Contract No: HY/2019/18

 

Wanchai Development Phase II and Central Wanchai Bypass

Sampling, Field Measurement and Testing Work (Stage 4)

 

Environmental Permit no. EP-364/2009/H,

Further Evironmental permit nos. fep-01/364/2009,  FEp-06/364/2009/a, FEp-07/364/2009/H, fep-10/364/2009/B and fep-11/364/2009/E

 

Quarterly Environmental Monitoring
and Audit Report

 

- March 2021 to May 2021

 

 

 

 

 

 

 

 

 

 

 

 

CLIENTS:

PREPARED BY:

 

 

Civil Engineering and Development

Department

 

and

 

Highways Department

 

Lam Geotechnics Limited

 

19/F, Remex Centre,

42 Wong Chuk Hang Road,

Hong Kong.

 

Telephone: (852) 2882-3939

Facsimile: (852) 2882-3331

E-mail: info@lamenviro.com

Website: http://www.lamenviro.com

 

 

 

 

 

CHECKED by:



 

 

 

 

 

                                               

Raymond Dai

Environmental Team Leader

 

 

 

DATE:

 

 

 

05  Julyne[h1]  2021


Table of contents

 

1.       Introduction.. 9910

1.1         Scope of the Report 9910

1.2         Structure of the Report 9910

2.       Project Background.. 101011

2.1         Background. 101011

2.2         Scope of the Project and Site Description.. 101011

2.3         Division of the Project Responsibility. 111112

2.4         Project Organization and Contact Personnel 141415

2.5         Principal Work and Activities. 151516

3.       Monitoring Requirements. 171718

3.1.        Noise Monitoring. 171718

3.2.        Air quality monitoring. 191920

4.       Monitoring Results. 212122

4.1.        Noise Monitoring Results. 222223

4.2.        Real Time Noise Monitoring Results. 242426

4.3.        Air quality monitoring Results. 262630

4.4.        Waste Monitoring Results. 292934

5.       Compliance Audit.. 323237

5.1.        Noise Monitoring. 323237

5.2.        Real Tim


e Noise Monitoring. 323237

5.3.        Air quality monitoring. 333339

5.4.        Site Audit 333340

5.5.        Review of the Reasons for and the Implications of Non-compliance. 333340

5.6.        Summary of action taken in the event of and follow-up on non-compliance. 333340

6.      Complaints, Notification of Summons and Prosecution.. 343441

7.      Cumulative Construction Impact due to the Concurrent Projects  363643

8.       Conclusion.. 373744


lIST OF TABLES

 

Table III        Principal Work Activities for Contract no. HK/2009/02

Table IV       Principal Work Activities for Contract no. HY/2009/15

Table V        Principal Work Activities for Contract no. HY/2009/19

Table VII      Principal Work Activities for Contract no. HY/2010/08

Table VIII     Principal Work Activities for Contract no. HY/2011/08

Table 2.1      Schedule 2 Designated Projects under this Project

Table 2.2      Details of Individual Contracts under the Project

Table 2.3      Contact Details of Key Personnel

Table 2.6      Principal Work Activities for Contract no. HK/2009/02

Table 2.7      Principal Work Activities for Contract no. HY/2009/15

Table 2.8      Principal Work Activities for Contract no. HY/2009/19

Table 2.10    Principal Work Activities for Contract no. HY/2010/08

Table 2.11    Principal Work Activities for Contract no. HY/2011/08

Table 3.1      Noise Monitoring Stations

Table 3.2      Real Time Noise Monitoring Stations

Table 3.3      Air quality monitoring Stations

Table 4.2      Noise Monitoring Stations for Contract nos. HK/2009/02

Table 4.3      Noise Monitoring Station for Contract nos. HY/2009/15

Table 4.4      Noise Monitoring Stations for Contract no. HY/2009/19

Table 4.5      Noise Monitoring Stations for Contract no. HY/2010/08

Table 4.6     Noise Monitoring Stations for Contract no. HY/2011/08

Table 4.7      Real Time Noise Monitoring Stations for Contract no. HY/2009/19

Table 4.8      Real Time Noise Monitoring Stations  for Contract no. HY/2011/08

Table 4.11    Air quality monitoring Station for Contract no. HK/2009/02

Table 4.12    Air quality monitoring Station for Contract no. HY/2009/15

Table 4.13    Air quality monitoring Stations for Contract no. HY/2009/19

Table 4.15    Air quality monitoring Stations for Contract no. HY/2010/08

Table 4.16    Air quality monitoring Stations for Contract no. HY/2011/08

Table 4.18    Details of Waste Disposal for Contract no. HK/2009/02

Table 4.20    Details of Waste Disposal for Contract no. HY/2009/15

Table 4.21    Details of Waste Disposal for Contract no. HY/2009/19

Table 4.23    Details of Waste Disposal for Contract no. HY/2010/08

Table 4.24   Details of Waste Disposal for Contract no. HY/2011/08

Table 6.1      Cumulative Statistics on Complaints

Table 6.2      Cumulative Statistics on Successful Prosecutions

 

 

lIST OF FIGUREs

 

Figure 2.1         Project Layout

Figure 2.2         Project Organization Chart

Figure 3.1         Locations of Environmental Monitoring Stations

 

lIST OF APPENDIces

 

Appendix 2.1    Environmental Mitigation Implementation Schedule

Appendix 3.1    Action and Limit Level

Appendix 4.1    Noise Monitoring Results and Graphical Presentations

Appendix 4.2    Real-time Noise Monitoring Results and Graphical Presentations

Appendix 4.3    Air Quality Monitoring Results and Graphical Presentations

Appendix 5.1    Event Action Plans

Appendix 6.1    Complaint Log

Appendix 6.2     Notification of Exceedance

Appendix 7.1    Construction Programme of Individual Contracts


 

EXECUTIVE SUMMARY

 

  1. This is the Environmental Monitoring and Audit (EM&A) Quarterly Report – March 2021 to May 2021 specific for Environmental Permit no. EP-364/2009/H, Further Environmental Permit nos. FEP-01/364/2009, FEP-06/364/2009/A, FEP-07/364/2009/H, FEP-10/364/2009/B and FEP-11/364/2009/E. The EM&A report is prepared by the Environmental Team (ET) employed under Contract No. HY/2019/18 – Wan Chai Development Phase II and Central Wanchai Bypass – Sampling, Field Measurement and Testing Works (Stage 4). This report presents the environmental monitoring findings and information recorded during the period from 27 February 20201 to 26 May 2021. The cut-off date of reporting is at 26th of each reporting quarter.

 

  1. In the reporting period, the principal work activities of individual contracts are included as follows:

Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

Major construction activities for Contract no. HK/2009/02 have been commenced on 26 April 2011. During this reporting period, the principal work activities are summarized as below:

Table III      Principal Work Activities for Contract no. HK/2009/02

March 2021March 2021

April 2021April 2021

May 2021May 2021

Ÿ   Seepage rectification works at CWB tunnel.Seepage rectification works at CWB tunnel.

Ÿ   Seepage rectification works at CWB tunnel.Seepage rectification works at CWB tunnel.

Ÿ   Seepage rectification works at CWB tunnel.

Ÿ    Seepage rectification works at CWB tunnel.

 

 

Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/H

Major construction activities for Contract no. HY/2009/19 have been commenced on March 2011. During this reporting period, the principal work activities are summarized as below:

Table V      Principal Work Activities for Contract no. HY/2009/19

March 2021March 2021

April 2021April 2021

May 2021May 2021

Ÿ   Bridge noise enclosure & parapet construction and road works.

Ÿ   Hing Fat Street road works.

Ÿ   Soft Landscaping works.

Ÿ   Open area hard paving.

Ÿ   D12 & Open Area fire main laying works.

Ÿ   D9 to D12 and P22 to P25 drainage works.

Ÿ   Rumsey Street modification works.

Ÿ   EVB injection grouting work.

Ÿ   Promenade works at EVB.

Ÿ   IEC Eastbound Corbel construction

Ÿ   Road marking modification work at IEC Westbound downstream

Ÿ   Construction of enlarge parapet at IEC Eastbound.

Ÿ   IEC Westbound drainage modification work

Ÿ    Removal of launching girder componentsBridge noise enclosure & parapet construction and road works.

Ÿ    Hing Fat Street road works.

Ÿ    Soft Landscaping works.

Ÿ    Open area hard paving.

Ÿ    D12 & Open Area fire main laying works.

Ÿ    D9 to D12 and P22 to P25 drainage works.

Ÿ    Rumsey Street modification works.

Ÿ    EVB injection grouting work.

Ÿ    Promenade works at EVB.

Ÿ    IEC Eastbound Corbel construction

Ÿ    Road marking modification work at IEC Westbound downstream

Ÿ    Construction of enlarge parapet at IEC Eastbound.

Ÿ    IEC Westbound drainage modification work

Ÿ   Removal of launching girder components

Ÿ   Bridge noise enclosure & parapet construction and road works.

Ÿ   Hing Fat Street road works.

Ÿ   Soft Landscaping works.

Ÿ   Open area hard paving.

Ÿ   D12 & Open Area fire main laying works.

Ÿ   D9 to D12 and P22 to P25 drainage works.

Ÿ   Rumsey Street modification works.

Ÿ   EVB injection grouting work.

Ÿ   Promenade works at EVB.

Ÿ   IEC Eastbound Corbel construction

Ÿ   Road marking modification work at IEC Westbound downstream

Ÿ   Construction of enlarge parapet at IEC Eastbound.

Ÿ   IEC Westbound drainage modification work

Ÿ   Removal of launching girder components

Ÿ    Demolition of PRE OfficeBridge noise enclosure & parapet construction and road works.

Ÿ    Hing Fat Street road works.

Ÿ    Soft Landscaping works.

Ÿ    Open area hard paving.

Ÿ    D12 & Open Area fire main laying works.

Ÿ    D9 to D12 and P22 to P25 drainage works.

Ÿ    Rumsey Street modification works.

Ÿ    EVB injection grouting work.

Ÿ    Promenade works at EVB.

Ÿ    IEC Eastbound Corbel construction

Ÿ    Road marking modification work at IEC Westbound downstream

Ÿ    Construction of enlarge parapet at IEC Eastbound.

Ÿ    IEC Westbound drainage modification work

Ÿ    Removal of launching girder components

Ÿ   Demolition of PRE Office

Ÿ   Bridge noise enclosure & parapet construction and road works.

Ÿ   Hing Fat Street road works.

Ÿ   Soft Landscaping works.

Ÿ   Open area hard paving.

Ÿ   D12 & Open Area fire main laying works.

Ÿ   D9 to D12 and P22 to P25 drainage works.

Ÿ   Rumsey Street modification works.

Ÿ   EVB injection grouting work.

Ÿ   Promenade works at EVB.

Ÿ   IEC Eastbound Corbel construction

Ÿ   Road marking modification work at IEC Westbound downstream

Ÿ   Construction of enlarge parapet at IEC Eastbound.

Ÿ   IEC Westbound drainage modification work

Ÿ   Removal of launching girder components

Ÿ   Demolition of PRE Office

Ÿ    Bridge noise enclosure & parapet construction and road works.

Ÿ    Hing Fat Street road works.

Ÿ    Soft Landscaping works.

Ÿ    Open area hard paving.

Ÿ    D12 & Open Area fire main laying works.

Ÿ    D9 to D12 and P22 to P25 drainage works.

Ÿ    Rumsey Street modification works.

Ÿ    EVB injection grouting work.

Ÿ    Promenade works at EVB.

Ÿ    IEC Eastbound Corbel construction

Ÿ    Road marking modification work at IEC Westbound downstream

Ÿ    Construction of enlarge parapet at IEC Eastbound.

Ÿ    IEC Westbound drainage modification work

Ÿ    Removal of launching girder components

Ÿ    Demolition of PRE Office

 

 

Contract no. HY/2010/08 – Central and WanChai Bypass – Slip road 8 section under FEP-10/364/2009B

Table VII      Principal Work Activities for Contract no. HY/2010/08

March 2021March 2021

April 2021April 2021

May 2021May 2021

Ÿ   Drainage improvement works

Ÿ   Utility diversion works

Ÿ    Junction modificationDrainage improvement works

Ÿ    Utility diversion works

Ÿ   Junction modification

Ÿ   Drainage improvement works

Ÿ   Utility diversion works

Ÿ    Junction modificationDrainage improvement works

Ÿ    Utility diversion works

Ÿ   Junction modification

Ÿ   NiNi

 

Contract no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009/E

Table VIII       Principal Work Activities for Contract no. HY/2011/08

March 2021March 2021

Ÿ   Nil

 

 

Noise Monitoring

  1. Noise monitoring was conducted at M1b – Rooftop of Wan Chai Ferry Pier; M2b - Noon-day gun area; M3a - Tung Lo Wan Fire Station; M4b - Victoria Center; M5b - City Garden, M6 - HK Baptist Church Henrietta Secondary School, M7a – Harbour Building on a weekly basis.
  2. With respect to the demolition of Ex-Harbour Road Sports Centre, the respective noise monitoring station M1a – Harbour Road Sports Centre were finely adjusted on 16 and 25 May 2017 and thereafter to the Footbridge for Harbour Road Sports for noise monitoring.
  3. Noise monitoring at M4b - Victoria Centre was temporarily relocated to the G/F of Victoria Centre due to the access difficulty on 23 March 2020. The temporary noise monitoring point for M4b has been proposed and agreed by the IEC at the G/F of Victoria Centre. Noise monitoring for M4b resumed to original location on 7 September 2020.
  4. Noise monitoring at M7e - International Finance Centre (Eastern End of Podium), M7w - International Finance Centre (Western End of Podium) and M8 - City Hall were temporarily suspended on 16 June 2020 with respect to work completion confirmed by CWB RSS since 16 June 2020.
  5. Noise monitoring at M1b - Rooftop of Wan Chai Ferry Pier was temporarily suspended on 23 December 2020 with respect to work completion confirmed by WDII RSS since 22 December 2020.
  6. As confirmed with CWB RSS, major construction activities of HY/2009/15 under FEP-06/364/2009/A and HY/2010/08 under FEP-10/364/2009/B have been completed, only minor defects rectification works remains while no PME will be used for the remaining minor defects rectification works. As such, the noise monitoring stations M2b – Noon-day gun area and M3a – Tung Lo Wan Fire Station have been temporarily suspended from 22 March 2021 onward.
  7. As confirmed with CWB RSS, major construction activities of HY/2009/15 under FEP-06/364/2009/A and HY/2010/08 under FEP-10/364/2009/B have been completed, only minor defects rectification works remains while no PME will be used for the remaining minor defects rectification works. As such, the noise monitoring stations M2b – Noon-day gun area and M3a – Tung Lo Wan Fire Station have been temporarily suspended from 22 March 2021 onward.
  8. As confirmed with CWB RSS, the major construction works of HY/2009/19 at Rumsey Street Flyover and Planter under FEP-07/364/2009/H have been completed and no PME will be used for the remaining minor defects rectification works. As such, the noise monitoring station M7a – Harbour Building has been temporarily suspended from 24 May 2021 onward.
  9. Noise monitoring at M6 - HK Baptist Church Henrietta Secondary School was temporarily suspended from 30 November 2020 as the school is temporarily closed and refused our access due to public health concern. Monitoring has been resumed on 10 March 2021.
  10. Limit level exceedance was recorded at M6 - HK Baptist Church Henrietta Secondary School on 18 March 2021 in the reporting period. After the investigation, the exceedance was concluded as non-Project related.

 

       Real time Noise Monitoring

   xii.        24-hour real time noise monitoring was conducted at RTN1 - FEHD Hong Kong Transport Section Whitefield Depot for the pilling works in FEHD Whitfield Depot and RTN2 – Tunnel (North Point Section) and Island Eastern Corridor Link during the period from 28 September 2012 til 10am on 5 October 2012 in the reporting period.

  xiii.        Real time noise monitoring station at Oil Street Community Liaison Centre (RTN2- Oil Street Community Centre) was relocated from Oil Street Community Liaison Centre to Hong Kong Electric (RTN2a- Electric Centre) on 5 Oct which is a representative of the noise sensitive receiver City Garden. The baseline noise level of RTN2a will adopt the results derived from the baseline noise monitoring conducted in Electric Centre from 4 December 2009 to 17 December 2009.

  xiv.        As confirmed by CWB RSS, the IECL parapet removal operations will commence in March 2013.  Liaison was conducted with HK Baptist Church Henrietta Secondary School and Po Leung Kuk Yu Lee Mo Fan Memorial School regarding the set up of RTN3 real time noise monitoring station.  Po Leung Kuk Yu Lee Mo Fan Memorial School grant permission for set up on 4 Sep 2012 and station set up was performed on 14 Sep 2012.

   xv.        Real Time Noise Monitoring at RTN3- Po Leung Kuk Yu Lee Mo Fan Memorial School was commenced since 06 Oct 2012.

  xvi.        Causeway Bay Community Centre has granted permission for set up of real time noise monitoring station on 21 Dec 2012 and station set up was performed on 27 Dec 2012.  The Baseline noise level of RTN4- Causeway Bay Community Centre will adopt the results from the baseline noise monitoring report for EP/364/2009 in 22 April 2010 in which approved by EPD.

 xvii.        According to clause 3.1 stated in EP-364/2009B, “the real-time monitoring system shall be in place no later than two weeks before the commencement date of demolition works of the existing Island Eastern Corridor”. IEC demolition associated construction works was commenced on 3 Feb 2013 and Real time noise monitoring at RTN4-Causeway Bay Community Centre was commenced on 13 Jan 2013.

xviii.        Real-time noise monitoring station RTN1-FEHD Whitfield Depot was finely adjusted from 2/F to roof-top at FEHD Whitfield Depot on 24 June 2013 with respect to the commencement of advance works for IEC parapet demolition.

  xix.        With respect to the non-CWB Project building construction at Oil Street, the real-time noise monitoring station RTN2a- Hong Kong Electric Centre was finely adjusted from Northeast Side to Northwestern side at Roof Top location.

  1. As confirmed with CWB RSS, major construction activities of HY/2011/08 under FEP- 11/364/2009/E have been completed, only minor defects rectification works remains while no PME will be used for the remaining minor defects rectification works. As such, the noise monitoring station M4b, real-time noise monitoring stations RTN1, RTN2a and RTN4 were no longer associated with Contract HY/2011/08 from 9 February 2021 onward.
  2. 24-hour real time noise monitoring was conducted at RTN1- FEHD Hong Kong Transport Section Whitfield Depot. No limit level exceedance was recorded in the reporting period.

 

  1. 24-hour real time noise monitoring was conducted at RTN2a-Hong Kong Electric Centre. No limit level exceedance was recorded in the reporting period.

 

  1. 24-hour real time noise monitoring was conducted at RTN3 - Yu Lee Mo Fan Memorial School.

-               Limit level exceedances were recorded on 9, 10, 17 and 18 March 2021 in the reporting period. After the investigation, the exceedances were concluded as non-Project related.

  1. Limit level exceedance was recorded on 19, 21, 22 and 23 December 2020 in the reporting period. After the investigation, the exceedance was concluded as non-Project related.

-               No action or limit level exceedance was recorded in the April 2021 reporting period.

-                Limit level exceedance was recorded on 30, 31 December 2020, 14, 16, 18, 23, 25 and 26 January 2021 in the reporting period. After the investigation, the exceedance was concluded as non-Project related.

-               Limit level exceedance were recorded on 5, 6, 11, 12, 13, 17 and 21 May 2021 in the reporting period. After the investigation, all exceedances were concluded as non-project related.exceedance was recorded on 27 January 2021 in the reporting period. After the investigation, the exceedance was concluded as non-Project related.

 

  1. 24-hour real time noise monitoring was conducted at RTN4-Causeway Bay Community Centre. No action or limit level exceedance was recorded at in the reporting period.

 

Air Quality Monitoring

  1. Due to extension of site boundary by contractor of HY/2009/19, location of air quality monitoring station CMA1b – Oil Street Community Liaison Centre has been finely adjusted on 21 April 2012.
  2. With respect to the proposed demolition of eastern podium of Oil Street Site Office, the respective air quality monitoring station CMA1b – Oil Street Site Office was finely adjusted from East podium of the Oil Street Site Office to the West podium of the Oil Street Site Office on 21 December 2016.
  3. With respect to the proposed demolition of the Oil Street Site Office, the respective air quality monitoring station CMA1b – Oil Street Site Office was finely adjusted from the Oil Street Site Office to Harbor Grand Hotel Boundary Wall from 05 June 2017 onwards.
  4. With respect to work completion confirmed by CWB RSS, air quality monitoring at MA1e - International Finance Centre (Eastern End of Podium) and MA1w - International Finance Centre (Western End of Podium) were temporarily suspended from 16 June 2020 onwards and CMA5b - Pedestrian Plaza was temporarily suspended from 20 July 2020 onwards.
  5. 1-hour and 24-hour Total Suspended Particulates (TSP) monitoring were conducted at CMA1b - Harbor Grand Hotel Boundary Wall; CMA2a - Causeway Bay Community Center; CMA3a - CWB PRE Site Office Area; CMA4a – Society for the Prevention of Cruelty to Animals; MA1b – Harbour Building on every six days basis in the reporting period.
  6. With respect to work completion confirmed by WDII RSS, air quality monitoring at CMA4a –

Society for the Prevention of Cruelty to Animals was temporarily suspended and CMA3a- CWB PRE Site Office Area would no longer associated with Contract HK/2009/02 from 23 December 2020 onwards.

  1. As confirmed with CWB RSS, major construction activities of HY/2011/08 under FEP- 11/364/2009/E have been completed, only minor defects rectification works remains while no PME will be used for the remaining minor defects rectification works. As such, the air quality monitoring stations CMA1b - Harbour Grand Hotel Boundary Wall and CMA2a – Causeway Bay Community Centre were no longer associated with Contract HY/2011/08 from 9 February 2021 onward.
  2. As demolition of concrete slab work will be conducted at CMA1b - Harbour Grand Hotel Boundary Wall and there is no other appropriate locations for installation of sampler, air quality monitoring station CMA1b - Harbour Grand Hotel Boundary Wall will be represented by CMA2a-Causeway Bay Community Centre from 12 March 2021 onward due to short separation distance between two stations.
  3. As confirmed with CWB RSS, major construction activities of HY/2009/15 under FEP-06/364/2009/A and HY/2010/08 under FEP-10/364/2009/B have been completed, only minor defects rectification works remains while no PME will be used for the remaining minor defects rectification works. As such, the air quality monitoring station CMA3a – CWB PRE site office has been temporarily suspended from 22 March 2021 onward.
  4. As confirmed with CWB RSS, the major construction works of HY/2009/19 at Rumsey Street Flyover and Planter under FEP-07/364/2009/H have been completed and no PME will be used for the remaining minor defects rectification works. As such, the air quality monitoring station MA1b – Harbour Building has been temporarily suspended from 24 May 2021 onward.
  5. No action or limit level exceedance was recorded in the December March 20201 reporting period.
  6. Two action level exceedances of 24hr TSP were recorded at CMA2a and MA1b on 17 April 2021 in the reporting period. After the investigation, all exceedances were concluded as non-project related.
  7. No action or limit level exceedance was recorded in the January 2021 reporting period.
  8. No action or limit level exceedance was recorded in the FebruaryMay 2021 reporting period.

 

Complaints, Notifications of Summons and Successful Prosecutions

  1. An ICC complaint was referred to the ET on 10 March 2021 (CASE Ref: CASE# 3-6647057872). The complainant reported that suspected disposal of construction waste into the sea was observed at the works area underneath IEC on 8 March 2021 and video could be provided for follow-up.

The ET confirmed with the Resident Site Staff that:

The complainant was unable to be reached at this moment and no such video is available;

According to the site records, removal of the temporary work at the marine pile caps in front of City Garden Block 6 was undertaken on the date of the incident (8 March 2021);

The construction waste handling procedures for the concerned construction activities are as follows:

                      I.        Break up temporary concrete plinths on the pile caps underneath existing IEC bridge;

                     II.        Clear the concrete debris by collecting them in nylon bags; and

                    III.        Transport the occupied nylon bags to stockpile area at land portion of C19 site by marine vessel for further disposal off site to Public Fill Reception Facilities by dump truck.

As the video mentioned in the complaint is unavailable, there is no sufficient information to conclude that the complaint was considered as related to the removal of the temporary work at the marine pile caps in front of City Garden Block 6.

Despite the RSS advised that specific construction waste handling procedures for removal of the temporary work at the marine pile caps were available on the date of incident, the Contractor of HY/2009/19 was recommended to provide training to site personnel in proper waste management as preventive measure.

  1. An ICC complaint was referred to the ET on 9 December 2020 (CASE Ref: CASE# 3-6572708255). The complainant reported that the newly planted trees at SR13 were suspected to be unhealthy and withered.

The ET confirmed with the Resident Site Staff that:

-                 It is confirmed that the location and species of the concerned planted trees are tallied with the latest approved landscape plan.

-                 The planting date for such trees is 19 October 2020.

-                 Regular maintenance (i.e. establishment works under C19 Contract) should be provided for the concerned trees including but not limited to (i) daily watering and (ii) pruning when necessary.  After the establishment works under C19, the soft landscaping works will be handed over and maintained by LCSD.

-                 Latest concern tree information:

(i) Species – Lagerstroemia speciosa

(ii) Health condition – Fair

(iii) Planting location – SR13

 

In view of the above information, the complaint was considered as related to the newly planted trees at SR13. The planting date for such trees is 19 October 2020. The RSS confirmed that the location and species of the concerned trees planted at SR13 are tallied with the latest submitted landscape plan and health condition of such trees is fair.

 

Despite the RSS advised that the location and species of the trees at SR13 were planted in according to the latest submitted landscape plan and health condition of such trees is fair, the Contractor of HY/2009/19 was recommended to provide proper maintenance to the planted trees at SR13. A follow-up inspection was conducted for the trees at SR13 on 16 December 2020 and was found tally with the information provided by the Contractor.

  1. No environmental complaints, summons and prosecutions were received in the January April 2021 reporting period.
  2. No environmental complaints, summons and prosecutions were received in the February May 2021 reporting period.

 

 

 

1.         Introduction

1.1          Scope of the Report

1.1.1.     Lam Geotechnics Limited (LGL) has been appointed to work as the Environmental Team (ET) under Environmental Permit no. EP-364/2009/H and Further Environmental permit nos. FEP-01/364/2009, FEP-06/364/2009/A, FEP-07/364/2009/H, FEP-10/364/2009/B and FEP-11/364/2009/E to implement the Environmental Monitoring and Audit (EM&A) programme as stipulated in the EM&A Manual of the approved Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A Manual of the approved EIA Report for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001).

1.1.2.     This report presents the environmental monitoring and auditing work carried out in accordance to the Section 10.3 of EM&A Manual and “Environmental Monitoring and Audit Requirements” under Particular Specification Section 27.

1.1.3.     This report documents the finding of EM&A works during the period from 27 November February 20201 to 26 February May 2021.

1.2          Structure of the Report

 

Section 1          Introduction – details the scope and structure of the report.

 

Section 2          Project Background – summarizes background and scope of the project, site description, project organization and contact details of key personnel during the reporting period.

 

Section 3          Monitoring Requirements – summarizes all monitoring parameters, monitoring locations, monitoring frequency, duration and action plan.

 

Section 4          Monitoring Results – summarizes the monitoring results obtained in the reporting period.

 

Section 5          Compliance Audit – summarizes the auditing of monitoring results, all exceedances environmental parameters.

 

Section 6          Complaints, Notification of summons and Prosecution – summarizes the cumulative statistics on complaints, notification of summons and prosecution

 

Section 7          Cumulative Construction Impact due to the Concurrent Projects summarizes the relevant cumulative construction impact due to the concurrent activities of the concurrent Projects.

 

Section 8          Conclusion

2.         Project Background

2.1          Background

2.1.1.     “Wan Chai Development phase II and Central-Wan Chai Bypass” and “Central-Wan Chai Bypass and Island Eastern Corridor Link” (hereafter called “the Project”) are Designed Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO).  The Environmental Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan Chai Development phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) have been approved on 31 August 2001 and 11 December 2008 respectively.

2.1.2.     The key purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai North and North Point for construction of the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed under the project will be developed as a world-class waterfront promenade joining that at the new Central waterfront for public enjoyment.

2.1.3.     There is a compelling and present need for the CWB to provide relief to the very congested east-west Connaught Road Central/Harcourt Road / Gloucester Road Corridor (the Corridor) which is currently operating beyond its capacity. The CWB will provide relief to the existing congestion along the Corridor and cater for the anticipated growth of traffic on Hong Kong Island. Without the CWB and its access roads, there will not be sufficient capacity to serve the heavy traffic demands at both strategic and local levels.

 

2.2          Scope of the Project and Site Description

2.2.1.     Design and Construction of Central – Wan Chai Bypass and Island Eastern Corridor Link under the Project involves the construction and operation of a trunk road and its road tunnel more than 800m in length between portals that is shown at Figure 2.1.

2.2.2.     The study area encompasses existing developments from Central to North Point. The scope of the Central-Wanchai Bypass (CWB) and Island Eastern Corridor Link (IECL) includes:

·          A dual three-lane trunk road, approximately 4.5 km in length, and tunnel approximately 3.7 km in length defined from the connection with the existing Rumsey Street Flyover in Central, through to a connection with the existing Island Eastern Corridor to the east of the Causeway Bay Typhoon Shelter (CBTS);

·          The Central Interchange near the Rumsey Street Flyover to provide road connections to the Central area;

·          Tunnel control buildings and ventilation buildings;

·          Slip roads to connect the CWB to the local road system in the Wan Chai North and Causeway Bay area;

·          Associated road lighting, road signing, traffic control and surveillance system; and

·          Other associated works.

 

2.2.3.     The project also contains various Schedule 2 DPs that, under the EIAO, require Environmental Permits (EPs) to be granted by the DEP before they may be either constructed or operated. Table 2.1 summarises the five individual DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.

Table 2.1    Schedule 2 Designated Projects under this Project

Item

Designated Project

EIAO Reference

Reason for inclusion

DP1

Central-Wanchai Bypass (CWB) including its road tunnel and slip roads

Schedule 2, Part I, A.1 and A.7

Trunk road and road tunnel more than 800 m in length

DP2

Road P2 and other roads which are classified as primary/district distributor roads

Schedule 2, Part I, A.1

Primary / district distributor roads

DP3

Reclamation works including associated dredging works

Schedule 2, Part I, C.1 and C.12

Reclamation more than 5 ha in size and a dredging operation less than 100 m from a seawater intake point

DP5

Wan Chai East Sewage Outfall

Schedule 2, Part I, F.5 and F.6

Submarine sewage pipelines with a total diameter more than 1,200 mm and include a submarine sewage outfall

DP6

Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha Tsui

Schedule 2, Part I, C.12

A dredging operation less than 100 m from a seawater intake point

 

2.3          Division of the Project Responsibility

2.3.1.     Due to the multi-contract nature of the Project, there are a number of contracts sub-dividing the whole works area into different work areas to be commenced.  Contractors of individual contracts will be required by the EP holder to apply Further Environmental Permits such that the impact monitoring stations are sub-divided accordingly to facilitate the implementation of EM&A programme and to streamline the EM&A reporting for individual FEP holders correspondingly.

2.3.2.     In the reporting period, the following construction Contracts were on-going and Contract HY/2009/01, HY/2009/17, 04/HY/2006, HY/2009/15, HY/2009/18 and HK/2010/06 had been completed. The details of individual contracts are summarized in Table2.2.

Table 2.2    Details of Individual Contracts under the Project

Contract No.

Contract Title

Associated DP(s)

Construction Commencement Date

HY/2009/17

Central – Wan Chai Bypass (CWB) at FEHD Whitfield Depot – Advanced piling works.

DP1

5 October 2010

(Completed)

HY/2009/18

Central – Wan Chai Bypass (CWB) – Central Interchange

DP1

21 April 2011

(Completed)

04/HY/2006

Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street

DP1

September 2010

(Completed)

HK/2009/01

Wan Chai Development Phase II – Central – Wan Chai Bypass at Hong Kong Convention and Exhibition Centre – Tunnel Works

DP1, DP2

25 August 2011

(Completed)

HK/2009/02

Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel)

DP1

26 April 2011

HY/2009/15

Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section)

DP1

13 July 2011

 

HY/2009/19

Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link

DP1

24 March 2011

HK/2010/06

Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen Wan Line

DP3

22 March 2011

(Completed)

HK/2012/08

Wan Chai Development Phase II- Central-Wan Chai Bypass at Wan Chai West

DP1,DP2, DP3

10 March 2014

(Completed)

HY/2010/08

Central- Wanchai Bypass Tunnel – Tunnel (Slip Road 8)

DP1, DP2, DP3

21 March 2013

HY/2011/08

Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning

DP1

8 October 2014

(Completed)

 

2.3.3.     The construction works of Contract no. 04/HY/2006 – Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong Street under FEP-04/364/2009/A was completed, and the FEP was surrendered by the Contractor on 11 February 2011.

2.3.4.     Construction of bored pile E3B under HY/2009/17 was confirmed completed and the respective work area under FEP-03/364/2009 was handover and inspected under HY/2009/19 from 19 Dec 2012 onwards. Subsequently, the FEP-03/364/2009 was surrendered by the Contractor on 28 March 2013.

2.3.5.     Construction works under HK/2010/06 was confirmed completed and the respective work area under FEP-08/364/2009/A was handover and inspected under HK/2012/08 from 22 Sep 2014 onwards. Subsequently, the FEP-08/364/2009/A was surrendered by the Contractor on 3 October 2014.

2.3.6.     The Construction works under HY/2009/15 was confirm completed by the RSS from 27 October 2017 onwards. The weekly site audit inspection and the associated monitoring station for HY/2009/15 were temporary suspended from 27 October 2017 onwards.

2.3.7.     The Construction works under HY/2009/18 was confirm completed by the RSS from 25 April 2018 onwards. The weekly site audit inspection and the associated monitoring station for HY/2009/18 were temporary suspended from 27 April 2018 onwards.

2.3.8.     As confirmed with WDII RSS and with respect to the joint inspection conducted with IEC on 25 May 2018, RSS, ET and IEC share the view that there is no adverse environmental impact of remaining works under Contract HK/2009/01 and the respective environmental site inspection and associated monitoring station were temporary suspended from 26 May 2018 onwards. FEP-02/364/2009 was surrendered by the Contractor on 3 September 2018.

2.3.9.     As confirmed with CWB RSS, major construction activities of HY/2011/08 under FEP-11/364/2009/E have been completed, only minor defects rectification works remains while no PME will be used for the remaining minor defects rectification works. As such, the weekly environmental site inspection for Contract no. HY/2011/08 has been temporarily suspended from 20 July 2020 onward.

2.3.10.   As confirmed with WDII RSS, there is no more remaining works for HK/2009/02 under EP- 364/2009 on 22 December 2020 and agreed with IEC on 23 December 2020, the weekly environmental site inspection for Contract no. for HK/2009/02 under EP-364/2009/H was suspended from 23 December 2020 onward.

2.3.11.      As confirmed with CWB RSS, major construction activities of HY/2009/15 under FEP-06/364/2009/A and HY/2010/08 under FEP-10/364/2009/B have been completed, only minor defects rectification works remains while no PME will be used for the remaining minor defects rectification works. As such, the weekly environmental site inspection for Contract no. HY/2009/15 and HY/2010/08 have been temporarily suspended from 22 March 2021 onward.

 

 

 

2.4          Project Organization and Contact Personnel

2.4.1.     Civil Engineering and Development Department and Highways Department are the overall project controllers for the Wan Chai Development Phase II and Central-Wan Chai Bypass respectively. For the construction phase of the Project, Project Engineer, Contractor(s), Environmental Team and Independent Environmental Checker are appointed to manage and control environmental issues.

2.4.2.     The proposed project organization and lines of communication with respect to environmental protection works are shown in Figure 2.2.  Key personnel and contact particulars are summarized in Table 2.3.

Table 2.3    Contact Details of Key Personnel

Party

Role

Post

Name

Contact No.

Contact Fax

AECOM

Engineer’s Representative for WDII

Senior Resident Engineer

Mr. S.K. Lo

3519 9033

2587 1877

Engineer’s Representative  for CWB

President Resident Engineer

Mr. David Kwan

3762 2759

2142 5577

Chun Wo – CRGL Joint Venture

Contractor under Contract no. HK/2009/02

Site Agent

Mr. David Yan

9106 3890

2827 9996

Environmental Officer

Mr. Samuel Chan

9646 5780

3758 8551

Chun Wo - CRGL - MBEC Joint Venture

Contractor under Contract no. HY/2009/19

Project Manager

Mr. William Leung

3758 8879

3757 8901

Site Agent

Mr. William Luk

9456 9819

Deputy Site Agent

Mr. Andrew Cheng

9161 9446

Environmental Officer

Mr. Kenneth Chan

6387 3939

Construction Manager (Marine)

Mr. Wingo Wong

9300 2625

Construction Manager (Noise Barrier)

Mr. Jerry Siu

9493 3664

Construction Manager (Land)

Mr. Yung Kwok Wah

9834 1010

China State Construction Engineering (HK) Ltd.

Contractor under Contract no. HY/2009/15

Project Director

Mr. Chris Leung

3577 6393

2865 5229

Site Agent

Mr. Patrick Ho

3557 6405

2566 2192

Environmental Officer

Mr. Gabriel Wong

6114 9590

China State

Contractor under Contract no. HY/2010/08

Project Director

Mr. Chris Leung

3467 4299

3586 9303

Project Manager

Mr. Chan Ying Lun

3418 3001

Site Agent

Mr. Danny Chan

9232 4754

Environmental Officer

Mr. Gabriel Wong

6114 9590

Lam Geotechnics Limited

Environmental Team (ET)

Environmental Team Leader (ETL)

Mr. Raymond Dai

2882 3939

2882 3331

RAMBOLL Limited

Independent Environmental Checker (IEC)

Independent Environmental Checker (IEC)

Mr. David Yeung

3465 2888

3465 2899

 

 

2.5          Principal Work and Activities

2.5.1.     Major construction activities for Contract no. HK/2009/02 have been commenced on 26 April 2011. During this reporting period, the principal work activities are summarized in Table2.6:

Table 2.6    Principal Work Activities for Contract no. HK/2009/02

March 2021December 2020

April 2021January 2021

May 2021February 2021

Ÿ    Seepage rectification works at CWB tunnel.Tunnel water seepage rectification works

Ÿ   Demolition of Site Office and associated civil works

Ÿ   Seepage rectification works at CWB tunnel.Nil

Ÿ   Seepage rectification works at CWB tunnel.

Ÿ    Seepage rectification works at CWB tunnel.

 

 

2.5.2.     Major construction activities for Contract no. HY/2009/19 have been commenced on March 2011. During this reporting period, the principal work activities are summarized in Table 2.8:

Table 2.8    Principal Work Activities for Contract no. HY/2009/19

March 2021December 2020

April 2021January 2021

May 2021February 2021

Ÿ   Bridge noise enclosure & parapet construction and road works.

Ÿ   Hing Fat Street road works.

Ÿ   Soft Landscaping works.

Ÿ   Open area hard paving.

Ÿ   D12 & Open Area fire main laying works.

Ÿ   D9 to D12 and P22 to P25 drainage works.

Ÿ   Rumsey Street modification works.

Ÿ   EVB injection grouting work.

Ÿ   Promenade works at EVB.

Ÿ   IEC Eastbound Corbel construction

Ÿ   Road marking modification work at IEC Westbound downstream

Ÿ   Construction of enlarge parapet at IEC Eastbound.

Ÿ   IEC Westbound drainage modification work

Ÿ    Removal of launching girder componentsBridge noise enclosure construction & parapet construction and road works.

Ÿ    Hing Fat Street road works.

Ÿ    Soft Landscaping works.

Ÿ    Open area hard paving

Ÿ    D12 & Open Area fire main laying works.

Ÿ    D9 to D12 and P22 to P25 drainage works.

Ÿ    Rumsey Street modification works.

Ÿ    EVB injection grouting work.

Ÿ    Promenade works at EVB.

Ÿ   IEC Eastbound Corbel construction

Ÿ   Bridge noise enclosure & parapet construction and road works.

Ÿ   Hing Fat Street road works.

Ÿ   Soft Landscaping works.

Ÿ   Open area hard paving.

Ÿ   D12 & Open Area fire main laying works.

Ÿ   D9 to D12 and P22 to P25 drainage works.

Ÿ   Rumsey Street modification works.

Ÿ   EVB injection grouting work.

Ÿ   Promenade works at EVB.

Ÿ   IEC Eastbound Corbel construction

Ÿ   Road marking modification work at IEC Westbound downstream

Ÿ   Construction of enlarge parapet at IEC Eastbound.

Ÿ   IEC Westbound drainage modification work

Ÿ   Removal of launching girder components

Ÿ    Demolition of PRE OfficeBridge noise enclosure construction & parapet construction and road works.

Ÿ    Hing Fat Street road works.

Ÿ    Soft Landscaping works.

Ÿ    Open area hard paving

Ÿ    D12 & Open Area fire main laying works.

Ÿ    D9 to D12 and P22 to P25 drainage works.

Ÿ    Rumsey Street modification works.

Ÿ    EVB injection grouting work.

Ÿ    Promenade works at EVB.

Ÿ    IEC Eastbound Corbel construction

Ÿ    Road marking modification work at IEC Westbound downstream

Ÿ   Construction of enlarge parapet at IEC Eastbound

Ÿ   Bridge noise enclosure & parapet construction and road works.

Ÿ   Hing Fat Street road works.

Ÿ   Soft Landscaping works.

Ÿ   Open area hard paving.

Ÿ   D12 & Open Area fire main laying works.

Ÿ   D9 to D12 and P22 to P25 drainage works.

Ÿ   Rumsey Street modification works.

Ÿ   EVB injection grouting work.

Ÿ   Promenade works at EVB.

Ÿ   IEC Eastbound Corbel construction

Ÿ   Road marking modification work at IEC Westbound downstream

Ÿ   Construction of enlarge parapet at IEC Eastbound.

Ÿ   IEC Westbound drainage modification work

Ÿ   Removal of launching girder components

Ÿ   Demolition of PRE Office

Ÿ    Bridge noise enclosure & parapet construction and road works.

Ÿ    Hing Fat Street road works.

Ÿ    Soft Landscaping works.

Ÿ    Open area hard paving.

Ÿ    D12 & Open Area fire main laying works.

Ÿ    D9 to D12 and P22 to P25 drainage works.

Ÿ    Rumsey Street modification works.

Ÿ    EVB injection grouting work.

Ÿ    Promenade works at EVB.

Ÿ    IEC Eastbound Corbel construction

Ÿ    Road marking modification work at IEC Westbound downstream

Ÿ    Construction of enlarge parapet at IEC Eastbound.

Ÿ    IEC Westbound drainage modification work

Ÿ    Erection of bamboo scaffold

 

2.5.3.     Major construction activities for Contract no. HY/2010/08 have been commenced on March 2013. During the reporting period, the principal work activities are summarized in Table 2.10

             Table 2.10     Principal Work Activities for Contract no. HY/2010/08

March 2021December 2020

April 2021January 2021

May 2021February 2021

Ÿ   Drainage improvement works

Ÿ   Utility diversion works

Ÿ    Junction modificationDrainage improvement works

Ÿ    Utility diversion works

Ÿ   Junction modification

Ÿ   Drainage improvement works

Ÿ   Utility diversion works

Ÿ    Junction modificationDrainage improvement works

Ÿ    Utility diversion works

Ÿ   Junction modification

Ÿ    NiDrainage improvement works

Ÿ    Utility diversion works

Ÿ   Junction modification

 

2.5.4.     Contract no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009/E. During the reporting period, the principal work activities are summarized in Table 2.11

            Table 2.11   Principal Work Activities for Contract no. HY/2011/08

March 2021December 2020

Ÿ   Nil

 

 

2.5.5.     Implementation status of the recommended mitigation measures during this reporting period is presented in Appendix 2.1.

3.         Monitoring Requirements

3.1.          Noise Monitoring

Noise Monitoring Stations

3.1.1.     The noise monitoring stations for the Project are listed and shown in Table 3.1 and Figure 3.1.  Appendix 3.1 shows the established Action/Limit Levels for the monitoring works.

Table 3.1    Noise Monitoring Station

Station

Description

M1b***

Rooftop of Wan Chai Ferry Pier

M2b

Noon Gun Area

M3a

Tung Lo Wan Fire Station

M4b

Victoria Centre

M5b

City Garden

M6

HK Baptist Church Henrietta Secondary School

M7a

Harbour Building

M7e*

International Finance Centre (Eastern End of Podium)

M7w

International Finance Centre (Western End of Podium)

M8**

City Hall

Remark*: Location ID has been updated from M7 to M8 for City Hall

Remark**: M7e has become a reference station starting from 7 Aug 2012

Remarks***: The monitoring station M1a was relocated as M1b – Rooftop of Wan Chai Ferry Pier on 2 November

2020.

 

Real time Noise Monitoring Stations

3.1.2.     The noise monitoring stations for the Project are listed and shown in Table 3.2 and Figure 3.1.. Appendix 3.1 shows the established Action/Limit Levels for the monitoring works.

Table 3.2    Real Time Noise Monitoring Station

District

Station

Description

Tin Hau

RTN1

FEHD Hong Kong Transport Section Whitefield Depot

North Point

RTN2a*

Electric Centre

North Point

RTN3

Po Leung Kuk Yu Lee Mo Fan Memorial School

Tin Hau

RTN4

Causeway Bay Community Centre

Remarks*: RTN2 was relocated from Oil Street Community Liaison Centre to Electric Centre on 05 Oct 2012 and re-designated as RTN2a.

 

Noise Monitoring Parameters, Frequency and Duration

3.1.3.     The construction noise level shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq (30 minutes) shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. For all other time periods, Leq (5 minutes) shall be employed for comparison with the Noise Control Ordinance (NCO) criteria. Supplementary information for data auditing, statistical results such as L10 and L90 shall also be obtained for reference.

3.1.4.     Noise monitoring shall be carried out at all the designated monitoring stations. The monitoring frequency shall depend on the scale of the construction activities. The following is an initial guide on the regular monitoring frequency for each station on a weekly basis when noise generating activities are underway:

·          One set of measurements between 0700 and 1900 hours on normal weekdays.

3.1.5.     Real time noise shall be carried out at the designated monitoring stations. The following is an initial guide on the regular monitoring frequency for each station on a 24 hours daily basis when noise generating activities are underway:

·          One set of measurements between 0700 and 1900 hours on normal weekdays.

·          One set of measurements between 1900 and 2300 hours on normal weekdays and 0700 and 2300 hours on public holidays.

·          One set of measurements between 2300 and 0700 hours on next day on everyday.

3.1.6.     If construction works are extended to include works during the hours of 1900 – 0700 as well as public holidays and Sundays, additional weekly impact monitoring shall be carried out during respective restricted hours periods. Applicable permits under NCO shall be obtained by the Contractor.

Monitoring Equipment

3.1.7.     As referred to in the Technical Memorandum ™ issued under the NCO, sound level meters in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying out the noise monitoring. Immediately prior to and following each noise measurement the accuracy of the sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency. Measurements may be accepted as valid only if the calibration level from before and after the noise measurement agree to within 1.0 dB.

3.1.8.     Noise measurements shall not be made in fog, rain, wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with a portable wind speed meter capable of measuring the wind speed in m/s.

3.1.9.     The sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency before deployment to the site and during each site visit. Measurements may be accepted as valid only if the calibration level from before and after the noise measurement agree to within 1.0 dB.

3.2.          Air quality monitoring

Air Quality Monitoring Stations

3.2.1.     The air quality monitoring stations for the Project are listed and shown in Table 3.3 and Figure 3.1. Appendix 3.1 shows the established Action/Limit Levels for the monitoring works.

Table 3.3  Air quality monitoring Stations

Station ID

Monitoring Location

Description

CMA1b

Harbour Grand Hotel Boundary Wall

North Point

CMA2a

Causeway Bay Community Centre

Causeway Bay

CMA3a

CWB PRE Site Office

Causeway Bay

CMA4a

Society for the Prevention of Cruelty to Animals

Wan Chai

CMA5b

Pedestrian Plaza**

Wan Chai

MA1e

International Finance Centre (Eastern End of Podium)

Central

MA1w

International Finance Centre (Western End of Podium)

Central

MA1b

Harbour Building

Central

Remarks*: The location ID of monitoring station CMA1b was updated as “Oil Street Site Office” in April 2013. With respect to the removal of Oil Street Site Office, the respective air quality monitoring station CMA1b was finely adjusted on 11 September 2015. The location ID of monitoring station CMA1b was updated as “Harbour Grand Hotel Boundary Wall” with respect to the fine adjustment of monitoring station from the Oil Street Site Office to Harbour Grand Hotel Boundary Wall from 05 June 2017 onwards due to demolition of Oil Street Site Office.

Remarks**:  With respect to the area handover, the air quality monitoring station CMA5a at Children Playgrounds opposite to the Pedestrian Plaza was relocated to the Pedestrian Plaza on 3 December 2014. The station reference and location ID of the air quality monitoring station CMA5a was updated as CMA5b and Pedestrian Plaza respectively.

 

Air quality monitoring Parameters, Frequency and Duration

3.2.2.     One-hour and 24-hour TSP levels should be measured to indicate the impacts of construction dust on air quality. The 24-hour TSP levels shall be measured by following the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.

3.2.3.     All relevant data including temperature, pressure, weather conditions, elapsed-time meter reading for the start and stop of the sampler, identification and weight of the filter paper, and any other local atmospheric factors affecting or affected by site conditions, etc., shall be recorded down in detail.

3.2.4.     For regular impact monitoring, the sampling frequency of at least once in every six-days, shall be strictly observed at all the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least three times in every six-days should be undertaken when the highest dust impact occurs.

Sampling Procedure and Monitoring Equipment

3.2.5.     High volume samplers (HVSs) in compliance with the following specifications shall be used for carrying out the 1-hour and 24-hour TSP monitoring:

·          0.6 – 1.7 m3 per minute adjustable flow range;

·          Equipped with a timing / control device with +/- 5 minutes accuracy for 24 hours operation;

·          Installed with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;

·          Capable of providing a minimum exposed area of 406 cm2;

·          Flow control accuracy: +/- 2.5% deviation over 24-hour sampling period;

·          Equipped with a shelter to protect the filter and sampler;

·          Incorporated with an electronic mass flow rate controller or other equivalent devices;

·          Equipped with a flow recorder for continuous monitoring;

·          Provided with a peaked roof inlet;

·          Incorporated with a manometer;

·          Able to hold and seal the filter paper to the sampler housing at horizontal position;

·          Easily changeable filter; and

·          Capable of operating continuously for a 24-hour period.

 

3.2.6.     Initial calibration of dust monitoring equipment shall be conducted upon installation and thereafter at bi-monthly intervals. The transfer standard shall be traceable to the internationally recognized primary standard and be calibrated annually. The concern parties such as IEC shall properly document the calibration data for future reference. All the data should be converted into standard temperature and pressure condition.

3.2.7.     Laboratory Measurement / Analysis

3.2.8.     A clean laboratory with constant temperature and humidity control, and equipped with necessary measuring and conditioning instruments to handle the dust samples collected, shall be available for sample analysis, and equipment calibration and maintenance. The laboratory should be HOKLAS accredited.

3.2.9.     Filter paper of size 8” x 10” shall be labelled before sampling. It shall be a clean filter paper with no pinholes, and shall be conditioned in a humidity-controlled chamber for over 24-hours and be pre-weighed before use for the sampling.

3.2.10.   After sampling, the filter paper loaded with dust shall be kept in a clean and tightly sealed plastic bag. The filter paper shall then be returned to the laboratory for reconditioning in the humidity controlled chamber followed by accurate weighing by an electronic balance with readout down to 0.1 mg. The balance shall be regularly calibrated against a traceable standard.

3.2.11.   All the collected samples shall be kept in a good condition for 6 months before disposal.

4.       Monitoring Results

4.0.1.     Per EPD’s letter dated 3 Aug 2012 (received by ET on 6 Aug 2012 through HyD), noise monitoring at M8 – City Hall commenced on 7 Aug 2012, and the monitoring station M7e – International Finance Centre (Eastern Podium) has become a reference station starting from 7 Aug 2012.

4.0.2.     Due to safety concerns, the monitoring location for M4b – Victoria Centre has been finely adjusted from 7 June 2012.

4.0.3.     Monitoring for report of review baseline noise level was performed from 11 April 2011 to 8 June 2011.  Then the report was submitted on the 20 June 2011, verified by IEC on 18 July 2011 and was approved by ER by January 2012.  The new baseline is used for the noise calculation starting from the January 2012 reporting period.

4.0.4.     The environmental monitoring will be implemented based on the division of works areas of each designed project managed under different contracts with separate FEP applied by individual contractors.  Overall layout showing work areas of various contracts, latest status of work commencement and monitoring stations is shown in Figure 2.1 and Figure 3.1. The monitoring results are presented in according to the Individual Contract(s).

4.0.5.     The Construction works under HY/2009/18 was confirm completed by the RSS from 25 April 2018 onwards. The associated monitoring station for HY/2009/18 were temporary suspended from 27 April 2018 onwards.

4.0.6.     The Construction works under HY/2009/15 was confirm completed by the RSS from 27 October 2017 onwards. The associated monitoring station for HY/2009/15 were temporally suspended from 27 October 2017 onwards.

4.0.7.     As confirmed with WDII RSS and with respect to the joint inspection conducted with IEC on 25 May 2018, RSS, ET and IEC share the view that there is no adverse environmental impact of remaining works under Contract HK/2009/01 and the associated monitoring station were temporary suspended from 26 May 2018 onwards.

4.0.8.     In the reporting period, the concurrent contracts are as follows:

Ÿ   Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/H

Ÿ   Contract no. HK/2009/02 Wanchai Development Phase II – Central- Wanchai Bypass at Wanchai East under FEP-01/364/2009

Ÿ   Contract no. HY/2010/08 – Central and WanChai Bypass – Slip road 8 Section under FEP-10/364/2009/B

Ÿ   Contract no. HY/2011/08 –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009/E

 

  4.1.       Noise Monitoring Results

 

Contract no. HK/2009/02 - Wanchai Development Phase II - Central - Wanchai Bypass at Wanchai East (CWB Tunnel) under FEP-01/364/2009

4.1.1.                The commencement of construction works for Contract no. HK/2009/02 under FEP-01/364/2009 is on 26 April 2011.The proposed division of air quality monitoring stations are summarized in Table 4.2 below. The monitoring station M1a was relocated as M1b – Rooftop of Wan Chai Ferry Pier on 2 November 2020.

Table 4.2    Noise Monitoring Stations for Contract no. HK/2009/02

Station

Description

M1b

Rooftop of Wan Chai Ferry Pier

Reporting period of December 2020

4.1.1.                No action or limit level exceedance was recorded in the reporting period.

4.1.1.                As confirmed with WDII RSS, there is no more remaining works for HK/2009/02 under EP- 364/2009 on 22 December 2020 and agreed with IEC on 23 December 2020. The noise monitoring at M1b - Rooftop of Wan Chai Ferry Pier was temporarily suspended on 23 December 2020.

4.1.1.                Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 4.1.

 

Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/H

4.1.1.     Noise monitoring for the tunnel works under contract no. HY/2009/19 was commenced on 24 April 2011. The proposed division of noise monitoring stations are summarized in Table 4.4 below.

Table 4.4    Noise Monitoring Stations for Contract no. HY/2009/19

Station

Description

M4b

Victoria Centre

M5b

City Garden

M6

HK Baptist Church Henrietta Secondary School

M7a

Harbour Building

 

         

 

 

 

Reporting period of December March 20210

4.1.1       Limit level exceedance was recorded at M6 - HK Baptist Church Henrietta Secondary School on 18 March 2021 in the reporting period.

4.1.2       No construction works was conducted under HY/2009/19 around the monitoring location. As such, the exceedance was considered as non-Project related.

4.1.1.                No action or limit level exceedance was recorded in this reporting period.

Reporting period of AprilJanuary 2021

4.1.2.     No action or limit level exceedance was recorded in this reporting period.

Reporting period of FebruaryMay 2021

4.1.3.     No action or limit level exceedance was recorded in this reporting period.

4.1.4.     Noise monitoring at M6 - HK Baptist Church Henrietta Secondary School was temporarily suspended from 30 November 2020 as the school is temporarily closed and refused our access due to public health concern. Monitoring has been resumed on 10 March 2021.

4.1.1.                Noise monitoring at M6 - HK Baptist Church Henrietta Secondary School was temporarily suspended from 30 November 2020 as the school is temporarily closed and refused our access due to public health concern. Monitoring will be resumed when the access to the school is granted.

4.1.5.     Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 4.1 and the Notification of Exceedance can be referred in Appendix 6.2.

4.1.6.     As confirmed with CWB RSS, the major construction works of HY/2009/19 at Rumsey Street Flyover and Planter under FEP-07/364/2009/H have been completed and no PME will be used for the remaining minor defects rectification works. As such, the noise monitoring station M7a – Harbour Building has been temporarily suspended from 24 May 2021 onward.

Contract no. HY/2010/08 – Central-Wanchai Bypass –Wanchai Bypass Tunnel (Slip Raod 8 Section) under FEP-10/364/2009/B

4.1.7.     The commencement of construction works for Contract no. HY/2010/08 under FEP-10/364/2009/B was on 02 September 2013. Noise monitoring was commenced on 02 September 2013. The proposed divisions of noise monitoring stations are summarized in Table 4.5 below.

Table 4.5    Noise Monitoring Stations for Contract no. HY/2010/08

Station

Description

M2b

Noon Gun Area

M3a

Tung Lo Wan Fire Station

4.1.8.     As confirmed with CWB RSS, junction modification works in Central area would be conducted by Contract HY/2010/08 starting from July 2018 and tentatively completed in September 2018. The noise monitoring station M7e - International Finance Centre (Eastern End of Podium), M7w - International Finance Centre (Western End of Podium) and M8 City Hall would tentatively associated with Contract HY/2010/08.

4.1.9.     As confirmed with Resident Site Staff, the junction modification under Contract HY/2010/08 at Central Area was generally completed while the remaining works was considered to be no adverse impact and not related to DP works. As such, The noise monitoring station M7e - International Finance Centre (Eastern End of Podium), M7w - International Finance Centre (Western End of Podium) and M8 – City Hall would no longer associated with Contract HY/2010/08 in August 2019 reporting month.

Reporting period of December March 202120

4.1.10.   No action or limit level exceedance was recorded in the reporting period.

4.1.11.   As confirmed with CWB RSS, major construction activities of HY/2010/08 under FEP-10/364/2009/B have been completed, only minor defects rectification works remains while no PME will be used for the remaining minor defects rectification works. As such, the noise monitoring stations M2b – Noon-day gun area and M3a – Tung Lo Wan Fire Station have been temporarily suspended from 22 March 2021 onward.

Reporting period of January 2021

4.1.1.                No action or limit level exceedance was recorded in the reporting period.

Reporting period of February 2021

4.1.1.                No action or limit level exceedance was recorded in the reporting period.

4.1.12.   Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 4.1.

Contract no. HY/2011/08 – Central - Wan Chai Bypass (CWB) – Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning

4.1.1.                Noise monitoring for the Central Interchange works under contract no. HY/2011/08 was commenced on 22 April 2011.The proposed division of noise monitoring stations for Contract no. HY/2011/08 are summarized in Table 4.6 below:

Table 4.6      Noise Monitoring Stations for Contract no. HY/2011/08

Station

Description

M4b

Victoria Centre

 

Reporting period of December 2020

4.1.1.                No action or limit level exceedance was recorded in the reporting period.

Reporting period of January 2021

4.1.1.                Limit No action or limit level exceedance was recorded in the reporting period.

 

Reporting period of February 2021

4.1.1.                No action or limit level exceedance was recorded in the reporting period.

4.1.1.                As confirmed with CWB RSS, major construction activities of HY/2011/08 under FEP- 11/364/2009/E have been completed, only minor defects rectification works remains while no PME will be used for the remaining minor defects rectification works. As such, the noise monitoring station M4b - Victoria Centre were no longer associated with Contract HY/2011/08 from 9 February 2021 onward.

4.1.1.                Noise monitoring results measured in this reporting period are reviewed and summarized.  Details of noise monitoring results and graphical presentation can be referred in Appendix 4.1

  4.2.       Real Time Noise Monitoring Results

Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/H

4.2.1.     Real time noise monitoring results measured in this reporting period are reviewed and summarized. Details of real time noise monitoring results and graphical presentation can be referred to Appendix 4.2

4.2.2.     The proposed division of noise monitoring stations are summarized in Table 4.7 below. Real time noise monitoring for major construction works under contract no. HY/2009/19 was commenced on 24 April 2011.

Table 4.7    Real Time Noise Monitoring Stations for Contract no. HY/2009/19

Location ID

District

Description

RTN1

Tin Hau

FEHD Hong Kong Transport Section Whitefield Depot

RTN2a

North Point

Electric Centre  (Replacement of RTN2)

RTN3

North Point

Pok Leung Kuk Yu Lee Mo Fun Memorial School

RTN4

Tin Hau

Causeway Bay Community Centre

* Real time noise monitoring results and graphical presentation during night time period are for information only.

*Real-time noise monitoring results and graphical presentation for RTN3 during restricted hours are for information only as no night classes were conducted at the educational institute.

             Reporting period of December March 20210

4.2.3.     No action or limit level exceedance was recorded at RTN1 - FEHD Hong Kong Transport Section Whitfield Depot in the reporting period.

4.2.4.     No action or limit level exceedance was recorded at RTN2a - Hong Kong Electric Centre in the reporting period.

4.2.1.     Limit level exceedances were recorded at RTN3 - Yu Lee Mo Fan Memorial School on 9, 10, 17 and 18 March 2021 in the reporting period.

4.2.2.     After checking with the Contractor, there was no construction works conducted under the Contractor HY/2009/19 around the monitoring station at RTN3 - Yu Lee Mo Fan Memorial School on 9, 10, 17 and 18 March 2021 during the monitoring period. As such, the exceedances were considered as non-Project related.

4.2.1.                Limit level exceedance was recorded at RTN3 - Yu Lee Mo Fan Memorial School on 19, 21, 22 and 23 December 2020 during daytime in the reporting period.

4.2.1.                After checking with the Contractor, there was no construction works conducted under the Contractor HY/2009/19 around the monitoring station on 19, 21, 22 and 23 December 2020 during the monitoring period. As such, the exceedance was considered as non-Project related.

4.2.3.     No action or limit level exceedance was recorded at RTN4 – Causeway Bay Community Centre in the reporting period.

Reporting period of January April 2021

4.2.4.     No action or limit level exceedance was recorded at RTN1 - FEHD Hong Kong Transport Section Whitfield Depot in the reporting period.

4.2.1.                Limit level exceedance was recorded at RTN1 - FEHD Hong Kong Transport Section Whitfield Depot on 30 December 2020, 2 and 12 January 2021 in the reporting period.

4.2.1.                After checking with the Contractor, there was no construction works conducted under the Contractor HY/2009/19 around the monitoring station on 30 December 2020, 2 and 12 January 2021 during the monitoring period. As such, the exceedances were considered as non-Project related.

4.2.5.     No action or limit level exceedance was recorded at RTN2a - Hong Kong Electric Centre in the reporting period.

4.2.6.     No action or limit level exceedances were recorded at RTN3 - Yu Lee Mo Fan Memorial School in the reporting period.

4.2.1.                Limit level exceedance was recorded at RTN3 - Yu Lee Mo Fan Memorial School on 30, 31 December 2020, 14, 16, 18, 23, 25 and 26 January 2021 during daytime in the reporting period.

4.2.1.                After checking with the Contractor, there was no construction works conducted under the Contractor HY/2009/19 around the monitoring station on  30, 31 December 2020, 14, 16, 18, 23, 25 and 26 January 2021 during the monitoring period. As such, the exceedance was considered as non-Project related.

4.2.7.     No limit level exceedance was recorded at RTN4 – Causeway Bay Community Centre in the reporting period.

Reporting period of February May 2021

4.2.8.     No action or limit level exceedance was recorded at RTN1 - FEHD Hong Kong Transport Section Whitfield Depot in the reporting period.

4.2.1.                Limit level exceedance was recorded at RTN1 - FEHD Hong Kong Transport Section Whitfield Depot on 4 and 6 February 2021 during daytime in the reporting period.

4.2.1.                After checking with the Contractor, there was no construction works conducted under the Contractor HY/2009/19 around the monitoring station on 4 and 6 February 2021 during the monitoring period. As such, the exceedance was considered as non-Project related.

4.2.9.     No action or limit level exceedance was recorded at RTN2a - Hong Kong Electric Centre in the reporting period.

4.2.10.   Limit level exceedance were recorded on 5, 6, 11, 12, 13, 17 and 21 May 2021 in the reporting period.

4.2.11.   After checking with the Contractor, there was no construction works conducted under the Contractor HY/2009/19 around the monitoring station at RTN3 - Yu Lee Mo Fan Memorial School on 5, 6, 11, 12, 13, 17 and 21 May 2021 during the monitoring period. As such, the exceedances were considered as non-Project related.

4.2.1.                Limit level exceedance was recorded at RTN3 - Yu Lee Mo Fan Memorial School on 27 January 2021 during daytime in the reporting period.

4.2.1.                After checking with the Contractor, there was no construction works conducted under the Contractor HY/2009/19 around the monitoring station on 27 January 2021 during the monitoring period. As such, the exceedance was considered as non-Project related.

4.2.12.   No action or limit level exceedance was recorded at RTN4 - Causeway Bay Community Centre in the reporting period.

4.2.13.   Real time noise monitoring results measured in this reporting period are reviewed and summarized. Details of real time noise monitoring results and graphical presentation can be referred to Appendix 4.2


Contract no. HY/2011/08 – Central - Wan Chai Bypass (CWB) – Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning

4.2.1.                The proposed division of noise monitoring stations are summarized in Table 4.8 below. Real time noise monitoring for major construction works under contract no. HY/2011/08 was commenced on 19 March 2015.

Table 4.8    Real Time Noise Monitoring Stations for Contract no. HY/2011/08

Location ID

District

Description

RTN1

Tin Hau

FEHD Hong Kong Transport Section Whitfield Depot

RTN2a1

North Point

Hong Kong Electric Centre

RTN4

Tin Hau

Causeway Bay Community Centre

* Real time noise monitoring results and graphical presentation during restrict hours and night time period are for information only and noise during CNP period shall be controlled under NCO.

    Remarks 1: With respect to the possession of site area Portion Xa and Portion Xb since 7 March 2016 as confirmed by CWB RSS, real time noise monitoring station RTN2a was associated with Contract no. HY/2011/08 from 07 March 2016 onwards

4.2.1.                As confirmed with CWB RSS, major construction activities of HY/2011/08 under FEP- 11/364/2009/E have been completed, only minor defects rectification works remains while no PME will be used for the remaining minor defects rectification works. As such, the realtime noise monitoring stations RTN1, RTN2a and RTN4 were no longer associated with Contract HY/2011/08 from 9 February 2021 onward.

Reporting period of December 2020

4.2.1.                No action or limit level exceedance was recorded at RTN1 - FEHD Hong Kong Transport Section Whitfield Depot in the reporting period.

4.2.1.                No action or limit level exceedance was recorded at RTN2a - Hong Kong Electric Centre in the reporting period.

4.2.1.                No action or limit level exceedance was recorded at RTN4 – Causeway Bay Community Centre in the reporting period.

Reporting period of January 2021

4.2.1.                Limit level exceedance was recorded at RTN1 - FEHD Hong Kong Transport Section Whitfield Depot on 30 December 2020, 2 and 12 January 2021 in the reporting period.

4.2.1.                After checking with the Contractor, there was no construction works conducted under the Contractor HY/2011/08 around the monitoring station on 30 December 2020, 2 and 12 January 2021 during the monitoring period. As such, the exceedances were considered as non-Project related.

4.2.1.                No action or limit level exceedance was recorded at RTN2a - Hong Kong Electric Centre in the reporting period.

4.2.1.                No limit level exceedance was recorded at RTN4 – Causeway Bay Community Centre in the reporting period.

Reporting period of February 2021

4.2.1.                Limit level exceedance was recorded at RTN1 - FEHD Hong Kong Transport Section Whitfield Depot on 4 and 6 February 2021 during daytime in the reporting period.

4.2.1.                After checking with the Contractor, there was no construction works conducted under the Contractor HY/2011/08 around the monitoring station on 4 and 6 February 2021 during the monitoring period. As such, the exceedance was considered as non-Project related.

4.2.1.                No action or limit level exceedance was recorded at RTN2a - Hong Kong Electric Centre in the reporting period.

4.2.1.                No action or limit level exceedance was recorded at RTN4 - Causeway Bay Community Centre in the reporting period.

4.2.1.                Real time noise monitoring results measured in this reporting period are reviewed and summarized. Details of real time noise monitoring results and graphical presentation can be referred to Appendix 4.2

  4.3.       Air quality monitoring Results

4.3.1       Due to extension of site boundary by contractor of HY/2009/19, location of air quality monitoring station CMA1b – Oil Street Community Liaison Centre has been finely adjusted on 21 April 2012.

Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

4.1.1                The commencement of construction works for HK/2009/02 under FEP-01/364/2009 is on 26 April 2011. The proposed division of air quality monitoring stations are summarized in Table 4.11 below.

Table 4.11 Air quality monitoring Station for Contract no. HK/2009/02

Station

Description

CMA3a

CWB site office at  Wanchai Waterfront Promenade

CMA4a

Society for the Prevention of Cruelty to Animals

Reporting period of December 2020

4.1.1                No action or limit level exceedance was recorded in the reporting period.

4.1.1                With respect to work completion confirmed by WDII RSS, air quality monitoring at CMA4a – Society for the Prevention of Cruelty to Animals was temporarily suspended from 23 December 2020 onwards and CMA3a – CWB PRE Site Office Area would no longer associated with Contract HK/2009/02 from 23 December 2020 onwards.

4.1.1                Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air quality monitoring results and graphical presentation can be referred in Appendix 4.3.  

Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/H

4.3.2       Air quality monitoring for the tunnel works was commenced on 26 April 2011 for Contract no. HY/2009/19 under FEP-07/364/2009/H. The proposed division of air quality monitoring stations are summarized in Table 4.13 below.

Table 4.13 Air quality monitoring Stations for Contract no. HY/2009/19

Station

Description

CMA1b

Harbour Grand Hotel Boundary Wall

CMA2a

Causeway Bay Community Centre

MA1b

Harbour Building

Reporting period of December March 20210

4.3.3       No action or limit level exceedance was recorded in the reporting period.

Reporting period of AprilJanuary 2021

4.3.4       One action level exceedances of 24hr TSP were recorded at CMA 2a on 17 April 2021 in the reporting period.

4.3.5       After the investigation, it was noted that removal of launching girder parts was undertaken on the monitoring date at around monitoring station CMA2a under Contractor of HY/2009/19 and no particular observation regarding air quality impact was observed during sampling. Meanwhile, elevated PM2.5 (Range from 8.5μg/m3 to 47.5μg/m3) and PM10 (Ranged from 16.1μg/m3 to 68.6μg/m3) level was recorded at EPD's Central/Western, Eastern General Station, Central Roadside Station and Causeway Bay Roadside Station. In addition, similar elevation in TSP level were recorded across the same period on 17 April 2021 at another AQM station at Central area (MA1b:201.1μg/m3), while no construction work was carried out around. In view of the above, the action level exceedance was considered to be non-project related and contributed by local ambient condition. No exceedance was recorded in the subsequent 1hr TSP monitoring on 19 April 2021. Nevertheless, the Contractor of HY/2009/19 was reminded to maintain regularly dust suppression measures for any potential dusty surface and dust generating operation around the concerned location to avoid any potential cumulative air quality impact.

4.3.6       One action level exceedances of 24hr TSP were recorded at MA1b on 17 April 2021 in the reporting period.

After the investigation, it was noted that no construction works was undertaken on the monitoring date at around monitoring station MA1b under Contractor of HY/2009/19 and no particular observation regarding air quality impact was observed during sampling. Meanwhile, elevated PM2.5 (Range from 8.5μg/m3 to 47.5μg/m3) and PM10 (Ranged from 16.1μg/m3 to 68.6μg/m3) level was recorded at EPD's Central/Western, Eastern General Station, Central Roadside Station and Causeway Bay Roadside Station.  In view of the above, the action level exceedance was considered to be non-project related and contributed by local ambient condition. No exceedance was recorded in the subsequent 1hr TSP monitoring on 19 April 2021

4.1.1                No action or limit level exceedance was recorded in the reporting period.

Reporting period of February May 2021

4.3.7       No action or limit level exceedance was recorded in the reporting period.

4.3.8       As demolition of concrete slab work will be conducted at CMA1b - Harbour Grand Hotel Boundary Wall and there is no other appropriate locations for installation of sampler, air quality monitoring station CMA1b - Harbour Grand Hotel Boundary Wall will be suspended and represented by CMA2a-Causeway Bay Community Centre from 12 March 2021 onward due to short separation distance between two stations.

4.3.9       As confirmed with CWB RSS, the major construction works of HY/2009/19 at Rumsey Street Flyover and Planter under FEP-07/364/2009/H have been completed and no PME will be used for the remaining minor defects rectification works. As such, the air quality monitoring station MA1b – Harbour Building has been temporarily suspended from 24 May 2021 onward.

4.3.10    Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air quality monitoring results and graphical presentation can be referred in Appendix 4.3.  

 

Contract no. HY/2010/08 – Central-Wanchai Bypass –Wanchai Bypass Tunnel (Slip Road 8 Section) under FEP-10/364/2009/B

4.3.11    The commencement of construction works for Contract no. HY/2010/08 under FEP-10/364/2009/B was on July 2014. Air quality monitoring was commenced on 14 July 2011. The proposed division of air quality monitoring stations are summarized in Table 4.15 below.

Table 4.15 Air quality monitoring Station for Contract no. HY/2010/08

Station

Description

CMA3a

CWB PRE Site Office

4.3.12    As confirmed with CWB RSS, junction modification works in Central area would be conducted by Contract HY/2010/08 starting from July 2018 and tentatively completed in September 2018. The noise monitoring station MA1e - International Finance Centre (Eastern End of Podium) and MA1w - International Finance Centre (Western End of Podium) would tentatively associated with Contract HY/2010/08.

4.3.13    As confirmed with Resident Site Staff, the junction modification under Contract HY/2010/08 at Central Area was generally completed while the remaining works was considered to be no adverse impact and not related to DP works. As such, the air quality monitoring station MA1e - International Finance Centre (Eastern End of Podium) and MA1w - International Finance Centre (Western End of Podium) would no longer associated with Contract HY/2010/08 in August 2019 reporting month.

Reporting period of December March 20210

4.3.14    No action or limit level exceedance was recorded in the reporting period.

4.3.15    As confirmed with CWB RSS, major construction activities of HY/2010/08 under FEP-10/364/2009/B have been completed, only minor defects rectification works remains while no PME will be used for the remaining minor defects rectification works. As such, the air quality monitoring station CMA3a – CWB PRE site office has been temporarily suspended from 22 March 2021 onward.

Reporting period of January 2021

4.1.1                No action or limit level exceedance was recorded in the reporting period.

Reporting period of February 2021

4.1.1                No action or limit level exceedance was recorded in the reporting period.

4.3.16    Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air quality monitoring results and graphical presentation can be referred in Appendix 4.3. 

Contract no. HY/2011/08 – Central - Wan Chai Bypass (CWB) – Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning

4.1.1                Air quality monitoring for the Central Interchange works under contract no. HY/2011/08 was commenced on 21 April 2011. The proposed division of air quality monitoring stations are summarized in Table 4.16 below.

Table 4.16   Air quality monitoring Stations for Contract no. HY/2011/08

Station

Description

CMA1b

Oil Street Site Office

CMA2a

Causeway Bay Community Centre

4.1.1                As confirmed with CWB RSS, major construction works and landscape works associated with WVB and nearby roads under HY/2011/08 are completed and only minor defects rectification works within WVN and tunnel area remain, in view of the defects rectification works are minor and are carried out in indoor area, it is considered that no adverse air quality impacts will be caused to nearby sensitive receivers. The air quality monitoring station MA1e - International Finance Centre (Eastern End of Podium) and MA1w - International Finance Centre (Western End of Podium) would no longer associated with Contract HY/2011/08 and were temporary suspended on 16 June 2020 and CMA5b - Pedestrian Plaza was temporarily suspended from 20 July 2020 onwards.

4.1.1                As confirmed with CWB RSS, major construction activities of HY/2011/08 under FEP- 11/364/2009/E have been completed, only minor defects rectification works remains while no PME will be used for the remaining minor defects rectification works. As such, the air quality monitoring stations CMA1b - Harbour Grand Hotel Boundary Wall and CMA2a – Causeway Bay Community Centre were no longer associated with Contract HY/2011/08 from 9 February 2021 onward.

Reporting period of December 2020

4.1.1                No action or limit level exceedance was recorded in the reporting period.

Reporting period of January 2021

4.1.1                No action or limit level exceedance was recorded in the reporting period.

Reporting period of February 2021

4.1.1                No action or limit level exceedance was recorded in the reporting period.

4.1.1                Air quality monitoring results measured in this reporting period are reviewed and summarized.  Details of air quality monitoring results and graphical presentation can be referred in Appendix 4.3.  

 

  4.4.       Waste Monitoring Results

Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel) under FEP-01/364/2009

4.4.1.     Inert and non-inert C&D waste were disposed of in this reporting period. Details of the waste flow table are summarized in Table 4.18.

Table 4.18  Details of Waste Disposal for Contract no. HK/2009/02

Waste Type*

Quantity this quarter,  m3

Cumulative-to-Date.  m3

Disposal / Dumping Grounds

Inert C&D materials disposed

Nil 096

552321.83

TKO137, TM 38

Inert C&D materials recycled

Nil

46520

WCR2

Non-inert C&D materials disposed

0Nil 3.8

6524.60

SENT Landfill

Non-inert C&D materials recycled

Nil

N/A

N/A

Chemical waste disposed

Nil

17718

N/A

 

Marine Sediment (Type 1 – Open Sea Disposal) , m3

Nil

65663

South Cheung Chau

 

Contract no. HY/2009/15 – Central-Wanchai Bypass – Tunnel (Causeway Bay Typhoon Shelter Section) under FEP-06/364/2009/A

4.4.2.     No Inert & Non-inert C&D wastes were disposed of in this reporting period. Details of the waste flow table are summarized in Table 4.20.

Table 4.20 Details of Waste Disposal for Contract no. HY/2009/15

Waste Type*

Quantity this quarter,  m3

Cumulative-to-Date.  m3

Disposal / Dumping Grounds

Inert C&D materials disposed, m3

Nil

Nil

625202.92

245453.3

Tuen Mun Area 38

TKO137 FB

Inert C&D materials recycled, m3

Nil

358660.77

HY/2009/11

ex-PCWA

TS4 /TS2

WDII

Lun Ku Tan

WENT

HY/2010/08

Non-inert C&D materials disposed, m3

138.98Nil

Nil

4814675.657

1.58

SENT Landfill

WENT Landfill

Non-inert C&D materials recycled

, m3

Nil

5496446.2

Xun Xiang Metalware

Skylight Recycle

(paper)

Chemical waste disposed, kg

Nil

22755

Dunwell Group

Marine Sediment (Type1-Open Sea Disposal (Dedicate Sites) &Type 2-Confined Marine Disposal), m3

Nil

5684

South of the Brothers

 

Contract no. HY/2009/19 – Central – Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/H

4.4.3.     Inert C&D materials was recycled non-inert C&D waste was disposed of in this reporting period. Details of the waste flow table are summarized in Table 4.21.

Table 4.21  Details of Waste Disposal for Contract no. HY/2009/19

Waste Type*

Quantity this quarter,  m3

Cumulative-to-Date.  m3

Disposal / Dumping Grounds

Inert C&D materials disposed

2,668.14450.44

830777.19833227.63

TKO137

TM38

Inert C&D materials recycled

Nil

82349.7

N/A

Non-inert C&D materials disposed

128.27196.21

9178.089374.29

SENT Landfill

Non-inert C&D materials recycled

Nil

565.63

N/A

Chemical waste disposed

0.09*6

16.5335

N/A

Marine Sediment (Tunnel) (Type 1- Open Sea Disposal), m3

Nil

20737.96

South of Cheung Chau

Marine Sediment (Tunnel) (Type 1- Open Sea Disposal (Dedicated Sites) & Type 2 – Confined Marine Disposal), m3

Nil

30751

East of Sha Chau

Marine Sediment (Approach Ramp) (Type 2 – Confined Marine Disposal), m3

Nil

6491

East of Sha Chau

             Remark:

*: 0.09 ton of chemical waste was disposed of in the reporting period of December 2020 and the cumulative chemical waste disposed in this reporting period shall be 16.35+0.09+0.09=16.53tons.

 

 

 

Contract no. HY/2010/08 Central – Wan Chai Bypass (CWB) – Tunnel (Slip Road 8) under FEP-10/364/2009/B

4.4.4.     Inert and Non-inert C&D wastes were disposed of in this reporting period. Details of the waste flow table are summarized in Table 4.23.

Table 4.23  Details of Waste Disposal for Contract no. HY/2010/08

Waste Type*

Quantity this quarter,  m3

Cumulative-to-Date,  m3

Disposal / Dumping Grounds

Inert C&D materials disposed

 

388.787.939

Nil

Nil

Nil

599582.16599590.099 262656.6

82911.8

72711.86

TM 38 / CW / TKO137SF

WENT

SENT

TKO area 137

Inert C&D materials recycled

Nil

Nil

Nil

Non-inert C&D materials disposed

214.067405.611

6843.577249.18

SENT

Non-inert C&D materials recycled

Nil

Nil

Nil

Chemical waste disposed

Nil

1431

Nil

Type 1 – Open Sea Disposal

Nil

16753.225

East Sha Chau/ South Brothers Island

Type 2 – Confined Marine disposal

Nil

1243.2

East Sha Chau

 

 

           

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Contract no. HY/2011/08 Central –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009/E

4.4.5.     No inert and Non-inert C&D wastes were disposed of in this reporting period. Details of the waste flow table are summarized in Table 4.24.

Table 4.24  Details of Waste Disposal for Contract no. HY/2011/08

Waste Type*

Quantity this quarter,  m3

Cumulative-to-Date,  m3

Disposal / Dumping Grounds

Inert C&D materials disposed

Nil28.233

8730.8078730.807

 CWPF & TKO137

Inert C&D materials recycled

Nil

Nil

 Nil

Non-inert C&D materials disposed

Nil48.289

9393.1789393.178

                SENT

Non-inert C&D materials recycled

Nil

347.12

Nil

Chemical waste disposed (kg)

Nil

3800

Nil

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

5.         Compliance Audit

5.0.1.     The Event Action Plan for construction noise and air quality are presented in Appendix 5.1.

5.1.          Noise Monitoring

Contract no. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel)

5.1.1.                No action or limit level exceedance was recorded in the December 2020 reporting period.

Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/H

5.1.1.     Limit level exceedance was recorded at M6 - HK Baptist Church Henrietta Secondary School on 18 March 2021 in the reporting period. After the investigation, the exceedance was concluded as non-Project related.

5.1.1.                No action or limit level exceedance was recorded in the December 2020 reporting period.

5.1.2.     No action or limit level exceedance was recorded in the January April 2021 reporting period.

5.1.3.     No action or limit level exceedance was recorded in the February May 2021 reporting period.

Contract no. HY/2010/08 – Central-Wanchai Bypass – Tunnel (Slip Road 8 Section) under FEP-10/364/2009/B

5.1.4.     No action or limit level exceedance was recorded in the December March 20210 reporting period.

5.1.1.                No action or limit level exceedance was recorded in the January 2021 reporting period.

5.1.1.                No action or limit level exceedance was recorded in the February 2021 reporting period.

Contract no. HY/2011/08 Central –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009/E

5.1.1                No action or limit level exceedance was recorded in the December 2020 reporting period.

5.1.1                No action or limit level exceedance was recorded in the January 2021 reporting period.

5.1.1                No action or limit level exceedance was recorded in the February 2021 reporting period.

5.2.          Real Time Noise Monitoring

Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/H

5.2.1      24-hour real time noise monitoring was conducted at RTN1 - FEHD Hong Kong Transport Section Whitfield Depot. No action or limit level exceedance was recorded in December March 20201 reporting period.

24-hour real time noise monitoring was conducted at RTN2a – Hong Kong Electric Centre. No action or limit level exceedance was recorded in December March 20201 reporting period.

24-hour real time noise monitoring was conducted at RTN3 - Yu Lee Mo Fan Memorial School. Limit level exceedances were recorded on 9, 10, 17 and 18 March 2021 in the reporting period. After the investigation, the exceedances were concluded as non-Project related.

24-hour real time noise monitoring was conducted at RTN3 - Yu Lee Mo Fan Memorial School. Limit level exceedance was recorded on 19, 21, 22 and 23 December 2020. After the investigation, the exceedance was concluded as non-Project related.

24-hour real time noise monitoring was conducted at RTN4 – Causeway Bay Community Centre. No action or limit level exceedance was recorded in December March 20201 reporting period.

5.2.2      24-hour real time noise monitoring was conducted at RTN1 - FEHD Hong Kong Transport Section Whitfield Depot. No action or limit level exceedance was recorded in April 2021 reporting period.

1.1.1                24-hour real time noise monitoring was conducted at RTN1 - FEHD Hong Kong Transport Section Whitfield Depot. Limit level exceedance was recorded on 30 December 2020, 2 and 12 January 2021. After the investigation, the exceedance was concluded as non-Project related.

24-hour real time noise monitoring was conducted at RTN2a – Hong Kong Electric Centre. No action or limit level exceedance was recorded in January April 20201 reporting period.

24-hour real time noise monitoring was conducted at RTN3 - Yu Lee Mo Fan Memorial School. No action or limit level exceedance was recorded in the April 2021 reporting period.

24-hour real time noise monitoring was conducted at RTN3 - Yu Lee Mo Fan Memorial School. Limit level exceedance was recorded on 30, 31 December 2020, 14, 16, 18, 23, 25 and 26 January 2021. After the investigation, the exceedance was concluded as non-Project related.

24-hour real time noise monitoring was conducted at RTN4 – Causeway Bay Community Centre. No action or limit level exceedance was recorded in January April 2021 reporting period.

5.2.3      24-hour real time noise monitoring was conducted at RTN1 - FEHD Hong Kong Transport Section Whitfield Depot. No action or limit level exceedance was recorded in May 2021 reporting period.

1.1.1                24-hour real time noise monitoring was conducted at RTN1 - FEHD Hong Kong Transport Section Whitfield Depot. Limit level exceedance was recorded on 4 and 6 February 2021. After the investigation, the exceedance was concluded as non-Project related.

24-hour real time noise monitoring was conducted at RTN2a – Hong Kong Electric Centre. No action or limit level exceedance was recorded in February May 2021 reporting period.

24-hour real time noise monitoring was conducted at RTN3 - Yu Lee Mo Fan Memorial School. Limit level exceedance were recorded on 5, 6, 11, 12, 13, 17 and 21 May 2021 in the reporting period. After the investigation, all exceedances were concluded as non-project related.

24-hour real time noise monitoring was conducted at RTN3 - Yu Lee Mo Fan Memorial School. Limit level exceedance was recorded on 27 January 2021. After the investigation, the exceedance was concluded as non-Project related.

24-hour real time noise monitoring was conducted at RTN4 – Causeway Bay Community Centre. No action or limit level exceedance was recorded in February May 2021 reporting period.

Contract no. HY/2011/08 Central –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009/E

1.1.1                24-hour real time noise monitoring was conducted at RTN1 - FEHD Hong Kong Transport Section Whitfield Depot. No action or limit level exceedance was recorded in December 2020 reporting period.

24-hour real time noise monitoring was conducted at RTN2a – Hong Kong Electric Centre. No action or limit level exceedance was recorded in December 2020 reporting period.

24-hour real time noise monitoring was conducted at RTN4 – Causeway Bay Community Centre. No action or limit level exceedance was recorded in December 2020 reporting period.

1.1.1                24-hour real time noise monitoring was conducted at RTN1 - FEHD Hong Kong Transport Section Whitfield Depot. Limit level exceedance was recorded on 30 December 2020, 2 and 12 January 2021. After the investigation, the exceedance was concluded as non-Project related.

24-hour real time noise monitoring was conducted at RTN2a – Hong Kong Electric Centre. No action or limit level exceedance was recorded in January 2021 reporting period.

24-hour real time noise monitoring was conducted at RTN4 – Causeway Bay Community Centre. No action or limit level exceedance was recorded in January 2021 reporting period.

1.1.1                24-hour real time noise monitoring was conducted at RTN1 - FEHD Hong Kong Transport Section Whitfield Depot. Limit level exceedance was recorded on 4 and 6 February 2021. After the investigation, the exceedance was concluded as non-Project related.

24-hour real time noise monitoring was conducted at RTN2a – Hong Kong Electric Centre. No action or limit level exceedance was recorded in February 2021 reporting period.

24-hour real time noise monitoring was conducted at RTN4 – Causeway Bay Community Centre. No action or limit level exceedance was recorded in February 2021 reporting period.

5.3.          Air quality monitoring

Contract nos. HK/2009/02 - Wan Chai Development Phase II - Central - Wan Chai Bypass at Wan Chai East (CWB Tunnel)

1.1.1                No action or limit level exceedance was recorded in the December 2020 reporting period.

Contract no. HY/2009/19 - Central - Wanchai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link under FEP-07/364/2009/H

5.2.4      No action or limit level exceedance was recorded in the December March 20201 reporting period.

5.2.5      Two action level exceedances of 24hr TSP were recorded at CMA2a and MA1b on 17 April 2021 in the reporting period. After the investigation, all exceedances were concluded as non-project related.No action or limit level exceedance was recorded in the January 2021 reporting period.

5.2.6      No action or limit level exceedance was recorded in the February May 2021 reporting period.

 

Contract no. HY/2010/08 – Central-Wanchai Bypass – Tunnel (Slip Raod 8 Section) under FEP-10/364/2009/B

5.2.7      No action or limit level exceedance was recorded in the December March 20201 reporting period.

1.1.1                No action or limit level exceedance was recorded in the January 2021 reporting period.

1.1.1                No action or limit level exceedance was recorded in the February 2021 reporting period.

Contract no. HY/2011/08 Central –Central - Wan Chai Bypass (CWB) –Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning under FEP-11/364/2009/E

1.1.1                No action or limit level exceedance was recorded in the December 2020 reporting period.

1.1.1                No action or limit level exceedance was recorded in the January 2021 reporting period.

1.1.1                No action or limit level exceedance was recorded in the February 2021 reporting period.

5.4.          Site Audit

5.4.1       There was no non-compliance from the site audits in the reporting period. During environmental site inspections conducted during the reporting period, minor deficiencies were noted.  However, the Contractor rectified all deficiencies after receipt of notification.

5.5.          Review of the Reasons for and the Implications of Non-compliance

5.5.1       There was no non-compliance from the site audits in the reporting quarter.

5.6.          Summary of action taken in the event of and follow-up on non-compliance

5.6.1       No particular action was taken for site audits since non-compliance was recorded in the reporting period.

6.         Complaints, Notification of Summons and Prosecution

9.0.1.     An ICC complaint was referred to the ET on 10 March 2021 (CASE Ref: CASE# 3-6647057872). The complainant reported that suspected disposal of construction waste into the sea was observed at the works area underneath IEC on 8 March 2021 and video could be provided for follow-up.

The ET confirmed with the Resident Site Staff that:

The complainant was unable to be reached at this moment and no such video is available;

According to the site records, removal of the temporary work at the marine pile caps in front of City Garden Block 6 was undertaken on the date of the incident (8 March 2021);

The construction waste handling procedures for the concerned construction activities are as follows:

                      I.        Break up temporary concrete plinths on the pile caps underneath existing IEC bridge;

                     II.        Clear the concrete debris by collecting them in nylon bags; and

                    III.        Transport the occupied nylon bags to stockpile area at land portion of C19 site by marine vessel for further disposal off site to Public Fill Reception Facilities by dump truck.

As the video mentioned in the complaint is unavailable, there is no sufficient information to conclude that the complaint was considered as related to the removal of the temporary work at the marine pile caps in front of City Garden Block 6.

Despite the RSS advised that specific construction waste handling procedures for removal of the temporary work at the marine pile caps were available on the date of incident, the Contractor of HY/2009/19 was recommended to provide training to site personnel in proper waste management as preventive measure.

6.0.1                An ICC complaint was referred to the ET on 9 December 2020 (CASE Ref: CASE# 3-6572708255). The complainant reported that the newly planted trees at SR13 were suspected to be unhealthy and withered.

The ET confirmed with the Resident Site Staff that:

-                 It is confirmed that the location and species of the concerned planted trees are tallied with the latest approved landscape plan.

-                 The planting date for such trees is 19 October 2020.

-                 Regular maintenance (i.e. establishment works under C19 Contract) should be provided for the concerned trees including but not limited to (i) daily watering and (ii) pruning when necessary.  After the establishment works under C19, the soft landscaping works will be handed over and maintained by LCSD.

-                 Latest concern tree information:

            (i) Species – Lagerstroemia speciosa

            (ii) Health condition – Fair

            (iii) Planting location – SR13

           

In view of the above information, the complaint was considered as related to the newly planted trees at SR13. The planting date for such trees is 19 October 2020. The RSS confirmed that the location and species of the concerned trees planted at SR13 are tallied with the latest submitted landscape plan and health condition of such trees is fair.

 

Despite the RSS advised that the location and species of the trees at SR13 were planted in according to the latest submitted landscape plan and health condition of such trees is fair, the Contractor of HY/2009/19 was recommended to provide proper maintenance to the planted trees at SR13. A follow-up inspection was conducted for the trees at SR13 on 16 December 2020 and was found tally with the information provided by the Contractor.

6.0.1       No environmental complaint was received in the January April 2021 reporting period.

6.0.2       No environmental complaint was received in the February May 2021 reporting period.

6.0.3       The details of cumulative complaint log and summary of complaints are presented in Appendix 6.1.

6.0.4       Cumulative statistic on complaints and successful prosecutions are summarized in Table 6.1 and Table 6.2 respectively.

Table 6.1    Cumulative Statistics on Complaints

Reporting Period

     No. of Complaints

Commencement of Works up to last reporting period

1098

December March 20210 to February May 2021

1

Project-to-Date

   11009

 

Table 6.2    Cumulative Statistics on Successful Prosecutions

Environmental Parameters

Cumulative No. Brought Forward

No. of Successful Prosecutions this period (Offence Date)

Cumulative No. Project-to-Date

Air

1

0

1

Noise

109

01 (23 November 2020)

10

Water

2

0

2

Waste

0

0

0

Total

132

     01

13

 

7.         Cumulative Construction Impact due to the Concurrent Projects

7.0.1.     According to Condition 3.4 of the EP-364/2009/G, this section addresses the relevant cumulative construction impact due to the concurrent activities of the current projects including the Central Reclamation Phase III (CRIII), Wan Chai Development Phase II (WDII), Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) and Wan Chai Development Phase II – Central – Wan Chai Bypass at Wan Chai East (CWB Tunnel).

7.0.2.     According to the Final EM&A Report of Central Reclamation Phase III (CRIII) for Contract HK 12/02, the major construction activities were completed by end of January 2014 and no construction activities were undertaken thereafter and the water quality monitoring was completed in October 2011.  As such, it is considered that there were no cumulative construction impact due to the concurrent activities of the current projects with the Central Reclamation Phase III (CRIII) undertaken by contractor HK12/02 in the reporting period.

7.0.3.     According to the construction programme of Central-Wanchai Bypass at Wanchai West at the Central Reclamation Phase III area, no works was conducted in February May 2021 reporting period. In view of the above, the cumulative construction impact due to the Central Reclamation Phase III (CRIII) was not anticipated.

7.0.4.     According to the construction programme of Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects, no construction works under Wan Chai Development Phase II was conducted at Wan Chai. The major construction activities under Central-Wan Chai Bypass and Island Eastern Corridor Link Projects were modification works at Central; bridge noise enclosure installation works, road works, drainage works, soft landscape works and ventilation building ABWF work at North Point area in the reporting period. In addition, other non-Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects were observed undertaken at Wan Chai North and North Point area.

7.0.1.                According to the construction programme of Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects, no construction works under Wan Chai Development Phase II was conducted at Wan Chai. The major construction activities under Central-Wan Chai Bypass and Island Eastern Corridor Link Projects were modification works at Central; seabed reinstatement at Causeway Bay, drainage improvement work and utility diversion works at Victoria Park; bridge noise enclosure installation works, road works, drainage works, soft landscape works and ventilation building ABWF work at North Point area in the reporting period. In addition, other non-Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link projects were observed undertaken at Wan Chai North and North Point area.

7.0.5.     As relevant site mitigation measures for air quality and construction noise were implemented, no significant air quality impact and noise impact from construction activities was concluded in the reporting period. Besides, no project related exceedance was recorded in the reporting period.  Thus, it is evaluated that the cumulative construction impact from the concurrent projects including Wan Chai Development Phase II (WDII), Central-WanChai Bypass (CWB), Island Eastern Corridor Link projects (IECL) was insignificant.

 

 

8.         Conclusion

8.0.1.     The EM&A programme was carried out in accordance with the EM&A Manual requirements, minor alterations to the programme proposed were made in response to changing circumstances.

8.0.2.     There was no non-compliance from the site audits in the December March2020, JanuaryApril and February May 2021 reporting period.

8.0.3.     One environmental complaint was received in this reporting quarter.

8.0.4.     The construction programmes of individual contracts are provided in Appendix 7.1.


 [h1]