.2.6. Initial calibration of dust monitoring equipment
shall be conducted upon installation and thereafter at bi-monthly intervals.
The transfer standard shall be traceable to the internationally recognized
primary standard and be calibrated annually. The concern parties such as IEC
shall properly document the calibration data for future reference. All the data
should be converted into standard temperature and pressure condition.
3.2.7. Laboratory Measurement / Analysis
3.2.8. A clean laboratory with constant temperature and
humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
3.2.9. Filter paper of size 8” x 10” shall be labelled
before sampling. It shall be a clean filter paper with no pinholes, and shall
be conditioned in a humidity-controlled chamber for over 24-hours and be
pre-weighed before use for the sampling.
3.2.10. After sampling, the filter paper loaded with dust
shall be kept in a clean and tightly sealed plastic bag. The filter paper shall
then be returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
readout down to 0.1 mg. The balance shall be regularly calibrated against a
traceable standard.
3.2.11. All the collected samples shall be kept in a good
condition for 6 months before disposal.
4.0.1. Per EPD’s letter
dated 3 Aug 2012 (received by ET on 6 Aug 2012 through HyD), noise monitoring
at M8 – City Hall commenced on 7 Aug 2012, and the monitoring station M7e –
International Finance Centre (Eastern Podium) has become a reference station
starting from 7 Aug 2012.
4.0.2. Due to safety
concerns, the monitoring location for M4b – Victoria Centre has been finely
adjusted from 7 June 2012.
4.0.3. Monitoring for report of review baseline noise
level was performed from 11
4.0.4. The environmental monitoring will be implemented
based on the division of works areas of each designed project managed under
different contracts with separate FEP applied by individual contractors. Overall layout showing work areas of various
contracts, latest status of work commencement and monitoring stations is shown
in Figure
2.1 and Figure 3.1. The monitoring results
are presented in according to the Individual Contract(s).
4.0.5. In the reporting period, the concurrent contracts are
as follows:
Contract
no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (
Contract
no. HY/2009/18 – Central –Wanchai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
Contract
no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link under FEP-07/364/2009
Contract
no. HK/2009/01 –Wanchai Development Phase II – Central –Wanchai Bypass at Hong
Kong Convention and Exhibition Centre under FEP-02/364/2009
Contract
no. HK/2009/02 Wanchai Development Phase II – Central- Wanchai Bypass at Wanchai
East under FEP-01/364/2009
Contract
no. HK/2012/08 – Wan Chai Development Phase II – Central- Wan Chai Bypass at
Wan Chai West under FEP-09/364/200/B
Contract
no. HY/2010/08 – Central and WanChai Bypass – Slip road 8 Section under
FEP-10/364/2009/B
Contract no. HY/2011/08 –Central - Wan
Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning under FEP-11/364/2009/B
Contract no.
HY/2009/18 – Central – Wanchai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
4.1.1.
Noise
monitoring for the Central Interchange works under contract no. HY/2009/18 was
commenced on 22
Table
4.1
Noise Monitoring Station for Contract no. HY/2009/18
Station |
Description |
*M7e |
International Finance Centre (Eastern End of Podium) |
M7w |
International Finance Centre (Western End of Podium) |
M8 |
City Hall |
* Remark: M7e has become a reference station starting from 7 Aug 2012
4.1.2. No exceedance was recorded in this
reporting quarter.
4.1.3. Noise
monitoring results measured in this reporting period are reviewed and
summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 4.1.
Contract no. HK/2009/01 - Wanchai Development Phase
II - Central - Wanchai Bypass at Hong Kong Convention and Exhibition Centre -
Tunnel Works under FEP-02/364/2009 and Contract no. HK/2009/02 - Wanchai
Development Phase II - Central - Wanchai Bypass at Wanchai East (CWB Tunnel)
under FEP-01/364/2009
4.1.4.
The
commencement of construction works for Contract no. HK/2009/01 under
FEP-02/364/2009 is on 25 August 2011
and HK/2009/02 under FEP-01/364/2009 is on 26
Table
4.2
Noise
Monitoring Stations
for Contract nos. HK/2009/01 and HK/2009/02
Station |
Description |
M1a |
Footbridge at Ex-Harbour Road Sports Centre |
Reporting period of June 2017
4.1.5.
Five limit level exceedances were recorded at M1a – Footbridge for
Ex-Harbour Road Sports Centre on 31 May 2017 and 08, 13, 22 and 26 June 2017 in
the reporting period.
4.1.6.
No Construction works was conducted under Contract HK/2009/01 around the
monitoring station on 31 May 2017 and 08, 13, 22 and 26 June 2017 in the reporting
period, non WDII-CWB Projects construction works were observed on 31 May 2017
and 08, 13, 22 and 26 June 2017 during the monitoring period as the major noise
contribution. Hence, the exceedances were considered as non-Project related.
4.1.7.
Despite rebar fixing, and formwork fixing works was conducted on 31 May
2017 and 13 and 26 June 2017 under Contract HK/2009/02, and concreting works
was conducted on 08 and 22 June 2017 under Contact HK/2009/02, non WDII-CWB
Projects construction works was observed on 31 May 2017 and 08, 13, 22 and 26
June 2017 during monitoring period and observed as the major noise
contribution. Hence, the exceedances were considered as non-Project related.
Reporting period of July 2017
4.1.8.
Four limit level exceedances were recorded at M1a – Footbridge for
Ex-Harbour Road Sports Centre on 07, 13, 20 and 26 July 2017 in the reporting period.
4.1.9.
After checking with Contractor of HK/2009/01, no construction works was
conducted under Contract HK/2009/01 around the monitoring station on 07, 13, 20
and 26 July 2017 in the reporting period, non WDII-CWB Projects construction
works were observed on 07 and 13 July 2017 during the monitoring period as the
major noise contribution while breaking works under Contract HK/2009/02 were
observed during the monitoring period on 20 and 26 July 2017 as the major noise
contribution. Hence, the exceedances were considered as non-Project related
under Contract HK/2009/01.
4.1.10.
After checking with Contractor of HK/2009/02, despite loading and
unloading conducted by crane was carried out under Contract HK/2009/02 on 07
July 2017 with breaking works conducted momentarily around the concerned
location during the time of measurement, the continuous sheet piling works next
to the monitoring station under non WDII-CWB Contractor was observed as the
major noise contribution during monitoring. In view of the momentary noise
emanated from breaking works was observed having no influential effect on the
noise level during the measurement, the exceedance was considered as non-Project
related.
4.1.11.
After checking with Contractor of HK/2009/02, despite concreting,
loading and unloading conducted by crane was carried out under Contract
HK/2009/02 on 13 July 2017, no major noise emanation was observed while
breaking works next to the monitoring station under non WDII-CWB Contractor was
observed as the major noise contribution during monitoring. In view of the
above, the exceedance was considered as non-Project related.
4.1.12.
After checking with Contractor of HK/2009/02, backfilling works, breaking
works and unloading of C&D material from barge to land were conducted under
Contract HK/2009/02 on 20 July 2017 around the monitoring location during the
time of measurement while bored pile works was observed conducted around the
monitoring location under non WDII-CWB Project at the time of measurement.
Despite the breaking works was considered as the major noise contribution
during the measurement hence the exceedance is considered as Project related,
the noise impact to the nearest NSR is further assessed considering the
boundary location of the monitoring station and no adverse noise impact to the
nearest NSR is identified. Nevertheless, in view of the recorded boundary
condition, the Contractor of HK/2009/02 is suggested to adopt additional noise
mitigation measures to avoid potential cumulative impact to nearby
stakeholders.
4.1.13.
After checking with Contractor of HK/2009/02, backfilling works,
breaking works and unloading of C&D material from barge to land were
conducted under Contract HK/2009/02 on 26 July 2017 around the monitoring
location during the time of measurement while bored pile works was observed
conducted around the monitoring location under non WDII-CWB Project at the time
of measurement. The breaking works under Contract HK/2009/02 was observed as
the major noise contribution during the measurement hence the exceedance is
considered as Project related and the adverse noise impact to the nearest NSR
was resulted. The Contractor of HK/2009/02 was requested to submit a remedial
action plan according to the Event and Action Plan. Remedial actions including
i) reduction in no. of breakers operating in parallel ii) operate breakers
intermittently and iii) covering of breaker head with acoustic material were
implemented by the Contractor on 03 August 2017.
Reporting period of August 2017
4.1.14.
One limit level
exceedances were recorded at M1a – Footbridge for Ex-Harbour Road Sports Centre
on 04 August 2017 in the reporting period.
4.1.15.
After checking with Contractor of HK/2009/01,
no construction works was conducted under Contract HK/2009/01 around the
monitoring station on 04 August 2017 in the reporting period, while breaking
works under Contract HK/2009/02 was observed on 04 August 2017 during the
monitoring period as the major noise contribution. Hence, the exceedances were
considered as non-Project related under Contract HK/2009/01.
4.1.16.
After checking with Contractor of HK/2009/02, backfilling work and breaking
works were conducted under Contract HK/2009/02 on 04 August 2017 around the
monitoring location during the time of measurement. Despite the breaking works
was considered as the major noise contribution during the measurement and the
exceedance is considered as Project related, the noise impact to the nearest
NSR is further assessed considering the boundary location of the monitoring
station and no adverse noise impact to the nearest NSR is identified.
Nevertheless, in view of the recorded boundary condition, the Contractor of
HK/2009/02 is suggested to adopt additional noise mitigation measures to avoid
potential cumulative impact to nearby stakeholders.
4.1.17. Noise monitoring results measured in this
reporting period are reviewed and summarized.
Details of noise monitoring results and graphical presentation can be
referred in Appendix 4.1.
Contract no.
HY/2009/15 - Central-Wanchai Bypass – Tunnel (
4.1.18.
The
commencement of construction works for Contract no. HY/2009/15 under
FEP-06/364/2009/A was on 13 July 2011. Noise
monitoring was commenced on 13 July 2011. The proposed
division of noise monitoring stations are summarized in Table 4.3 below.
Table
4.3
Noise Monitoring
Station for Contract nos. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
4.1.19.
No action or limit level exceedance was recorded in this reporting quarter.
4.1.20.
Details of noise monitoring results and
graphical presentation can be referred in Appendix 4.1.
Contract no. HY/2009/19 - Central -
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/D
4.1.21. Noise monitoring for the tunnel works under
contract no. HY/2009/19 was commenced on 24
Table 4.4
Noise Monitoring
Stations for Contract no. HY/2009/19
Station |
Description |
M4b |
Victoria Centre |
M5b |
|
M6 |
HK |
Reporting period of June 2017
4.1.22.
Three limit level exceedances were recorded at M6 – HK Baptist Church
Henrietta Secondary School on 08, 16 and 19 June 2017 in this reporting period.
4.1.23.
Despite lifting works by crane and falsework erection works were
conducted under Contract HY/2009/19 on 08 and 19 June 2017 respectively, no
construction activity was conducted on 16 June 2017 and traffic noise was
observed as the major noise contribution on 08, 16 and 19 June 2017. Hence, the
exceedances were considered as non-Project related.
Reporting period of July 2017
4.1.1
One limit level exceedance was recorded at M6
– HK Baptist Church Henrietta Secondary School on 18 July 2017 in this
reporting period.
4.1.2
Despite installation of launching girder was
conducted under Contract HY/2009/19 on 18 July 2017, nearby IEC traffic noise
was observed as the major noise contribution during monitoring period. Hence,
the exceedances were considered as non-Project related.
Reporting period of August 2017
4.1.24.
No action or limit level exceedance was
recorded in this reporting period.
4.1.25.
Noise monitoring results measured in this
reporting period are reviewed and summarized.
Details of noise monitoring results and graphical presentation can be
referred in Appendix 4.1 and the Notification of Exceedance can be
referred in Appendix 6.2.
Contract no. HY/2010/08 –
Central-Wanchai Bypass –Wanchai Bypass Tunnel (Slip Raod 8 Section) under FEP-09/364/2009/B
4.1.26. The commencement of construction works
for Contract no. HY/2010/08 under FEP-10/364/2009/B was on 02 September 2013.
Noise monitoring was commenced on 02 September 2013. The proposed divisions of
noise monitoring stations are summarized in Table 4.5 below.
Table 4.5
Noise Monitoring Stations
for Contract
no. HY/2010/08
Station |
Description |
M3a |
Tung Lo Wan Fire Station |
4.1.27.
No action or limit level exceedance was recorded in this reporting quarter.
4.1.28.
Noise monitoring results measured in this reporting period are reviewed
and summarized. Details of noise
monitoring results and graphical presentation can be referred in Appendix 4.1.
Contract no.
HY/2011/08 – Central - Wan Chai Bypass (CWB) – Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning
4.1.29. Noise monitoring for the Central
Interchange works under contract no. HY/2009/18 was commenced on 22 April
2011.The proposed division of noise monitoring stations for Contract no.
HY/2009/18 are summarized in Table 4.6 below:
Table 4.6 Noise
Monitoring Stations for
Contract no. HY/2011/08
Station |
Description |
M4b |
Victoria Centre |
*M7e |
International Finance Centre (Eastern End of
Podium) |
M7w |
International Finance Centre (Western End of
Podium) |
M8 |
City Hall |
* Remark:
M7e has become a reference station starting from 7 Aug 2012
4.1.30.
No action or limit level exceedance was recorded in this reporting quarter.
4.1.31.
Noise monitoring results measured in this reporting period are reviewed
and summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 4.1
Contract no.
HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under FEP-07/364/2009/D
4.2.1.
Real
time noise monitoring results measured in this reporting period are reviewed
and summarized. Details
of real time noise monitoring results and graphical presentation can be
referred to Appendix 4.2
4.2.2.
The
proposed division of noise monitoring stations are summarized in Table 4.7
below. Real time noise monitoring for major construction works under contract
no. HY/2009/19 was commenced on 24
Table 4.7 Real Time Noise
Monitoring Stations
for Contract no. HY/2009/19
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD Hong Kong Transport Section Whitefield Depot |
RTN2a |
North Point |
Electric Centre
(Replacement of RTN2) |
RTN3 |
North Point |
Pok Leung Kuk Yu |
RTN4 |
Tin Hau |
|
* Real time noise monitoring results and graphical presentation during
night time period are for information only.
*Real-time noise monitoring results and graphical presentation for RTN3
during restricted hours are for information only as no night classes were
conducted at the educational institute.
Reporting period of June
2017
4.2.3.
Limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport
Section Whitfield Depot was recorded during daytime on 21 June 2017 in the
reporting period. After checking with Contractor of HY/2009/19, no construction
works was conducted on 21 June 2017 during the monitoring period while adverse
weather condition was recorded during the monitoring period and considered as
the major noise contribution. Hence, the exceedances were considered as
non-Project related.
4.2.4.
Limit level exceedances were recorded at RTN2a- Hong Kong Electric
Centre was recorded during daytime on 21 June 2017 in the reporting period. After
checking with Contractor of HY/2009/19, no construction works was conducted on
21 June 2017 during the monitoring period while adverse weather condition was
recorded during the monitoring period and considered as the major noise
contribution. Hence, the exceedances were considered as non-Project related.
4.2.5.
Limit level exceedances were recorded at RTN3- Yu Lee Mo Fan Memorial
School was recorded during daytime on 13 and 21 June 2017 in the reporting
period. After checking with Contractor of HY/2009/19, despite erection of
U-beam structure was conducted on 13 June 2017, no major noise concern was
considered and no construction works was conducted on 21 June 2017 during the
monitoring period while adverse weather condition was recorded during the
monitoring period on 13 and 21 June 2017 and considered as the major noise
contribution. Hence, the exceedances were considered as non-Project related.
4.2.6.
No limit level exceedance was recorded at RTN4- Causeway Bay Community
Centre was recorded in the reporting period.
Reporting period of July
2017
4.2.1.
No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport Section
Whitfield Depot was recorded in the reporting period.
4.2.2.
Limit level exceedances were recorded at
RTN2a- Hong Kong Electric Centre was recorded during daytime on 24 July 2017 in
the reporting period. After checking with Contractor of HY/2009/19, trimming
bored pile head and sheet pile installation was conducted behind Administration
Building Structure while external wall maintenance work at HK Electric Centre
was recorded across the monitoring date and potentially contributed to the
recorded noise. In view of the above, the exceedances were considered as
non-Project related.
4.2.3.
Limit level exceedances were recorded at
RTN3- Yu Lee Mo Fan Memorial School was recorded during daytime on 08 July 2017
in the reporting period. After checking with Contractor of HY/2009/19, no
construction works was conducted during the monitoring period and the
exceedance is potentially contributed by nearby IEC traffic. Hence, the
exceedance was considered as non-Project related.
4.2.4.
No limit level exceedance was recorded at RTN4- Causeway Bay Community Centre
was recorded in the reporting period.
Reporting
period of August 2017
4.2.5.
No limit level exceedance
was recorded at RTN1-FEHD Hong Kong Transport Section Whitfield Depot was
recorded in the reporting period.
4.2.6.
Limit level exceedances were recorded at
RTN2a- Hong Kong Electric Centre was recorded during daytime on 10 August 2017 in
the reporting period. After checking with Contractor of HY/2009/19, concreting,
excavation and trimming bored pile head were conducted behind Administration
Building Structure while construction works under non-CWB construction site was
observed across August 2017 and potentially contributed to the recorded noise.
In view of the above, the exceedances were considered as non-Project related.
4.2.7.
Limit level exceedances were recorded at
RTN3- Yu Lee Mo Fan Memorial School was recorded during daytime on 23 August
2017 in the reporting period. After checking with Contractor of HY/2009/19, no
construction works was conducted during the monitoring period with respect to
the hoisting of the Typhoon Signal No.8 and the exceedance is considered to be
contributed by adverse weather condition. Hence, the exceedance was considered
as non-Project related.
4.2.8.
No limit level exceedance
was recorded at RTN4- Causeway Bay Community Centre was recorded in the reporting
period.
4.2.9.
Real
time noise monitoring results measured in this reporting quarter are reviewed
and summarized. Details of real time noise monitoring results and graphical
presentation can be referred to Appendix
4.2
Contract no.
HY/2011/08 – Central - Wan Chai Bypass (CWB) – Tunnel Buildings, Systems and
Fittings, and Works Associated with Tunnel Commissioning
4.2.10.
The proposed division of noise monitoring stations are summarized in Table
4.8 below. Real time noise monitoring for major construction works
under contract no. HY/2011/08 was commenced on 19 March 2015.
Table 4.8 Real
Time Noise
Monitoring Stations for Contract
no. HY/2011/08
Location ID |
District |
Description |
RTN1 |
Tin Hau |
FEHD
Hong Kong Transport Section Whitfield Depot |
RTN2a1 |
North Point |
Hong
Kong Electric Centre |
RTN4 |
Tin
Hau |
Causeway Bay Community Centre |
* Real time noise monitoring results and graphical presentation during
restrict hours and night time period are for information only and noise during
CNP period shall be controlled under NCO.
Remarks 1: With
respect to the possession of site area Portion Xa and Portion Xb since 7 March
2016 as confirmed by CWB RSS, real time
noise monitoring station RTN2a was associated with Contract no. HY/2011/08 from
07 March 2016 onwards
Reporting period of June 2017
4.2.11.
Limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport
Section Whitfield Depot was recorded during daytime on 21 June 2017 in the reporting
period. After checking with Contractor of HY/2011/08, no construction works was
conducted on 21 June 2017 during the monitoring period while adverse weather
condition was recorded during the monitoring period and considered as the major
noise contribution. Hence, the exceedances were considered as non-Project
related.
4.2.12.
Limit level exceedances were recorded at RTN2a- Hong Kong Electric
Centre was recorded during daytime on 21 June 2017 in the reporting period. After
checking with Contractor of HY/2011/08, no construction works was conducted on
21 June 2017 during the monitoring period while adverse weather condition was
recorded during the monitoring period and considered as the major noise
contribution. Hence, the exceedances were considered as non-Project related.
4.2.13.
No limit level exceedance was recorded at RTN4- Causeway Bay Community
Centre were recorded in the reporting period.
Reporting period of July 2017
4.2.14.
No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport
Section Whitfield Depot was recorded in the reporting period.
4.2.15.
Limit level exceedances were recorded at RTN2a- Hong Kong Electric
Centre was recorded during daytime on 24 July 2017 in the reporting period. After
checking with Contractor of HY/2011/08, despite concreting, rebar fixing,
formwork erection and excavation were conducted at Administration works area,
no particular noise impact was considered while external wall maintenance work
at HK Electric Centre was observed across the monitoring date and potentially
contributed to the recorded noise. In view of the above, the exceedances were
considered as non-Project related.
4.2.16.
No limit level exceedance was recorded at RTN4- Causeway Bay Community Centre
were recorded in the reporting period.
Reporting period of August 2017
4.2.1.
No limit level exceedance was recorded at
RTN1-FEHD Hong Kong Transport Section Whitfield Depot was recorded in the reporting
period.
4.2.2.
Limit level exceedances were recorded at
RTN2a- Hong Kong Electric Centre was recorded during daytime on 10 August 2017 in
the reporting period. After checking with Contractor of HY/2011/08, despite
rebar fixing, formwork erection and excavation were conducted at Administration
works area, no particular noise impact was considered while construction works
under non-CWB construction site was observed across August 2017 and potentially
contributed to the recorded noise. In view of the above, the exceedances were
considered as non-Project related.
4.2.3.
No limit level exceedance was recorded at
RTN4- Causeway Bay Community Centre were recorded in the reporting period.
4.2.4.
Real
time noise monitoring results measured in this reporting quarter are reviewed
and summarized. Details of real time noise monitoring results and graphical
presentation can be referred to Appendix
4.2
4.3.1 Due to extension of site boundary by
contractor of HY/2009/19, location of air quality monitoring station CMA1b –
Oil Street Community Liaison Centre has been finely adjusted on 21
Contract no.
HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central Interchange under
FEP-05/364/2009/A
4.3.2
Air quality monitoring for the Central
Interchange works under contract no. HY/2009/18 was commenced on 21 April 2011.
The proposed division of air quality monitoring stations are summarized in Table
4.9 below.
Table 4.9
Air quality monitoring
Stations for Contract no. HY/2009/18
Station |
Description |
MA1e |
International Finance Centre (Eastern End of Podium) |
MA1w |
International Finance Centre (Western End of Podium) |
4.3.3
No action or limit level exceedance was
recorded in the reporting period.
4.3.4
Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of air quality monitoring
results and graphical presentation can be referred in Appendix 4.3.
Contract no. HK/2009/01 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at
4.3.5
The
commencement of construction works for Contract no. HK/2009/01 under
FEP-02/364/2009 is on 25 August 2011. The
proposed division of air quality monitoring stations are summarized in Table
4.10 below.
Table 4.10
Air quality monitoring
Station for Contract no. HK/2009/01
Station |
Description |
CMA5b |
Pedestrian Plaza |
Reporting period
of June 2017
4.3.6
One 1hr TSP limit level exceedance was
recorded at CMA5b – Pedestrian Plaza on 03 June 2017 in the reporting period.
4.3.7
After checking with the Contractor of
HK/2009/01, no construction works was undertaken around the monitoring location
on the monitoring date under Contractor of HK/2009/01 and no particular
observation regarding air quality impact was observed during sampling while sweeping
works conducted directly at the monitoring station by Pedestrian Plaza
management office could potentially contribute to the elevated particulates
level in the vicinity of the monitoring equipment. Hence, the exceedance is
considered as not related to the Project.
Reporting period
of July 2017
4.3.8
No exceedance was recorded in the reporting
period.
Reporting period
of August 2017
4.3.9
One 1hr TSP limit level exceedance was
recorded at CMA5b – Pedestrian Plaza on 29 August 2017 in the reporting period.
4.3.10
After checking with the Contractor of
HK/2009/01, no construction works was undertaken around the monitoring location
on the monitoring date under Contractor of HK/2009/01 and no particular
observation regarding air quality impact was observed during sampling. Non
WDII-CWB Project construction activities and road traffic was observed opposite
to the monitoring station on the monitoring date. Meanwhile, gardening and
sweeping works conducted directly at the monitoring station by Pedestrian Plaza
management office was observed across the monitoring period and would
potentially contributed to the particulates level in the vicinity of the
monitoring equipment. Hence, the exceedance is considered as not related to the
Project.
4.3.11 Air quality monitoring results measured in this
reporting period are reviewed and summarized.
Details of air quality monitoring results and graphical presentation can
be referred in Appendix 4.3.
Contract no. HK/2009/02 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under
FEP-01/364/2009
4.3.12 The commencement of construction works for
HK/2009/02 under FEP-01/364/2009 is on 26
Table
4.11
Air quality monitoring
Station for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
4.3.13
No action or limit level exceedance was
recorded in the reporting period.
4.3.14 Air quality monitoring results measured in this
reporting period are reviewed and summarized.
Details of air quality monitoring results and graphical presentation can
be referred in Appendix
4.3.
Contract no.
HY/2009/15 - Central-Wanchai Bypass – Tunnel (
4.3.15
The
commencement of construction works for Contract no. HY/2009/15 under
FEP-06/364/2009/A was on 13 July 2011. The proposed division of air
quality monitoring stations are summarized in Table 4.12
below.
Table 4.12 Air quality monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB site office at Wanchai
Waterfront Promenade |
4.3.16
No action or limit level exceedance was
recorded in the reporting period.
4.3.17 Air quality monitoring results measured
in this reporting period are reviewed and summarized. Details of air quality monitoring results and
graphical presentation can be referred in Appendix 4.3.
Contract no.
HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link under FEP-07/364/2009/D
4.3.18 Air quality monitoring for the tunnel works was
commenced on 26
Table
4.13
Air quality monitoring
Stations
for Contract no. HY/2009/19
Station |
Description |
CMA1b |
Harbour
Grand Hotel Boundary Wall |
CMA2a |
|
Reporting period
of June 2017
4.3.19
One 1hr TSP limit level exceedance was
recorded at CMA1b – Harbour Grand Hotel Boundary Wall on 03 June 2017 in the reporting
period.
4.3.20
No construction works was undertaken around
the monitoring location on the monitoring date under Contractor of HY/2009/19
and no particular observation regarding air quality impact was observed during
sampling and dust mitigation measure including haul road and dusty surface
maintained in dampened condition were generally implemented. The exceedance was
considered to be non-project related and potentially contributed by localized
ambient condition and other environmental factor.
Reporting period
of July 2017
4.3.21
No exceedance was recorded in the reporting
period.
Reporting period
of August 2017
4.3.22
No exceedance was recorded in the reporting
period.
4.3.23
Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of air quality monitoring results and graphical presentation can
be referred in Appendix 4.3.
Contract
no. HK/2012/08- Wan Chai Development Phase II – Central-Wan Chai Bypass at Wan
Chai West under FEP-09/364/2009/B and FEP-12/364/2009/D
4.3.24
The commencement of construction works for
Contract no. HK/2012/08 under FEP-09/364/2009/C was on May 2014. Air quality
monitoring was commenced on 14 July 2011. The proposed division of air quality
monitoring stations are summarized in Table 4.14 below.
Table 4.14
Air quality monitoring
Station for Contract
no. HK/2012/08
Station |
Description |
CMA5b |
Pedestrian
Plaza |
Reporting period of June 2017
4.3.25
One 1hr TSP limit level exceedance was
recorded at CMA5b – Pedestrian Plaza on 03 June 2017 in the reporting period.
4.3.26
After checking with the Contractor of
HK/2012/08, despite manhole installation was undertaken around the monitoring
location on the monitoring date under Contractor of HK/2012/08 and no
particular observation regarding air quality impact was observed during
sampling while sweeping works conducted directly at the monitoring station by
Pedestrian Plaza management office could potentially contribute to the elevated
particulates level in the vicinity of the monitoring equipment. Hence, the
exceedance is considered as not related to the Project.
Reporting period of July 2017
4.3.27
No exceedance was recorded in the reporting
period.
Reporting period of August 2017
4.3.28
One 1hr TSP limit level exceedance was
recorded at CMA5b – Pedestrian Plaza on 29 August 2017 in the reporting period.
4.3.29
After checking with the Contractor of
HK/2012/08, no construction works was undertaken around the monitoring location
on the monitoring date under Contractor of HK/2012/08 and no particular
observation regarding air quality impact was observed during sampling. Non
WDII-CWB Project construction activities and road traffic was observed opposite
to the monitoring station on the monitoring date. Meanwhile, gardening and
sweeping works conducted directly at the monitoring station by Pedestrian Plaza
management office was observed across the monitoring period and would
potentially contributed to the particulates level in the vicinity of the
monitoring equipment. Hence, the exceedance is considered as not related to the
Project.
4.3.30
Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of air quality monitoring results and
graphical presentation can be referred in Appendix
4.3.
Contract no. HY/2010/08 – Central-Wanchai Bypass –Wanchai Bypass Tunnel
(Slip Road 8 Section) under FEP-09/364/2009/B
4.3.31
The commencement of construction works for
Contract no. HY/2010/08 under FEP-09/364/2009/B was on July 2014. Air quality
monitoring was commenced on 14 July 2011. The proposed division of air quality
monitoring stations are summarized in Table 4.15 below.
Table 4.15
Air quality monitoring
Station for Contract
no. HY/2010/08
Station |
Description |
CMA3a |
CWB
PRE Site Office |
4.3.32
No action or limit level exceedance was recorded
in the reporting period.
4.3.33
Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of air quality monitoring results and
graphical presentation can be referred in Appendix
4.3.
Contract no. HY/2011/08 – Central - Wan Chai
Bypass (CWB) – Tunnel Buildings, Systems and Fittings, and Works Associated
with Tunnel Commissioning
4.3.34
Air quality monitoring for the Central
Interchange works under contract no. HY/2011/08 was commenced on 21 April 2011.
The proposed division of air quality monitoring stations are summarized in Table
4.16 below.
Table 4.16 Air quality monitoring
Stations for Contract
no. HY/2011/08
Station |
Description |
MA1e |
International
Finance Centre (Eastern End of Podium) |
MA1w |
International
Finance Centre (Western End of Podium) |
CMA1b |
Oil
Street Site Office |
CMA2a |
Causeway
Bay Community Centre |
Reporting period of June 2017
4.3.35
One 1hr TSP limit level exceedance was
recorded at CMA5b – Pedestrian Plaza on 03 June 2017 in the reporting period.
4.3.36
After checking with the Contractor of
HY/2011/08, rebar and formwork fixing works was undertaken around the
monitoring location on the monitoring date under Contractor of HY/2011/08 and
no particular observation regarding air quality impact was observed during
sampling while sweeping works conducted directly at the monitoring station by
Pedestrian Plaza management office could potentially contribute to the elevated
particulates level in the vicinity of the monitoring equipment. Hence, the
exceedance is considered as not related to the Project.
4.3.37
One 1hr TSP limit level exceedance was
recorded at CMA1b – Harbour Grand Hotel Boundary Wall on 03 June 2017 in the reporting
period.
4.3.38
After checking with the Contractor of HY/2011/08,
rebar and formwork fixing works was undertaken around the monitoring location
on the monitoring date under Contractor of HY/2011/08 and no particular
observation regarding air quality impact was observed during sampling and dust
mitigation measure including hard paving of haul road were generally
implemented. The exceedance was considered to be non-project related and
potentially contributed by localized ambient condition and other environmental
factor.
Reporting period of July 2017
4.3.39
No exceedance was recorded in the reporting
period.
Reporting period of August 2017
4.3.40
One 1hr TSP limit level exceedance was
recorded at CMA5b – Pedestrian Plaza on 29 August 2017 in the reporting period.
4.3.41
Despite grouting, scabbling and indoor
plastering works was undertaken around the monitoring location on the
monitoring date at the under Contractor of HY/2011/08 and no particular
observation regarding air quality impact was observed during sampling and dust
mitigation measure include watering during scabbling were implemented. Non
WDII-CWB Project construction activities and road traffic was observed opposite
to the monitoring station on the monitoring date. Meanwhile, gardening and
sweeping works conducted directly at the monitoring station by Pedestrian Plaza
management office was observed across the monitoring period and would
potentially contributed to the particulates level in the vicinity of the
monitoring equipment. Hence, the exceedance is considered as not related to the
Project.
4.3.42
Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of air quality monitoring results and
graphical presentation can be referred in Appendix
4.3.
Contract no. HK/2009/01 - Wan Chai Development
Phase II - Central - Wan Chai Bypass at
4.4.1.
Inert
and non-inert C&D waste was disposed of in this reporting period. Details
of the waste flow table are summarized in Table 4.17.
Table
4.17 Details of Waste Disposal for Contract no. HK/2009/01
Inert C&D materials
disposed |
4.465 |
107988.315 |
TKO137, TM38 |
Inert C&D materials
recycled |
Nil |
98512.03 |
N/A |
Non-inert C&D
materials disposed |
18.4 |
5297.46 |
SENT Landfill |
Non-inert C&D
materials recycled |
Nil |
1285746 |
N/A |
Chemical waste disposed |
Nil |
10400 |
Kwun Kee (Chemical Waste Collector) |
Marine Sediment (Type 1- Open Seas
Disposal), m3 |
Nil |
11527 |
South of Cheung Chau |
Marine Sediment (Type 1 – Open Sea Disposal
(Dedicate Sites) & Type 2 – Confined Marine Disposal) , m3 |
Nil |
16261 |
East
of Cha Chau South
Brothers |
Contract no. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel)
under FEP-01/364/2009
4.4.2.
Inert and non-inert C&D waste were disposed of in this reporting
period. Details of the waste flow table are summarized in Table 4.18.
Table 4.18 Details of Waste Disposal for Contract no.
HK/2009/02
Inert C&D materials
disposed |
137.4 |
522303.81 |
TKO137, TM 38 |
Inert C&D materials
recycled |
Nil |
46520 |
WCR2 |
Non-inert C&D
materials disposed |
762 |
5178.32 |
SENT Landfill |
Non-inert C&D
materials recycled |
Nil |
N/A |
N/A |
Chemical waste disposed |
Nil |
17718 |
N/A |
Marine Sediment (Type 1
– Open Sea Disposal) , m3 |
Nil |
65663 |
South Cheung Chau |
Contract no. HY/2009/18 - Central - Wan Chai Bypass
(CWB) – Central Interchange under FEP-05/364/2009/A
4.4.3.
Inert and non-inert C&D waste was disposed of in this reporting
period. Details of the waste flow table are summarized in Table 4.19.
Table 4.19 Details of Waste Disposal for
Contract no. HY/2009/18
Inert C&D materials
disposed |
138.09 |
1415420.84 |
T.K.O. 137 |
Inert C&D materials
recycled |
Nil |
58787.05 |
N/A |
Non-inert C&D
materials disposed |
30.61 |
4397.23 |
SENT Landfill |
Non-inert C&D materials recycled (tonnes) |
Nil |
878.37 |
N/A |
Chemical waste disposed |
Nil |
6772 |
N/A |
Remarks:
The cumulative amount of inert C&D material disposed has been updated in
the reporting period.
Contract no. HY/2009/15 - Central-Wanchai Bypass –
Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A
4.4.4.
Inert and non-inert C&D waste was disposed of in this reporting
period. Details of the waste flow table are summarized in Table 4.20.
Table 4.20 Details of Waste Disposal for
Contract no. HY/2009/15
Inert C&D materials
disposed |
Nil Nil |
625200.92 245453.3 |
Tuen Mun Area 38 TKO137 FB |
Inert C&D materials
recycled |
Nil |
358660.77 |
HY/2009/11, ex-PCWA TS4 |
Non-inert C&D materials
disposed |
1.18 Nil |
4675.09 1.58 |
SENT Landfill WENT Landfiill |
Non-inert C&D
materials recycled |
Nil |
5496446.2 |
Xun Xiang Metal ware Skylight Recycle (paper) |
Chemical waste disposed |
Nil |
22755 |
Dunwell Group |
Marine Sediment
(Type1-Open Sea Disposal (Dedicate Sites) &Type 2 – Confined Marine
Disposal), m3 |
Nil |
5684 |
South of the Brothers |
Contract no. HY/2009/19 – Central –
Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
under FEP-07/364/2009/D
4.4.5.
Inert C&D materials was recycled non-inert C&D waste was disposed of in this reporting period. Details
of the waste flow table are summarized in Table 4.21.
Table 4.21 Details of Waste Disposal for
Contract no. HY/2009/19
Inert C&D materials
disposed |
36124.411 |
723118.33 |
N/A |
Nil |
82349.7 |
N/A |
|
Non-inert C&D
materials disposed |
234.89 |
6117.78 |
SENT Landfill |
Non-inert C&D
materials recycled |
Nil |
565.63 |
N/A |
Chemical waste disposed |
0.75 |
10.9 |
N/A |
Marine Sediment (Tunnel) (Type 1- Open Sea
Disposal), m3 |
Nil |
20556 |
South of Cheung Chau |
Marine Sediment (Tunnel) (Type 1- Open Sea
Disposal (Dedicated Sites) & Type 2 – Confined Marine Disposal), m3 |
Nil |
30751 |
East
of Sha Chau |
Contract no.
HK/2012/08 Wan Chai Development Phase II - Central-Wan Chai Bypass at Wan Chai
West under FEP-09/364/2009/B and FEP-12/364/2009/D
4.4.6.
No inert and Non-inert C&D wastes were
disposed of in this reporting period. Details of the waste flow table are
summarized in Table 4.22.
Table
4.22 Details of Waste Disposal for Contract no. HK/2012/08
Waste
Type* |
Quantity
this quarter, m3 |
Cumulative-to-Date,
m3 |
Disposal
/ Dumping Grounds |
Inert C&D materials disposed |
238 91 |
183316 116759 |
TKO137 TM38 |
Inert C&D materials recycled |
Nil |
Nil |
N/A |
Non-inert C&D materials disposed |
535 |
8172 |
N/A |
Non-inert C&D materials recycled |
NIL |
Nil |
N/A |
Chemical waste disposed |
NIL |
Nil |
N/A |
Marine Sediment (Type 1) Disposal, m3 |
Nil |
3145 |
South of Cheung Chau/ South of Brothers |
Remarks: The
quantity of inert C&D material disposed, recycled, non-inert C&D
material disposed, recycled are reported up to calendar month on 31 August
2017.
Remarks: The
amount of inert C&D material disposed in the reporting quarter at TM38 have
been clarified as 91m3 and the cumulative amount of inert C&D
material disposed at TM38 have been clarified as 116759m3.
Contract no. HY/2010/08
Central – Wan Chai Bypass (CWB) –
Tunnel (Slip Road 8) under FEP-10/364/2009/B
4.4.7.
No inert and Non-inert C&D wastes were
disposed of in this reporting period. Details of the waste flow table are
summarized in Table 4.23.
Table 4.23 Details
of Waste Disposal for Contract no. HY/2010/08
Waste Type* |
Quantity this quarter, m3 |
Cumulative-to-Date, m3 |
Disposal / Dumping Grounds |
Inert C&D
materials disposed |
396.32 Nil Nil 29.06 |
584332.17 262656.6 82911.8 72699.21 |
TM 38 WENT SENT TKO area 137 |
Inert C&D
materials recycled |
Nil |
Nil |
Nil |
Non-inert C&D
materials disposed |
843.45 |
5386.48 |
SENT |
Non-inert C&D
materials recycled |
Nil |
Nil |
Nil |
Chemical waste
disposed |
Nil |
1431 |
Nil |
Type 1 – Open Sea
Disposal |
Nil |
16368.4 |
East Sha Chau/ South Brothers Island |
Type 2 – Confined
Marine disposal |
Nil |
549.2 |
East Sha Chau |
Remarks: The cumulative
amount of non-inert C&D material and chemical waste disposed has been
clarified in the reporting quarter.
Contract no. HY/2011/08
Central –Central - Wan Chai Bypass
(CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning under FEP-11/364/2009B
4.4.8.
No inert and Non-inert C&D wastes were
disposed of in this reporting period. Details of the waste flow table are
summarized in Table 4.24.
Table
4.24 Details
of Waste Disposal for Contract no. HY/2011/08
Waste Type* |
Quantity this quarter, m3 |
Cumulative-to-Date, m3 |
Disposal / Dumping Grounds |
Inert C&D materials disposed |
659.16 |
1340.46 |
Nil |
Inert C&D materials recycled |
Nil |
Nil |
Nil |
Non-inert C&D materials disposed |
913.27 |
3539.32 |
Nil |
Non-inert C&D materials recycled |
Nil |
31.72 |
Nil |
Chemical waste disposed (kg) |
Nil |
3800 |
Nil |
5.0.1. The Event Action Plan for construction noise and air
quality are presented in Appendix 5.1.
Contract no. HY/2009/18 - Central - Wan Chai Bypass (CWB) – Central
Interchange under FEP-05/364/2009/A
5.1.1.
No action of limit level exceedance was
recorded in this reporting quarter.
Contract no. HK/2009/01 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Hong Kong Convention and
Exhibition Centre - Tunnel Works
Reporting period of June 2017
5.1.2.
Five limit level exceedances were recorded at M1a – Footbridge for
Ex-Harbour Road Sports Centre on 31 May 2017 and 08, 13, 22 and 26 June 2017 in
the reporting period.
5.1.3.
No Construction works was conducted under Contract HK/2009/01 around the
monitoring station on 31 May 2017 and 08, 13, 22 and 26 June 2017 in the reporting
period, non WDII-CWB Projects construction works were observed on 31 May 2017
and 08, 13, 22 and 26 June 2017 during the monitoring period as the major noise
contribution. Hence, the exceedances were considered as non-Project related.
Reporting period of July 2017
5.1.4.
Four limit level exceedances were recorded at M1a – Footbridge for
Ex-Harbour Road Sports Centre on 07, 13, 20 and 26 July 2017 in the reporting
period.
5.1.5.
After checking with Contractor of HK/2009/01, no construction works was
conducted under Contract HK/2009/01 around the monitoring station on 07, 13, 20
and 26 July 2017 in the reporting period, non WDII-CWB Projects construction
works were observed on 07 and 13 July 2017 during the monitoring period as the
major noise contribution while breaking works under Contract HK/2009/02 were
observed during the monitoring period on 20 and 26 July 2017 as the major noise
contribution. Hence, the exceedances were considered as non-Project related
under Contract HK/2009/01.
Reporting period of August 2017
5.1.6.
One limit level exceedances were recorded at M1a – Footbridge for
Ex-Harbour Road Sports Centre on 04 August 2017 in the reporting period.
5.1.7.
After checking with Contractor of HK/2009/01, no construction works was
conducted under Contract HK/2009/01 around the monitoring station on 04 August
2017 in the reporting period, while breaking works under Contract HK/2009/02
was observed on 04 August 2017 during the monitoring period as the major noise
contribution. Hence, the exceedances were considered as non-Project related
under Contract HK/2009/01.
Contract no. HK/2009/02 - Wan Chai
Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel)
Reporting period of June 2017
5.1.8.
Five limit level exceedances were recorded at M1a – Footbridge for
Ex-Harbour Road Sports Centre on 31 May 2017 and 08, 13, 22 and 26 June 2017 in
the reporting period.
5.1.9.
Despite rebar fixing, and formwork fixing works was conducted on 31 May
2017 and 13 and 26 June 2017 under Contract HK/2009/02, and concreting works
was conducted on 08 and 22 June 2017 under Contact HK/2009/02, non WDII-CWB
Projects construction works was observed on 31 May 2017 and 08, 13, 22 and 26
June 2017 during monitoring period and observed as the major noise
contribution. Hence, the exceedances were considered as non-Project related.
Reporting period of July 2017
5.1.10.
Four limit level exceedances were recorded at M1a – Footbridge for
Ex-Harbour Road Sports Centre on 07, 13, 20 and 26 July 2017 in the reporting
period.
5.1.11.
After checking with Contractor of HK/2009/02, despite loading and
unloading conducted by crane was carried out under Contract HK/2009/02 on 07
July 2017 with breaking works conducted momentarily around the concerned
location during the time of measurement, the continuous sheet piling works next
to the monitoring station under non WDII-CWB Contractor was observed as the
major noise contribution during monitoring. In view of the momentary noise
emanated from breaking works was observed having no influential effect on the
noise level during the measurement, the exceedance was considered as non-Project
related.
5.1.12.
After checking with Contractor of HK/2009/02, despite concreting,
loading and unloading conducted by crane was carried out under Contract
HK/2009/02 on 13 July 2017, no major noise emanation was observed while
breaking works next to the monitoring station under non WDII-CWB Contractor was
observed as the major noise contribution during monitoring. In view of the
above, the exceedance was considered as non-Project related.
5.1.13.
After checking with Contractor of HK/2009/02, backfilling works, breaking
works and unloading of C&D material from barge to land were conducted under
Contract HK/2009/02 on 20 July 2017 around the monitoring location during the
time of measurement while bored pile works was observed conducted around the
monitoring location under non WDII-CWB Project at the time of measurement.
Despite the breaking works was considered as the major noise contribution
during the measurement hence the exceedance is considered as Project related,
the noise impact to the nearest NSR is further assessed considering the
boundary location of the monitoring station and no adverse noise impact to the
nearest NSR is identified. Nevertheless, in view of the recorded boundary
condition, the Contractor of HK/2009/02 is suggested to adopt additional noise mitigation
measures to avoid potential cumulative impact to nearby stakeholders.
5.1.14.
After checking with Contractor of HK/2009/02, backfilling works,
breaking works and unloading of C&D material from barge to land were
conducted under Contract HK/2009/02 on 26 July 2017 around the monitoring
location during the time of measurement while bored pile works was observed
conducted around the monitoring location under non WDII-CWB Project at the time
of measurement. The breaking works under Contract HK/2009/02 was observed as
the major noise contribution during the measurement hence the exceedance is
considered as Project related and the adverse noise impact to the nearest NSR
was resulted. The Contractor of HK/2009/02 was requested to submit a remedial
action plan according to the Event and Action Plan. Remedial actions including
i) reduction in no. of breakers operating in parallel ii) operate breakers
intermittently and iii) covering of breaker head with acoustic material were
implemented by the Contractor on 03 August 2017.
Reporting period of August 2017
5.1.15.
One limit level exceedances were recorded at M1a – Footbridge for
Ex-Harbour Road Sports Centre on 04 August 2017 in the reporting period.
5.1.16.
After checking with Contractor of HK/2009/02, backfilling work and breaking
works were conducted under Contract HK/2009/02 on 04 August 2017 around the
monitoring location during the time of measurement. Despite the breaking works
was considered as the major noise contribution during the measurement and the
exceedance is considered as Project related, the noise impact to the nearest
NSR is further assessed considering the boundary location of the monitoring
station and no adverse noise impact to the nearest NSR is identified.
Nevertheless, in view of the recorded boundary condition, the Contractor of
HK/2009/02 is suggested to adopt additional noise mitigation measures to avoid
potential cumulative impact to nearby stakeholders.
Contract no. HY/2009/15 - Central-Wanchai Bypass –
Tunnel (
5.1.17.
No action or limit level exceedance was
recorded in this reporting quarter.
Contract
no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/D
Reporting period of June 2017
5.1.18.
Three limit level exceedances were recorded at M6 – HK Baptist Church
Henrietta Secondary School on 08, 16 and 19 June 2017 in this reporting period.
5.1.19.
Despite lifting works by crane and falsework erection works were
conducted under Contract HY/2009/19 on 08 and 19 June 2017 respectively, no
construction activity was conducted on 16 June 2017 and traffic noise was
observed as the major noise contribution on 08, 16 and 19 June 2017. Hence, the
exceedances were considered as non-Project related.
Reporting period of July 2017
5.1.20.
One limit level exceedance was recorded at M6 – HK Baptist Church
Henrietta Secondary School on 18 July 2017 in this reporting period.
5.1.21.
Despite installation of launching girder was conducted under Contract
HY/2009/19 on 18 July 2017, nearby IEC traffic noise was observed as the major
noise contribution during monitoring period. Hence, the exceedances were
considered as non-Project related.
Reporting period of August 2017
5.1.22.
No action or limit level exceedance was recorded in this reporting
period.
Contract
no. HY/2010/08 – Central-Wanchai Bypass – Tunnel (Slip Road 8 Section) under
FEP-10/364/2009/B
5.1.23.
No action of limit level exceedance was recorded in the reporting
quarter
Contract
no. HY/2011/08 Central –Central - Wan Chai Bypass (CWB) –Tunnel Buildings,
Systems and Fittings, and Works Associated with Tunnel Commissioning under
FEP-11/364/2009B
5.1.24.
No action of limit level exceedance was recorded in the reporting
quarter.
5.2.1 No action
or limit level exceedance was recorded in the reporting quarter.
Contract
no. HK/2009/01 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
Hong Kong Convention and Exhibition Centre - Tunnel Works
Reporting period
of June 2017
5.2.2
One 1hr TSP limit level exceedance was recorded at CMA5b – Pedestrian
Plaza on 03 June 2017 in the reporting
period.
5.2.3
After checking with the Contractor of HK/2009/01, no construction works
was undertaken around the monitoring location on the monitoring date under
Contractor of HK/2009/01 and no particular observation regarding air quality
impact was observed during sampling while sweeping works conducted directly at
the monitoring station by Pedestrian Plaza management office could potentially
contribute to the elevated particulates level in the vicinity of the monitoring
equipment. Hence, the exceedance is considered as not related to the Project.
Reporting period
of July 2017
5.2.4
No exceedance was recorded in the reporting period.
Reporting period
of August 2017
5.2.5
One 1hr TSP limit level exceedance was recorded at CMA5b – Pedestrian
Plaza on 29 August 2017 in the reporting period.
5.2.6
After checking with the Contractor of HK/2009/01, no construction works
was undertaken around the monitoring location on the monitoring date under
Contractor of HK/2009/01 and no particular observation regarding air quality
impact was observed during sampling. Non WDII-CWB Project construction
activities and road traffic was observed opposite to the monitoring station on
the monitoring date. Meanwhile, gardening and sweeping works conducted directly
at the monitoring station by Pedestrian Plaza management office was observed
across the monitoring period and would potentially contributed to the
particulates level in the vicinity of the monitoring equipment. Hence, the
exceedance is considered as not related to the Project.
Contract
nos. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at
Wan Chai East (CWB Tunnel)
Reporting
period of March 2017
5.2.7
No action or limit level exceedance was recorded in the reporting
quarter.
Contract no. HY/2009/15 - Central-Wanchai Bypass –
Tunnel (Causeway Bay Typhoon Shelter Section) FEP-06/364/2009/A
5.2.8
No action or limit level exceedance was recorded in the reporting
quarter.
Contract
no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/D
5.2.9
One 1hr TSP limit level exceedance was recorded at CMA1b – Harbour Grand
Hotel Boundary Wall on 03 June 2017 in the reporting period.
5.2.10
No construction works was undertaken around the monitoring location on
the monitoring date under Contractor of HY/2009/19 and no particular
observation regarding air quality impact was observed during sampling and dust
mitigation measure including haul road and dusty surface maintained in dampened
condition were generally implemented. The exceedance was considered to be
non-project related and potentially contributed by localized ambient condition
and other environmental factor.
Reporting period of July 2017
5.2.11
No exceedance was recorded in the reporting period.
Reporting period of August 2017
5.2.12
No exceedance was recorded in the reporting period.
Contract no. HK/2012/08 Wan Chai Development Phase II - Central-Wan Chai
Bypass at Wan Chai West under FEP-09/364/2009/B and FEP-12/364/2009/D
Reporting period of June 2017
5.2.13
One 1hr TSP limit level exceedance was recorded at CMA5b – Pedestrian
Plaza on 03 June 2017 in the reporting period.
5.2.14
After checking with the Contractor of HK/2012/08, despite manhole
installation was undertaken around the monitoring location on the monitoring
date under Contractor of HK/2012/08 and no particular observation regarding air
quality impact was observed during sampling while sweeping works conducted
directly at the monitoring station by Pedestrian Plaza management office could
potentially contribute to the elevated particulates level in the vicinity of
the monitoring equipment. Hence, the exceedance is considered as not related to
the Project.
Reporting period of July 2017
5.2.15
No exceedance was recorded in the reporting period.
Reporting period of August 2017
5.2.16
One 1hr TSP limit level exceedance was recorded at CMA5b – Pedestrian
Plaza on 29 August 2017 in the reporting period.
5.2.17
After checking with the Contractor of HK/2012/08, no construction works
was undertaken around the monitoring location on the monitoring date under
Contractor of HK/2012/08 and no particular observation regarding air quality
impact was observed during sampling. Non WDII-CWB Project construction
activities and road traffic was observed opposite to the monitoring station on
the monitoring date. Meanwhile, gardening and sweeping works conducted directly
at the monitoring station by Pedestrian Plaza management office was observed
across the monitoring period and would potentially contributed to the
particulates level in the vicinity of the monitoring equipment.. Hence, the
exceedance is considered as not related to the Project.
Contract no. HY/2010/08 – Central-Wanchai Bypass –
Tunnel (Slip Raod 8 Section) under FEP-10/364/2009/B
5.2.18
No exceedance was recorded in the reporting quarter
Contract no. HY/2011/08 Central –Central - Wan Chai Bypass
(CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel
Commissioning under FEP-11/364/2009B
5.2.19
One 1hr TSP limit level exceedance was recorded at CMA5b – Pedestrian
Plaza on 03 June 2017 in the reporting period.
5.2.20
After checking with the Contractor of HY/2011/08, rebar and formwork
fixing works was undertaken around the monitoring location on the monitoring
date under Contractor of HY/2011/08 and no particular observation regarding air
quality impact was observed during sampling while sweeping works conducted directly
at the monitoring station by Pedestrian Plaza management office could
potentially contribute to the elevated particulates level in the vicinity of
the monitoring equipment. Hence, the exceedance is considered as not related to
the Project.
5.2.21
One 1hr TSP limit level exceedance was recorded at CMA1b – Harbour Grand
Hotel Boundary Wall on 03 June 2017 in the reporting period.
5.2.22
After checking with the Contractor of HY/2011/08, rebar and formwork
fixing works was undertaken around the monitoring location on the monitoring
date under Contractor of HY/2011/08 and no particular observation regarding air
quality impact was observed during sampling and dust mitigation measure
including hard paving of haul road were generally implemented. The exceedance
was considered to be non-project related and potentially contributed by
localized ambient condition and other environmental factor.
Reporting period
of July 2017
5.2.23
No exceedance was recorded in the reporting period.
Reporting period
of August 2017
5.2.24
One 1hr TSP limit level exceedance was recorded at CMA5b – Pedestrian
Plaza on 29 August 2017 in the reporting period.
5.2.25
Despite grouting, scabbling and indoor plastering works was undertaken
around the monitoring location on the monitoring date at the under Contractor
of HY/2011/08 and no particular observation regarding air quality impact was
observed during sampling and dust mitigation measure include watering during
scabbling were implemented. Non WDII-CWB Project construction activities and
road traffic was observed opposite to the monitoring station on the monitoring
date. Meanwhile, gardening and sweeping works conducted directly at the
monitoring station by Pedestrian Plaza management office was observed across
the monitoring period and would potentially contributed to the particulates
level in the vicinity of the monitoring equipment. Hence, the exceedance is
considered as not related to the Project.
Contract
no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/D
Reporting period
of June 2017
5.3.1
Limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport
Section Whitfield Depot was recorded during daytime on 21 June 2017 in the reporting
period. After checking with Contractor of HY/2009/19, no construction works was
conducted on 21 June 2017 during the monitoring period while adverse weather
condition was recorded during the monitoring period and considered as the major
noise contribution. Hence, the exceedances were considered as non-Project
related.
5.3.2
Limit level exceedances were recorded at RTN2a- Hong Kong Electric
Centre was recorded during daytime on 21 June 2017 in the reporting period. After
checking with Contractor of HY/2009/19, no construction works was conducted on
21 June 2017 during the monitoring period while adverse weather condition was
recorded during the monitoring period and considered as the major noise
contribution. Hence, the exceedances were considered as non-Project related.
5.3.3
Limit level exceedances were recorded at RTN3- Yu Lee Mo Fan Memorial
School was recorded during daytime on 13 and 21 June 2017 in the reporting
period. After checking with Contractor of HY/2009/19, despite erection of
U-beam structure was conducted on 13 June 2017, no major noise concern was
considered and no construction works was conducted on 21 June 2017 during the
monitoring period while adverse weather condition was recorded during the
monitoring period on 13 and 21 June 2017 and considered as the major noise contribution.
Hence, the exceedances were considered as non-Project related.
5.3.4
No limit level exceedance was recorded at RTN4- Causeway Bay Community
Centre was recorded in the reporting period.
Reporting period of July
2017
5.3.5
No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport
Section Whitfield Depot was recorded in the reporting period.
5.3.6
Limit level exceedances were recorded at RTN2a- Hong Kong Electric
Centre was recorded during daytime on 24 July 2017 in the reporting period. After
checking with Contractor of HY/2009/19, trimming bored pile head and sheet pile
installation was conducted behind Administration Building Structure while
external wall maintenance work at HK Electric Centre was recorded across the
monitoring date and potentially contributed to the recorded noise. In view of
the above, the exceedances were considered as non-Project related.
5.3.7
Limit level exceedances were recorded at RTN3- Yu Lee Mo Fan Memorial
School was recorded during daytime on 08 July 2017 in the reporting period. After
checking with Contractor of HY/2009/19, no construction works was conducted
during the monitoring period and the exceedance is potentially contributed by
nearby IEC traffic. Hence, the exceedance was considered as non-Project
related.
5.3.8
No limit level exceedance was recorded at RTN4- Causeway Bay Community
Centre was recorded in the reporting period.
Reporting
period of August 2017
5.3.9
No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport
Section Whitfield Depot was recorded in the reporting period.
5.3.10
Limit level exceedances were recorded at RTN2a- Hong Kong Electric
Centre was recorded during daytime on 10 August 2017 in the reporting period.
After checking with Contractor of HY/2009/19, concreting, excavation and
trimming bored pile head were conducted behind Administration Building
Structure while construction works under non-CWB construction site was observed
across August 2017 and potentially contributed to the recorded noise. In view
of the above, the exceedances were considered as non-Project related.
5.3.11
Limit level exceedances were recorded at RTN3- Yu Lee Mo Fan Memorial
School was recorded during daytime on 23 August 2017 in the reporting period.
After checking with Contractor of HY/2009/19, no construction works was
conducted during the monitoring period with respect to the hoisting of the
Typhoon Signal No.8 and the exceedance is considered to be contributed by
adverse weather condition. Hence, the exceedance was considered as non-Project
related.
5.3.12
No limit level exceedance was recorded at RTN4- Causeway Bay Community
Centre was recorded in the reporting period.
Contract no. HY/2011/08 Central –Central - Wan Chai Bypass (CWB) –Tunnel
Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning
under FEP-11/364/2009B
Reporting period of June 2017
5.3.13
Limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport
Section Whitfield Depot was recorded during daytime on 21 June 2017 in the reporting
period. After checking with Contractor of HY/2011/08, no construction works was
conducted on 21 June 2017 during the monitoring period while adverse weather
condition was recorded during the monitoring period and considered as the major
noise contribution. Hence, the exceedances were considered as non-Project related.
5.3.14
Limit level exceedances were recorded at RTN2a- Hong Kong Electric
Centre was recorded during daytime on 21 June 2017 in the reporting period. After
checking with Contractor of HY/2011/08, no construction works was conducted on
21 June 2017 during the monitoring period while adverse weather condition was
recorded during the monitoring period and considered as the major noise
contribution. Hence, the exceedances were considered as non-Project related.
5.3.15
No limit level exceedance was recorded at RTN4- Causeway Bay Community
Centre were recorded in the reporting period.
Reporting
period of July 2017
5.3.16
No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport
Section Whitfield Depot was recorded in the reporting period.
5.3.17
Limit level exceedances were recorded at RTN2a- Hong Kong Electric
Centre was recorded during daytime on 24 July 2017 in the reporting period. After
checking with Contractor of HY/2011/08, despite concreting, rebar fixing,
formwork erection and excavation were conducted at Administration works area,
no particular noise impact was considered while external wall maintenance work
at HK Electric Centre was observed across the monitoring date and potentially
contributed to the recorded noise. In view of the above, the exceedances were
considered as non-Project related.
5.3.18
No limit level exceedance was recorded at RTN4- Causeway Bay Community
Centre were recorded in the reporting period.
Reporting period of August 2017
5.3.19
No limit level exceedance was recorded at RTN1-FEHD Hong Kong Transport
Section Whitfield Depot was recorded in the reporting period.
5.3.20
Limit level exceedances were recorded at RTN2a- Hong Kong Electric
Centre was recorded during daytime on 10 August 2017 in the reporting period. After
checking with Contractor of HY/2011/08, despite rebar fixing, formwork erection
and excavation were conducted at Administration works area, no particular noise
impact was considered while construction works under non-CWB construction site
was observed across August 2017 and potentially contributed to the recorded
noise. In view of the above, the exceedances were considered as non-Project
related.
5.3.21
No limit level exceedance was recorded at RTN4- Causeway Bay Community
Centre were recorded in the reporting period.
5.4.1
There was no non-compliance from the site
audits in the reporting period. During environmental site inspections conducted
during the reporting quarter, minor deficiencies were noted. However, the Contractor rectified all
deficiencies after receipt of notification.
5.5.1
An inspection report (under WPCO) regarding
suspected non-compliance of construction site discharge and acknowledgement of
Receipt of a Legal Sample were issued by the EPD to the Contractor of
HY/2009/19 after inspection conducted by the EPD on 29 June 2017 at Watson
Road.
5.5.2
A project related noise exceedance was
recorded from the breaking works under Contract HK/2009/02 at M1a - Footbridge
at Ex-Harbour Road Sports Centre on 20 July 2017. The breaking works was
observed as the major noise contribution during the measurement hence the
exceedance is considered as Project related while no adverse noise impact to
the nearest NSR was resulted based on the assessment on the monitoring location
and nearest NSR.
5.5.3
A project related noise exceedance was
recorded from the breaking works under Contract HK/2009/02 at M1a - Footbridge
at Ex-Harbour Road Sports Centre on 26 July 2017. The breaking works was
observed as the major noise contribution during the measurement hence the
exceedance is considered as Project related and adverse noise impact to the
nearest NSR was resulted. The Contractor of HK/2009/02 was requested to submit
a remedial action plan according to the Event and Action Plan.
5.5.4
An inspection report (under APCO) regarding
improper dust suppression measures during excavation was issued by the EPD to
the Contractor of HK/2009/02 after inspection conducted by the EPD on 24 August
2017.
5.5.5
A project related noise exceedance was
recorded from the breaking works under Contract HK/2009/02 at M1a - Footbridge
at Ex-Harbour Road Sports Centre on 04 August 2017. The breaking works was
observed as the major noise contribution during the measurement hence the
exceedance is considered as Project related while no adverse noise impact to
the nearest NSR was resulted based on the assessment on the monitoring location
and nearest NSR.
5.6.1
The RSS and Environmental Team shall keep in
view the construction site discharge under Contract HY/2009/19 and conduct
regular checking for the concerned construction site discharge and notify the
Contractor for necessary follow up, if required.
5.6.2
Further project related noise exceedance
recorded on 20 July 2017 from the breaking works under Contract HK/2009/02,
despite no adverse impact was assessed from the noise assessment at the nearest
NSR, the Contractor of HK/2009/02 was recommended to implement noise mitigation
measures to avoid potential nuisance to nearby stakeholder.
5.6.3
Further to the project related noise
exceedance recorded on 26 July 2017 under Contract HK/2009/02, remedial actions
including i) reduction in no. of breakers operating in parallel ii) operate
breakers intermittently and iii) covering of breaker head with acoustic
material were implemented by the Contractor on 03 August 2017. Additional noise
monitoring was conducted 03 August 2017 and it was concluded that there are no
further adverse impact to the nearest NSR upon implementation of remedial
actions.
5.6.4
The RSS and Environmental Team shall keep in
view the construction site dust mitigation measure under Contract HK/2009/02 and
notify the Contractor for necessary follow up, if required.
5.6.5
Further to the project related noise
exceedance recorded on 04 August 2017 from the breaking works under Contract
HK/2009/02, despite no adverse impact was assessed from the noise assessment at
the nearest NSR, the Contractor of HK/2009/02 was recommended to implement
noise mitigation measures to avoid potential nuisance to nearby stakeholder.
6.0.1
Four environmental complaints were received in the reporting period.
6.0.2
First EPD complaint was referred to the ET on 13 July 2017 (CASE Ref:
H05/RS/00021311-17). The complainant reported that construction work from a
construction site near Renaissance Hong Kong Harbour View Hotel was found
around 2315 hrs on 26 June 2017, causing noise nuisance.
ET confirmed with the Resident Site
Staff that Manual re-bar fixing works was carried out under Contract HK/2009/02
from 2300hrs to 2330hrs on 26 June 2017 at Portion 5 Bay 15 (Non - Designated
Area) top slab area adjacent to the covered walkway of the Wan Chai Ferry Pier.
1 no. of generator was operated at ground level and 2 nos. of generators were
operated below ground level from 2300hrs to 2400hrs on 26 June 2017. In
addition 16 electric water pump were operated below ground level from 2300hrs
to 2400hrs on 26 June 2017.
Notwithstanding the information stated
in above item 1), according to relevant Resident Site Staff site record, it was
recorded that 1 no. of mobile crane and 1 no. of bar bender were deployed and
operated at Portion 5 area (West of Wan Chai Ferry Pier) under Contract
HK/2009/02 after 2300hrs on 26 July 2017. Upon warning given by WDII Resident
Site staff to the Contractor of HK/2009/02, the operation of crawler crane for
lifting rebar and operation of bar bender machine were suspended at around
2315hrs on 26 June 2017.
No construction activity and site
operation was carried out under Contract HK/2009/01 from 2300hrs to 2400hrs on
26 June 2017.
According to the RSS site information,
manual re-bar fixing works was carried out under Contract HK/2009/02 from
2300hrs to 2330hrs on 26 June 2017 at Portion 5 Bay 15 (Non - Designated Area)
top slab area adjacent to the covered walkway of the Wan Chai Ferry Pier. 1 no.
of generator was operated at ground level and 2 nos. of generators were
operated below ground level from 2300hrs to 2400hrs on 26 June 2017 while 16
electric water pump were operated below ground level at Portion 5 Bay from
2300hrs to 2400hrs on 26 June 2017 and the relevant Construction Noise Permit
GW-RS0527-17 for the above operation was in place. However, site record on the
model of generators deployed on the concerned night was not available.
Notwithstanding the above, according to
relevant Resident Site Staff site record, it was recorded that 1 no. of mobile
crane and 1 no. of bar bender machine were deployed and operated at Portion 5
area (West of Wan Chai Ferry Pier) under Contract HK/2009/02 after 2300hrs on
26 July 2017 without a valid Construction Noise Permit. Upon warning given by
WDII Resident Site staff to the Contractor of HK/2009/02, the operation of
crawler crane for lifting rebar and operation of bar bender machine were
suspended at around 2315hrs on 26 June 2017. According to Contractor of
HK/2009/02, the operation bar bender machine was suspended upon warning by RSS
team and the operation of crawler crane was suspended upon moving to a proper location
to avoid obstruction for next day work.
Meanwhile, no construction activity and
site operation was carried out under Contract HK/2009/01 from 2300hrs to
2400hrs on 26 June 2017. In view of the above operation of powered mechanical
equipment under Contract HK/2009/02 beyond 2300hrs, the Contractor of
HK/2009/02 was required and urged to implement the following remedial measures
to ensure the strict construction noise permit compliance including:-
Fully review the site control system for
construction works carried out during restricted hours, in particular to ensure
the frontline supervisors responsible for restricted hours construction
operations are trained with comprehensive understanding on the requirement of
the Construction Noise Permit in force to ensure the PMEs deployed are in
compliance with relevant Construction Noise Permit.
To assign delegated and competent
personnel on-site to conduct checking on the deployment of PMEs on-site prior
and during restricted hours to ensure only PMEs allowed under relevant
Construction Noise Permit would be operated.
In addition, the following preventive
measures are also recommended including the Contractor of HK/2009/02 is
recommended to provide regular briefing and training section to site staffs and
frontline workers to enhance the workers awareness and understanding on
relevant Construction Noise Permit(s) requirement during restricted hours.
The Contractor of HK/2009/02 is
recommended to review the construction operation planning procedures to ensure
relevant PME(s) required for conducting the planned operation to ensure
required PME are adequate considered and covered by relevant Construction Noise
Permit.
In view of the recent concern over
restricted hours construction operations, a meeting was held amongst the CEDD,
the RSS team, the Contractor of HK/2009/02 and the Environmental Team on 21
July 2017 to review the site control measures and enhancement measures to be
adopted for restricted hours construction operations control for Construction
Noise Permit Compliance. A detailed implementation plan would be prepared by
the Contractor of HK/2009/02 and further supplemented.
6.0.3
Second EPD complaint was referred to the ET on 17 July 2017 (CASE Ref:
H05/RS/00022136-17). The complainant reported that night time construction
noise emanated from construction works conducted during early hours of 14 July
2017 at Island Eastern Corridor near Provident Centre.
An ICC complaint case (Ref:
2-4122021589) was Referred to the ET on 25 July 2017. The complainant reported
that the workers are now doing extremely noisy works at the Island Eastern
Corridor near Provident Centre affecting the nearby residents. As the ICC
complaint case refers to the noise concern at the same location at the same
hours on the same date, hence the ICC case is considered as the same complaint
case under the EPD complaint for investigation purpose.
ET confirmed with the Resident Site
Staff that emergency road repairing work including the repairing of movement
joint at Pier 46 and three potholes along IEC Westbound was carried out under
Contract HY/2009/19 around the concerned location from 0000hrs to 0600hrs on 14
July 2017. Total 1 no. of hand held breaker and 1 no. of hand held drill for
grout mixing were operated.
According to the RSS site information,
emergency road repairing work including the repairing of movement joint at Pier
46 and three potholes along IEC Westbound was carried out under Contract
HY/2009/19 around the concerned location from 0000hrs to 0600hrs on 14 July
2017. Total 1 no. of hand held breaker and 1 no. of hand held drill for grout
mixing were operated. A written advance notification was issued to the EPD on
13 July 2017 regarding the aforesaid emergency road repairing works. In view of
the public concern, the Contractor of HY/2009/19 is recommended to adopt
additional noise mitigation measure for future emergency road repairing works,
if any, at night time hours around the concerned location. In response to the
public concern, the Contractor of HY/2009/19 would adopt the following
additional measures for future emergency road repairing works including: i) For
any emergency works requiring, for example, breaking or any other noisy
activities, wherever possible, temporary noise barrier or acoustic mat will be
use to fence of the line of sight between the noise emanating source and the
NSR, ii) Covering breaking head with acoustic mat to minimize noise if breaking
would be conducted and iii) complete noisy work as soon as possible to minimize
disturbance to the nearby residents.
6.0.4
Third EPD complaint was referred to the ET on 21 July 2017 (CASE Ref:
H05/RS/00022835-17). The complainant reported that mechanical noise was
emanated from a construction site near Renaissance Hong Kong Harbour View Hotel
and Wanchai Pier from late night till dawn recently, causing noise nuisance.
ET confirmed with the Resident Site
Staff that unloading of fill material was conducted under Contract HK/2009/02
at WCR3 area (West of Wan Chai Ferry Pier) from 2300hrs on 19 July 2017 to
0540hrs on 20 July 2017. 1 no. of grab dredger was operated for the above
construction works. No construction activities or site operation was conducted
under Contract HK/2009/01 from 2300hrs on 19 July 2019 to 0700hrs on 20 July
2017.
According to the RSS site information, unloading
of fill material was conducted under Contract HK/2009/02 at WCR3 area (West of
Wan Chai Ferry Pier) from 2300hrs on 19 July 2017 to 0540hrs on 20 July 2017. 1
no. of grab dredger was operated for the above construction works and relevant
Construction Noise Permit GW-RS0348-17 was in place and noise barrier with
surface mass density of not less than 5kg/m2 was provided to the power
generating part of the grab dredger operated from 2300hrs on 19 July 2017 to
0540hrs on 20 July 2017. Meanwhile, no construction activities or site
operation was conducted under Contract HK/2009/01 from 2300hrs on 19 July 2019
to 0700hrs on 20 July 2017.
In view of the public concern, the
Contractor of HK/2009/02 was reminded to upkeep the site control system for
construction works carried out during restricted hours and night time for
Construction Noise Permit compliance and maintain regular maintenance of the
plant and equipment deployed to avoid potential nuisance to the nearby public.
6.0.5
Fourth ICC complaint was referred to the ET on 26 July 2017 (CASE Ref:
#2-4162467151). The complainant reported that no watering system was provided
to the excavation works conducted at a CEDD Construction Site near Wanchai
Ferry Pier resulting in dust impact to the public area beyond site hoarding.
ET confirmed with the Resident Site
Staff that breaking works and backfilling works were conducted under Contract
HK/2009/02 at the concerned location on 25 July 2017 afternoon.
Dust mitigation measures including water
spraying was implemented for the above construction activities on 25 July 2017
at the concerned location.
According to the RSS site information,
breaking works and backfilling works were conducted under Contract HK/2009/02
at the concerned location on 25 July 2017 afternoon while dust mitigation
measures including water spraying was implemented for the above construction
activities on 25 July 2017 at the concerned location. During Environmental Team
ad hoc inspection conducted on 26 July 2017, water spraying was found insufficient
to mitigate the extended area of breaking operation and construction dust
impact to surroundings public area was observed. Subsequently, Contractor of
HK/2009/02 was reminded to enhance the dust suppression measure for the dust
generating works.
In response to the observed
environmental concern, the Contractor of HK/2009/02 has strengthened the water
spraying coverage to all breaking operation area and haul road to minimize the
potential dust impact. Follow up inspection was conducted by Environmental Team
on 27 July 2017 and no further dust impact was observed.
6.0.6
The details of cumulative complaint log
and summary of complaints are presented in Appendix
6.1.
6.0.7
An inspection report (under WPCO) regarding
suspected non-compliance of construction site discharge and acknowledgement of
Receipt of a Legal Sample were issued by the EPD to the Contractor of
HY/2009/19 after inspection conducted by the EPD on 29 June 2017 at Watson
Road.
6.0.8
An inspection report (under APCO) regarding
improper dust suppression measures during excavation was issued by the EPD to
the Contractor of HK/2009/02 after inspection conducted by the EPD on 24 August
2017.
6.0.9
Cumulative statistic on complaints and successful prosecutions are summarized
in Table
6.1 and Table 6.2 respectively.
Table 6.1 Cumulative
Statistics on Complaints
Reporting Period |
No. of Complaints |
Commencement of Works up to last reporting quarter |
80 |
June 2017 to August 2017 |
4 |
Project-to-Date |
84 |
Table 6.2 Cumulative Statistics on Successful
Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this quarter
(Offence Date) |
Cumulative No. Project-to-Date |
Air |
1 |
0 |
1 |
Noise |
1 |
0 |
1 |
Waste |
- |
0 |
0 |
Total |
2 |
0 |
2 |
7.0.2.
According to the Final EM&A Report of
Central Reclamation Phase III (CRIII) for Contract HK 12/02, the major
construction activities were completed by end of January 2014 and no
construction activities were undertaken thereafter and the water quality
monitoring was completed in October 2011.
As such, it is considered that there were no cumulative construction
impact due to the concurrent activities of the current projects with the
Central Reclamation Phase III (CRIII) undertaken by contractor HK12/02 in the
reporting period.
7.0.3.
According to the construction programme of
Central-Wanchai Bypass at Wanchai West at the Central Reclamation Phase III
area include road and drain works, backfilling works and reinstatement of
Culvert and Cooling mains reinstatement of planter at P1 road were performed in
August 2017 reporting period. As no project related exceedance were
recorded during the reporting period, cumulative construction impact due to the
concurrent activities of the current projects with the Central Reclamation
Phase III (CRIII) was considered as insignificant.
7.0.4.
According
to the construction programme of Wan Chai Development Phase II, Central-Wan
Chai Bypass and Island Eastern Corridor Link projects, the major construction
activities under Wan Chai Development Phase II were road and drains
construction, tunnel construction and backfilling works at Wan Chai West and
Wan Chai East. The major construction activities under Central-Wan Chai Bypass
and Island Eastern Corridor Link Projects were drainage works and ventilation
building construction at Central; temporary reclamation removal works at
Causeway Bay, road works and side wall construction at Victoria Park; bridge
construction, piling works, foundation works and building construction at North
Point area in the reporting period. In addition, other non-Wan Chai Development
Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects was observed undertaken at Wan
Chai North and North Point area.
7.0.5.
No significant air impact from construction
activities was anticipated in the reporting period. Besides, no project related
exceedance was recorded during the air and noise environmental monitoring
events in the reporting period. Thus, it is evaluated that the cumulative
construction impact from the concurrent projects including Central Reclamation
Phase III (CRIII), Wan Chai Development Phase II (WDII), Central-WanChai Bypass
(CWB), Island Eastern Corridor Link projects (IECL) was insignificant.
8.0.1. The EM&A programme was carried out
in accordance with the EM&A Manual requirements, minor alterations to the
programme proposed were made in response to changing circumstances.
Air
quality monitoring
8.0.2. One 1hr TSP limit level exceedance was
recorded at CMA1b – Oil Street Site Office was recorded on 03 June 2017 in the
reporting period. The exceedance was concluded as non Project related.
8.0.3. One 1hr TSP limit level exceedance was
recorded at CMA5b – Pedestrian Plaza was recorded on 03 June 2017 in the
reporting period. The exceedance was concluded as non Project related.
8.0.4. One 1hr TSP limit level exceedance was
recorded at CMA5b – Pedestrian Plaza on 29 August 2017 in the reporting period.
The exceedance was concluded as non Project related.
Noise monitoring
8.0.5. Five limit level exceedances were
recorded at M1a – Footbridge for Ex-Harbor Road Sports Centre on 31 May 2017
and 08, 13, 22 and 26 June 2017 in the reporting period. The exceedances were
concluded as non Project related.
8.0.6. Three limit level exceedances were
recorded at M6 - HK Baptist Church Henrietta Secondary School on 08, 16 and 19
June 2017 in the reporting period. The exceedances were concluded as non
Project related.
8.0.7. Four limit level exceedances were
recorded at M1a – Footbridge for Ex-Harbor Road Sports Centre on 07, 13, 20 and
26 July 2017 in the reporting period. The exceedances recorded on 07 and 13
July 2017 were concluded as non Project related while the exceedances recorded
on 20 and 26 July 2017 were concluded as Project related.
8.0.8. One limit level exceedance was recorded
at M6 - HK Baptist Church Henrietta Secondary School on 18 July 2017 in the
reporting period. The exceedance was concluded as non Project related.
8.0.9. One limit level exceedance was recorded
at M1a – Footbridge for Ex-Harbor Road Sports Centre on 04 August 2017 in the
reporting period. The exceedance was concluded as Project related.
Real time noise monitoring
8.0.10. No project related exceedance was
recorded in June reporting period and no limit level exceedance was recorded in
July and August reporting period at RTN1- FEHD Hong Kong Transport Section Whitfield
Depot during this reporting period.
8.0.11. No project related exceedance was
recorded in June, July and August reporting period at RTN2a-Hong Kong Electric
Centre during this reporting period.
8.0.12. No project related exceedance was
recorded in June, July and August reporting period at RTN3-Yu Lee Mo Fan
Memorial School during this reporting period.
8.0.13. No limit level related exceedance was
recorded in June, July and August reporting period at RTN4- Causeway Bay
Community Centre in the reporting period.
Environmental Complaints
8.0.14. Four environmental complaints were
received in the reporting period.
8.0.15. First EPD complaint was referred to the
ET on 13 July 2017 (CASE Ref: H05/RS/00021311-17). The complainant reported
that construction work from a construction site near Renaissance Hong Kong
Harbour View Hotel was found around 2315 hrs on 26 June 2017, causing noise
nuisance.
ET confirmed with the Resident Site
Staff that Manual re-bar fixing works was carried out under Contract HK/2009/02
from 2300hrs to 2330hrs on 26 June 2017 at Portion 5 Bay 15 (Non - Designated
Area) top slab area adjacent to the covered walkway of the Wan Chai Ferry Pier.
1 no. of generator was operated at ground level and 2 nos. of generators were
operated below ground level from 2300hrs to 2400hrs on 26 June 2017. In
addition 16 electric water pump were operated below ground level from 2300hrs
to 2400hrs on 26 June 2017.
Notwithstanding the information stated
in above item 1), according to relevant Resident Site Staff site record, it was
recorded that 1 no. of mobile crane and 1 no. of bar bender were deployed and
operated at Portion 5 area (West of Wan Chai Ferry Pier) under Contract
HK/2009/02 after 2300hrs on 26 July 2017. Upon warning given by WDII Resident
Site staff to the Contractor of HK/2009/02, the operation of crawler crane for
lifting rebar and operation of bar bender machine were suspended at around
2315hrs on 26 June 2017.
No construction activity and site
operation was carried out under Contract HK/2009/01 from 2300hrs to 2400hrs on
26 June 2017.
According to the RSS site information,
manual re-bar fixing works was carried out under Contract HK/2009/02 from
2300hrs to 2330hrs on 26 June 2017 at Portion 5 Bay 15 (Non - Designated Area)
top slab area adjacent to the covered walkway of the Wan Chai Ferry Pier. 1 no.
of generator was operated at ground level and 2 nos. of generators were
operated below ground level from 2300hrs to 2400hrs on 26 June 2017 while 16
electric water pump were operated below ground level at Portion 5 Bay from
2300hrs to 2400hrs on 26 June 2017 and the relevant Construction Noise Permit
GW-RS0527-17 for the above operation was in place. However, site record on the
model of generators deployed on the concerned night was not available.
Notwithstanding the above, according to
relevant Resident Site Staff site record, it was recorded that 1 no. of mobile
crane and 1 no. of bar bender machine were deployed and operated at Portion 5
area (West of Wan Chai Ferry Pier) under Contract HK/2009/02 after 2300hrs on
26 July 2017 without a valid Construction Noise Permit. Upon warning given by
WDII Resident Site staff to the Contractor of HK/2009/02, the operation of
crawler crane for lifting rebar and operation of bar bender machine were
suspended at around 2315hrs on 26 June 2017. According to Contractor of
HK/2009/02, the operation bar bender machine was suspended upon warning by RSS
team and the operation of crawler crane was suspended upon moving to a proper
location to avoid obstruction for next day work.
Meanwhile, no construction activity and
site operation was carried out under Contract HK/2009/01 from 2300hrs to
2400hrs on 26 June 2017. In view of the above operation of powered mechanical
equipment under Contract HK/2009/02 beyond 2300hrs, the Contractor of HK/2009/02
was required and urged to implement the following remedial measures to ensure
the strict construction noise permit compliance including:-
Fully review the site control system for
construction works carried out during restricted hours, in particular to ensure
the frontline supervisors responsible for restricted hours construction
operations are trained with comprehensive understanding on the requirement of
the Construction Noise Permit in force to ensure the PMEs deployed are in
compliance with relevant Construction Noise Permit.
To assign delegated and competent
personnel on-site to conduct checking on the deployment of PMEs on-site prior
and during restricted hours to ensure only PMEs allowed under relevant
Construction Noise Permit would be operated.
In addition, the following preventive
measures are also recommended including the Contractor of HK/2009/02 is
recommended to provide regular briefing and training section to site staffs and
frontline workers to enhance the workers awareness and understanding on
relevant Construction Noise Permit(s) requirement during restricted hours.
The Contractor of HK/2009/02 is
recommended to review the construction operation planning procedures to ensure
relevant PME(s) required for conducting the planned operation to ensure
required PME are adequate considered and covered by relevant Construction Noise
Permit.
In view of the recent concern over
restricted hours construction operations, a meeting was held amongst the CEDD,
the RSS team, the Contractor of HK/2009/02 and the Environmental Team on 21
July 2017 to review the site control measures and enhancement measures to be
adopted for restricted hours construction operations control for Construction
Noise Permit Compliance. A detailed implementation plan would be prepared by
the Contractor of HK/2009/02 and further supplemented.
8.0.16. Second EPD complaint was referred to the
ET on 17 July 2017 (CASE Ref: H05/RS/00022136-17). The complainant reported
that night time construction noise emanated from construction works conducted
during early hours of 14 July 2017 at Island Eastern Corridor near Provident
Centre.
An ICC complaint case (Ref:
2-4122021589) was Referred to the ET on 25 July 2017. The complainant reported
that the workers are now doing extremely noisy works at the Island Eastern
Corridor near Provident Centre affecting the nearby residents. As the ICC
complaint case refers to the noise concern at the same location at the same
hours on the same date, hence the ICC case is considered as the same complaint
case under the EPD complaint for investigation purpose.
ET confirmed with the Resident Site
Staff that emergency road repairing work including the repairing of movement
joint at Pier 46 and three potholes along IEC Westbound was carried out under
Contract HY/2009/19 around the concerned location from 0000hrs to 0600hrs on 14
July 2017. Total 1 no. of hand held breaker and 1 no. of hand held drill for
grout mixing were operated.
According to the RSS site information,
emergency road repairing work including the repairing of movement joint at Pier
46 and three potholes along IEC Westbound was carried out under Contract
HY/2009/19 around the concerned location from 0000hrs to 0600hrs on 14 July
2017. Total 1 no. of hand held breaker and 1 no. of hand held drill for grout mixing
were operated. A written advance notification was issued to the EPD on 13 July
2017 regarding the aforesaid emergency road repairing works. In view of the
public concern, the Contractor of HY/2009/19 is recommended to adopt additional
noise mitigation measure for future emergency road repairing works, if any, at
night time hours around the concerned location. In response to the public
concern, the Contractor of HY/2009/19 would adopt the following additional
measures for future emergency road repairing works including: i) For any
emergency works requiring, for example, breaking or any other noisy activities,
wherever possible, temporary noise barrier or acoustic mat will be use to fence
of the line of sight between the noise emanating source and the NSR, ii)
Covering breaking head with acoustic mat to minimize noise if breaking would be
conducted and iii) complete noisy work as soon as possible to minimize
disturbance to the nearby residents.
8.0.17. Third EPD complaint was referred to the
ET on 21 July 2017 (CASE Ref: H05/RS/00022835-17). The complainant reported
that mechanical noise was emanated from a construction site near Renaissance
Hong Kong Harbour View Hotel and Wanchai Pier from late night till dawn
recently, causing noise nuisance.
ET confirmed with the Resident Site
Staff that unloading of fill material was conducted under Contract HK/2009/02
at WCR3 area (West of Wan Chai Ferry Pier) from 2300hrs on 19 July 2017 to
0540hrs on 20 July 2017. 1 no. of grab dredger was operated for the above
construction works. No construction activities or site operation was conducted
under Contract HK/2009/01 from 2300hrs on 19 July 2019 to 0700hrs on 20 July
2017.
According to the RSS site information,
unloading of fill material was conducted under Contract HK/2009/02 at WCR3 area
(West of Wan Chai Ferry Pier) from 2300hrs on 19 July 2017 to 0540hrs on 20
July 2017. 1 no. of grab dredger was operated for the above construction works
and relevant Construction Noise Permit GW-RS0348-17 was in place and noise
barrier with surface mass density of not less than 5kg/m2 was provided to the
power generating part of the grab dredger operated from 2300hrs on 19 July 2017
to 0540hrs on 20 July 2017. Meanwhile, no construction activities or site
operation was conducted under Contract HK/2009/01 from 2300hrs on 19 July 2019
to 0700hrs on 20 July 2017.
In view of the public concern, the
Contractor of HK/2009/02 was reminded to upkeep the site control system for
construction works carried out during restricted hours and night time for
Construction Noise Permit compliance and maintain regular maintenance of the
plant and equipment deployed to avoid potential nuisance to the nearby public.
8.0.18. Fourth ICC complaint was referred to the
ET on 26 July 2017 (CASE Ref: #2-4162467151). The complainant reported that no
watering system was provided to the excavation works conducted at a CEDD
Construction Site near Wanchai Ferry Pier resulting in dust impact to the
public area beyond site hoarding.
ET confirmed with the Resident Site
Staff that breaking works and backfilling works were conducted under Contract
HK/2009/02 at the concerned location on 25 July 2017 afternoon.
Dust mitigation measures including water
spraying was implemented for the above construction activities on 25 July 2017
at the concerned location.
According to the RSS site information,
breaking works and backfilling works were conducted under Contract HK/2009/02
at the concerned location on 25 July 2017 afternoon while dust mitigation
measures including water spraying was implemented for the above construction
activities on 25 July 2017 at the concerned location. During Environmental Team
ad hoc inspection conducted on 26 July 2017, water spraying was found
insufficient to mitigate the extended area of breaking operation and construction
dust impact to surroundings public area was observed. Subsequently, Contractor
of HK/2009/02 was reminded to enhance the dust suppression measure for the dust
generating works.
In response to the observed
environmental concern, the Contractor of HK/2009/02 has strengthened the water
spraying coverage to all breaking operation area and haul road to minimize the
potential dust impact. Follow up inspection was conducted by Environmental Team
on 27 July 2017 and no further dust impact was observed.
8.0.19. The construction programmes of individual contracts are provided in Appendix 8.1.